APHC010671122022
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3457]
THURSDAY, THE 6th DAY OF AUGUST 2026
PRESENT
THE HONOURABLE SRI JUSTICE HARINATH.N
WRIT PETITION NO: 39920/2022
Between:
1. M/S.
STERLITE
TECHNOLOGIES
LIMITED,
HAVING
ITS
REGISTERED OFFICE AT. 4TH FLOOR, GODREJ MILLENNIUM,
KOREGAON ROAD 9, STS 12/1, PUNE-411001, MAHARASHTRA
ALSO AT, 3RD FLOOR, IFFCO TOWERS PLOT NO3, SECTOR -29,
GURUGRAM - 122002 REPRESENTED BY MR. KARUNAKAR DASH
STATE HEAD PROJECTS FOR TELANGANA AND ANDHRA
PRADESH REGION, AGED ABOUT 52 YEARS, RIO 5TH FLOOR,
SHANGRILA PLAZA, ROAD NO 2, BANJARA HILLS, HYDERABAD
500034.
...PETITIONER
AND
1. THE STATE OF ANDHRA PRADESH, KAKINADA SMART CITY
CORPORATION LIMITED
REPRESENTED BY ITS, MANAGING
DIRECTOR HAVING ITS REGISTERED OFFICE AT.
2-33-10,
PEKETI VARI STREET,
PERRAJUPETA, KAKINADA, ANDHRA
PRADESH - 533003
2. STATE OF ANDHRA PRADESH,
THROUGH, PRINCIPAL
SECRETARY
MUNICIPAL ADMINISTRATION AND URBAN
DEVELOPMENT SECRETARIAT, VELAGAPUDI, AMARAVATHI
3. STATE
OF
ANDHRA
PRADESH,
THROUGH
PRINCIPAL
SECRETARY
FINANCE
DEPARTMENT,
SECRETARIAT,
VELAGAPUDI, AMARAVATHI,
THULLAR MANDAL, GUNTUR
DISTRICT
4. IDBI BANK, REPRESENTED BY ITS, BANK MANAGER HAVING ITS
BRANCH
OFFICE
AT.
TRADE
FINANCE
DEPARTMENT,
SPECIALISED CORPORATE BRANCH,PRIDE HOUSE, SECOND
FLOOR, UNIVERSITY ROAD, GANESH KHIND, PUNE- 41101
...RESPONDENT(S):
Petition under Article 226 of the Constitution of India praying that in the
circumstances stated in the affidavit filed therewith, the High Court may be
pleased topleased to issue a writ or writs in the nature of mandamus or such
other writ, order or direction or any other appropriate writ or direction declaring
inaction of the Respondent No. 1 in releasing Rs. 5.25 (Rupees Five Crore
Twenty Five Lakh Only) which stands approved and admitted for the works
executed by the Petitioner under the Contract for Development and
Implementation of Smart City Solutions in Kakinada dated 30.06.2017, despite
Respondent No. 1 admitting the bills and declaring the letter issued by
Respondent No 1 vide Lr No KSCCL /B .G. Encashment /2022, dt 20 -12 2022 thereby instructing Respondent No 4 to invoke the bank guarantee
furnished by the Petitioner Company vide B. G. Nos. 170390IBGP00382 and
170390IBGP00385 amounting to Rs. 3. 78 Crores, dt 04 -05 -2017 to arm
twist the Petitioner Company for demanding the abovesaid admitted amount
of Rs. 5. 25 crores as illegal, unfair, unreasonable and arbitrary and in
violation of Article 14 and Article 19 of the Constitution of India, and
consequently to set aside the letter issued by Respondent No. 1 vide Lr No
KSCCL /B .G. Encashment /2022, dt 20 -12 -2022 and direct the Respondent
No 1 to release the admitted amount Rs. 5 .25 (Rupees Five Crore Twenty
Five Lakh Only) to the Petitioner along with interest at 18 percentage from the
date on which the payments became due till date of payment and pass
Prayer is amended as per CO dt 26/12/2022 vide order passed in IA 03/2022.
IA NO: 1 OF 2022
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased
To direct. (a) Respondent No.1 to not threaten or encash the Petitioner's
bank guarantee No. 170390IBGP00382 and 1703901BGP00385 amounting to
Rs.3.78 Crores. (b) Respondent No.1 to stay the operation of letter dated
06.12.2022 and restrain from taking any coercive actions against the
Petitioner in terms of the letter dated 06.12.2022 or any other letter later
issued for a similar purpose. and (c) Respondent No 4 to not act upon any
letter or instruction from Respondent No. 1 to encash the Petitioner's bank
guarantee No. 170390IBGP00382 and 170390IBGP00385 amounting to
Rs.3.78 Crores, (d) Respondent No 1 to expeditiously initiate and complete
transfer if Rs. 5.25 (Rupees Five Crore Twenty Five Lakh Only) to the
Petitioner. and (e) to pass
IA NO: 2 OF 2022
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased
pleased to direct the Respondent No.1 to not to encash the Petitioner's bank
guarantee No. 170390IBGP00382 & 170390113GP00385 amounting to
Rs.3.78 Crores, restrain from taking any coercive steps against the Petitioner
pursuant to its letter dt. 20-12-2022 and Respondent No.4, to not act upon any
letter or instruction from respondent. No.1 to encash the Petitioner's bank
guarantee No. 170390IBGP00382 and 170390IBGP00385 amounting to Rs.
3.78 Crores pending disposal of the main writ petition and to pass
IA NO: 3 OF 2022
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased
pleased to permit the Petitioner Company to amend the main prayer of the writ
petition as follows: "Hon'ble Court be pleased to issue a writ or writs in the
nature of mandamus or such other writ, order or direction or any other
appropriate writ or direction declaring inaction of the Respondent No. 1 in
releasing Rs. 5.25 (Rupees Five Crore Twenty Five Lakh Only) which stands
approved and admitted for the works executed by the Petitioner under the
Contract for Development and Implementation of Smart City Solutions in
Kakinada dated 30.06.2017 despite Respondent No. 1 admitting the bills and
declaring
the
letter
issued
by
Respondent
No.
1.
vide
Lr,No.KSCCL/B.G.Encashment/2022, dt.20-12-2022 thereby instructing
Respondent No.4 to invoke the bank guarantee
furnished by the
Petitioner Company vide B.G,Nos. 170390IBGP00382 & 170390IBGP00385
amounting to Rs.3.78 Crores, cit, 04-05-2017 to arm twist the Petitioner
Company for demanding the above said admitted amount of Rs,5.25 crores as
illegal, unfair, unreasonable and arbitrary and in violation of Article 14 and
Article 19 of the Constitution of India, and consequently to set aside the letter
issued by Respondent No. 1 vide Lr.No.KSCCL/B.G.Encashment/2022, dt.2012-2022 and direct the Respondnet No. 1 to release the admitted amount Rs.
5.25 (Rupees Five Crore Twenty Five Lakh Only) to the Petitioner along with
interest at 18% from the date on which the payments became due till date of
payment; and pass
Counsel for the Petitioner:
1. JAVVAJI SARATH CHANDRA
Counsel for the Respondent(S):
1. M Krishna Rao SC for skl vzm kkd Municipal Corporations
2. GP FOR MUNCIPAL ADMN URBAN DEV
The Court made the following:
THE HONOURABLE SRI JUSTICE HARINATH.N
WRIT PETITION No.39920 of 2022
ORDER:
1. The petitioner has filed the writ petition seeking a direction to the
respondent No.1 to release an amount of Rs.5,25,00,000/- being the
approved and admitted amount payable to the petitioner towards the
works executed by the petitioner under the Contract for development
and implementation of Smart City Solutions in Kakinada and further
declaration of letter dated 20.12.2022 issued by the respondent No.1
instructed the respondent No.4 to invoke the bank guarantee.
2. The learned counsel appearing for the petitioner submits that the
petitioner is a company incorporated under the Companies Act, 1956
and is in the business of extending technological and infrastructure
services. The petitioner was the successful bidder and selected as a
systems integrator for the Kakinada Smart City Programme.
3. The scope of work of the petitioner was in following four Phases;
a) Phase : 1 involved supply, installation, commissioning, training
and operationalization of command and control center and data
center (DC) with infrastructure needed to run Smart Lights, VMD,
environmental Sensors, Waste Management, Smart parking,
Disaster Management & Camera feed of existing surveillance
deployment of Police on Video Wall, Smart Pole
– Timeline: date of signing of agreement + 3 (three) months
b) Phase : 2 – Supply and Commissioning of 100% Core and
Aggregate ring electronics, passive infrastructure with network
live. Supply and commissioning of 3 Access ring electronics,
passive instrastructure with 30% installation and commissioning
of CCTV and Wifi Access Points
– Timeline : date of signing of agreement + 6 (six) months
c) Phase : 3 – 100% completion of Access & Service Layer and
network Go Live. Commissioning of balance smart city solutions
with Geographical Information System (GIS) & ERP integration.
–Timeline : Date of signing of agreement + 9 (nine) months
d) O& M Phase
– Timeline : Go Live Phase of all phases i.e., Date of signing
of agreement + 9 (nine) months + 60 (sixty) months.
4. The value of the contract is Rs.94,89,23,426/- which includes capital
expenditure of Rs.66,48,74,880/- and operational expenditure of
Rs.28,40,48,546/- which is payable to the petitioner for performance of
its obligations. The scope of work was subsequently enhanced by Rs.
3,89,00,000/-.
5. The general conditions of the contract mandate payment by the
respondent No.1 within a period of 60 days from the date of receipt of
invoice or request for payment from the petitioner. It is submitted that
the respondent No.1 failed to release the outstanding amount, which
was admitted and undisputed. The respondent No. 1 was due an
amount of Rs. 19,39,07,230/- since February, 2020. Though the
petitioner received no payment, the petitioner continued to provide
uninterrupted service through the COVID pandemic in the larger public
interest.
6. It is submitted that the respondent No.1 had admitted the dues payable
vide their letters dated 23.01.2021, 23.12.2021 and 09.03.2022. As no
amounts were forthcoming from respondent No. 1, the petitioner was
unable to meet the operational costs and faced acute financial
difficulties in paying the staff and other vendors. Having no other option,
the petitioner exited from the project by addressing letters dated
05.03.2022 with effect from 09.03.2022. The petitioner sought for
release of the bank guarantees.
7. Aggrieved by the inaction on part of the respondents in releasing the
payments, the petitioner filed WP.No.8065 of 2022; this Court vide order
dated 30.04.2022 directed the respondents to release the payments in
six weeks. The respondent No.1 did not release any payments;
however, admitted the liability of Rs.5,25,00,000/- in addition to the
Rs.19.20 crores. It is specifically admitted by the respondents, vide their
communication dated 16.06.2022, that the respondent is due Rs.19.20
crores, and they further confirmed an additional amount of Rs.5.25
crores, which is also approved for release.
8. The petitioner has invoked the dispute resolution clause for claiming
the disputed amounts and insofar as the admitted amounts are
concerned, the respondents would have to release the same. The
Rs.19,39,00,000/- were belatedly released by the respondent No.1 in
the second week of October, 2022, before contempt case No.2561 of
2022 was taken up for hearing.
9. The respondent No.1 vide letter dated 01.11.2022 called upon the
petitioner to restore all elements of system integration projects. That
failure to restore the services would render the petitioner liable for
penalties and termination of the contract. It is submitted that the
petitioner submitted a detailed response that the petitioner had
withdrawn from the contract with effect from 09.03.2022 and that the
respondent No.1 is responsible for the petitioner to withdraw from the
contract and that the outstanding dues were called upon to be paid and
that the petitioner is open for discussions for resumption of work.
10. It is submitted that the respondent No.1, instead of releasing the
admitted payments, kept on addressing letters calling upon the
petitioner to resume the services. The respondent No.1 issued a letter
dated 06.12.2022, holding out the threat of encashment of the bank
guarantee amounting to Rs.3.78 crores in the event the petitioner does
not resume the services.
11. The learned counsel for the petitioner submits that by an order dated
26.12.2022, this Court directed the respondents not to take any
coercive steps regarding encashment of the bank guarantee. It is
submitted that the bank guarantee was encashed, and that the
petitioner shall claim a refund in the Arbitration proceedings, and that
the writ petition seeking a direction to the respondent No.1 to release
the admitted due amount of Rs.5.25 crores is restricted.
12. The respondent No.1 has filed a counter; it is not disputed that the
petitioner was a successful bidder for the implementation of Smart City
Solutions in Kakinada. It is also stated in the counter that on
12.01.2022, the petitioner submitted a letter of their intention to
withdraw from the project with effect from 09.03.2022 if the outstanding
payments are not made.
13. It is also stated that the petitioner has not complied with the exit
management plan clause of the agreement. It is also stated that the
respondent No.1 addressed a letter dated 15.03.2022 to complete the
proper handover of the project and to ensure the smooth transfer of the
system from the petitioner. It is also stated that the petitioner
intentionally avoided the physical handover of the project solely to
conceal the equipment's non-functionality.
14. The respondent No.1 in the counter has stated that the amount of
Rs.5.25 crores could not be released as the petitioner failed to submit
the detailed bills. The respondent No.1, again in the counter at
paragraph No.8, submits that the admitted amount of Rs.5.25 crores
was approved, the bills were uploaded on the CFMS portal, and the
respondent No.3 is competent to release the approved bills. It is also
stated in the counter that respondent No.1 has addressed letters to
respondents Nos. 2 and 3 requesting the release of the petitioner's
pending bills. It is also stated that the petitioner was also informed of the
same. It is also stated that the bank guarantee of Rs. 3.78 crores was
encashed on 21.12.2022, and the amount was credited to the account
of the respondent No. 1 on 22.12.2022.
15. Heard the learned counsel for the petitioner and the learned standing
counsel for the respondent No.1. Perused the material on record.
16. The short point for consideration is whether a direction to the
respondent Nos.1 to 3 can be issued for release of the approved and
admitted amount of Rs.5.25 crores.
17. The respondent No.1 has admitted Rs.5.25 crores as approved and due
payable to the petitioner on several occasions. The respondent No.1
has categorically and unequivocally informed the petitioner about the
amounts due and that their efforts to credit the amounts to the
petitioner’s account are in progress.
18. The counter filed by the respondent No.1 and the annexures filed along
with the counter also do not dispute the approved and admitted amount
of Rs.5.25 crores due and payable to the petitioner. Correspondence
from the respondent No.1 calling upon the petitioner to resume the
services after lapse of eight (8) months after the petitioner withdrew
from the project cannot accrue a fresh cause of action for the
respondent No.1 for withholding the admitted payments.
19. It is left open for the petitioner to raise the grievance about encashment
of bank guarantee by invoking the dispute resolution clause of the
contract. Insofar as the approved and admitted amount is concerned,
the respondent Nos.1 to 3 would have to release the same.
20. In light of these considerations, the writ petition is allowed in part,
directing the respondent Nos.1 to 3 to verify and release the approved
and admitted amount of Rs.5,25,00,000/- within a period of twelve
weeks from the date of receipt of this order. There shall be no order as
to costs.
As a sequel, miscellaneous applications pending, if any, shall stand
closed.
___________________
JUSTICE HARINATH.N
Date : 06.08.2026
RSD/KGM
Whether the order is:
Speaking
Reportable
Reasoned
Non-reportable
☑
☑
THE HONOURABLE SRI JUSTICE HARINATH.N
WRIT PETITION No.39920 of 2022
Date: 06.08.2026
RSD/KGM
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review