IN THE HIGH COURT OF MANIPUR
AT IMPHAL
[1]
Arbitration P(J2) No.1 of 2019
M/s Simplex Projects Ltd. Through its Director
19, Nellie Sengupta Sarani 3rd Floor, Kolkata 700087
- Versus –
1.
2.
3.
4.
[2]
... Petitioner
State of Manipur through its Chief Secretary, Secretariat, Imphal.
Public Works Department Through its Chief Engineer Manipur,
Khuyathong Imphal 795001
The Executive Engineer Division NO.I PWD, Manipur, Khuyathong
Imphal 795001.
Axis Bank Ltd. Through its Manager, office at 7, Shakespeare Sarani,
Kolkata 700071
… Respondents
Arbitration P(J2) No.2 of 2019
M/s Simplex Projects Ltd. Through its Director,
19, Nellie Sengupta Sarani 3rd Floor, Kolkata 700087
- Versus –
... Petitioner
1.
2.
State of Manipur through Chief Secretary, Secretariat, Manipur.
Public Works Department Through its Chief Engineer Manipur,
Khuyathong Imphal 795001
3.
4.
The Executive Engineer, Monitoring & Quality Control Division PWD, Manipur
State Bank Of India, Through Manager SAMB II, 1 Middleton Street,
Kolkata-7000071
… Respondents
[3]
Arbitration P(J2) No.3 of 2019
M/s Simplex Projects Ltd. Through its Director
19, Nellie Sengupta Sarani 3rd Floor, Kolkata 700087
- Versus –
1.
2.
3.
4.
... Petitioner
State of Manipur , through Chief Secretary, Secretariat, Manipur.
Public Works Department Through its Chief Engineer Manipur,
Khuyathong Imphal 795001
The Executive Engineer Division NO.I PWD, Manipur, Khuyathong
Imphal 795001.
The Executive Engineer, Monitoring & Quality Control Division PWD,
Manipur
… Respondents
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 1
BEFORE
HON'BLE THE CHIEF JUSTICE MR. RAMALINGAM SUDHAKAR
For the Petitioner ∷ Shri S.D.Singh,Advocate
In all petitions
For the respondents ∷ Shri N.Kumarjit, AG
Date of judgment and order
∷ 23.01.2020
O R D E R (CAV)
[1]
The prayers in the three Arbitration petitions are as follows:―I. Prayer in Arb. P(J2) No.1 of 2019
(a)
Stay the operation of the letter No EE/ B.D.-I/ Tombisena/ 1819/524 dated 5.10.2019 issued by the Respondent no.3 whereby
invoked the Bank Guarantees (i) Bank Guarantee No.11640100002263
dated 19.2.2014 for a sum of Rs.27,77,000/- and (ii) Bank Guarantee
No.11640100002462 dated 24.5.2014 for a sum for Rs.1,98,33,700/-.
(b)
Restrain the Respondent no.4 from encashing the Bank
Guarantees (i) Bank Guarantee No.11640100002263 dated 19.2.2014
for a sum of Rs.27,77, 000/- and (ii) Bank Guarantee No.
11640100002462 dated 24.5.2014 for a sum of Rs.1,98,33,700/-,
(c)
issue directions to the Respondents to make the payment of
Rs. 1,25,00,000/- as admitted by them in the letter dated 3.6.2017 as till
date it has not been paid to the Petitioner herein.
(d)
Further new bills of the 4th RA bill and the extra work bill
submitted by the respondent to be certified and paid as per the
certification.
(e)
issue directions to the Respondent no.1 to 3 to make the
arrangement of the funds and other resources so that the works can
be recommenced and completed and the Respondents, the
Respondents are in position to release the payment from time to time,
before the recommencement.
(f)
issue direction to the govt. of India (urban development) and
the Mahud department (PWD nodal agency executing the works) as
per the letter 3.6.2017 & 19.6.2017 to make the budgetary allocation
before the commencement of this work. This is required as presently
there is no sanction of the budget as per the own admission of the
department for ht sum of Rs. 34.00 crore required as per the department
letter to complete the works.
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 2
(g)
issue directions to the Respondents to provide all the drawings,
designs etc and to make the entire land/site encumbrances free for
execution of the works and provide security during the course of
execution of the works. (Referred to their letter dated admitting the
contents above 3rd June 2017)
(h)
Restrain the Respondent no.1 to 3 from taking any coercive
action against the Petitioner and from creating any hindrances in the
smooth execution of the works as per the terms and conditions of the
contract;
(i)
Pass such and further order(s) as this Hon’ble Court may
deem fit and proper in the facts and circumstance of the present case.”
II. Prayer in Arb. P(J2) No.2 of 2019
(a) Stay the operation of the letter No. EE/ MQCD/CORR/2019-20/102
dated 23.09.2019 issued by the Respondent no 3 whereby invoked
the Bank Guarantee 0750215BG0000002 dated 1.1.2015 for a sum
of Rs. 6,03,43,14-66.00 and other
subsequent
letter dated
16.10.2019 and 6.11.2019,
(b) Restrain the Respondent no 4 from encashing the bank guarantee
0750215BG000002 dated 1.1.2015 for a sum of Rs. 6,03,43, 166.00,
(c) Restrain the Respondent no 1 to 3 from taking any coercive action
against the petitioner and from creating any hindrances in the smooth
execution of the works as per the terms and conditions of the
contract,
(d) Pass such and further order(s) as this Hon’ble court may deem fit
and proper in the facts and circumstances of the 789 present case.”
(iii)
―Prayer in Arb. P(J2) No.3 of 2019
a) set aside the impugned order dated 7.10.2019 passed by the
Respondent No.3 and operation thereof be stayed by this Hon’ble
Court during the pendency of present petition.
b) issue directions to the Respondent to take decision relating to the
extension sought for by the Petitioner to complete the work/ project
and grant the extension of time to the Petitioner to execute the work
as sought for up-to 30.6.2020;
c) Issue
directions for considering
the representation
dated
17.10.2019 sent by the Petitioner to the Respondent;
d) Issue directions to the Respondent to supply all the drawings for
balance work forthwith as per the terms of the MOU2 signed
5.7.2017 and as per annexure 4 to the representation dated
17.10.2019 between the respondent and the petitioner, so that the
work programme can be submit for execution of the works and
further to take decision relating to the funds by approving the CDA
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 3
and permit to Petitioner to raise the monthly Bill on recording of the
works executed in the measurement books and the payment be made
timely to the Petitioner as per terms and conditions of the contract
clause 7 of the GCC.
e) Issue directions to the Respondents to take decisions which are
required under the contract for execution of the works and permit the
petitioner to continue with the execution of works during the pendency
of present matter.
f) Restrain the Respondents from taking any coercive action against
the petitioner pertaining the Bank Guarantee a submitted and taking
any steps for re-inviting tender for the project known “IT-SEZ” Imphal
(Manipur).
g) Release of the payment to the petitioner for the bills submitted to the
petitioner.”
[2]
These three petitions are filed under section 9 of the Arbitration and
Conciliation Act, 1996. The petitioner seeks an interim order to protect its right
against the respondent State alleging that the Bank Guarantee furnished towards
EMD and performance guarantee is to be enforced contrary to law and against the
principle of fair play. It is further alleged that the respondents are acting arbitrarily
in violation of the terms and conditions of the Contract and therefore, the petition is
filed for interim protection invoking section 9 of the Arbitration and Conciliation Act,
1996. There are other reliefs in the nature of direction for release of funds. Notice
was taken by respondents on 11.11.2019. The case was not admitted. The
respondent raised a preliminary objection on maintainability.
[3]
The facts in Arbitration P.(J2) No.1 of 2019 as pleaded by the
petitioner are that the second respondent, Public Works Department is the nodal
agency for execution of certain works. The respondents invited tender on 7.2.2014
for execution of works known as ―Construction of Tombisana Market for
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 4
Rehabilitation of Women Vendors at Khwairamband Bazar, Imphal. The petitioner
participated in the bid which was two cover bid and the petitioner was declared to
be technically suitable bidder and was accepted and the financial bid was also
accepted. Consequently, the petitioner was directed to submit Bank Guarantee
towards the earnest money deposit and as required by the terms of contract, Bank
Guarantee dated 19.02.2014 was submitted for Rs.27,77,000/- which was
forwarded to the respondents vide letter dated 19.02.2014. The Bank Guarantee
was towards earnest money deposit to be returned after execution of the
agreement and submission of Performance Guarantee on commencing of the work
in accordance with terms and conditions of the contract. The respondents do not
have the unfettered right to encash the Bank Guarantee. The respondents issued
the letter of intent dated 4.3.2014 signed by the respondent No.3 and the
petitioner’s bid was accepted and the value of the contract was specified as
Rs.39,66,72,501/-. The period of completion was shown as 24 months. Thereafter,
series of correspondences ensued between the petitioner
and the respondents.
The petitioner also submitted another Bank Guarantee dated 24.5.2014 for a sum
of Rs.1,98,33,700/- being 5% of the contract value. M/s Axis Bank issued the Bank
Guarantee towards the performance which was submitted to the respondents. One
issue of dispute that arose between the party is relating to mobilisation advance on
the basis of the Bank Guarantee furnished. The allegation of the petitioner is that
the respondents committed delay in releasing the mobilisation advance despite
submission of Bank Guarantee resulting in delay in execution of work adversely
affecting the petitioner besides mulcting them with interest. The difficulty of the
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 5
petitioner also mounted because of the various law and order situations in Manipur.
The petitioner relied upon various correspondences between the petitioner and the
respondents on various difficulties they have in executing the project and non-cooperation of the respondent department. These details are factual in nature and
not very relevant for the present dispensation in view of the preliminary issue raised
by the respondent State.
The Bank Guarantee and Performance
Guarantee were extended
from time to time. Various correspondences are relied upon by the petitioner to
plead that the delay was not on account of the petitioner but inaction on the part of
the respondents. The petitioner also refutes the allegation made in the letters of
the respondent where the petitioner is alleged to have not complied with the terms
of the contract and delayed the project. The cause of action for filing these
petitions after a series of correspondences relating to complaint against each other
appears to be the letter written by the respondent to the Bank seeking to encash
the Bank Guarantee . The petitioner submits that two Bank Guarantee have been
encashed. It is pleaded that Bank Guarantees have been encashed without any
justification and contrary to the terms and conditions of the Bank Guarantee. While
on one hand, the respondents by the letter dated 20.9.2018, sought for extension
of the Bank Guarantee upto 15.10.2018, they changed
their mind to invoke Bank
Guarantee which shows their arbitrary conduct. The petitioners specific plea is at
para No.89 and 90 which read as under:―89.
That it is submitted that all four ingredients for grant of the reliefs in
the present matter qua the Bank Guarantees i.e. special equities, irretrievable
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 6
injury – injustice, fraud and non invocation of the Bank Guarantee in terms of
Bank Guarantee itself which is conditional are made out in the present matter
for the grant of reliefs as sought for. It is submitted that irreparable injury would
be caused to the Petitioner in case the Respondent are permitted to invoke and
encash the Bank Guarantee, the invocation is palpably bad and it shows the
bad intention of the Respondent.
90.
That the petitioner submits that the Respondents are State
instrumentality and they cannot be permitted to act arbitrarily, illegally in order to
cause prejudice to the Petitioner herein. It is settled position of law that the
arbitrary action on the part of the Respondent authority even in contractual
matter would lead to the violation of the article 14 of the Constitution of India.
The Petitioner would like to submit before this Hon’ble Court that the facts of the
present matter are sufficient to establish that the Respondents are not acting
fairly and they cannot be permitted to take unreasonable action against the
Petitioner and would cause a serious prejudice to their legal rights.”
[4]
The case of the petitioner in the Arbitration P. (J2) No.2 of 2019 is
that the present petition has been filed against the illegal action of the respondents
as the respondent no.3 herein without any cause of action and justification issued a
letter dated 23.09.2019 to respondent no.4 for invocation of Bank Guarantee
towards the mobilization advance for sum of Rs 6,03,43,166.00 being Bank
Guarantee no. 0750215BG0000002 dated 01.01.2015 valid upto 31.12.2015 from
the State Bank of India. It is submitted that the said invocation by the respondent
no.3 is contrary to the law as laid down by the Hon'ble Supreme Court in (1999) 8
SCC 436; Hindustan Construction Company Ltd. Vs. State of Bihar and
others and also to the terms and condition of the said Bank Guarantee and as such
the invocation of the same is per se illegal.
That the said letter dated 23.03.2019 only came to notice of the
petitioner
on
18.10.2019.
It
is
submitted
that
the
bank
guarantee
of
Rs.6,03,43,166/- was furnished towards the mobilisation advance, could be invoked
and encashed only on arising of the contingencies as stipulated in the Bank
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 7
Guarantee itself. The stipulations of the Bank Guarantee would also disclose that
the bank guarantee is conditional. The letter dated 23.09.2019 would also show
that Bank Guarantees have been invoked and the conditions as prescribed in the
bank guarantees have not been fulfilled. Therefore the invocation of the bank
guarantees is per se illegal and cannot be entertained. The decision of the Hon'ble
Supreme Court in Hindustan construction Ltd. versus State of Bihar (supra)
is squarely applicable.
It is further pleaded that the invocation letter 23.09.2019 would make
it clear that the invocation is totally bad and it has not been done in the terms of
the bank guarantee and as such the invocation is totally bad in law and cannot be
acted upon. For all the reasons, the letter dated 23.09.2019 issued by the
Respondent No.3 invoking the bank guarantees needs to be quashed. The
mobilisation advance bank guarantee cannot be encashed as the amount got
recovered as per the R.A. Bills raised.
Learned counsel for the petitioner submits that the reliefs as sought
for in the present case clearly fall within the ambit of section 9 of the Act and as
such the petitioner is filing the present petition invoking the jurisdiction of this
Hon'ble Court for granting the reliefs as prayed for in the present case.
[5]
The case of the petitioner in Arbitration P.(J2) No.3 of 2019 is that in
terms of the letter dated 7.10.2019 at page No. 273 and 274 issued by the
Executive Engineer, Monitoring & Quality Control Division, PWD, Manipur, the
Respondent No.4 herein had issued a letter dated 7.10.2019 purportedly under
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 8
clause 3 of the agreement/ and arrived at conclusion that as the Petitioner haş
failed to execute the works. Along with the said letter annexure-1 has been
enclosed and in the said Annexure-1, the reasons on various points have been
narrated. The impugned letter dated 7th October, 2019 at page No.273 and 274 is
extracted as below:―GOVERNENMENT OF MANIPUR
PUBLIC WORKS DEPARTMENT
----No. EE/MQCD/CORR/2019-20/95
Imphal, the 7th Oct. 2019
To
M/S Simplex Projects Limited,
12/1, Nellie Sengupta Sarani,
Kolkata- 700087
Subject-
Notice on Final action under clause 3 of the agreement
For the work “Setting up of IT-SEZ building-I"
Reference:
1. Agreement no. - 6/EE/M&QCD/14-15/SE
2. Work Order No. EE/MQCD/WO/6 dt 22/12/2014
3. Notices: i) EE/MQCD/IT-SEZ/2014-15/94 dt.21/9/2015
ii) EE/MQCD/IT-SEZ/2014-15/19 dt. 27/4/2016)
iii) EE/MQCD/IT-SEZ/2014-15/125 dt. 8/8/2016
iv) EE/MQCD/IT-SEZ/2016-17/191 dt.11/2/2017
v) EE/MQCD/IT-SEZ/2017-18/240 dt. 11/4/2017
vi) EE/MQCD/IT-SEZ/2017-18/103 dt. 24/8/201/
vil) EE/MQCD/IT-SEZ/2017-18/146 dt. 26/10/2017
viii) EE/MQCD/IT-SEZ/2017-18/174 dt. 27/11/2017
ix) EE/MQCD/IT-SEZ/2017-18/199 dt. 22/12/2017
x) EE/MQCD/IT-SEZ/2018-19/37 dt. 25/05/2018
xi) EE/MQCD/Corr/2018-19/17 dt. 22/04/2019
xii) EE/MQCD/Corr/2019-20/78 dt. 18/09/2019
4. MOU dt 04/11/2015
5. MOU-2 dt 05/07/2017
Dear Sir,
Whereas under Clause 3 of the aforesaid agreement the Engineer-in-Charge
shall have powers to take action under clause 3 in the event of delay or
suspension in the execution of the aforesaid work by the contractor so that in the
opinion of the Engineer-in-Charge (which shall be final and binding) the contractor
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 9
have already failed to complete the work by the extended date of completion,
whereas you have delayed/suspended the execution of the aforesaid work and as
per the opinion of the undersigned, the Engineer-in-Charge (which is final and
binding), you have already failed to complete the work by the extended date of
completion, and whereas you were served with show cause in this regard under
this office no. EE/MQCD/Corr/2019-20/78 dt. 18/09/2019 but your reply vide letter
no. .SPL/C-274 (Civil Secretariat)/196/19-20 dt. 25/09/2019 received in response
to show cause has been considered carefully but not found to the satisfaction of
the Engineer-in-charge. The reasons for not accepting the reply are place in Parawise in the enclosed Annexure-I
Therefore under powers delegated to me under sub-clause 3(a) & 3(b), I,
Shri Ch. Uttam Singh, the Engineer-in-Charge for the aforesaid work under the
aforesaid agreement, for and on behalf of the Governor of Manipur, hereby
(i)
Determine the contract as aforesaid upon which determination yours earnest
money deposit, security deposit already recovered, Performance Guarantee and
the Bank Guarantee Bond against Mobilization advance stand absolutely forfeited
to the Government and shall be absolutely at the disposal of Government, and
(ii) Take out such part of the work out of your hand, as remains unexecuted, for
giving it to another contractor to complete the work, and you shall have no claim to
compensation for any loss sustained by you by reasons of your having purchased
or procured any materials or entered into any engagement or made any advances
on account of or with a view to the execution of the work or the performance of the
contract. You are also hereby served with notice to the effect that the work
executed by you will be measured up on 15/10/2019 for which you are asked to
attend tor Joint measurement failing which the work will be measured, by the
department unilaterally in your absence and result of measurement will be final
and will be binding on you.
(iii) You shall not be allowed to participate in the tendering process for the
balance work.
This is without prejudice to Government's right to take action under any other
clauses or sub-clauses of the agreement and to realize Government dues and
losses and damages whatsoever under such clauses or sub-clauses.
Yours faithfully,
Sd/(Ch. Uttam Singh)
Executive Engineer
Monitoring & Quality Control Division
PWD, Manipur
---Endt No. No. EE/MOCD/CORR/2018-19/ Imphal, the 7th Oct 2019
Copy to
1.
The Chief Engineer (Bldg), PWD, Manipur
2.
The Addl. Chief Engineer - II, PWD, Manipur
3.
The Superintending Engineer-l, PWD, Manipur
4.
The Superintending Engineer (Electrical), PWD, Manipur
5.
The Executive Engineer, Electrical Division No.I 1, PWD, Manipur
6.
The file
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 10
(Ch. Uttam Singh)
Executive Engineer
Monitoring & Quality Control Division
PWD, Manipur”
Mere perusal of the said annexure would make it clear that the
Respondents are totally unjustified in saying that there was no inaccessibility to the
site or it was responsibility of the Petitioner to get road constructed for
accessibilities of the site. The Respondents relied upon the issuance of drawings
along with the letter dated 20.10.2016 and 20.01.2017, by overlooking the fact that
after the said letter various communications have been sent and even mentioned in
the Memo of Understanding-2 dated 5.7.2017 as a pre-condition to execute the
works to supply the entire drawings by 31.7.2017 and it is not the case of the
Respondents that the Respondents have ever supplied the drawings by the
aforesaid date. The Respondents by virtue of the aforesaid letter had determined
the contract and thereby they intended to communicate to the Petitioner that all the
amount pertaining to the earnest money, security deposit, performance guarantee
and Bank Guarantee towards mobilization advance stand absolutely forfeited to the
Government and would be at the disposal of the Government. The further
stipulation has been made in the said letter that as the Petitioner would not be
permitted to participate in tendering process of balance work
It would also be relevant here to mention that although the
respondent has relied on the 2(two) letters dated 20.10.2016 and 20.1.2017, the
respondent has kept silent on the letters written by the petitioner for the mentioned
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 11
subject of the non receipt of drawings & decisions pending pertaining to technical
issues till date.
That the Petitioner herein was surprised to receive the aforesaid letter
from the Respondents as the issuance of said letter for coercive action was totally
unjustified and it came to be issued dehors
the terms and conditions of the
contract as well as true and correct facts relating to the non-completion of works
and completion of the project, accordingly the Petitioner herein has sent a
communication dated 17.10.2019 to the Respondents and pointed out all the
relevant facts relating to the failure on the part of Respondents to perform their
contractual obligation on various fronts including the non-supply of drawings, nonaccessibility to the site. The Petitioner also relied upon various communications as
sent earlier and mentioned in the present petition also and made it clear that it is
the Respondents who are responsible for delay and for non-completion of project.
The Petitioner herein had made it clear that the Petitioner would complete the 75%
of leftover work by 21.3.2020 and 100% work would be completed on 30.6.2020. It
is submitted that there is no escalation clause and the execution of works by the
Petitioner, particularly when there is no dispute relating to the quality of works
executed by the petitioner and the petitioner is tested contractor throughout, it
would be in the interest of public and project itself that the Respondents should not
get enter into the area of inviting the tender from new contractor and waste 3-4
months on such issues and thereafter to fix up the date for completion of project
beyond the period as requested by the Petitioner vide letter dated 17.10.2019 for
the completion of the project.
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 12
That the said letter would make it clear that the Petitioner herein had
bifurcated the value of works which remained to have been executed and then
mentioned the facts for non-availability of the drawings vis-à-vis the balance works
pending and mere perusal thereof would make it clear that the percentage of works
as left over would be about 60% and the drawings out of 60% work left over, the
drawings pertaining to 48 % are still not available.
[6]
The petitioner pleaded that they are willing to complete the work and
also seek protection of Court to restrain respondents from enforcing the Bank
Guarantee. The petitioner pleads that if the Bank Guarantee is invoked, it will
jeopardise their interest. Hence, these petitions under section 9 of the Act have
been filed before this Court. It was taken up for hearing on 11.11.2019 and
adjourned to 12.11.2019. A preliminary objection was raised by the learned
Advocate General and the following statement was recorded in the common order
dated 13.11.2019 passed in all the three cases as extracted below:―13.11.2019
IN THE HIGH COURT OF MANIPUR
AT IMPHAL
Arb. P. (J2) No. 1 of 2019 With
Arb. P (J2) No. 2 of 2019 With
Arb. P. (J2) No. 3 of 2019
M/S. Simplex Projects Ltd.
State of Manipur & Ors.
Arb.P.(J2) No.1, 2 and 3 of 2019
- Versus –
……. Petitioner
…. Respondents
Page 13
BEFORE
HON’BLE THE CHIEF JUSTICE MR. RAMALINGAM SUDHAKAR
13.11.2019
[1]
Mr. S.D. Singh, learned counsel appears for the petitioner. Mr. R.K.
Umakanta, learned Government Advocate states that he will appear on behalf of
the State in all the cases and assist Mr. N. Kumarjit, learned Advocate General in
all these matters.
[2]
There is preliminary objection raised by the State referring to Section
9 read with Section 2(1)(e) of the Arbitration and Conciliation Act, 1996. It is
pleaded that the High court of Manipur does not have original jurisdiction.
Therefore, the arbitration petitions are not maintainable.
[A]
Section 9 of the Arbitration and Conciliation Act, 1996 reads as
follows:-
―9. Interim measures, etc., by Court.—(1) A party may, before or
during arbitral proceedings or at any time after the making of the
arbitral award but before it is enforced in accordance with section 36,
apply to a court:(i) for the appointment of a guardian for a minor or a person of
unsound mind for the purposes of arbitral proceedings; or
(ii) for an interim measure of protection in respect of any of the
following matters, namely:—
(a) the preservation, interim custody or sale of any goods
which are the subject-matter of the arbitration agreement;
(b) securing the amount in dispute in the arbitration;
(c) the detention, preservation or inspection of any property
or thing which is the subject-matter of the dispute in arbitration,
or as to which any question may arise therein and authorising for
any of the aforesaid purposes any person to enter upon any land
or building in the possession of any party, or authorising any
samples to be taken or any observation to be made, or
experiment to be tried, which may be necessary or expedient for
the purpose of obtaining full information or evidence;
(d) interim injunction or the appointment of a receiver;
(e) such other interim measure of protection as may appear
to the court to be just and convenient, and the Court shall have
the same power for making orders as it has for the purpose of,
and in relation to, any proceedings before it.
(2) Where, before the commencement of the arbitral proceedings, a
Court passes an order for any interim measure of protection under
sub-section (1), the arbitral proceedings shall be commenced within a
period of ninety days from the date of such order or within such
further time as the Court may determine.
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 14
(3) Once the arbitral tribunal has been constituted, the Court shall not
entertain an application under sub-section (1), unless the Court finds
the circumstances exist which may not render the remedy provided
under section 17 efficacious]
[B]
Section 2(1) (e) of the Arbitration and Conciliation Act, 1996 reads
as follows :
(i) in the case of an arbitration other than international
commercial arbitration, the principal Civil Court of original jurisdiction
in a district, and includes the High Court in exercise of its ordinary
original civil jurisdiction having jurisdiction to decide the questions
forming the subject-matter of the arbitration if the same had been the
subject-matter of a suit, but does not include any Civil Court of a
grade inferior to such Principal Civil Court, or any Court of Small
Causes;
(ii) in the case of international commercial arbitration, the High Court
in exercise of its ordinary original civil jurisdiction, having jurisdiction
to decide the questions forming the subject-matter of the arbitration if
the same had been the subject-matter of a suit, and in other cases, a
High Court having jurisdiction to hear appeals from decrees of Courts
subordinate to that High Court.
[3]
Learned counsel for the State refers to APPENDIX – 15 of the High
Court of Manipur Rules, 2019, which provides only for appointment of Arbitrator by
the Chief Justice of the High Court of Manipur, and not for entertaining an
application under Section 9 of the Arbitration and Conciliation act, 1996. He
pleaded that this High Court has no jurisdiction to entertain the petition as it is not
a Court within the meaning of Section 2(1)(e) of the Arbitration and Conciliation
Act, 1996.
In this regard, it will be useful to refer to Appendix-15 of the High
Court of Manipur Rules, 2019 which is as follows:-
APPENDIX – 15
APPOINTMENT OF ARBITRATOR BY THE CHIEF JUSTICE OF
THE HIGH COURT OF MANIPUR SCHEME, 2019
THE HIGH COURT OF MANIPUR AT IMPHAL
In exercise of the powers conferred on the Chief Justice of the
High Court of Manipur under sub-Section (10) of Section 11 of the
Arbitration and Conciliation Act, 1996, I hereby make the following
scheme :
1. Short title: This scheme may be called the Appointment of
Arbitrators by the Chief Justice of the High Court of Manipur Scheme,
2019.‖
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 15
[4]
Mr. S.D. Singh, learned counsel appearing for the petitioner seeks
some time to argue on the objection on the maintainability of the petition. Pleading
that the petitioner is facing extreme hardship consequent to the enforcement of
the Bank Guarantee, he stated that to prove the petitioner bonafide, a letter of
Bank of Baroda addressed to Axis Bank dated 15.06.2019 for extending the Bank
Guarantee in favour of the respondents upto 31.12.2019 in all the three cases
totaling to a sum of Rs. 6,30,15,836/- is available. The learned counsel undertakes
to produce the extended Bank guarantee issued by Axis Bank on or before
20.11.2019. He, therefore, pleaded that respondents should refrain from enforcing
the Bank guarantee till then or until orders of this Court.
[5]
On the preliminary issue, both sides will be heard on the next
hearing date or thereafter. In so far as enforcement of the Bank guarantee is
concerned, respondents are agreeable to keep the issue in abeyance subject to the
plea of non-maintainability of the petition as a preliminary issue, and that too only
till the next date of effective hearing.
[6]
In view of the above, list the matter on 20.11.2019 so as to enable
the petitioner in all the three cases to produce the extended bank guarantee valid
upto 31.12.2019 or later as per Bank of Baroda’s letter dated 15.06.2019 and its
Annexure issued in favour of the respondents.
[7]
The respondents undertaking, not to enforce bank the guarantee till
20.11.2019 is recorded, subject to the petitioner furnishing the extended Bank
guarantee.
[8]
At the request, list the matter on 20.11.2019.
CHIEF JUSTICE
Sandeep‖
[7]
Thereafter, the case was adjourned to 20.11.2019 at the request of
Mr.S.D.Singh to furnish the Bank Guarantee which, however, was not furnished as
undertaken and therefore, on 20.11.2019, the following order was passed:―20.11.2019
Ms. Binarani, learned advocate appears on behalf of Mr. T.
Sadananda, learned counsel for the petitioner and Mr. N. Kumarjit, learned
Advocate General, Manipur appears for the respondents assisted by Mr. R.K.
Umakanta, learned Government Advocate.
By order dated 13.11.2019 interim protection was granted to the
petitioners. Respondents were directed not to enforce the bank guarantee
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 16
subject to the petitioner furnishing an extended bank guarantee. Para No. 5, 6,
7 & 8 of the order dated 13.11.2019 read as follows :
“[5]
On the preliminary issue, both sides will be heard on the next
hearing date or thereafter. In so far as enforcement of the Bank guarantee is
concerned, respondents are agreeable to keep the issue in abeyance subject
to the plea of non-maintainability of the petition as a preliminary issue, and
that too only till the next date of effective hearing.
[6]
In view of the above, list the matter on 20.11.2019 so as to enable
the petitioner in all the three cases to produce the extended bank guarantee
valid upto 31.12.2019 or later as per Bank of Baroda’s letter dated 15.06.2019
and its Annexure issued in favour of the respondents.
[7]
The respondents undertaking, not to enforce bank the guarantee till
20.11.2019 is recorded, subject to the petitioner furnishing the extended Bank
guarantee.
[8]
At the request, list the matter on 20.11.2019.”
Today, when the matter is taken up, Ms. Binarani, learned advocate
states that Mr. T. Sadananda, learned counsel for the petitioner is not able to
appear in the matter and therefore, she seeks another date. She did not
produce the extended Bank guarantee as undertaken. Petitioners have failed to
comply with undertaking given.
In view of the specific order passed by this Court to furnish the
extended bank guarantee which has not been furnished or proof submitted,
there is breach. Hence, the embargo on respondents in the order dated
13.11.2019 stands vacated. Respondents are at liberty to proceed with their
claim in accordance with law.
At the request of the learned Advocate General and counsel
appearing on behalf of the petitioner, list the matter again on 03.12.2019.”
[8]
Thereafter, the case was taken up for hearing on the issue
of
maintainability and the counsel for either sides argued only on the issue of
maintainability.
[9]
Heard Mr.S.D.Singh, learned counsel for the petitioner in all the three
cases and Mr.N.Kumarjit, learned AG for the respondents.
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 17
[10]
LEGAL CONTENTIONS
Learned counsel for the petitioner relied upon the provisions of
Section 2 (1) (e), Sec. 9 and Sec. 42 of the Arbitration and Conciliation Act, 1996
which are as under:―2. Definitions.
(1) In this Part, unless the context otherwise requires,
******
******
(e) ―Court‖ means –
(i) In the case of an arbitration other than international commercial arbitration,
the principal Civil Court of original jurisdiction in a district, and includes the High
Court in exercise of its ordinary original civil jurisdiction, having jurisdiction to
decide the questions forming the subject-matter of the arbitration if the same
had been the subject-matter of a suit, but does not include any civil court of a
grade inferior to such principal Civil Court, or any Court of Small Causes;
(ii) In the case of international commercial arbitration, the High Court in
exercise of its ordinary original civil jurisdiction, having jurisdiction to decide the
questions forming the subject-matter of the arbitration if the same had been
the subject matter of a suit, and in other cases, a High Court having jurisdiction
to hear appeals from decrees of courts subordinate to that High Court.‖
*****
*****
*****
*****
―9. Interim measures etc. by Court.
(1) A party may, before, or during arbitral proceedings or at any time after the
making of the arbitral award but before it is enforced in accordance with section
36, apply to a Court –
(i) for the appointment of a guardian for a minor or person of unsound mind for
the purposes of arbitral proceedings; or
(ii) for an interim measure or protection in respect of any of the following
matters, namely:
(a) The preservation, interim custody or sale of any goods which are the
subject matter of the arbitration agreement;
(b) Securing the amount in dispute in the arbitration;
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 18
(c) The detention, preservation or inspection of any property or thing
which is the subject-matter of the dispute in arbitration, or as to which any
question may arise therein and authorising for any of the aforesaid purposes
any person to enter upon any land or building in the possession of any party, or
authorising any samples to be taken or any observation to be made, or
experiment to be tried, which may be necessary or expedient for the purpose of
obtaining full information or evidence;
(d) Interim injunction or the appointment of a receiver;
(e) Such other interim measure of protection as may appear to the Court
to be just and convenient,
and the Court shall have the same power for making orders as it has for the
purpose of, and in relation to, any proceedings before it.
(2) Where, before the commencement of the arbitral proceedings, a Court
passes an order for any interim measure of protection under sub-section (1),
the arbitral proceedings shall be commenced within a period of ninety days
from the date of such order or within such further time as the Court may
determine.
(3) Once the arbitral tribunal has been constituted, the Court shall not entertain
an application under sub-section (1), unless the Court finds that circumstances
exists which may not render remedy provided under Section 17 efficacious.‖
****
****
“42. Jurisdiction.- Notwithstanding anything contained elsewhere in this
Part or in any other law for the time being in force, where with respect to an
arbitration agreement any application under this Part has been made in a Court,
that Court alone shall have jurisdiction over the arbitral proceedings and all
subsequent applications arising out of that agreement and the arbitral
proceedings shall be made in that Court and in no other Court.‖
Referring to Section 2(1)(e), the petitioner’s counsel pleads that Court of
principal civil original jurisdiction in the district is the Court
for the purpose of
Section 9 application, however, Section 2(1)(e) also includes High Court in exercise
of its ordinary original civil jurisdiction. Hence, the High Court of Manipur is
competent to entertain Section 9 application and therefore, the application for
interim protection is justified. In terms of section 42, since an application was filed
by the same petitioner, on an earlier occasion on a different cause of action, the
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 19
High Court of Manipur has jurisdiction. He also refers to the contract dated 4th
March, 2014 and specifically to clause 13 wherein parties have agreed to the
jurisdiction of Manipur High Court. Hence, Section 9 application is maintainable. The
respondents have themselves agreed to the jurisdiction of this Court.
[11]
He also relied upon two decisions of the Hon’ble Supreme Court in
the cases of Adhunik Steels Ltd. Vs. Orissa Manganese and Minerals (P)
Ltd. reported in (2007) 7 SCC 125 and State of West Bengal and others vs.
Association Contractors reported in (2015) 1 SCC 32 to support the above
plea.
[12]
Learned Advocate General, Mr.N.Kumarjit opposes the Section 9
petitions stating that Sections 20 and 21 of the Manipur (Courts) Act, 1955(Act 56
of 1955) alone will apply and pleaded that a reading of Section 2(1)(e) of the
Arbitration and Conciliation Act, 1996 read with Manipur (Courts) Act, 1955 (Act 56
of 1955) and Section 15 of the Code of Civil Procedure,
the Court of original
jurisdiction to deal with cases in terms of Section 9 of the Arbitration and
Conciliation Act, 1996 and for granting any relief as an interim measure would be a
Civil Court of original jurisdiction at Manipur as provided under Manipur (Courts)
Act, 1955 (Act 56 of 1955). Sections 20 and 21 of the Manipur (Courts) Act,
1955(Act 56 of 1955) read as under:―20. District Court to be principal civil court of original
jurisdiction.- The district court shall be principal civil of original jurisdiction in
the district.
21.
Original jurisdiction of district courts.- Save as otherwise
provided by any other law for the time being in force, the district court, shall,
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 20
subject to the provisions of section 15 of the Code of Civil Procedure, 1908,
have original jurisdiction in all civil suits without limits as regards the value.‖
Section 15 of the Code of Civil Procedure reads as under:―15.
Court in which suits to be instituted. – Every suit shall be instituted in
the Court of the lowest grade competent to try it.‖
Hence, the petitions before the High Court is not maintainable as it will be without
jurisdiction.
[13]
It is further pleaded that the High Court of Manipur does not exercise
the power of ordinary original civil jurisdiction. The petitioner is, therefore, not
entitled to move this Court for such relief. Hence, the petitions should be dismissed.
The earlier application said to have been filed by the same petitioner was disposed
of as infructuous. No decision on merits was passed. In any event, it has no
relevance to the present case and the cause of action is different. The petitioner is
misreading all the provisions of Arbitration Act without referring the Manipur
(Courts) Act, 1955.
[14]
In the present case, the petitioner’s specific plea is that this Court has
got jurisdiction to hear Section 9 applications in view of the proceeding of the
respondent, Public Works Department dated 4th March,2014 accepting the tender
submitted by the petitioner on certain terms and conditions. The petitioner
specifically refers to clause 13 of the Public Works Department’s acceptance letter
dated 4.3.2014 at page No.72 which is quoted below:―GOVERNMENT OF MANIPUR
PUBLIC WORKS DEPARTMENT
No.EE/BD-I/Tombisana Market/2013-14/
To,
Arb.P.(J2) No.1, 2 and 3 of 2019
Imphal, the 4th March,2014
Page 21
M/S. Simplex Projects Ltd.
12/1/Nellie Sengupta Sarani,
Kolkata – 700 087
Subject:-
Ref:-
Letter of Intent for the work, ―Construction of Tombisana Market
for rehabilitation of Women Vendors at Khwairamband Bazar,
Imphal‖
Notice
Inviting
Dt.07.02.2014
E-tender
No.EE/BD-I/Tombisana
Market/2013:
Dear Sir (s)
Your tender for the work mentioned above has been accepted on behalf of
the Governor of Manipur at your negotiated tender amount of Rs.39,66,72,512.20 (Rupees
thirty nine crores sixty six lakhs seventy-two thousand five hundred twelve and point two
zero only) which is 5.02 % above the estimated cost of Rs.37,77,13,045/- (Rupees thirty
seven crores seventy-seven lakhs thirteen thousand and forty-five only).
****
***
****
***
13.
Jurisdiction of court in respect of any dispute cases shall be under High
Court of Manipur at Imphal.
****
****
Sd/(Kh.Randhir Singh)
Executive Engineer,
Building Division No.I, PWD, Manipur.‖
[15]
It is therefore pleaded by the petitioner that since the respondents
themselves had agreed that in respect of any dispute, the jurisdiction Court will be
the High Court of Manipur at Imphal, these applications are maintainable and
legally justified.
[16]
In the present case, the factual dispute apart, the primary objection is
on the maintainability of Section 9 application. A specific question was made to the
petitioner’s counsel, Shri S.D.Singh as to whether the High Court of Manipur
exercises ordinary original civil jurisdiction. He fairly stated that it does not exercise
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 22
ordinary original civil jurisdiction. If that be the case, a reading of Section 2(1)(e)
makes it clear that the principal Civil Court of original jurisdiction in the district
alone will have jurisdiction to entertain an application dealing with the subject
matter of the arbitration. The inclusion of the High Court is only when it exercises
ordinary original civil jurisdiction like in the case of
chartered High Courts like
Calcutta High Court, Bombay High Court, Madras High Court and such other High
Courts which by specific provision, exercise ordinary original civil jurisdiction. The
High Court of Manipur does not exercise ordinary original civil jurisdiction and
therefore, it is not a Court within the meaning of Section 2(1) (e) of the Arbitration
and Conciliation Act, 1996. As a result, Section 9 application is not maintainable
before this Court.
Section 42, which was relied upon by the learned counsel for the
petitioner, deals with jurisdiction of the Court in relation to any proceeding relating
to an arbitration agreement where an application has already been made in a Court
and that Court alone will have jurisdiction over the arbitral proceeding and
subsequent application arising out of the agreement. In the present case, there is
no application pending in respect of the arbitration agreement before this Court
prior to the filing of the present application. Hence, reference to Section 42 of the
Arbitration and Conciliation Act, 1996 is of no relevance and a misconception.
[17]
Learned Advocate General was correct in referring to Manipur (Courts)
Act, 1955 (Act 56 of 1955) where the definition of district Court is clearly stated to
be the Principal Court of civil original jurisdiction. A reading of Sec. 20 and Sec. 21
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 23
of the Manipur (Courts) Act, 1955 (Act 56 of 1955) which have been already
extracted above makes it very clear that district court alone has the power of
original civil jurisdiction and to entertain an application under Section 9 of the
Arbitration and Conciliation Act, 1996 in terms of Section 2(1)(e) of the Arbitration
and Conciliation Act.
[18]
In the case of Adhunik Steels Ltd. (supra), the affected party
already moved the district Court at Sundargarh under section 9 of the Act against
the opposite party to restrain them from terminating the contract. It is a case
relating to contract in respect of mines. The primary and core legal issue that was
considered in that case was what are the relevant parameters for grant of interim
relief under section 9 of the Arbitration and Conciliation Act, 1996. Para No.21 of
the said case is extracted as below:―21. It is true that the intention behind Section 9 of the Act is the issuance of
an order for preservation of the subject matter of an arbitration agreement.
According to learned counsel for Adhunik Steels, the subject matter of the
arbitration agreement in the case on hand, is the mining and lifting of ore by it
from the mines leased to O.M.M. Private Limited for a period of 10 years and its
attempted abrupt termination by O.M.M. Private Limited and the dispute before
the arbitrator would be the effect of the agreement and the right of O.M.M.
Private Limited to terminate it prematurely in the circumstances of the case. So
viewed, it was open to the court to pass an order by way of an interim measure
of protection that the existing arrangement under the contract should be
continued pending the resolution of the dispute by the arbitrator. May be, there
is some force in this submission made on behalf of the Adhunik Steels. But, at
the same time, whether an interim measure permitting Adhunik Steels to carry
on the mining operations, an extraordinary measure in itself in the face of the
attempted termination of the contract by O.M.M. Private Limited or the
termination of the contract by O.M.M. Private Limited, could be granted or not,
would again lead the court to a consideration of the classical rules for the grant
of such an interim measure. Whether an interim mandatory injunction could be
granted directing the continuance of the working of the contract, had to be
considered in the light of the well-settled principles in that behalf. Similarly,
whether the attempted termination could be restrained leaving the
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 24
consequences thereof vague would also be a question that might have to be
considered in the context of well settled principles for the grant of an
injunction. Therefore, on the whole, we feel that it would not be correct to say
that the power under Section 9 of the Act is totally independent of the well
known principles governing the grant of an interim injunction that generally
govern the courts in this connection. So viewed, we have necessarily to see
whether the High Court was justified in refusing the interim injunction on the
facts and in the circumstances of the case.‖
It did not deal with case of jurisdiction of the High Courts to entertain
an application under section 9, when it does not exercise ordinary original civil
jurisdiction. Hence, it is of no relevance.
[19]
In the case of State of West Bengal and others vs. Association
Contractors (supra), it is a reference by a Division Bench of the Hon’ble Supreme
Court and decided by a larger Bench of three judges. The scope of referral order is
as follows:-
"In this appeal, the question that arises for decision is which Court will have
the jurisdiction to entertain and decide an application under Section 34 of the
Arbitration and Conciliation Act, 1996 (hereinafter for short 'the Act')?‖
[20]
It was a case where Section 9 application was commenced before the
Calcutta High Court exercising ordinary original civil jurisdiction . It was a case
where before the arbitration award, Section 9 application was moved before the
Calcutta High Court exercising ordinary original civil jurisdiction and thereafter,
application under Section 34 of the Act was moved before the principal Civil Court
which came to be contested by the parties and on the interpretation of Section 2(1)
(e) and Section 42 of the Arbitration and Conciliation Act, 1996, the Hon’ble
Supreme Court interpreted the definition of the word ―Court‖ in Section 2(1)(e) with
reference to Section 42 of the Act. It will be useful to refer to the view of the
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 25
Hon’ble Supreme Court on the scope of definition of word ―Court‖ of
section
2(1)(e) in relation to Section 42 and which court is the competent Court under
section 2(1)(e). Para Nos.18 and 20 reads as under:―18. In contrast with applications moved under Section 8 and 11 of the Act,
applications moved under Section 9 are to the "court" as defined for the
passing of interim orders before or during arbitral proceedings or at any time
after the making of the arbitral Award but before its enforcement. In case an
application is made, as has been made in the present case, before a particular
court, Section 42 will apply to preclude the making of all subsequent
applications under Part-I to any court except the court to which an application
has been made under Section 9 of the Act.‖
(Emphasis supplied).
****
***
―20. As noted above, the definition of "court" in Section 2(1)(e) is materially
different from its predecessor contained in Section 2(c) of the 1940 Act. There
are a variety of reasons as to why the Supreme Court cannot possibly be
considered to be "court" within the meaning of Section 2(1)(e) even if it retains
seisin over the arbitral proceedings. Firstly, as noted above, the definition is
exhaustive and recognizes only one of two possible courts that could be "court"
for the purpose of Section 2(1)(e). Secondly, under the 1940 Act, the
expression "civil court" has been held to be wide enough to include an appellate
court and, therefore would include the Supreme Court as was held in the two
judgments aforementioned under the 1940 Act. Even though this proposition
itself is open to doubt, as the Supreme Court exercising jurisdiction under
Article 136 is not an ordinary Appellate Court, suffice it to say that even this
reason does not obtain under the present definition, which speaks of either the
Principal Civil Court or the High Court exercising original jurisdiction. Thirdly, if
an application would have to be preferred to the Supreme Court directly, the
appeal that is available so far as applications under Sections 9 and 34 are
concerned, provided for under Section 37 of the Act, would not be available.
Any further appeal to the Supreme Court under Article 136 would also not be
available. The only other argument that could possibly be made is that all
definition sections are subject to context to the contrary. The context of Section
42 does not in any manner lead to a conclusion that the word "court" in Section
42 should be construed otherwise than as defined. The context of Section 42 is
merely to see that one court alone shall have jurisdiction over all applications
with respect to arbitration agreements which context does not in any manner
enable the Supreme Court to become a "court" within the meaning of Section
42. It has aptly been stated that the rule of forum conveniens is expressly
excluded by section 42. See: JSW Steel Ltd. vs. Jindal Praxair Oxygen Co.Ltd.,
(2006) 11 SCC 521 at para 59. Section 42 is also markedly different from
Section 31(4) of the 1940 Act in that the expression "has been made in a court
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 26
competent to entertain it" does not find place in Section 42. This is for the
reason that, under Section 2(1)(e), the competent Court is fixed as the Principal
Civil Court exercising original jurisdiction or a High Court exercising original civil
jurisdiction, and no other court. For all these reasons, we hold that the
decisions under the 1940 Act would not obtain under the 1996 Act, and the
Supreme Court cannot be "court" for the purposes of Section 42.‖
(Emphasis supplied)
[21]
In para No.25 of the aforesaid judgement, it has been clearly held
that the definition of Section 2(1)(e) is exhaustive and specific in that only the
principal Court of civil original jurisdiction (i.e.) the district court and the High Court
exercising ordinary original civil jurisdiction alone will be the Court in terms of
Section 2(1)(e) and no other Court. Para No.25 reads as follows:―25. Our conclusions therefore on Section 2(1)(e) and Section 42 of the
Arbitration Act, 1996 are as follows:
(a) Section 2(1)(e) contains an exhaustive definition marking out only the
Principal Civil Court of original jurisdiction in a district or a High Court having
original civil jurisdiction in the State, and no other court as "court" for the
purpose of Part-I of the Arbitration Act, 1996.
****
****
****
****
(e) In no circumstances can the Supreme Court be "court" for the purposes of
Section 2(1)(e), and whether the Supreme Court does or does not retain seisin
after appointing an Arbitrator, applications will follow the first application made
before either a High Court having original jurisdiction in the State or a Principal
Civil court having original jurisdiction in the district as the case may be.
****
****
****
****
(g) If a first application is made to a court which is neither a Principal Court of
original jurisdiction in a district or a High Court exercising original jurisdiction in
a State, such application not being to a court as defined would be outside
Section 42. Also, an application made to a court without subject matter
jurisdiction would be outside Section 42. The reference is answered
accordingly.‖
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 27
As observed earlier, the High Court of Manipur does not exercise
ordinary original civil jurisdiction. The above clearly answers the
point in issue
against the petitioners.
[22]
Another plea made by the petitioner’s counsel that in respect of any
dispute, it will be the High Court of Manipur at Imphal which will have jurisdiction is
no ground to entertain this application under section 9 because the High Court of
Manipur does not exercise ordinary original civil jurisdiction for the reasons already
stated above. Manipur High Court does not fall within the definition of a Court in
terms of Section 2(1)(e) of the Arbitration Act. The parties cannot by agreement
bestow jurisdiction when under the provision of Section 2(1)(e), the High Court of
Manipur does not exercise ordinary original civil jurisdiction. The Hon'ble Supreme
Court in the case of Hakam Singh vs. M/s Gammon (India) Ltd.; 1971 (1)
SCC 286 held in para No.4 as under:―4.The Code of Civil Procedure in its entirety applies to proceedings under
the Arbitration Act. The jurisdiction of the Courts under the Arbitration Act to
entertain a proceeding for filing an award is accordingly governed by the
provisions of the Code of Civil Procedure. By Clause 13 of the agreement it was
expressly stipulated between the parties that the contract shall be deemed to
have been entered into by the parties concerned in the City of Bombay. In any
event the, respondent have their principal office in Bombay and they were liable
in respect of a cause of action- arising under the terms of the tender to be sued
in the Courts at Bombay. It is not open to the parties by agreement to confer
by their agreement jurisdiction on a Court which it does not possess under the
Code. But where two courts or more have under the Code of Civil Procedure
jurisdiction to try a suit or proceeding an agreement between the parties that
the dispute between them shall be tried in one of such Courts is not contrary to
public policy. Such an agreement does not contravene Section 28 of the
Contract Act.‖
(emphasis supplied)
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 28
The same principle applies to the Arbitration Act as well.
[23]
Accordingly,
the
objection
raised
by
the
respondents
on
maintainability is sustained and all the applications are rejected.
CHIEF JUSTICE
FR/NFR
Opendro(rt)
WAIKH Digitally
signed by
WAIKHOM
OM
TONEN MEITEI
TONEN Date:
2020.01.27
14:05:13
MEITEI +05'30'
Arb.P.(J2) No.1, 2 and 3 of 2019
Page 29
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review