* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 18 August 2026
Pronounced on: 16 September 2026
+
FAO (COMM) 119/2025
M/s. Shivani Handlooms (WCIS) Ltd.
..... Appellant
Through: Mr. Ashok Kumar Soni,
Ms.Priyanka Soni and KM. Sarita,
Advocates
Versus
UNION OF INDIA
..... Respondent
Through: Mr. Rohan Jaitley CGSC,
Mr.Dev Pratap Shahi, Mr Akshay
Sharma, Mr. Varun Pratap Singh and
Mr. Yogya Bhatia, Advocates
CORAM:
HON'BLE MR. JUSTICE C. HARI SHANKAR
HON'BLE MR. JUSTICE VINOD KUMAR
JUDGMENT
16.09.2026
%
VINOD KUMAR , J.
1. The present appeal preferred under Section 37 of
Arbitration and Conciliation Act, 1996 read with Section
13 (1A) of the Commercial Courts Act, 2015 has
challenged a judgment dated 10.02.2025 of learned District
Judge-03, Patiala House Courts, Delhi.
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 1
2. Vide the impugned judgment, learned District Judge had
allowed a petition ARBTN. No. 4499/2017 (filed by
respondent no.1 herein) raising objections under Section
34 of the Arbitration and Conciliation Act, 1996 and set
aside the Award dated 09.11.2011 passed by the Sole
Arbitrator.
3. For the sake of convenience, the appellant would also be
referred to as ‘claimant’ and respondent no.1 would be
referred to as ‘respondent’. Respondent no.2 is the Sole
Arbitrator and is not a party to the dispute.
DISPUTE
4. The claimant was awarded a contract by the respondentGovt. of India/Ministry of Defence for supply of 35897
blankets at various places including Pune. The Pune
consignment of 7660 blankets was rejected by the
respondent on the ground that it did not meet prescribed
specifications. Therefore, the same was taken back by the
claimant. But the respondent refused to make the payment
towards the remaining of consignments, which were sent
even to the places other than Pune. Hence, the dispute. As
per clause 24 of Rules of the Director General of Supplies
and Disposals (DGS&D) applicable to this contract, the
dispute was to be resolved through Arbitration. On an
application under Section 11 of the Arbitration and
Conciliation Act 1996, the Arbitrator was appointed, who
proceeded with the arbitration.
CLAIM PETITION
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 2
5. The case of the claimant, as per the Statement of Claim, is
that it is a Small Scale Industry covered under The Micro,
Small and Medium Enterprises Development Act, 2006.
The claimant was awarded a Rate Contract dated
24.01.2007 for the supply of blankets for the period from
12.01.2007 to 01.06.2009. The contract was subject to the
terms and conditions as contained in Director General of
Supplies and Disposals-156 (DGS&D – 156) and other
General and Special Conditions of Contract incorporated
therein, including the General Conditions of Contract
detailed in DGS&D - 68. Pursuant to the said Rate
Contract, the Director General Border Roads, Delhi Cantt.
issued a Supply Order dated 05.06.2008 for the supply of
35897 blankets at the rate of Rs.598/- per blanket, to be
delivered at various stations. According to the claimant,
advance samples were required to be approved before the
delivery. The claimant offered the advance samples on
16.06.2008, however, according to the claimant the
respondent did not inspect the same and returned the same
and vide communication dated 11.07.2008, asked the
claimant to resubmit the samples. The respondent also
changed the terms of inspection authority as stipulated in
the supply order.
6. In
another
communication
dated
17.07.2008,
the
respondent further informed the claimant that the samples
would be now approved by the Board of Officers at
Headquarter and called the claimant to furnish nine
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 3
samples. According to the claimant, the samples were
thereafter offered before the Board of Officers appointed
by the respondent and were approved by the Board.
Thereafter, upon issuance of the inspection notes, blankets
were dispatched to the different consignees specified under
the Supply Order.
7. As per the claimant, barring the consignment supplied to
the Pune, which was rejected on 31.01.2009, the remaining
supplies (i.e. 28327 blankets) were found to be in
conformity with the prescribed specification. For the entire
quantity of 28327 blankets, the purchasers released the
inspection notes. So far as the Pune consignment is
concerned, claimant submitted that the supply was made
according to the contractual terms and specifications, but
on account of the rejection by Pune Consignee, the
claimant lifted those blankets and did not raise any claim
and has also not received any payment towards the said
consignment.
8. The claimant furnished the following particulars of the
supplies made to different consignees, other than Pune
Consignee:
Sl.
No.
Consignee
department at
Number of Date
blankets
Delivery
of
1.
Pathankoat
09.07.2008
2.
Pathankoat
20.08.2008
3.
Hanumangarh
25.08.2008
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 4
4.
Chandigarh
18.09.2008
5.
Udhampur
15.10.2008
6.
Gauhati
04.11.2008
7.
Gauhati
29.11.2008
8.
Gauhati
04.01.2009
9.
Gauhati
11.02.2009
10.
Gauhati
14.02.2009
9. According to the claimant, the respondent had accepted
these goods and has also even released relevant documents
to claimant in token of acceptance of the goods. The same
were submitted to the respondent. The claimant submits
that by 31.03.2009, within the delivery schedule, it had
supplied the aforesaid 28327 blankets, the value of which
comes to Rs.1,71,61,653. Under the terms of the Supply
Order, the respondent was required to release 95% of the
payment was payable on proof of inspection and
submission of the provisional receipt of the consignee with
the balance 5% payable thereafter in accordance with the
contractual terms. However, according to the claimant the
respondent failed to make the payment of Rs.45,38,820
towards the said 95% payment outstanding amount and
withheld the balance 5% payment. Therefore, the
respondent committed a breach of the contractual terms by
failing to make payment in accordance.
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 5
10.As per claim petition, the respondent in a letter dated
25.05.2009 communicated to the claimant that the supplies
made since July 2008 till Feb 2009 had been rejected being
substandard and asked the claimant to replace the same.
11.The claimant further averred that by this period, the goods
already supplied were partly consumed by the respondent.
The claimant also questioned the storage condition of the
respondent. Further it was averred that the letter of the
respondent dated 25.05.2009 was not in accordance to the
terms of clause ‘c’ and ‘d’ of the Supply Order, under
which
consignments
were
rejected.
The
claimant,
therefore, made a claim for a sum of Rs. 45,38,820/-. The
claimant also prayed for further sum of Rs. 45 lacs as
compensation having been suffered due to breach of the
contract by the respondent.
12.The claimant calculated interest at the rate of 18% per
annum up to 14.01.2011 at Rs.15,58,050/- and, in addition,
also claimed the cost of Rs.1,50,000/-. Further, he claimed
interest at the rate of 18% per annum from the date of
award till realization.
13.Subsequently, by an application under Section 23(3) of the
Arbitration and Conciliation Act, 1996 the claimant sought
amendment of its monetary claim. It was stated that, upon
recalculation, the claimant had found that apart from
Rs.45,38,820/-, the balance 5% payment in respect of
supplies made to Pathankot, Hanumangarh and Chandigarh
had also remained unpaid. The claimant, therefore, sought
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 6
that its claim for the balance price be read as
Rs.48,14,747/- instead of Rs.45,38,820/-, thereby seeking
an additional amount of Rs.2,75,927/-.
STATEMENT OF OBJECTIONS i.e. REPLY AND
COUNTER CLAIMS BY RESPONDENT
14. The respondent contested the claim petition by filing a
Counter Statement/Objection and subsequently even filed
a reply to the rejoinder.
15.The case of the respondent, in short, is that they were made
to change the inspection clauses and the Inspecting Officer
and the inspection Authority due to refusal by the
inspecting authority specified in the contract to inspect it.
The respondent admits that after the amendment of the
inspection clause and the terms relating thereto, it was
agreed between the parties that the Board of Officers of
respondent would inspect the sample and the approved
sample would be sent to each of the consignee. According
to the respondent, the claimant did not make the supplies
as per the prescribed specifications. Therefore, the
consignment supplied to the Pune consignee was rejected
on 13.01.2009. As per the respondent, the claimant failed
to replace the rejected goods supplied to the Pune
consignee.
16.It was further averred that some complaints regarding the
goods supplied by the claimant, were received from
Central Vigilance Commission (in short CVC) and
thereafter, it was found that the supplies made by the
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 7
claimant were not as per the prescribed specifications. To
satisfy itself, the respondent also sent the samples to the
Border Roads Development Board (BRDB), which were
thereafter, transmitted to Ministry of Textile, New Delhi.
On test, it was found that the goods supplied by the
claimant were not meeting the prescribed specification.
The respondent, therefore, lodged a complaint with the
Economic Offence Wing and an FIR was also lodged.
According to the respondent, as the claimant had not made
the supplies as per terms of the Supply Order, the
respondent was entitled to reject the same in terms of
Clause (c) and (d) of Supply Order, which read as under:
“(c) Correctness of stores: The supplier, shall he
responsible for the correct supply of the stores being
ordered and shall replace the same free of cost if
found not conforming to the required specifications
or incomplete in anyway."
(d) Guarantee/Warranty:- The period of warranty
shall be 12 months from the date of supply of the
stores or from the date of use whichever is later. The
supplier shall be responsible for free replacement of
stores supplied which are notified as defective in
materials
specification/
workmanship
or
performance by the consignee/ Indenter. The
consignee Indenter will notify each defect within a
period not exceeding one month of receipt of stores
and the supplier will provide free replacement
within a period not exceeding one month of such
notification.”
17.It was further averred that a complaint was received in the
office of CVC from a firm named ‘Lybn’, pursuant to
which CVC issued a notice to the respondent. The
respondent, thereafter, took random samples in the absence
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 8
of the claimant and sent the same for testing. Out of the
three samples as tested by the Textile Committee, two
were found not to be meeting the prescribed specifications.
Thus, according to the respondent, the claimant had
supplied 28237 inferior quality blankets, thereby causing a
loss of Rs.66.06 lacs.
18.Countering the submission of the claimant that the goods
are deemed to have been accepted by the respondent by
using it, more specifically in view of the fact that it did not
specify as to out of which lot, the three samples were taken
out and found sub standard, the respondent averred that out
of the lots supplied to the different consignees, the samples
were drawn only from the consignment made to one
consignee only. Therefore, it was not necessary to file
evidence of samples taken from the other lots supplied by
the claimant.
19.On the basis of the aforesaid allegations, the respondent
also raised counter-claims against the claimant. The
respondent claimed liquidated damages at the rate of 5% of
the contract amount on the ground that the claimant had
failed to perform its contractual obligations within the
stipulated time. The respondent further claimed a sum of
Rs.66.01 lacs towards the alleged loss suffered by it on
account of the supply of blankets which, according to the
respondent, were of inferior quality and not in conformity
with the prescribed specifications. The respondent,
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 9
therefore, prayed for dismissal of the claims raised by the
claimant and for allowing its counter claims.
REJOINDER OF THE CLAIMANT TO THE REPLY
AND THE COUNTER CLAIMS MADE BY
RESPONDENT
20.In its rejoinder, the claimant reiterates that the supplies
were made only after the samples had been approved by
the Board of Officers and the goods had been inspected in
accordance with the amended inspection procedure. It is
submitted that, except for the consignment supplied to
Pune, the supplies had been accepted by the respective
consignees and the relevant inspection and receipt
documents had also been issued. The claimant disputes the
submission of the respondent that the supplies made by it
were not as per the contractual specifications.
21.The claimant further disputes the respondent's reliance
upon the subsequent complaints and testing of samples to
contend that all the supplies were defective. It is contended
that the respondent has not established that the samples
subsequently tested were representative of the entire
quantity supplied by the claimant. The claimant also
disputes the respondent's reliance upon the subsequent
investigation and test reports for rejecting the supplies
which had already been inspected and accepted.
22.The claimant, therefore, denies its liability to replace the
supplies or compensate the respondent for the alleged loss.
It is submitted that the respondent had wrongfully withheld
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 10
the outstanding payment despite acceptance of the
supplies. The claimant, therefore, reiterates its claim for
the unpaid amount, interest and other reliefs and prays for
dismissal of the objections and counter claims raised by
the respondent.
REPLY BY RESPONDENT TO REJOINDER
23.The respondent has admitted in their reply to the rejoinder
that the CVC had acted on some complaint from Lybn
International New Delhi who had alleged that the claimant
has supplied inferior quality of goods. The respondent also
conceded that they did not receive any complaint from any
of consignees except from Pune. On the objection of the
claimant that Ministry of Textile is not a part of the
Agency agreed between the parties to test the goods, the
submission of the respondent is that it does not make a
difference as there is no specific clause as to who would be
the testing authority and submitted that as the officials of
the authority named in the contract had refused to inspect
the samples, the respondent had to substitute Director
General
Border
Road
as
the
Inspection
agency
subsequently. Even they did not have scientific means to
test the samples. Therefore, the claimant took advantage of
it by not supplying blankets as per terms.
24.In regard to the acceptance of the goods by consignees, the
respondent averred that the same were accepted in good
faith and have laid much emphasis on the supply made to
Pune. The respondent has further pleaded that several
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 11
letters were written by it as well as by the consignee at
Pune to replace the stores already rejected but the claimant
did not replace nor made further balance supply.
The respondent has relied upon the letter dated 25.05.2009
and clause (c) & (d) of the Agreement terms. According to
the respondent, still the substantial quantity as supplied by
claimant is lying with them and the claimant has been
wrongfully paid and is not entitled for any amount.
AWARD IN NUTSHELL
25.After perusing the evidence led by the parties, learned
Arbitrator noted that the respondent had not denied the
short payment of the amount of Rs.45,38,820/- to the
claimant towards 95% of balance amount of blankets
supplied. Further the respondent has not denied quantity
and date of supply as specified in statement of claims.
Learned Arbitrator concluded that the consignments were
sent at 10 places, as specified in para 9 of the Statement of
Claims (also reproduced in para 8 of this judgment). The
consignee at Pune is not mentioned in this list as the
consignment was rejected by the respondent and claimant
had taken back the rejected goods and had not made any
claim in respect thereof. Therefore, it was held that the
claimant was entitled to the claimed amount as against the
10 consignments supplied on various dates, as specified in
para 9 of the Statement of Claims. On the counter claim of
the respondent, the Sole Arbitrator, while rejecting the
same, held as under:
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 12
“ON COUNTER CLAIMS OF THE RESPONDENT
The respondent has raised their counter claim by
giving calculation of hypothetical loss in blankets
procurement by HQ, DGBR by dividing it in the
following parts :a) loss due to less weight in blankets for 28237
number of blankets at Rs.42.21 lacs.
b) loss due to inferior quality i.e. less quantity of
wool claiming Rs. 598/- per blanket.
AWARD ON COUNTER
RESPONDENT
CLAIM
OF
THE
I have come to the conclusion that the rejection by
the respondent has been invalid and discuss the
same in detail while deciding the claim of the
claimant and therefore, the counter claim of the
respondent are rejected. It is also rejected for the
reason that burden to prove that there was less
weight in the blankets and net wool it was for the
respondent to prove. The respondent has not filed
any documentary evidence. The respondent also has
not filed any documentary evidence of the
conclusion has been arrived by average in price and
for each blanket which was not even tested. I have
discussed this issue while deciding claim No.1 of the
claimant and have mentioned several reasons to
reject it.
Moreover, the consumer has rather accepted the
goods and found it as per the terms of the contract
and therefore for all these reasons I reject the
counter claim of the respondent while
manufacturing the blankets there are several
elements including wool, quality of wool, labour,
capital invested, duties, electricity and other
elements the price being consolidated it was for the
respondent to prove that breakup and the market
price of it on the alleged date of breach. The
respondent has failed to file any documents in this
regard.”
26.Observing so, the Arbitrator awarded a sum of
Rs.45,38,820/- in favour of the claimant with interest at
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 13
18% per annum from 01.06.2009 till actual payment.
Arbitrator further awarded a sum of Rs.2,75,927/- towards
the balance 5% payment with interest at 18% from the date
of the Award till actual payment. The claimant’s claim
towards compensation was rejected and the counter claims
raised by the respondent were also rejected.
OBJECTIONS UNDER SECTION 34 OF THE
ARBITRATION AND CONCILIATION ACT
27.Union of India (respondent no.1 herein) filed objections
under Section 34 of the Arbitration and Conciliation Act,
1996 before learned District Judge, who held that there
was a specific clause in the contract that the claimant will
have to compensate the respondent if there is delay in
delivery of goods and that the taken back Pune
consignment was not replaced and therefore the appellant
violated conditions ‘c’ and ‘d’ of the Supply Order. Hence,
the respondent was entitled for damages in accordance
with the contractual terms.
28.Learned District Judge further held that since the Union of
India had raised a counter claim claiming compensation/
liquidated damages, the Arbitrator was under the duty to
render a finding on thereon. Holding that the Arbitrator
failed to do so, the whole award was held to be vitiated.
Consequently, learned District Judge set aside the
impugned award.
ANALYSIS OF RIVAL SUBMISSIONS OF THE
PARTIES IN APPEAL UNDER SECTION 37 OF THE
ARIBTRATION AND CONCILIATION ACT, 1996
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 14
29.As already stated, aggrieved by the said judgment of
learned District Judge, the claimant has filed this appeal
submitting that the jurisdiction of learned District Judge
was limited and there was no ground for setting aside a
well reasoned Award on a flimsy ground. Learned Counsel
for the appellant has drawn the attention of this Court that
the appellant’s claim is towards supplies to the consignees
on ten dates at different places and the same do not include
Pune. It is submitted that the appellant has raised no claim
against Pune consignment because the same had been
taken back by the appellant. However, it is submitted that
simply taking back the consignment does not mean that the
same were of inferior quality. Nor does it mean that
blankets supplied at other places were also substandard.
30.Learned Counsel for the respondent, on the other hand, has
drawn our attention to the counter claim of the respondent
– Union of India as filed before the Arbitrator. In this
counter claim, the counter claimant has prayed for
liquidated damages, which is 5% of the contract amount,
on account of failure to supply the stores in time. Further,
the counter claimant has calculated the losses incurred by
them. The calculations of the same were filed as Annexure
C/C ‘C’, as per which, the loss was calculated as Rs.66.01
lacs.
31.Learned Counsel for the respondent-Union of India has
defended the impugned judgment submitting that once a
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 15
counter claim has been filed and pressed, the Arbitrator
must render a finding on the same, which learned
Arbitrator failed to do resulting in vitiation of the entire
Award.
32.Before proceeding further, we may also clarify that there is
a discrepancy in the number of blankets stated to have
been supplied, as appearing in the statement of claims.
While at certain places the claimant has referred to the
quantity of blankets supplied, other than the Pune
consignment, as 28327, the table giving the details of
supplies furnished by the claimant itself in para 9 of the
Statement of Claims, in respect of the ten consignments
specified therein, aggregates to 28237 blankets. The
respondent has also proceeded on the basis of 28237
blankets in its objections and counter claim. The Arbitrator
while considering the claim as well as the counter claim,
has also proceeded with the quantity of 28237 blankets.
Therefore, for the purpose of the present analysis, we
proceed on the basis of 28237 blankets, being the quantity
borne out from the detailed table of supplies given in para
9 of the Statement of Claims, which reproduced in para 8
of this judgment.
33.Admittedly, the contract required that the appellant shall
supply 35897 blankets to respondent at various places as
per demands raised. The final date of delivery was
31.03.2009. The appellant made supplies of 28237
blankets at various places except Pune. At Pune, 7660
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 16
blankets were supplied, which were returned to the
appellant on the ground of being inferior in quality.
Indisputably, the appellant has not replaced the same. In
the impugned judgment, learned District Judge was of the
opinion that the appellant herein had failed to replace the
blankets at Pune within time and therefore, the Arbitrator
was required to render a finding on the respondent’s claim
for damages arising out of the Pune consignment. It is
noteworthy that the Sole Arbitrator did not discuss at all
the reason for not awarding the compensation for non
replacement of blankets within specified time at Pune. The
perusal of the impugned award, relevant portion of which
has already been reproduced by us, would reveal that while
dealing with the counter claim of the respondent, learned
Arbitrator adverted his whole attention to the supplies
made at the places other than Pune. However, he has not
spoken a word on the issue of the compensation/damages
for failing to replace the stores at Pune in time as per
agreement. We would like to mention that as per clause ‘c’
of the Supply Order (already reproduced in counter claim),
the appellant was required to replace the defective blankets
and as per clause ‘d’, such replacement should take place
within one month of notification of defects in blankets.
34.The Pune consignee had rejected the blankets on the
ground that the same were not as per specifications. The
appellant took back the rejected blankets but did not
supply a fresh lot. It is on this account, that the respondent
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 17
claimed compensation in the counter claim, which has not
been decided by learned Arbitrator. He rejected the
contention of respondents in respect of all other supplies
but unfortunately had remained silent in respect of the
compensation for non replacement at Pune in time. As
already stated, as per terms and conditions of the Supply
Order, the appellant was under a duty to replace the
blankets within stipulated period, which was not done.
Needless to say, learned Arbitrator was required to
determine the damages in respect of Pune supplies as per
clause ‘e (i)’ of the supply order which is reproduced as
under:
“ e (i) Liquidated Damages - If supplier fails in
performance of this contract within the time fixed
under this contract or any other extension thereof,
the supplier shall be liable to pay liquidated
damages, a sum equivalent to ½% (Half percent) of
the contract price of the item per week of such delay
or part thereof. The supplier liability for LD shall
not exceed 05% (Five percent) of the contract price
of the item delayed. If the delivery is delayed beyond
10 weeks, the purchaser may at his own option,
terminate the contract.”
35.In para 6 of the counter claim, the respondent has made a
claim for liquidated damages in accordance with the
aforesaid clause. We agree with the opinion of the learned
District Judge that the Arbitrator has failed to render a
finding on Pune supplies which were rejected by the
respondent. It is not enough to absolve appellant on the
ground that the appellant had taken back the blankets from
Pune. The appellant must also compensate the respondent
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 18
for failure to replace the blankets. This part of
compensation was missed by learned Arbitrator. Learned
Counsel for the appellant has argued that learned
Arbitrator has given a specific finding that the respondent
had not been able to prove that blankets were defective and
therefore, rejection of Pune consignment was also not valid
as there is nothing on record to show that Pune blankets
were defective. Consequently, it is argued by learned
Counsel for the appellant, there was no reason for
awarding compensation for Pune consignment on the
ground of defectiveness. We have considered this
submission of learned Counsel for the appellant. We make
it clear that an appeal under Section 37 of the Arbitration
and Conciliation Act, 1996 is not a stage, where the Court
can itself determine as to whether the Pune consignment
was inferior to specifications. It is the Arbitrator who was
required to determine the said issue. His finding on the
quality of blankets is only on the consignments other than
Pune. The question, therefore, required to be determined
was whether the rejection of the Pune consignment was
justified and if so, whether the appellant was required to
replace the blankets within stipulated time and was liable
for damages on account of failure to do so. Admittedly, the
replacement supply was not made by the appellant and
consequently,
the
respondent
is
entitled
to
the
compensation on that account.
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 19
36.The Pune consignment was rejected by the respondent on
the ground of inferior quality. The appellant took back the
same and raised no objection at that stage. It was for
learned Arbitrator to decide as to whether the act of
appellant to take back the rejected blankets amounted to
admission of Pune consignment being of inferior quality
and, if so, whether the respondent was entitled to any
damages on account of failure to replace the same.
37.Here we wanted to take a practical view and therefore gave
a thought to the possibility as to whether we can separate
Pune consignment from other consignments. However, we
find that it is not possible to bifurcate and separate the
issue of damages towards Pune supplies until the same is
determined by the Arbitrator. This observation is in view
of the fact that all the supplies including Pune arise out of
a single contract, even though the consignments were sent
at different dates and at different places.
38.Moreover, it is not possible for us to calculate the damages
towards the non replacement of the Pune supplies as we
cannot step into the shoes of Arbitrator and undertake the
exercise of determining the compensation, which the
Arbitrator has failed to determine. Further, such an
exercise would amount to modification of the Award. We
would like to refer to Gayatri Balasamy v. M/s. ISG
Novasoft Technologies Limited, (2025) 7 SCC 1, wherein
the Supreme Court, while dealing with the scope of power
of the Court to modify an arbitral award under Section 34
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 20
and 37 of the Arbitration and Conciliation Act, 1996 held
as under:
I.
II.
III.
IV.
“87. Accordingly, the questions of law referred to by
Gayatri Balasamy (supra) are answered by stating
that the Court has a limited power under Sections 34
and 37 of the 1996 Act to modify the arbitral award.
This limited power may be exercised under the
following circumstances:
when the award is severable, by severing the
“invalid” portion from the “valid” portion of the
award, as held in Part II of our Analysis.
by correcting any clerical, computational or
typographical errors which appear erroneous on the
face of the record, as held in Part IV and V of our
Analysis;
post award interest may be modified in some
circumstances as held in Part IX of our Analysis;
and/or
Article 142 of the Constitution applies, albeit, the
power must be exercised with great care and caution
and within the limits of the constitutional power as
outlined in Part XII of our Analysis”.
39.In the above decision, while considering the question of
severability of an arbitral award, the Supreme Court also
referred to Section 34(2)(a)(iv) of Arbitration and
Conciliation Act, 1996 and held that “the proviso,
therefore, permits courts to sever the non-arbitrable ones.
This serves a two-fold purpose. First, it aligns with Section
16 of the 1996 Act, which affirms the principle of
kompetenz-kompetenz
–
that
is,
the
arbitrators’
competence to determine their own jurisdiction. Secondly,
it enables the court to sever and preserve the “valid”
part(s) of the award while setting aside the “invalid”
ones”.
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 21
40.In substance, the Supreme Court held that where the part
of award is severable, it can be set aside on the ground of
patent illegality and remaining part of award can be
upheld. However, in the instant case, the arbitrator was
required to determine the respondent’s claim for damages
arising out of the failure of the appellant to replace the
Pune consignment. On determination of compensation,
such amount could have been adjusted in the claim
awarded to the appellant. Therefore, as it is not possible to
sever the issue of compensation for violation of terms of
the contract towards Pune consignment, the whole award
has to go. Thus, it is clear that the award suffers from
patent illegality and learned District Judge has rightly held
so.
41.Accordingly, we find no merit in the appeal and the same
is hereby dismissed.
VINOD KUMAR, J
C. HARI SHANKAR, J
SEPTEMBER 16, 2026
VB
Signed By:PRAMOD
FAO (COMM) 119/2025
KUMAR VATS
12:43:28
Page 22
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review