Serial No.07
Regular List
HIGH COURT OF MEGHALAYA
AT SHILLONG
WP (C) No.143/2017
Date of Order: 08.08.2018
M/s Sarin’s Green House,
Nongrim Hills, Shillong
Coram:
Vs.
Union of India & ors
Hon’ble Mr. Justice Mohammad Yaqoob Mir, Chief Justice
Appearance:
For the Petitioner/Appellant(s)
For the Respondent(s)
: Mrs. PDB Baruah, Adv
Mr. N Mozika, Adv for R1-3
Mr. K Ch. Gautam, Adv R4
i)
Whether approved for reporting in
Law journals etc.:
ii)
Whether approved for publication
in press:
Yes
No
ORAL
1.
Respondent No.4-Engineering Projects (India) Limited an agency
for respondents No.2 and 3 has issued two work orders in favour of the
petitioner:
(a) Construction of 08 No’s of Single Men Barrack in 02 Blocks
of (G+III), 12 No’s. of Single JCO’s Accommodation and 04
No’s. Single Officer’s Accommodation including infrastructural
development works for Assam Rifles at Khonsa, Arunachal
Pradesh
dated
02.07.2009.
A
Letter
of
Intent
No.ASR/KHN/628/006 dated 17.06.2009 was issued.
(b) Construction of 01 No. Officer’s Mess, 01 No. Administrative
Block and 01 No. JCO’ Mess including infrastructural
development works for Assam Rifles at Khonsa, Arunachal
Pradesh
dated
30.11.2009.
A
Letter
of
Intent
No.ASR/KHN/628/006 dated 15.11.2009 was also issued.
2.
The stipulated date for completion of the said two work orders
was 16.02.2011 and 14.07.2011 respectively. Within the stipulated
period, it was not completed as a result whereof, extension of time was
granted up to 30.11.2013 but without any financial effect/escalations as
is clear from the communication dated 20.05.2013 addressed to the
respondent No.4. The respondent No.4 in turn has conveyed the same to
the petitioner vide communication dated 31.05.2013. Then, again time
was extended till 15.01.2014. Finally, the work was completed.
3.
The petitioner submitted the escalation bill which in turn was
submitted by the respondent No.4 to the Chief Engineer, Assam Rifles
on 21.09.2016 for an amount of Rs.1,54,87,613/- (Rupees one crore fifty
four lakhs eighty seven thousand and six hundred thirteen only). The
Directorate General Assam Rifles, Shillong vide order dated 25.10.2016
accorded sanction for an amount of Rs.1,00,43,884/- (Rupees one crore
forty three thousand eight hundred and eighty four only) for payment of
escalation bill to the respondent No.4 wherein, it is also mentioned that
the bill from EPIL (respondent No.4) is technically checked and passed
for an amount of Rs.1,00,43,884/- (Rupees one crore forty three
thousand eight hundred and eighty four only). After deduction, balance
amount of Rs.94,36,371/- (Rupees ninety four lakhs thirty six thousand
and three hundred seventy one only) was released in favour of the
respondent No.4. When the amount was not paid to the petitioner,
through her counsel notice was served upon the respondents No.3 and 4,
which has been responded vide communication dated 06.04.2017 whereunder, it was conveyed that extension of time to complete all works as
mentioned in the notice was granted by DGAR (Competent Financial
Authority) on the condition that “no escalation will be paid”. It has also
been mentioned that the contention of the contractor that MOU/contract
agreement stating escalation will be paid for justified extended period
shall have no bearing as the extension letter itself would have served as
a corrigendum to the contractual agreement/MOU and as such post
extension on specific terms of the original contract agreement would
stand merged with the letter granting extension of time with specific
conditions.
4.
Vide communication dated 15.03.2017 addressed to the
respondent No.4 by the respondent No.3, it has been conveyed that the
escalation bill for an amount of Rs.1,00,43,884/- (Rupees one crore forty
three thousand eight hundred and eighty four only) was paid to the
respondent No.4 but because of certain technical reasons approval has
been cancelled. The bill was directed to be reverted, by means of
Government Challan, to the Government account before 25.03.2017 to
regularize the said payment.
5.
Petitioner aggrieved of the action of the respondents in not paying
the escalated bill amount has filed the instant petition with a prayer that
the letters dated 06.04.2017 and dated 02.05.2017 may be set aside. The
respondents No.2 to 4 may be directed to immediately release the
escalation claim of the petitioner along with interest @ 12%.
6.
Learned counsel for the petitioner submits that admittedly the
petitioner due to unavoidable circumstances could not complete the
work as was allotted to him within the stipulated period. For the work
which was not completed, time was extended and finally executed. The
petitioner had submitted the escalation bill which was technically
verified by the respondent No.4 same was processed and sanctioned by
the respondents No.1 to 3 for an amount of Rs.1,00,43,884/- (Rupees
one crore forty three thousand eight hundred and eighty four only) but
not paid. Subsequently, approval for payment has been cancelled on the
ground that while granting extension for completion of work, it was
specifically mentioned in the extension letter that the extension of time
shall be without any financial effect/escalation, which according to the
petitioner would mean that further escalation beyond stipulated period
for completion of work shall not be allowable. But the escalation during
the actual period stipulated for completion of work had been worked
out, which was technically verified by the respondent No.4, as such was
payable.
7.
Learned counsel for the respondents No.1 and 2 submits that as
per Clause 16 of the General Conditions of Contract (hereinafter referred
to as GCC), escalation is not permissible at all but such a contention is
repelled by the learned counsel for the petitioner because as per the
condition No.7 of the Additional Conditions of Contract (hereinafter
referred to as ACC), escalation clause has been included whereas, as per
the condition No.1 of ACC, the provisions of the ACC shall take
precedence. The submission of the learned counsel for the petitioner is
well founded. It shall be quite advantageous to quote condition No.16 of
GCC and also conditions No.1 and 7 of ACC as hereunder:-
“(G.C.C.)
16.0 ESCALATION / PRICE VARIATION
No claim on account of any Price Variation / Escalation on
whatsoever ground shall be entertained at any stage of works. All
rates as per Bill of Quantities (BOQ)/Price-Bid quoted by
Contractor shall be firm and fixed for entire contract period as
well as extended period for completion of the works. No
escalation/price variation clause shall be applicable on this
contract.”
“(A.C.C.)
“1.0 The following Additional Conditions of Contract shall be
read in conjunction with General Conditions of Contract. If there
are any provisions in these Additional Conditions of Contract,
which are at variance with the provisions of General Conditions
of Contract, the provisions in these Additional Conditions of
Contract shall take precedence.”
“7.0 PRICE ADJUSTMENT
Payment due to increase/decrease in prices/wages after Receipt of
Tender for works:
If the prices of materials and / or wages of labour required for
execution of the work increase, the Contractor shall be
compensated for such increase as per provisions detailed below
and the amount of the contract shall accordingly be varied subject
to the condition that such compensation for escalation in prices
and wages shall be available only for the work done during the
stipulated period of the contract including the justified period
extended under the provision of clause 72.4.3 of G.C.C. of the
contract without any action under clause 72.4.1 of G.C.C. (as
modified in A.C.C.). However, for the work done during the
justified period extended as above, the compensation as detailed
below will be limited to prices/wages prevailing at the time of
stipulated date of completion or as prevailing for the period under
consideration whichever is less. No such compensation shall be
payable for a work for which the stipulated period of completion
is equal to or less than 12 months. Such compensation for
escalation in the prices of materials and labour, when due, shall be
worked out based on the following provisions. ........
......
.....
....
....
.....”
8.
The conditions No.1 and 7 of ACC clearly reveal that
compensation for escalation of prices and wages shall be available only
for the work done during the stipulated period of the contract including
the justified period extended under the provision of Clause 72.4.3 of
GCC of the contract. However, for the work done during the justified
period extended, compensation will be limited to prices/wages
prevailing at the time of stipulated dates of completion or as prevailing
for the period under consideration whichever is less.
9.
The centre of controversy is as to whether the petitioner shall be
entitled to compensation for escalation in prices/wages for the balance
work which he has completed during the extended period. The answer
has to be in the affirmative. It has to be clarified that in terms of
condition No.7 of ACC, the compensation for escalation during justified
extended period will be limited to prices/wages prevailing at the time of
stipulated dates of completion or as prevailing for the period under
consideration whichever is less.
10.
The position as such is clear i.e. incomplete work which has been
completed during extended period has to be paid but same has to be
limited to prices/wages as were prevailing at the time of stipulated dates
of completion i.e. in the case of work order No.1 as on 16.02.2011 and
in the case of work order No.2 as on 14.07.2011, whatever escalation
was prevailing in prices/wages for the incomplete work shall be payable.
Any further escalation beyond 16.02.2011 and 14.07.2011 respectively,
shall not be allowable.
11.
Learned counsel for the respondents next contended that the
petition is not maintainable. Supporting his submission relied on the
judgment reported in (2004) 12 SCC 327. In the reported judgment, it
has been held that “it is well settled that writ of or in the nature of
mandamus would not ordinarily issue for enforcing the terms and
conditions of a contract qua contract. A writ of mandamus would issue
when a question involving public law character arises for consideration.
It is also well settled that the High Court would not entertain a writ
petition involving disputed questions of fact”. Applying the same law to
the present case, there is no disputed question of fact neither prayer is
for enforcing any disputed terms and conditions of the contract.
12.
Learned counsel for the petitioner in support of maintainability of
the petition has placed reliance on the judgment rendered in the case of
“ABL International Ltd. and anr v. Export Credit Guarantee Corporation
of India Ltd. and ors”: (2004) 3 SCC 553. Paras 10 and 53 of the
reported judgment are relevant to be quoted:
“10. It is clear from the above observations of this Court in the
said case, though a writ was not issued on the facts of that case,
this Court has held that on a given set of facts if a State acts in an
arbitrary manner even in a matter of contract, an aggrieved party
can approach the court by way of writ under Article 226 of the
Constitution and the court depending on facts of the case is
empowered to grant the relief. The judgment in K.N. Guruswamy
v. State of Mysore was followed subsequently by this Court in the
case of D.F.O. v. Ram Sanehi Singh wherein this Court held:
(SCC p.865, para 4)
“By that order he has deprived the respondent of a valuable
right. We are unable to hold that merely because the source
of the right which the respondent claims was initially in a
contract, for obtaining relief against any arbitrary and
unlawful action on the part of a public authority he must
resort to a suit and not to a petition by way of a writ. In
view of the judgment of this Court in K.N. Guruswamy case
there can be no doubt that the petition was maintainable,
even if the right to relief arose out of an alleged breach of
contract, where the action challenged was of a public
authority invested with statutory power.”
(emphasis supplied)
“53. From the above, it is clear that when an instrumentality of the
State acts contrary to public good and public interest, unfairly,
unjustly and unreasonably, in its contractual, constitutional or
statutory obligations, it really acts contrary to the constitutional
guarantee found in Article 14 of the Constitution. Thus if we
apply the above principle of applicability of Article 14 to the facts
of this case, then we notice that the first respondent being an
instrumentality of the State and a monopoly body had to be
approached by the appellants by compulsion to cover its export
risk. The policy of insurance covering the risk of the appellants
was issued by the first respondent after seeking all required
information and after receiving huge sums of money as premium
exceeding Rs 16 lakhs. On facts we have found that the terms of
the policy do not give room to any ambiguity as to risk covered by
the first respondent. We are also of the considered opinion that the
liability of the first respondent under the policy arose when the
default of the exporter occurred and thereafter when the
Kazakhstan Government failed to fulfil its guarantee. There is no
allegation that the contracts in question were obtained either by
fraud or by misrepresentation. In such factual situation, we are of
the opinion, the facts of this case do not and should not inhibit the
High Court or this Court from granting the relief sought for by the
petitioner.”
13.
Applying the law as has been laid down by the Hon’ble Apex
Court, to the facts of the present case, it is quite clear that neither there is
misrepresentation nor fraud pleaded and alleged instead a justified claim
of the petitioner regarding compensation for escalation which in
principle initially has been sanctioned by the respondents but later on
arbitrarily revoked.
14.
The claim of the petitioner is not only fair and just but reasonable
as well. There is no disputed question of fact involved, position is clear
and admitted still right is denied in an arbitrary manner. Therefore, for
enforcement of such right, a remedy under Article 226 of the
Constitution of India cannot be denied. That being so petition is held to
be maintainable.
15.
The amount as compensation for escalation of prices/wages has
been technically checked by the respondent No.4 for an amount of
Rs.1,00,43,884/- (Rupees one crore forty three thousand eight hundred
and eighty four only) and sanctioned by the respondents-Assam Rifles
vide
order
bearing
No.VIII.11014/611/Khonsa/Engr-2008
dated
28.10.2016 and after deduction, fully vouched contingent bill for
Rs.94,36,371/- (Rupees ninety four lakhs thirty six thousand and three
hundred seventy one only) has been prepared but not drawn therefore,
not paid to the petitioner, shall be payable to the petitioner. As such, be
paid to the petitioner within a period of three months from today. In
default of payment within three months, same shall be payable with
interest @6% per annum. The letters impugned including letter dated
06.04.2017 providing for revoking the approval for payment of
compensation for escalation shall stand quashed.
16.
Petition succeeds and is disposed of as above.
(Mohammad Yaqoob Mir)
Chief Justice
Meghalaya
08.08.2018
“Lam AR-PS”
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review