Sr. No. 114
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
Case: WP(C) No. 2472/2022
Reserved on
: 18.09.2025
Pronounced on : 26.09.2025
01. M/s Saint Soldier Engineer and
Contractor Pvt. Ltd. Through its
Director Sham Singh Jamwal Age 66
Years S/o Sh. Sardar Singh Jamwal,
R/o B.P 159, Channi Himmat,
Jammu
Through :-
..... Petitioners(s)/Appellant(s)
Mr. Gagan Kohli, Advocate
Mr. Manik Bhardwaj, Advocate
Vs
01. UT of Jammu and Kashmir
Through Commissioner/Secretary to to
Govt. PWD (R&B)Department, Jammu.
.....Respondent(s)
02. Chief Engineer PWD
(R&B) Department, Jammu.
03. Executive Engineer PWD
(R&B) Construction Division-I, Jammu
Through :-
Mr. Ravinder Gupta, AAG
CORAM:
HON'BLE MR. JUSTICE WASIM SADIQ NARGAL, JUDGE
JUDGMENT
PRAYER
01. The present petition has been filed by the petitioner seeking writ of
Mandamus to command and direct the respondents to release the payment of
Rs.9787012/- in his favour alongwith 12% interest with regard to the works
of 20 mm thick open graded premix carpet on link road from Dera Camp to
Nikowal Sai KM 1 RD 0 to KM 7 RD 500 (length 5 km) and 50 mm thick
st
th
2|Page
WP(C) No. 2472/2022
Bitumen Macadam (BM) and laying 25 mm open graded premix carpet
(OGPC)s.
BRIEF FACTS
02. The petitioner is a registered contractor and claims to have executed
various works of Government and Semi Government organizations allotted to
him. Respondents in terms of E-NIT No.CD-1/63 of 2014-15 dated 10.03.2025
advertised the works for providing and laying 20 mm thick open graded
premix carpet on link road from Dera camp to Nikowal and the petitioner
participated in the auction process and accordingly was declared lowest bidder
by the respondents. By virtue of letter no. SEJ/4377-69 dated 01.08.2015,
allotted the three aforesaid works to the petitioner and the value of the work
was restricted upto Rs.50,33,700. After the allotment of the said works, the
scope of the work was enhanced for more up gradation of the road by way of
providing and laying of wet mix as per necessity at site by way of laying of
50 mm thick Bitumen Macadam (MB) and laying 25 mm open graded premix
carpet (OGPC) surfacing as the local people did not allow to execute the
work on the original specification allotted to the petitioner.
03. The post fact approval for the revised proposal on the proposed rate for
the execution of the work was also requested by respondent No. 3 vide
communication dated 16.07.2016.
An agreement for execution of the
aforesaid revised work was also executed between the petitioner and the
respondent no.3. The cost of the work notified for execution of the said work
was Rs.2,37,39,1000/-.
The Chief Engineer vide communication dated
04.08.2016 also accepted the proposed and recommended approval made by
the Superintendent Engineer.
It is urged that thereafter, the petitioner
3|Page
WP(C) No. 2472/2022
successfully completed all the works allotted to him in the year 2017 but the
respondents released part payment of the work executed by him and payment
to the tune of Rs.9787012/- was withheld without any reason or justification,
in spite of the fact that the Assistant Executive Engineer also entered the
work executed by the petitioner in the measurement book and prepared the
Bill amounting to Rs.9787012 vide communication dated 28/09/2018 after
adjusting all the running payments.
04. Further, it is urged that petitioner approached the respondents for payment
of his admitted due amount of Rs.9787012, but the same was not released and
was pending consideration. The further case as projected is that the Executive
Engineer vide communication dated 19/12/2020 also certified the lists of
works including the work of the petitioner where the work done liability has
been shown to be pending and payments were not released to the contractors
for the year 2015-16 to 2018-19 and the claims of the petitioner against the
works executed by him were not released due to non-availability of the funds.
It is also submitted that petitioner filed number of representation and
reminders to the respondents, but despite repeated representation and requests,
the payment of the petitioner was not released by the respondents and feeling
aggrieved of the same has approached this court through this petition for
redressal of his grievance.
LEGAL ANALYSIS
05.
Heard learned counsel for the parties and perused the record.
06.
The record reveals that notice in the instant petition was issued on
18.11.2022, but despite granting numerous opportunities to the respondents the
objections have not been filed. From the perusal of file, it is apparent that on
4|Page
WP(C) No. 2472/2022
04.09.2024 last and final opportunity for filing the objections was granted,
failing which it was made clear that the right to file the same shall stand closed
and the matter would be heard on its own merits. Inspite of availing last and
final opportunity, reply was not filed by Mr. Ravinder Gupta, learned AAG
and the matter was admitted to hearing and time was granted to file counter
affidavit which was also not filed and right to file the same stands closed
today. However, Mr. Ravinder Gupta was given an opportunity to argue the
matter in absence of counter affidavit. Thus the instant petition is taken up for
final disposal.
07. It is a well-settled principle in law of pleadings that where specific
averments have been made in a petition and the same are not controverted,
denied, or specifically traversed by the respondents in their reply or counter
affidavit, such non-denial amounts to an admission of the facts pleaded by the
petitioner. Silence or evasive denial cannot take the place of a categorical
traverse, and consequently, the uncontroverted pleadings are deemed to have
been admitted.
08. The record reveals that the petitioner, a registered government contractor,
was initially awarded a contract valued at ₹50,33,700/- for providing and
laying a 20 mm thick open-graded premix carpet on a 5 km stretch of the link
road from Dera Camp to Nikowal Sai. However, as per the necessity at site
and objections from local residents, the scope of work was revised to include
laying 50 mm thick Bitumen Macadam (BM) alongside 25 mm open-graded
premix carpet (OGPC).
09. This revision, duly approved by the competent authority, led to an
enhanced contract value of ₹2,37,39,1000/-.
5|Page
WP(C) No. 2472/2022
10. The petitioner completed the revised work in 2017 and submitted claims
for payment. The respondents released the part payment of work but despite an
admitted amount of Rs. 97,87,012, the same was withheld without justification
even after the final bills were settled and repeated representations were made
in this regard. The official communications from the Executive Engineer in
2016, 2018, and 2020 acknowledged the liability, but the respondents cited
paucity of funds as a reason for non-payment. Subsequent requests in 2021 and
2022 failed to secure the release of dues, prompting the petitioner to approach
this Court seeking a writ of mandamus directing payment with interest.
11. Upon consideration, it is evident that the petitioner satisfactorily executed
the contractual work as per the revised specifications sanctioned by the
respondents. The admitted liability has been acknowledged by the respondents
from time to time which can be authenticated from bare perusal of the official
record and final bills. The respondents’ counsel however have argued that the
claim of the petitioner is time-barred which as per record is not tenable and
cannot be justified.
12. The objection of the respondents regarding limitation is not tenable in the
eyes of law. This Court finds that the present claim is not a time-barred claim
in the strict sense. Sections 18 of the Limitation Act, 1963, which deal with the
effect of acknowledgment and part-payment, do not strictly govern the field in
matters arising under Article 226 of the Constitution. The present case is not
one of a stale demand being resurrected after long dormancy; rather, it
concerns a continuing liability of the State which stands acknowledged on
more than one occasion. For facility of reference, Sections 18 of the Limitation
Act is reproduced as under:-
6|Page
WP(C) No. 2472/2022
“18. Effect of acknowledgment in writing.—(1) Where, before the
expiration of the prescribed period for a suit or application in respect of
any property or right, an acknowledgment of liability in respect of such
property or right has been made in writing signed by the party against
whom such property or right is claimed, or by any person through whom
he derives his title or liability, a fresh period of limitation shall be
computed from the time when the acknowledgment was so signed.
(2) Where the writing containing the acknowledgment is undated, oral
evidence may be given of the time when it was signed; but subject to the
provisions of the Indian Evidence Act, 1872 (1 of 1872), oral evidence of
its contents shall not be received.
Explanation.—For the purposes of this section,—
(a) an acknowledgment may be sufficient though it omits to specify the
exact nature of the property or right, or avers that the time for payment,
delivery, performance or enjoyment has not yet come or is accompanied
by a refusal to pay, deliver, perform or permit to enjoy, or is coupled
with a claim to set off, or is addressed to a person other than a person
entitled to the property or right,
(b) the word “signed” means signed either personally or by an agent
duly authorised in this behalf, and
(c) an application for the execution of a decree or order shall not be
deemed to be an application in respect of any property or right.”
13. It is not disputed that the respondents themselves acknowledged the
liability in the year 2018, which was well within the period of limitation, and
the same was again reaffirmed in 2020. Once liability is admitted and the State
continues to enjoy the fruits of the work executed by the petitioner, it cannot
be permitted to turn around and deny payment on the plea of limitation.
14. The liability in the present case is in the nature of a recurring liability. The
work has been executed, utilized, and the benefits continue to accrue to the
respondents. In such cases, the cause of action is a continuing one, and every
day of non-payment constitutes a fresh infraction of the petitioner’s rights.
Therefore, the bar of limitation cannot be rigidly applied to defeat such claims.
15. It is equally well settled that the power under Article 226 of the
Constitution is discretionary in nature. While it is true that ordinarily claims
which are stale, delayed, or barred may not be entertained, the Court retains
7|Page
WP(C) No. 2472/2022
discretion to intervene where arbitrariness, admitted liability, or unjust
enrichment of the State is writ large.
16. Thus, the argument of Mr. Ravinder Gupta learned AAG that the writ
petition is time barred merely because the petitioner did not agitate his cause
earlier cannot be accepted. The duty of the State to pay for work executed and
enjoyed is a constitutional obligation flowing from Article 14, and delay in
seeking enforcement of such right cannot absolve the State from its
responsibility.
17. What emerges from the record is that the liability is admitted by the
respondents themselves. Once liability is admitted, the only question that
remains is with respect to delay in release of payment. Such delay, in the
opinion of this Court, requires to be enquired into so that responsibility can be
fixed upon the officers concerned. If contractors are compelled to knock at the
doors of the Court day in and day out for release of legitimate dues, the fault
lies not with the petitioner but with the respondents.
18. This Court notes with concern that such cases of withholding of admitted
dues are repeatedly coming before this Court, reflecting systemic inaction. The
writ court cannot turn a blind eye to such grievances on hyper-technical pleas
of limitation, when non-payment of the admitted liability being acknowledged
by the respondents from time to time is a recurring cause till the amount is
released.
19. Further this Court is of the considered view that once work has been
executed by the contractor in conformity with the terms and conditions of the
contract agreement, the concerned department is under a legal obligation to
release the payment without undue delay. The straight jacket formula of claim
8|Page
WP(C) No. 2472/2022
being time barred on hyper technical grounds cannot be imported or applied in
the present matter, nor can the limitation under Section 18 of the Limitation
Act be attracted to withhold such legitimate dues.
20. It is well settled that execution of work gives rise to a corresponding
obligation upon the State to honour its financial commitments. Any
administrative approval or availability of funds is a matter to be ensured by the
department prior to the allotment of work. After the execution of the contract,
no “post facto” objection can be raised to deny or delay payment.
21. This Court is constrained to observe that in numerous cases involving
government contracts, despite completion of work in accordance with the
terms and conditions of the contract, the payments due to contractors are not
released in a timely manner. The delay is often attributed to administrative
reasons, such as the need for administrative approval or the alleged paucity of
funds or the funds being diverted to other projects to frustrate the claim of the
contractors. In the present case as well, despite admitted liability and due
completion of work by the petitioner well in time the payment has been
unjustifiably withheld for a considerable period of time.
22. This Court has, on numerous occasions, been compelled to intervene in
matters where contractors, having fulfilled their contractual obligations in
letter and spirit, are denied timely release of their dues by government
departments. The State and its instrumentalities, despite enjoying the benefit of
completed works, unjustifiably withhold payment for years together, thereby
driving the contractors to litigate. Such unnecessary litigation clogs the docket
of constitutional courts, drains public resources, and erodes the confidence of
9|Page
WP(C) No. 2472/2022
citizens in the fairness of State action. This systemic malaise demands judicial
correction and policy direction.
23. Article 14 of the Constitution of India guarantees equality before the law
and equal protection of laws. The jurisprudence under Article 14 has evolved
far beyond formal equality, it now encompasses the principle that State action,
whether legislative, executive, or contractual, must not be arbitrary,
unreasonable, or unfair.
24. The Government, when entering into contracts or dealing with contractors,
does not shed its constitutional obligations. Unlike a private party, the State is
bound to act as a model litigant. Once the liability is admitted such as when
work is duly executed, measured, and certified the withholding of the
payment without justification amounts to arbitrary action and thus falls foul of
Article 14.
25. The Division Bench Of this court in case titled as Union Territory Of JK
& Ors vs Mohammad Atzal Reshi on 4 September, 2024 has been pleased to
hold as under;
19. Under the circumstances, this Court feels that an order
needs to be passed in this particular Letters Patent Appeal
which is exemplary and deterrent in nature to prevent the
Union Territory from filing such frivolous cases and
delaying the relief granted to the litigants. In this
particular case, the respondent herein has been kept
waiting for nine (9) years from the year 2015 for the
payment of his just dues which are not disputed. He was
compelled to file writ petition only because his admitted
dues were not being paid by the Union Territory for six
long years on the grounds of paucity of funds which
excuse is abominable and condemnable in the strongest
words. The UT LPA No. 121/2023 The government is part
of the Union Government which is the repository of the
lion's share of the wealth generated in this country in the
first instance and thereafter distributed to the states. It
10 | P a g e
WP(C) No. 2472/2022
shocks the conscience that we tout ourselves as the fifth
largest economy in the world, aspiring to be the third
largest soon, but do not have the funds to pay the
legitimate dues of the respondent amount to Rs. 20.97
Lacs, which denigrates and puts to doubt the lofty claims
of the economic prowess of the country.
26. It is pertinent to note that if, for instance, the Government owes ₹1 crore
for the work executed in 2016, and chooses to release this amount only after 5
to 10 years and that too forcing the contractors to litigate and if the Court
allows such petition thereafter by directing, to release the principal amount
without paying any interest or compensation, then it is the contractor who
unjustly bears the entire burden of delay. The petitioner suffers not only
monetary loss due to lack of timely liquidity, but also business hardship,
opportunity costs, and mental agony. If the amount had been released when it
became due, the contractor could have utilised the same in future projects or
earned interest had it been kept in a financial institution. This situation is
further exacerbated when, even after the contractor obtains a judgment after
multiple rounds of litigation, the judgment is not implemented in letter and
spirit. Contractors are often forced to file contempt petitions for enforcement,
which remain pending for years. It is only when courts takes a strict view, in
contempt matters the principal amounts is released, but, by then, considerable
time has been lost. Such delayed payments deprive contractors of their rightful
property without legal authority, which amounts to a violation of their
constitutional rights under Article 300A (right to property) and Article 21
(right to life and personal liberty), as the Hon’ble Supreme Court has
recognized that the deprivation of property must follow due process of law,
and unjust withholding causes significant hardship. Because delayed payment
11 | P a g e
WP(C) No. 2472/2022
amounts to virtual expropriation without authority of law. The State cannot
enrich itself by retaining the money of contractors indefinitely. Such conduct
undermines the rule of law and violates the guarantee of fairness embedded in
Article 300A.
27. Article 300A of the Constitution mandates that “no person shall be
deprived of his property save by authority of law.” Though the right to
property is no longer a Fundamental Right, the Hon’ble Supreme Court has
repeatedly held that it remains a constitutional right, and in a welfare State, it
assumes the character of a human right. Reliance is placed upon case titled
K.T Plantation Private Limited And another v. State of Karnataka (2011
9 SCC 1 , wherein the Hon’ble Apex Court ha held as under;
‘‘Article 300-A proclaims that no person can be deprived of his
property save by authority of law, meaning thereby that a person
cannot be deprived of his property merely by an executive fiat,
without any specific legal authority or without the support of law
made by a competent legislature. The expression “property” in
Article 300-A confined not to land alone, it includes intangibles
like copyrights and other intellectual property and embraces every
possible interest recognised by the law.’'
28.
From a contractual standpoint, Section 70 of the Indian Contract Act,
1872 imposes a duty to return benefits received without lawful justification,
preventing unjust enrichment. If the Government wrongfully withholds
payments, the contractor can claim compensation. Similarly, under Section 73
of the Contract Act, a party suffering loss due to breach of contract is entitled
12 | P a g e
WP(C) No. 2472/2022
to receive compensation for the loss or damage caused, which naturally
includes interest and damages for delayed payments.
29.
Relying upon the aforesaid principles of law, the Apex Court in case
titled Union of India v. Raman Iron Foundry (1962) 3 SCR 556, has
awarded interest on delayed payments, recognizing the contractor’s right to be
compensated for the financial hardship caused by delayed disbursal.
30.
Thus, this Court is of the view that consequently, delayed payments
causing financial ruin to contractors without due compensation are not only a
violation of contractual obligations but also breach constitutional safeguards.
The Courts must ensure that contractors receive timely payments along with
interest and compensation for losses incurred due to wrongful withholding,
failing which contractors face irreparable financial and business hardship.
31. This Court is of the considered view that such conduct on part of the
Government is wholly arbitrary and unfair. The State, as a model litigant, is
expected to act fairly and reasonably. It cannot take advantage of its position
and delay legitimate dues while contractors are subjected to procedural hurdles
and financial strain. If the law of limitation is to be applied strictly against the
petitioner, then the State must also be held accountable for each day of delay
in releasing admitted payments when there is no legal impediment or fault
attributed to contractors.
32.
The legal position regarding the payment of dues for contractual work
executed is well-settled by the Hon’ble Supreme Court in several authoritative
pronouncements. These judgments collectively underscore the imperative that
“contractual payments must not be unduly delayed or withheld by the State
without valid reasons.”
13 | P a g e
33.
WP(C) No. 2472/2022
As held by the Hon’ble Supreme Court in Ramakrishna Construction
Co. v. Union of India, (2010) 3 SCC 579, it is a settled proposition that once
work has been executed and the liability is admitted, the State cannot
arbitrarily withhold payment.
34.
Similarly, in Surya Constructions v. State of U.P., (1986) 3 SCC 247,
the Hon’ble Supreme Court observed that “courts can exercise writ
jurisdiction under Article 226 of the Constitution in cases where admitted
contractual dues are withheld without justification.’’
35.
In view of the above, this Court holds that where the delay in releasing
payments is attributable to the State, and there is no legal impediment or
contractual dispute, the Government must explain the cause of such delay.
Each day’s delay in the release of payment must be justified. In the absence of
such justification, the Government shall be liable to pay interest for the
delayed period to the affected contractor/petitioner. Further, the Government
shall also be liable to compensate the petitioner for the financial loss and
mental distress caused due to such delay. The principle of fairness demands
that the State cannot have a ‘win-win’ situation, where it delays payment for
years and still discharges only the principal amount, without any consequence
or accountability.
36.
Accordingly, this Court is of the view that it is the need of the hour that
the respondents be called upon by this Court to adopt a policy ensuring that
funds are earmarked and made available prior to the issuance of work orders or
execution of contracts. Once the work is completed and all formalities are
fulfilled, there should be no impediment in the expeditious release of payment.
In cases, where such delay is found to be unjustified or attributable to the
14 | P a g e
WP(C) No. 2472/2022
Government machinery, the contractor shall be entitled not only to interest on
delayed payments but also compensation, wherever appropriate.
37.
This Court further directs that in all such cases where the work has
been executed in accordance with the terms and conditions of contract and
administrative approval has already been accorded, the payment shall be
released to the contractors expeditiously without any delay. The Diversion of
budgetary heads or exhibition funds earmarked for the said work for any other
purpose shall not be permitted to defeat the legitimate claim of the contractor.
38.
It is made clear that if any payment is withheld for reasons not
attributable to the contractor, the State would be liable to pay interest on the
delayed amount at rates prevalent in nationalized banks from the date the
amount became due, till actual payment. In the eventuality, that such delay is
occasioned due to the inaction or lapse of the responsible officer(s), after
conducting detailed inquiry, the amount of interest so accrued shall be
recoverable from the salary component of the concerned delinquent officer(s).
39.
This Court cannot overlook the recurrent tendency of authorities to
withhold payments on flimsy pretexts, thereby subjecting contractors to
unnecessary hardship. In order to ensure accountability, it is directed that in
cases where the delay in releasing payments is due to the lapse or negligence
of officers concerned, the burden of interest liability shall not fall on the public
exchequer, but shall be recoverable from the salary components of such erring
officers who occasioned the delay. This measure is in consonance with the
principle
of
administrative
pronouncements.
accountability
as
evolved
by
judicial
15 | P a g e
40.
WP(C) No. 2472/2022
The Hon’ble Supreme Court of India has consistently maintained that
the State, despite its sovereign status, is not above its contractual obligations.
When the State acts arbitrarily, unfairly, or malafide in fulfilling such
contracts, it can be held accountable through judicial intervention. Notably, the
writ jurisdiction under Article 226 of the Constitution plays a crucial role in
enforcing these obligations, particularly in cases where the State’s conduct
reflects clear arbitrariness or unjust withholding of dues.
41.
The judicial trend clearly establishes that the State, when entering into
contracts, is bound by the same standards of fairness and accountability as any
private party. The writ jurisdiction under Article 226 acts as a powerful
corrective tool to prevent arbitrary, unfair, or mala fide conduct by the State in
contractual matters. Courts have unequivocally stated that technicalities or
administrative lacunae cannot be used as excuses for non-payment or nonperformance once the State has admitted its liability or the contract terms are
fulfilled. These decisions collectively underscore the principle that good
governance and equitable treatment must govern contractual dealings of the
State, ensuring justice and protection for contractors and service providers
alike.
42.
This Court expresses serious concern over the recurrent presentation of
cases involving the withholding of admitted dues by respondents, which
reflects a pattern of systemic inaction and neglect in honoring contractual
obligations. It is incumbent upon this Court, vested with writ jurisdiction, to
address such grievances decisively and not to permit dismissal of petitions on
hyper-technical grounds such as limitation, particularly where such pleas serve
as instruments for delaying justice and perpetuating arbitrariness.
16 | P a g e
43.
WP(C) No. 2472/2022
Reliance is also placed upon a case titled U.T of J&K v. Tejeinder
Singh bearing no LPA No. 139/2022 decided on 05.03.2025, wherein the
Hon’ble Division bench of this court has observed as under;
“Coming to the objection of Mr. Gupta with regard to the
entertaining of the time barred claim of the petitioner by the writ
court, suffice it to say, that the law of limitation, in particularly
'The Limitation Act', does not in stricto sensu apply to the
proceedings under Article 226 of the Constitution of India.
However, that does not mean that the writ petition can be filed
by a person aggrieved at the time of his choosing and even after
the considerable delay. The delay and laches is one of the
grounds on which this Court may refuse to exercise its
discretionary jurisdiction vested by Article 226 of the
Constitution. It is true and as is held by the Hon'ble Supreme
Court in the case of Bhailal Bhai (supra), that with a view to
determine as to whether there is unreasonable delay on the part
of the petitioner to approach the court under Article 226 of the
Constitution, the court shall keep in mind as to whether the suit
for claiming such relief would be barred by the law of limitation
or not.The maximum period fixed by the legislature as the time
within which the relief by way of civil suit in a civil court must
be brought may ordinarily be taken to be reasonable standard
by which delay in seeking remedy under Article 226 can be
measured. The Constitutional Court exercising its jurisdiction
under Article 226 of the Constitution of India may consider the
delay unreasonable even if it is less than the period of limitation
prescribed for a civil action. In a nut-shell, the remedy under
Article 226 of the Constitution of India is discretionary remedy
and this Court can refuse to entertain a claim which is not
brought before it within a reasonable period. What could be
reasonable period in a given case would depend upon the facts
and circumstances of such case.”
In the instant case, having regard to the fact that the appellants
have acknowledged their liability from time to time, we are of
the considered opinion that the writ petition was not hit by any
delay and laches. The work was stated to have been completed
and handed over to the respondent in September, 2014. The
period of limitation as per Article 56 of the Schedule to the
Limitation Act would have expired in September, 2017. There is
acknowledgement by the appellants dated 10.03.2017 and in
view of the provisions of Section 19, the period of limitation
prescribed for seeking the recovery of the amount by way of civil
action stood extended up to 10.03.2020. There is further
acknowledgement of the liability by the appellants on
20.12.2017 which would extend the period of limitation to
17 | P a g e
WP(C) No. 2472/2022
19.12.2020. There is another acknowledgement dated
20.10.2020 which takes the limitation period to 21.10.2023”.
44. This Court, in the light of what has been discussed hereinabove coupled
with the settled legal position deems it proper to allow the instant petition by
directing the respondents to release the outstanding amount of ₹97,87,012/along with interest at the rate 6% from the date of completion of work and
fulfilling all requisite codal formalities in 2017 until actual payment. As a
Constitutional Court, this court is not merely confined to adjudicating statutory
rights but are also empowered to issue appropriate directions, orders, or writs,
wherever, State action is found to be arbitrary, unreasonable, or in violation of
constitutional mandates, particularly those enshrined under Article 14. In
cases, where the statutory scheme is silent or where administrative practices
result in manifest injustice, what may be referred to as a grey area, this Court
is fully competent to lay down principles, evolve procedural safeguards, and
enforce obligations consistent with the rule of law.
45. Accordingly, this Court issues the following directions:
i.
The respondents shall release the outstanding principal amount of
₹97,87,012/- to the petitioner within a period of four (4) weeks from the date
of this judgment, without any further delay or excuse.
ii.
The interest shall be paid on the above amount at the rate of 6% from the
date of completion of work and fulfillment of all codal formalities in 2017
until actual payment.
46. In conclusion, this Court directs that the respondents are unequivocally
prohibited from denying or delaying payments legitimately due to the
petitioner under the pretext of administrative objections or financial
18 | P a g e
WP(C) No. 2472/2022
constraints. Such conduct would constitute an arbitrary exercise of power,
contrary to the principles enshrined under Articles 14 of the Constitution of
India, and would not withstand judicial scrutiny. The State, as a party to
contractual engagements, is duty-bound to uphold the principles of fairness,
transparency, and good governance, and to discharge its financial obligations
promptly and without undue delay.
47. This Court, having examined the admitted facts of the case and the binding
legal principles laid down by the Hon’ble Supreme Court, holds that the action
of the respondents in withholding the petitioner’s legitimate and undisputed
contractual dues is not only arbitrary but also deeply injurious to the
constitutional values of fairness, equity, and good governance enshrined under
Article 14 of the Constitution of India.
48. The continued failure to honour such financial obligations despite repeated
acknowledgments, finalisation of bills, and utilization of the work executed
amounts to a systemic breach of public trust and administrative accountability.
This conduct also undermines the larger goals of nation-building, for it
discourages lawful commercial engagement with the State, hampers
infrastructure development, and erodes investor and contractor confidence
particularly among small and medium enterprises that form the backbone of
public works execution.
49. Furthermore, the principle of compound interest, as recognized in fiscal
jurisprudence, supports the proposition that undue retention of monies,
especially over several years must carry with it not just simple interest, but
accrued or compounded interest, considering the opportunity costs, inflation,
and business loss suffered by the aggrieved party. The State cannot enrich
19 | P a g e
WP(C) No. 2472/2022
itself at the expense of private individuals and simultaneously resist its
obligation to compensate for the time-value of money.
50. The Court also deems it necessary to record that the repeated invocation of
untenable objections such as limitation or paucity of funds—despite the
admitted nature of liability, is not merely a procedural lapse but borders on
contempt of judicial discipline. Once such objections have been rejected in
binding precedents and prior cases, reiteration of the same without new legal
foundation amounts to wilful disregard of judicial authority, and must be
viewed seriously.
51. Therefore, this Court cannot remain a passive onlooker where admitted
dues are unjustifiably withheld under the guise of administrative delays or
financial constraints. Once it is established that work has been executed in
accordance with the terms of the contract and liability has been admitted, the
State cannot be permitted to evade its financial obligations. In the absence of a
valid legal impediment, this court holds that such conduct amounts to arbitrary
action and violates the principles of fairness and accountability. Accordingly,
this Court exercises its constitutional mandate by issuing guidelines in such
cases by directing the Government and its agencies to release the payment,
impose interest for delay, and fix accountability, both institutional and
individual ,so as to deter future lapses and uphold the public trust reposed in
the functioning of the State.
52. It is further clarified that in instances where payments are withheld despite
the undisputed completion of contractual obligations, the respondents shall be
liable to pay interest on the delayed amount at rates prevailing in nationalized
20 | P a g e
WP(C) No. 2472/2022
banks, calculated from the date the payment became due until the date of
actual realization by the petitioner.
53. In light of the foregoing, this Court issues the following directions to
ensure the effective enforcement of contractual payments and to uphold the
principles of fairness and accountability:
A. Obligation to Pay Post Completion: Once the work has been
executed strictly in accordance with the terms and conditions set out in
the tender and the agreement, the respondents shall be under a clear
statutory and contractual obligation to release the due payment without
any undue or arbitrary delay.
B. Rejection of Post-facto Administrative Objections: After the
execution of work, the respondents shall not be permitted to raise
objections pertaining to administrative approvals, sanction of funds, or
diversion of funds as grounds to withhold or delay payment.
C. Payment of Interest on Delayed Amounts: In cases, where the delay
in payment is not attributable to the contractors, the respondents shall be
liable to pay interest on the outstanding amount at the prevailing rates in
nationalized banks, calculated from the date the payment fell due until
the actual date of payment.
D. Personal Accountability for Malafide Conduct: Where delay or
withholding of payment arises from negligence, omission, or mala fide
conduct on the part of any officer or official, the accrued interest shall be
recovered from the salary or emoluments of such officer, thereby fixing
personal accountability and deterring arbitrary exercise of power.
21 | P a g e
WP(C) No. 2472/2022
E. Constitutional and Welfare Considerations: A welfare State cannot
legitimately plead “paucity of funds” when payments for works already
executed and utilized are withheld. The principle of economic justice
obliges the State to ensure that contractors, having fulfilled their part of
the bargain, are not subjected to financial distress on account of
arbitrary or habitual withholding of dues. In cases of habitual or willful
withholding, apart from interest, the Court may impose exemplary costs
against the erring department, to be deposited with the State Legal
Services Authority for utilisation towards public welfare purposes.
54. In addition, the Chief Secretary of the Union Territory is directed to
formulate and implement a Standard Operating Procedure (SOP) to ensure that
no admitted dues arising from completed contractual works are withheld
beyond a period of sixty (60) days from the date of submission of final bills
provided there is no legal impediment and all the codal formalities are
completed. It is further made clear that while formulating and implementing
the said SOP, the directions issued and observation made by this Court to
ensure the effective enforcement of contractual payments expeditiously with a
view to uphold the principle of fairness and accountability, shall be adhered to
in its letter and spirit. A compliance affidavit to this effect shall be filed within
six (6) weeks.
55. Let it be underscored that constitutional governance does not permit the
State to hide behind bureaucratic excuses while depriving its contractors of
their rightful dues. The dignity of governance lies not merely in rule-making,
but in timely honouring of obligations, duty which the State, as a model
litigant, is expected to uphold scrupulously. This Court, therefore, in exercise
22 | P a g e
WP(C) No. 2472/2022
of its powers under Article 226 of the Constitution of India, not only redresses
the grievance of the petitioner/contractors but also affirms the principle that
the State must act with transparency, fairness, and accountability in all its
contractual dealings.
56. Thus, in light of what has been discussed hereinabove coupled with settled
legal position, the writ petition preferred by the petitioner is allowed and
disposed of in the manner indicated above along with all connected
application(s).
(Wasim Sadiq Nargal)
Judge
Jammu:
26.09.2025
Mihul
Whether the order is speaking : Yes
Whether the order is reportable : Yes
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review