HIGH COURT OF CHHATTISGARH AT BILASPUR
WPC No. 3895 of 2026
M/s SA Infrastructure Consultants Private Limited Through Its, Deputy
General Manager, Legal And Secretariat, 1101 A , 11th Floor Tower, A- I I,
Corporate Park, Plot No. 7 A /1, Sector 142, Noida 201301, Uttar Pradesh,
India.
... Petitioner(s)
versus
1 - Union Of India Through The General Manager, South East Central
Railway (S E C R), New Zonal Building, Bilaspur, Chhattisgarh 495004
2 - Chief Project Manager (Construction) Through Deputy Chief Engineer
(Construction)- I I I South East Central Railway, Construction Organization, D
R M Office Complex, Kingsway, Nagpur- 440001, Maharashtra.
... Respondent(s)
(cause title taken from CIS)
For Petitioner(s)
:
Mr. Amrito Das, Sr. Advocate along with Mr.
Palash Tiwari, Advocate, Ms. Divya Verma and
Ms. Maya Jaiswal, Advocate
For Respondent(s)
:
Mr. R. K. Mishra, DSGI along with Ms. Annapurna
Tiwari, Advocate
Hon'ble Shri Ramesh Sinha, Chief Justice
Hon'ble Shri Ravindra Kumar Agrawal, Judge
Order on Board
Per Ramesh Sinha, Chief Justice
28/07/2026
1.
Heard Mr. Amrito Das, Sr. Advocate along with Mr. Palash Tiwari, Ms.
Divya Verma and Ms. Maya Jaiswal, learned counsel for the petitioner.
Also heard Mr. R.K. Mishra, DSGI, along with Ms. Annapurna Tiwari,
learned counsel for the Respondents.
2.
The present petition has been filed by the petitioner seeking the
following reliefs:“a) Issue a Writ of Mandamus, or any other
appropriate writ, order or direction, quashing and
setting aside, the Termination Notice dated
23.06.2026 issued by Respondent No.2 to the
Petitioner;
b) Issue a Writ of Mandamus, or any other
appropriate writ, order or direction, quashing and
setting aside the debarment of the Petitioner
from participation in the re-tender for the
balance work under Tender No. CEC-BSP-2223-23, as recorded in the Termination Notice
dated 23.06.2026;
c) Issue a Writ of Mandamus, or any other
appropriate writ, order or direction, quashing and
setting aside (i) the direction for forfeiture of the
Petitioner's Security Deposit, and (ii) the letter
dated 25.06.2026 issued by Respondent No. 2
to the Branch Manager, HDFC Bank Ltd.,
directing encashment of Bank Guarantee No.
027GT02230400011 dated 09.02.2023 and
restraining
the
Respondent
No.2
from
encashing, appropriating, receiving payment
under, or otherwise dealing with the said
Performance Bank Guarantee, and, in the event
the same has already been encashed in whole
or in part, directing the Respondent No.2 to
refund the amount so encashed to the Petitioner
together with interest;
d) Issue a writ in the nature of Prohibition and
such other Writ, Order or Direction to the
Respondent No.2 restraining the Respondent
No.2 from taking any coercive, arbitrary and
discriminatory action against the Petitioner
without following the due process of law; and / or
e) Pass such further or other orders as may be
deemed just, fit and necessary in the
circumstances of the case”
3.
The present writ petition has been filed challenging the Termination
Notice dated 23.06.2026 issued by Respondent No. 2 under Clause 62
of the General Conditions of Contract (GCC), whereby the contract
awarded to the petitioner for conducting the Final Location Survey,
geotechnical investigations and preparation of the Detailed Project
Report (DPR) for the proposed Gondia–Chanda Fort–Balharshah
railway doubling project was terminated, the Security Deposit was
ordered to be forfeited, the Performance Bank Guarantee was invoked
and the petitioner was debarred from participating in the balance work.
The petitioner submits that after execution of the contract on
05.04.2023, it substantially performed its contractual obligations and
completed nearly 80% of the consultancy work, while the remaining
activities were dependent upon approvals from the respondent
authorities.
Owing
to
such
approval-related
constraints,
the
respondents repeatedly granted five extensions of time, the last being
up
to
30.06.2026,
without
imposing
any
penalty,
thereby
acknowledging that the delay was not solely attributable to the
petitioner. Despite this, Respondent No. 2 issued a seven-day notice
followed by a forty-eight-hour notice, without meaningfully considering
the petitioner's detailed replies or affording an effective opportunity of
hearing, and terminated the contract even before expiry of the
extended contractual period. The petitioner contends that the
impugned termination, consequential forfeiture of the Security Deposit,
invocation of the Performance Bank Guarantee and debarment are
arbitrary, violative of the principles of natural justice and Articles 14 and
19(1)(g) of the Constitution of India, and are therefore liable to be
quashed.
4.
Learned Senior Counsel appearing for the petitioner submits that the
impugned Termination Notice dated 23.06.2026 is wholly arbitrary,
illegal, non-speaking and violative of Articles 14, 19(1)(g) and 21 of the
Constitution of India, as well as the principles of natural justice. It is
submitted that the petitioner was awarded the consultancy contract
pursuant to a valid tender process and, during the course of execution,
diligently performed its contractual obligations by completing nearly
80% of the project, including the aerial topographical survey,
geotechnical investigations, Detailed Project Report (DPR), land plans,
joint
measurement
surveys
and
preparation
of
General
Arrangement Drawings, while the remaining activities were dependent
upon approvals and technical decisions of the respondent authorities.
Learned counsel submits that the respondents themselves repeatedly
acknowledged the petitioner's satisfactory performance by granting five
extensions of time under Clause 17A of the GCC, the last extension
being up to 30.06.2026, after specifically recording that the reasons for
delay were acceptable and not attributable to the petitioner. Having
consciously treated the contract as subsisting, the respondents were
estopped from invoking the very same grounds to terminate the
contract before expiry of the extended period. It is further submitted
that although the petitioner furnished a detailed reply dated 23.04.2026
to the Seven Days' Notice explaining the actual progress of the work
and demonstrating that the balance activities were approvaldependent, the said reply was neither considered nor rejected by a
reasoned order. The Forty-Eight Hours' Notice was served belatedly,
thereby depriving the petitioner of any meaningful opportunity to
comply, and the impugned termination was issued mechanically
without recording any objective satisfaction as required under Clause
62 of the GCC.
Learned counsel further submits that the consequential
forfeiture of the Security Deposit, invocation of the Performance Bank
Guarantee and debarment from participating in the balance work are
merely consequential to the illegal termination and, therefore, cannot
survive independently. The order of debarment, having been passed
without any independent show cause notice, opportunity of hearing or
reasoned order, is in gross violation of the principles of natural justice
and the settled law laid down by the Hon'ble Supreme Court in
Verigamto Naveen v. Government of A.P., UMC Technologies Pvt. Ltd.
v. Food Corporation of India, Erusian Equipment & Chemicals Ltd. v.
State of West Bengal and Subodh Kumar Singh Rathour v. Kolkata
Metropolitan
Development Authority.
It
is
contended
that
the
respondents cannot approbate and reprobate by accepting the
petitioner's substantial performance, processing the DPR at various
governmental levels, extending the contractual period and thereafter
alleging lack of progress on the very same facts. The impugned action
is disproportionate, suffers from non-application of mind, defeats the
petitioner's legitimate expectation and promissory estoppel arising from
the respondents' own conduct, and results in grave civil and
commercial
consequences
affecting
the
petitioner's
reputation,
business and right to participate in future public procurement. It is,
therefore, prayed that the impugned Termination Notice dated
23.06.2026, together with the consequential forfeiture of the Security
Deposit, invocation of the Performance Bank Guarantee and order of
debarment, be quashed and appropriate consequential reliefs be
granted in favour of the petitioner.
5.
Learned counsel appearing for the respondents submits that the
present writ petition is devoid of merit and is liable to be dismissed. It is
submitted that the petitioner was awarded the contract for conducting
the Final Location Survey, geotechnical investigations and preparation
of the Detailed Project Report for the proposed Gondia–Chanda Fort–
Balharshah Doubling Project, subject to the terms and conditions of the
Agreement dated 05.04.2023 and the General Conditions of Contract
(GCC). Despite repeated opportunities and successive extensions of
time granted by the respondents, the petitioner failed to achieve
satisfactory progress and did not adhere to the agreed programme of
work within the stipulated period. It is further submitted that, in strict
compliance with Clause 62 of the GCC, the respondents first issued a
Seven Days' Notice dated 17.04.2026 calling upon the petitioner to
substantially improve the progress of work, followed by a Forty-Eight
Hours' Notice dated 16.06.2026 when no satisfactory improvement was
noticed. Even after expiry of the notice period, the petitioner failed to
recommence and complete the work as required. Consequently, the
competent authority, being satisfied that the petitioner had persistently
failed to perform its contractual obligations and had failed to adhere to
the agreed work programme, lawfully rescinded the contract under
Clause 62(1)(vii) and (viii) of the GCC by issuing the Termination
Notice dated 23.06.2026. It is submitted that the consequential
forfeiture of the Security Deposit, encashment of the Performance
Bank Guarantee and debarment from participating in the execution of
the balance work are express contractual consequences flowing from
the valid termination of the contract under the GCC. Learned counsel
further submits that the action of the respondents is neither arbitrary
nor violative of the principles of natural justice, as adequate
opportunities were afforded to the petitioner through the statutory
notices before invoking the contractual remedies. The respondents
acted strictly in accordance with the contractual terms to safeguard
public interest and to ensure timely completion of an important railway
infrastructure project. It is, therefore, submitted that the impugned
action is legal, justified and within the contractual powers vested in the
respondents, and no interference is warranted by this Hon'ble Court in
exercise of its extraordinary jurisdiction under Article 226 of the
Constitution of India.
6.
We have heard learned counsel for the parties and perused the
material available on record.
7.
Having heard learned counsel for the parties and upon perusal of the
pleadings and documents placed on record, this Court finds that the
present writ petition challenges the Termination Notice dated
23.06.2026 issued by Respondent No. 2 under Clause 62 of the
General Conditions of Contract (GCC), whereby the contract awarded
to the petitioner for conducting the Final Location Survey, geotechnical
investigations and preparation of the Detailed Project Report (DPR) for
the Gondia–Chanda Fort–Balharshah Doubling Project has been
terminated, the Security Deposit has been ordered to be forfeited, the
Performance Bank Guarantee has been directed to be encashed, and
the petitioner has been debarred from participating in the execution of
the balance work. Thus, this Court finds that the controversy essentially
arises out of the rights and obligations flowing from the contract
executed between the parties and the exercise of powers under the
contractual terms, including the dispute resolution mechanism provided
therein. Clause 64.1 of the General Conditions of Contract reads as
under:
“64.(1): Demand for Arbitration:
64.(1)(i): In the event of any dispute or
difference between the parties hereto as to
the construction or operation of this
contract, or the respective rights and
liabilities of the parties on any matter in
question, dispute or difference on any
account or as to the withholding by the
Railway of any certificate to which the
Contractor may claim to be entitled to, or if
the Railway fails to make a decision within
120 days, then and in any such case, but
except in any of the “excepted matters”
referred to in Clause 63.1 of these
Conditions, the Contractor, after 120 days
but within 180 days of his presenting his
final claim on disputed matters shall
demand in writing that the dispute or
difference be referred to arbitration.
64.(1)(ii)(a): The demand for arbitration
shall specify the matters which are in
question, or subject of the dispute or
difference as also the amount of claim
item-wise. Only such dispute or difference,
in respect of which the demand has been
made, together with counter claims or set
off, given by the Railway, shall be referred
to arbitration and other matters shall not be
included in the reference.
64.(1)(ii)(b): The parties may waive off the
applicability of Sub-Section 12(5) of
Arbitration and Conciliation (Amendment)
Act 2015, if they agree for such waiver in
writing, after dispute having arisen
between them, in the format given under
Annexure XV of these conditions.
64.(1)(iii)(a): The Arbitration proceedings
shall be assumed to have commenced
from the day, a written and valid demand
for arbitration is received by the Railway.
64.(1)(iii)(b): The claimant shall submit his
claims stating the facts supporting the
claims
alongwith
all
the
relevant
documents and the relief or remedy sought
against each claim within a period of 30
days from the date of appointment of the
Arbitral Tribunal.
64.(1)(iii)(c): The Railway shall submit its
defence statement and counter claim(s), if
any, within a period of 60 days of receipt of
copy of claims from Tribunal, unless
otherwise extension has been granted by
Tribunal.
64.(1)(iii)(d): Place of Arbitration: The place
of arbitration would be within the
geographical limits of the Division of the
Railway where the cause of action arose or
the Headquarters of the concerned
Railway or any other place with the written
consent of both the parties.
64.(1)(iv): No new claim shall be added
during proceedings by either party.
However, a party may amend or
supplement the original claim or defense
thereof during the course of arbitration
proceedings subject to acceptance by
Tribunal having due regard to the delay in
making it.
64.(1)(v): If the Contractor(s) does/do not
prefer his/their specific and final claims in
writing, within a period of 90 days of
receiving the intimation from the Railways
that the final bill is ready for payment,
he/they will be deemed to have waived
his/their claim(s) and the Railway shall be
discharged and released of all liabilities
under the contract in respect of these
claims.
64.(2): Obligation During Pendency of
Arbitration: Work under the contract shall,
unless otherwise directed by the Engineer,
continue during the arbitration proceedings, and
no payment due or payable by the Railway shall
be withheld on account of such proceedings,
provided, however, it shall be open for Arbitral
Tribunal to consider and decide whether or not
such work should continue during arbitration
proceedings
64.(3): Appointment of Arbitrator:
64.(3)(a): Appointment of Arbitrator where
applicability of section 12 (5) of Arbitration
and Conciliation Act has been waived off:
64.(3)(a)(i): In cases where the total value
of all claims in question added together
does not exceed 1,00,00,000/- (Rupees
One Crore), the Arbitral Tribunal shall
consist of a Sole Arbitrator who shall be a
Gazetted Officer of Railway not below
Junior Administrative Grade, nominated by
the General Manager The sole arbitrator
shall be appointed within 60 days from the
day when a written and valid demand for
arbitration is received by General Manager.
64.(3)(a)(ii): In cases not covered by the
Clause 64(3)(a)(i), the Arbitral Tribunal
shall consist of a panel of three Gazetted
Railway Officers not below Junior
Administrative Grade or 2 Railway
Gazetted Officers not below Junior
Administrative Grade and a retired Railway
Officer, retired not below the rank of Senior
Administrative Grade Officer, as the
arbitrators. For this purpose, the Railway
will send a panel of at least four (4) names
of Gazetted Railway Officers of one or
more departments of the Railway which
may also include the name(s) of retired
Railway Officer(s) empanelled to work as
Railway Arbitrator to the Contractor within
60 days from the day when a written and
valid demand for arbitration is received by
the General Manager.
Contractor will be asked to suggest to
General Manager at least 2 names out of
the panel for appointment as Contractor's
nominee within 30 days from the date of
dispatch of the request by Railway. The
General Manager shall appoint at least one
out of them as the Contractor's nominee
and will, also simultaneously appoint the
balance number of arbitrators either from
the panel or from outside the panel, duly
indicating the 'presiding arbitrator' from
amongst the 3 arbitrators so appointed.
General Manager shall complete this
exercise of appointing the Arbitral Tribunal
within 30 days from the receipt of the
names of Contractor's nominees. While
nominating the arbitrators, it will be
necessary to ensure that one of them is
from the Accounts Department. An officer
of Selection Grade of the Accounts
Department shall be considered of equal
status to the officers in Senior
Administrative Grade of other departments
of the Railway for the purpose of
appointment of arbitrator.
64.3.(a).iii: The serving railway officer
working in arbitral tribunal in the ongoing
arbitration cases as per clause 64.(3)(a)(i)
and clause 64.(3)(a)(ii) above, can
continue as arbitrator in the tribunal even
after his retirement.
64.(3)(b): Appointment of Arbitrator where
applicability of Section 12 (5) of Arbitration
and Conciliation Act has not been waived off:
(i) In cases where the total value of all
claims in question added together does not
exceed 50,00,000/-(Rupees Fifty Lakh),
the Arbitral Tribunal shall consist of a
Retired Railway Officer, retired not below
the rank of Senior Administrative Grade
Officer, as the arbitrator. For this purpose,
the Railway will send a panel of at least
four (4) names of retired Railway Officer(s)
empanelled to work as Railway Arbitrator
duly indicating their retirement dates to the
Contractor within 60 days from the day
when a written and valid demand for
arbitration is received by the General
Manager.
Contractor will be asked to suggest to
General Manager at least 2 names out of
the panel for appointment as arbitrator
within 30 days from the date of dispatch of
the request by Railway. The General
Manager shall appoint at least one out of
them as the arbitrator within 30 days from
the receipt of the names of Contractor's
nominees.
(ii) In cases where the total value of all
claims in question added together exceed
50,00,000/- (Rupees Fifty Lakh), the
Arbitral Tribunal shall consist of a Panel of
three (3) retired Railway Officer, retired not
below the rank of Senior Administrative
Grade Officer, as the arbitrators. For this
purpose, the Railway will send a panel of
at least four (4) names of retired Railway
Officer(s) empanelled to work as Railway
Arbitrator duly indicating their retirement
date to the Contractor within 60 days from
the day when a written and valid demand
for arbitration is received by the General
Manager.
Contractor will be asked to suggest to
General Manager at least 2 names out of
the panel for appointment as Contractor's
nominee within 30 days from the date of
dispatch of the request by Railway. The
General Manager shall appoint at least one
out of them as the Contractor's nominee
and will, also simultaneously appoint the
balance number of arbitrators either from
the panel or from outside the panel, duly
indicating the 'Presiding Arbitrator' from
amongst the 3 arbitrators so appointed.
General Manager shall complete this
exercise of appointing the Arbitral Tribunal
within 30 days from the receipt of the
names of Contractor's nominees. While
nominating the arbitrators, it will be
necessary to ensure that one of them has
served in the Accounts Department.
64.(3)(c)(i): If one or more of the arbitrators
appointed as above refuses to act as
arbitrator, withdraws from his office as
arbitrator, or vacates his/their office/offices
or is/are unable or unwilling to perform his
functions as arbitrator for any reason
whatsoever or dies or in the opinion of the
General Manager fails to act without undue
delay, the General Manager shall appoint
new arbitrator/arbitrators to act in his/their
place in the same manner in which the
earlier arbitrator/arbitrators had been
appointed. Such re-constituted Tribunal
may, at its discretion, proceed with the
reference from the stage at which it was
left by the previous arbitrator (s).
64.(3) (c) (ii): (a) The Arbitral Tribunal shall
have power to call for such evidence by
way of affidavits or otherwise as the
Arbitral Tribunal shall think proper, and it
shall be the duty of the parties hereto to do
or cause to be done all such things as may
be necessary to enable the Arbitral
Tribunal to make the award without any
delay. The proceedings shall normally be
conducted on the basis of documents and
written statements.
(b) Before proceeding into the merits of
any dispute, the Arbitral Tribunal shall first
decide and pass its orders over any plea
submitted/objections raised by any party, if
any, regarding appointment of Arbitral
Tribunal, validity of arbitration agreement,
jurisdiction and scope of the Tribunal to
deal with the dispute (s) submitted to
arbitration, applicability of time 'limitation' to
any dispute, any violation of agreed
procedure regarding conduct of the arbitral
proceedings or plea for interim measures
of protection and record its orders in day to
day proceedings. A copy of the
proceedings duly signed by all the
members of tribunal should be provided to
both the parties."
8.
A bare perusal of the aforesaid clause demonstrates that a complete
and efficacious adjudicatory mechanism has been contractually agreed
between the parties, governing not only invocation of arbitration but
also the procedure, timelines and scope of adjudication. In such
circumstances, it is well settled that writ jurisdiction under Article 226
ought not to be invoked in contractual disputes, particularly where
disputed questions of fact arise. The Hon’ble Supreme Court in Kerala
State Electricity Board v. Kurien E. Kalathil, (2000) 6 SCC 293 has
categorically held:
“10. We find that there is a merit in the first
contention of Mr. Raval. Learned Counsel has
rightly questioned the maintainability of the writ
petition. The interpretation and implementation of
a clause in a contract cannot be the subject
matter of a writ petition. Whether the contract
envisages actual payment or not is a question of
construction of contract. If a term of a contract is
violated, ordinarily the remedy is not the writ
petition under Article 226. We are also unable to
agree with the observations of the High Court
that the contractor was seeking enforcement of a
statutory contract. A contract would not become
statutory simply because it is for construction of a
public utility and it has been awarded by a
statutory body. We are also unable to agree with
the observation of the High Court that since the
obligations imposed by the contract on the
contracting parties come within the purview of the
Contract Act, that would not make the contract
statutory. Clearly, the High Court fell into an error
in coming to the conclusion that the contract in
question was statutory in nature.
11. A statute may expressly or impliedly confer
power on a statutory body to enter into contracts
in order to enable it to discharge its functions.
Dispute arising out of the terms of such contracts
or alleged breaches have to be settled by the
ordinary principles of law of contract. The fact
that one of the parties to the agreement is a
statutory or public body will not of itself affect the
principles to be applied. The disputes about the
meaning of a covenant in a contract or its
enforceability have to be determined according to
the usual principles of the Contract Act. Every act
of a statutory body need not necessarily involve
an exercise of statutory power. Statutory bodies,
like private parties, have power to contract or
deal with property. Such activities may not raise
any issue of public law. In the present case, it
has not been shown how the contract is statutory.
The contract between the parties is in the realm
of private law. It is not a statutory contract. The
disputes relating to interpretation of the terms
and conditions of such a contract could not have
been agitated in a petition under Article 226 of
the Constitution of India. That is a matter for
adjudication by a civil court or in arbitration if
provided for in the contract. Whether any amount
is due and if so, how much and refusal of the
appellant to pay it is justified or not, are not the
matters which could have been agitated and
decided in a writ petition. The contractor should
have been relegated to other remedies.”
9.
Having considered the rival submissions advanced by learned counsel
for the parties and upon perusal of the material available on record,
this Court is of the considered opinion that the disputes relating to the
validity of the termination of the contract, attribution of delay, alleged
breach of contractual obligations, forfeiture of the Security Deposit,
invocation
of
the
Performance
Bank
Guarantee
and
other
consequential contractual claims arise essentially out of the terms and
conditions of the contract executed between the parties. Such disputed
questions of fact require appreciation of evidence and interpretation of
the contractual provisions, which are more appropriately adjudicated in
the arbitral proceedings contemplated under Clause 64.1 of the
General Conditions of Contract. Accordingly, this Court is not inclined
to examine the merits of the contractual disputes in exercise of its
extraordinary jurisdiction under Article 226 of the Constitution of India,
leaving it open to the petitioner to avail the remedy of arbitration in
accordance with the dispute resolution mechanism contained in the
contract.
10.
The
Hon’ble
Supreme
Court,
Gorkha
Security
Services
v.
Government (NCT of Delhi), reported in (2014) 9 SCC 105, has
described blacklisting as being equivalent to the civil death of a person
because blacklisting is stigmatic in nature and debars a person from
participating in government tenders thereby precluding him from the
award of government contracts. It was held thus:
“16. It is a common case of the parties that the
blacklisting has to be preceded by a show-cause
notice. Law in this regard is firmly grounded and
does not even demand much amplification. The
necessity of compliance with the principles of natural
justice by giving the opportunity to the person against
whom action of blacklisting is sought to be taken has
a valid and solid rationale behind it. With blacklisting,
many civil and/or evil consequences follow. It is
described as “civil death” of a person who is foisted
with the order of blacklisting. Such an order is
stigmatic in nature and debars such a person from
participating in government tenders which means
precluding him from the award of government
contracts.”
11.
The said principle has been reiterated by the Hon’ble Supreme Court in
UMC Technologies Pvt. Ltd. v. Food Corporation of India, reported
in (2021) 2 SCC 551, which reads as under:“14. Specifically, in the context of blacklisting of a
person or an entity by the state or a state
corporation, the requirement of a valid, particularized
and unambiguous show cause notice is particularly
crucial
due
to
the
severe
consequences
of
blacklisting and the stigmatization that accrues to the
person/entity being blacklisted. Here, it may be
gainful to describe the concept of blacklisting and the
graveness of the consequences occasioned by it.
Blacklisting has the effect of denying a person or an
entity the privileged opportunity of entering into
government contracts. This privilege arises because
it is the State who is the counterparty in government
contracts and as such, every eligible person is to be
afforded an equal opportunity to participate in such
contracts, without arbitrariness and discrimination.
Not only does blacklisting takes away this privilege, it
also tarnishes the blacklisted person’s reputation and
brings
the
person’s
character
into
question.
Blacklisting also has long-lasting civil consequences
for the future business prospects of the blacklisted
person.”
12.
In light of the said decisions, it is clear that a prior show cause notice
granting a reasonable opportunity of being heard is an essential
element of all administrative decision-making and particularly so in
decisions pertaining to blacklisting which entail grave consequences
for the entity being blacklisted. In this case, furnishing of a valid show
cause notice is critical and a failure to do so would be fatal to any order
of blacklisting pursuant thereto.
13.
With regard to the order debarring the petitioner from participating in
the execution of the balance work is concerned, in view of the
aforesaid judgment, this Court finds that the same has been imposed
by the respondents without issuance of any independent show cause
notice, without affording any meaningful opportunity of hearing and
without passing a reasoned order, despite the fact that such debarment
visits the petitioner with serious civil and commercial consequences. It
is well settled that blacklisting or debarment cannot be sustained
unless the principles of natural justice are scrupulously followed. Since
no independent opportunity was afforded to the petitioner before
imposing the penalty of debarment, the said action is violative of the
principles of natural justice and cannot be sustained in law.
14.
Consequently, the writ petition is partly allowed.
15.
The order of debarment/blacklisting contained in the Termination Notice
dated 23.06.2026 is hereby quashed and set aside. However, the
petitioner is relegated to avail the remedy of arbitration under Clause
64.1 of the General Conditions of Contract for adjudication of all other
disputes arising out of or relating to the contract, including the validity
of termination, forfeiture of the Security Deposit, invocation of the
Performance Bank Guarantee and all consequential monetary and
contractual claims. It is made clear that this Court has not expressed
any opinion on the merits of the contractual disputes and all rights and
contentions of the parties are left open to be agitated before the
learned Arbitral Tribunal. No order as to costs.
Sd/(Ravindra Kumar Agrawal)
Judge
sagrika
Sd/(Ramesh Sinha)
Chief Justice
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review