IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 2ND DAY OF MARCH, 2026
PRESENT
THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
AND
THE HON'BLE MR. JUSTICE C.M. POONACHA
COMMERCIAL APPEAL NO. 515 OF 2025
BETWEEN:
1.
M/S S S POLICE PATIL AND COMPANY
ENGINEERS AND CLASS I CONTRACTORS
"MAHA SHARANU", P-149, FIRST FLOOR
APMC YARD, AMARGOL
HUBLI - 580 025
REPRESENTED BY
SAYASGOUDA S POLICE PATIL
AGED ABOUT 59 YEARS
…APPELLANT
(BY SRI YASHODHAR HEGDE, ADVOCATE)
AND:
Digitally
signed by
SRIDEVI S
Location:
High Court
of Karnataka
1.
THE DEPUTY COMMISSIONER
DHARWAD DISTRICT
DHARWAD - 580 001
…RESPONDENT
(BY SRI S.SANTHOSH GOGI, ADDITIONAL ADVOCATE GENERAL
A/W SRI K.S. HARISH, GOVERNMENT ADVOCATE)
THIS
COMAP
IS
FILED
UNDER
SECTION
13(1-A)
OF
COMMERCIAL COURTS ACT, 2015 PRAYING TO PASS AN ORDER
SETTING ASIDE THE ORDER DATED 04.08.2025 PASSED IN
COM.A.P. NO.85/2024 BY THE LXXXIII ADDITIONAL CITY CIVIL AND
SESSIONS JUDGE, COMMERCIAL COURT, BENGALURU (CCH-84)
(ANNEXURE-A) & ETC.
-2-
COMAP No. 515 of 2025
THIS COMMERCIAL APPEAL HAVING BEEN HEARD AND
RESERVED FOR JUDGMENT, COMING ON FOR PRONOUNCEMENT
THIS DAY, JUDGMENT WAS PRONOUNCED AS UNDER:
CORAM: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
and
HON'BLE MR. JUSTICE C.M. POONACHA
C.A.V. JUDGMENT
(PER: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE)
1.
The appellant has filed the present appeal under Section
37(1)(c) of the Arbitration and Conciliation Act, 1996 [A&C Act],
impugning an order dated 04.08.2025 passed by the learned
LXXXIII Additional City Civil and Sessions Judge, Commercial
Court, Bengaluru [Commercial Court] in COM.A.P.No.85/2024.
2.
The respondent had filed the said petition under Section 34 of
the A&C Act, praying for setting aside of the arbitral award dated
14.03.2024 [impugned award] delivered by an Arbitral Tribunal
comprising a sole arbitrator [Arbitral Tribunal]
3.
The impugned award was rendered in relation to disputes that
had arisen between the parties concerning the agreement dated
09.07.2018 [the Agreement].
-3-
COMAP No. 515 of 2025
4.
On 18.11.2017, the respondent issued a notice inviting
tenders for "Improvements of Roads and Drains in Annigeri Town
Municipal
limits
of
Dharwad
District
under
Nagarothana
(Municipality) 3rd phase project". The appellant submitted its bid
pursuant to the said notice. The appellant’s bid was accepted and
he was declared as the successful bidder. The appellant was
entrusted with the execution of works at a total value of
`6,23,67,867/- (Rupees Six Crores Twenty-Three Lakhs SixtySeven Thousand Eight Hundred and Sixty-Seven only). The Letter
of Acceptance [LOA] was issued by the respondent on 22.02.2018,
accepting the appellant’s bid. Thereafter, the parties entered into the
Agreement. The appellant was issued a notice dated 09.07.2018 to
proceed. Under the Agreement, the appellant was required to
commence work within two weeks of the notice.
5.
The appellant claimed that immediately after receipt of the
work order, it mobilised all the necessary resources to commence
and complete the work in accordance with the construction
programme. The execution of works was delayed on account of
various reasons, which the appellant claims were attributable to the
respondent. It claimed that the road from the bus stand to Agse
cross traversed a private property for about 688 meters. The said
-4-
COMAP No. 515 of 2025
property was not acquired by the respondent, and thus, the
appellant was unable to enter the same to execute the works.
Additionally, there was a delay in issuing the 'Good fit for
construction' drawings for the road works; a portion of the site was
not handed over, and the relocation of electrical poles was delayed.
These issues delayed the execution of the works. The appellant
claimed that for various reasons, it would execute works to an
extent of only `4,50,29,972/-, that is, only 72.2% of the total work to
be executed under the Agreement. This was solely for the reason
attributable to the respondent. The appellant claimed that it
submitted its fourth and final bill along with a price adjustment bill for
a sum of `46,87,473/-. It claimed that the respondent was unable to
provide all work fronts even after 17 months had elapsed, and that it
had become aware that the respondent was also proposing to take
up alternative works from the remaining amount allocated for the
said works under the Agreement.
6.
The principal dispute concerns the appellant’s claim for price
adjustment.
The project management consultant, M/s. Niketan
Consultants, Bengaluru, recommended the payment of the price
adjustment bill amounting to `46,87,473/- in terms of Clause 40 of
the Conditions of Contract [GCC]. The appellant claimed that the
-5-
COMAP No. 515 of 2025
Director, Directorate of Municipal Administration, also furnished a
report regarding the price adjustment bill. However, the respondent
failed to pay the amounts due. In view of the above, the appellant
invoked the arbitration agreement and sought the appointment of a
sole arbitrator under Clause 4 of the Special Conditions of Contract.
Since the Arbitral Tribunal was not constituted, the appellant filed a
petition (CMP No. 100001/2023), and, by an order dated
10.03.2023, a former Judge of this Court was appointed as the Sole
Arbitrator.
7.
The appellant filed the statement of claims before the Arbitral
Tribunal, raising the following claims.
"(i) Pending Price Adjustment Bill : Rs.44,48,415.00
(ii) Interest on delayed payment of RA Bill No.2:
Rs.1,07,567.00.
(iii) Expenditure on Legal and other Charges.
(iv) Interest charges on the above Claim No.(i) At 18%
per annum from the date they arose i.e., from 21-102020 to 31-08-2023"
8.
The respondent did not participate in the arbitral proceedings
despite receiving notice thereof. Consequently, the Arbitral Tribunal
proceeded to examine the claim without awaiting the respondent’s
participation. The appellant led evidence in order to establish its
claims. The Arbitral Tribunal formulated various points for
determination, including whether the appellant established that it
-6-
COMAP No. 515 of 2025
was entitled to a pending price adjustment bill to the extent of
`44,48,415/-.
9.
We consider it apposite to refer to the following extract of the
impugned award, which indicates that the Arbitral Tribunal had
examined the material before and had accepted the appellant’s
claim for the pending price adjustment bill:
"23. The Ex.P7 is the submission of Price Adjustment Bill
as per clause 40 of condition of contract and Claimant has
also sent a copy of it to the team leader Niketan
Consultants. Ex.P8 is the letter addressed to the
Respondent by the Claimant claiming Price Adjustment
Bill. Ex.P9 is a letter addressed by Niketan Consultants
wherein they have also referred to the agreement and
letter of Claimant and they have also recommended that
the Claimant is entitled for Price Adjustment Bill for
Rs.46,87,473/-. Based on that letter the Respondent has
sent a letter as per Ex.P10 to the Director of Directorate
Municipal Administration. In the said letter, it is mentioned
by the Respondent that the Claimant has carried out the
work as per the tender in respect of 9 works out of 12 and
he could not take up the remaining 3 works because of
obstruction and objection by the public. Therefore on
06.12.2020 after discussion with the District Incharge
Minister, the department decided to take up alternative
work. It is also mentioned that the bills in respect of 9
carried out work was paid within due date. It is also
mentioned that as the problems could not be solved
Inspite of expiry of tender period, the Claimant was
requested Respondent to close the tender and has
claimed the Price the Adjustment Bill. The said letter also
shows that the project management consultants has also
recommended for payment of the said bill. It is also
mentioned that the bill was prepared with star rate and
labour charge. Therefore it is requested that as the tender
amount was more than Rs.5 crores and as the tender was
approved by the Director and as per clause 40 of the
conditions of contract, requested to grant the Price
-7-
COMAP No. 515 of 2025
Adjustment Bill.
24. Ex. P11 is a letter in reply to Ex. P10 addressed by
Director, Municipal Administration dated 24.12.2021
wherein the Director has informed the Respondent to take
action as per the tender contract terms and conditions at
his level.
25. These Exs.P9, P10 and P11 documentary evidence
which are produced by the Claimant are not disputed or
denied by the Respondent. There is no statement of
objection filed by the Respondent nor the evidence given
by PW1 on oath is denied by the Respondent.
Documentary evidence Exs.P9, P10 and P11 corroborate
the oral evidence of PW1 and contents of claim statement.
The evidence placed before the Tribunal clearly shows
that the Claimant could not complete all the 12 works in
view of inaction on the part of the Respondent. He could
complete 9 works within the stipulated period of tender
and three works he could not complete because of the
delay and inaction on the part of the Respondent to hand
over the drawing and sites. On the other hand the
Claimant has brought to the notice of the Respondent the
delay and obstruction in carrying out the work because of
inaction on the part of the Respondent. But inspite of that
the tender was not closed nor Claimant was allowed to
carry out the three works. On the other hand on
06.12.2020 alternative work was taken by a discussion
with the local MLA the monitoring committee submitted a
alternative action plan proposal on 06.12.2020 and got its
approval on 07.12.2020. Therefore, the Claimant is
entitled for the Price Adjustment Bill. The Claimant has
also produced Ex. P18 letter addressed to team manager
wherein he has enclosed details for consideration in
arriving the price adjustment calculation, The Claimant
has taken the location, price adjustment formula used and
base index. The said document is not denied by the
Respondent. On the other hand, it is deem to have been
admitted by the Respondent and the said bill is also
recommended by the project management consultant
also.
26. If at all the Claimant is not entitled for the said Price
Adjustment Bill in terms of clause 40 of conditions of
contract, the Respondent could have denied it or could
have shown that the calculation arrived by the Claimant is
not correct or not admissible. The Respondent has neither
-8-
COMAP No. 515 of 2025
denied the claim statement by filing the statement of
objection nor denied oral evidence and documentary
evidence placed by the Claimant. Therefore, an adverse
inference will have to be drawn against the Respondent to
the effect that the claim in respect of price adjustment bill
amounting to Rs.44,48,415/- is not denied by the
Respondent on the other hand it is admitted by the
Respondent. Absolutely I find no grounds to deny the said
relief claimed by the Claimant which is supported by both
oral and documentary evidence. Accordingly, I answer
point no.1 in the affirmative."
10.
The Arbitral Tribunal allowed the claim for price adjustment
along with interest at the rate of 9% per annum from 09.03.2022 till
the date of the impugned award. However, it rejected the appellant's
claim for interest on delayed payment. Additionally, the Arbitral
Tribunal also awarded future interest at the rate of 15% per annum
on the claims awarded and awarded `2,50,000/- towards arbitrator's
fee, costs and expenses.
11. The respondent challenged the impugned award before the
learned Commercial Court mainly on two grounds. First, it claimed
that the impugned award was rendered without compliance with the
principles of natural justice, and the respondent was disabled from
effectively contesting the case. It gave an elaborate explanation of
why it could not attend the hearing before the Arbitral Tribunal
despite the notices. Second, it claimed that the price adjustment bill
under Clause 40 of the GCC was applicable only to contracts that
-9-
COMAP No. 515 of 2025
stipulated a completion period of more than 12 months. It argued
that since the Agreement was for a term of 12 months, the said
clause was inapplicable.
12. The learned Commercial Court rejected the contention that
the impugned award was rendered in violation of principles of
natural justice. The court found that the respondent had been given
notice of the Arbitral proceedings, and it was unable to establish any
impediment to appearing before the Arbitral Tribunal to present its
defence.
13.
However, the learned Commercial Court concluded that there
was a conflict between Clause 40 and Clause 40.1 of the GCC.
Whereas, in terms of Clause 40.1, the contract price was required to
be adjusted for an increase or decrease in rates and prices of
labour, materials, fuels and lubricants. However, Clause 40 also
referred to two government orders: the Government Order dated
26.11.2004 and the Government Order dated 21.11.2008. The
Court noted that in terms of the Government Order dated
21.11.2008, where the period of execution was more than 6 months,
but less or equal to 12 months, “star rates” in respect of specified
material (cement, steel and bitumen) only would be payable. The
Court noted an inherent contradiction between Clauses 40 and 40.1
- 10 -
COMAP No. 515 of 2025
of the GCC, as Clause 40.1 of the GCC also provided price
adjustment on account of variation in rates and prices of labour and
fuel.
14.
The learned Commercial Court also referred to the letter
written by the appellant to the respondent, which indicated that the
price adjustment bill had been prepared, adopting the formula in
respect of the components of labour, cement, steel, bitumen, fuel,
lubricants, plant and machinery and other materials.
15.
The learned Commercial Court concluded that the price
adjustment bill was contrary to the Government Order dated
21.11.2008, which would necessarily require the price adjustment to
be confined to cement, steel and bitumen. The Court observed that
this crucial aspect had not been brought to the learned Arbitral
Tribunal's notice and had escaped its attention. Additionally, the
learned Commercial Court also noted that under Cause 40.1, price
adjustment only for labour, material, fuel and lubricants was
permissible. But, the appellant had claimed price adjustment for
plant and machinery as well. The learned Commercial Court noted
that plant and machinery was not one of the resources for which
price adjustment is provided under Clause 40.1 of the GCC.
- 11 -
COMAP No. 515 of 2025
16.
In view of the above, the learned Commercial Court set aside
the impugned award.
REASONS AND CONCLUSIONS
17.
It is apparent from the above that the learned Commercial
Court has embarked on adjudication of the question whether the
price adjustment bill would fall within the terms of the Government
Order dated 21.11.2008. This was not an issue raised before the
Arbitral Tribunal.
18.
A plain reading of the grounds of challenge indicates that it
was the respondent's case that Clause 40 of the GCC is
inapplicable because the duration of the contract was twelve
months. The appellant has contested the same. The appellant
argued that the contract term should be extended because the delay
was attributable to the respondent. The impugned judgment
proceeds beyond the grounds of challenge raised by the
respondent. The learned Commercial Court has proceeded on the
basis that there were issues regarding, (a) the questions regarding a
conflict between Clauses 40 and 40.1 of the GCC and whether
Clause 40 or Clause 40.1 of the COC was applicable; and (b)
- 12 -
COMAP No. 515 of 2025
whether the price adjustment on account of plant and machinery fell
within the scope of Clause 40.1 of COC.
19.
We may at this stage note the clauses that were interpreted
by the learned Commercial Court. Clause 40 and 40.1 of the GCC
are set out below:
"40. Price Adjustment: (Refer GOK Order No.FD 59
Pro.Cell 2004, Bangalore Dated 26th November 2004
AND Government order No. FD 3 PCL 2008,
Bangalore, Dated :21-11-2008).
40.1 Contract price shall be adjusted for increase or
decrease in rates and prices of labour, materials, fuels
and lubricants in accordance with the following
principles and procedures and as per formulae given in
the Contract Data.
(a) The price Adjustment shall apply for the work done
from the date of commencement up to the end of
original period of completion or extensions granted by
the Employer and shall not apply to work carried out
beyond the stipulated period of completion for reasons
attributable to the Contractor;
(b) Price Adjustment shall be admissible from the date
of opening of tenders (original or extended)
(c) The price adjustment shall be determined during
each quarter from the formulae given in Contract Data.
(d) Following expressions and meanings are assigned
to the work done during the quarter.
R = Total value of work done during the quarter. It will
exclude value for works executed under variations for
which price adjustment (if any) will be worked out
separately based on the terms mutually agreed."
- 13 -
COMAP No. 515 of 2025
20.
Since Clause 40.1 also refers to the formulae in Contract
data, it is necessary to refer to the said formulae as well. The same
are set out below:
"Price Adjustment Formula
R=Value of work as defined in Clause 40.1 of Conditions of
Contract.
Adjustment for labour component:
(i) Price adjustment for increase or decrease in the cost
due to labour shall be paid in accordance with the following
formula:
VL=0.85 X PL/100 X R X(Li - Lo Where,
VL = Increase or decrease in the cost of work
during the quarter under consideration due to
changes in rates for local labour;
Lo = The average consumer price index for
industrial workers for ..........Centre for the
quarter preceding the date of opening of
tenders as published by the Labour Bureau,
Ministry of Labour, Government of India;
Li=The average consumer price index for
industrial workers for ..........Centre for the
quarter under consideration as published by
Labour Bureau, Ministry of Labour, Government
of India.
PL = Percentage of labour component of the
work
Adjustment for cement component
(ii) Price adjustment for increase or decrease in the cost of
cement component procured by the contractor shall be
paid in accordance with the following formula.
Vc=0.85 X Pc/100 X R X (Ci-Co)/Co, Where,
- 14 -
COMAP No. 515 of 2025
Vc= Increase or decrease in the cost of the
work during the quarter under consideration
due to changes in the rates for cement,
Co=The all India average wholesale price index
"for cement (Ordinary Portland Cement) for the
quarter preceding the date of opening of the
tenders as published by the Office of Economic
Advisor, Ministry of Commerce and Industry,
Government of India, New Delhi;
Ci = The all India average wholesale price index
for cement (Ordinary Portland Cement) for the
quarter under consideration as published by the
Office of Economic Advisor, Ministry of
Commerce and Industry, Government of India,
New Delhi
Pc = Percentage of cement component of the
work.
Note: For the application of this clause index of Ordinary
Portland Cement has been chosen to represent Cement
Group
Adjustment for steel component.
(iii) Price adjustment for increase or decrease in the cost of
steel procured by the contractor shall be paid in
accordance with the following formula.
Vs=0.85 XPs/100 X R X (Si-So/So, where,
Vs=Increase or decrease in the cost of work
during the quarter under consideration due to
changes in the rates for steel;
So=The all India average wholesale price index
for steel (steel rods) for the quarter preceding
the date of opening of Bids as published by the
Office of Economic Advisor, Ministry of
Commerce and Industry, Government of India,
New Delhi
Si=The all India average wholesale price index
for steel (steel rods) for the quarter under
consideration as published by the Office of
Economic Advisor, Ministry of Commerce and
Industry, New Delhi
- 15 -
COMAP No. 515 of 2025
Ps=Percentage of steel component of the work.
Note: For the application of this clause, index of steel rods
has been chosen to represent steel group.
Adjustment of Bitumen Component:
(iv) Price adjustment for increase or decrease in the cost of
bitumen shall be paid in accordance with the following
formula:
VB=0.85 X PB/100 X R X (Bi-Bo)/BO., Where
VB = Increase or decrease in the cost of work
during the quarter under consideration due to
changes in the rate for bitumen.
BO = The official retail price of bitumen at the
.......depot at..... on the day 30 days prior to the
date of opening of Bids.
Bi = The official retail price of bitumen at
the........ depot, at ...........for the 15th day of the
middle calendar month of the quarter under
consideration.
PB = Percentage of bitumen component of the
work.
Adjustment of Fuel and Lubricant component:
(v) Price adjustment for increase or decrease in cost of
Fuel and Lubricants shall be paid in accordance with the
following formula:
VF=0.85 X PF/100 X R X (Fi-Fo)/ Fo, Where,
VF = Increase or decrease in the cost of work
during the quarter under consideration due to
changes in the rates for Fuel and Lubricants.
Fo = The official retail price of High Speed
Diesel (HSD) at the IOC/HPCL/BPCL at..... on
the day 30 days prior to the date of opening of
Bids.
Fi=The official retail price of HSD at the
IOC/HPCL/BPCL at .....for the 15th day of the
- 16 -
COMAP No. 515 of 2025
middle calendar month of the quarter under
consideration
PF = Percentage of Fuel and Lubricant
component of the work.
Note: For the application of this Clause the price of HSD
has been chosen to represent Fuel and Lubricant Group
Adjustment for Construction Machinery Component:
(vi) Price adjustment for increase or decrease in the cost of
Construction Machinery procured by the contractor shall be
paid in accordance with the following formula:
VF =0.85 X PCM /100 X R X (Pi-Po)/Po, Where
VF=Increase or decrease in the cost of work
during the quarter under consideration due to
changes in the rates for Construction
Machinery.
PO=The all India average wholesale price index
for Construction Machinery for the quarter
preceding the date of opening of bids, as
published by the Office of the Economic
Advisor, Delhi Ministry of Commerce and
Industry, Government of India, New Delhi
Pi=The all India average wholesale price index
for Construction Machinery for the quarter
under consideration as published by the Office
of the Economic Advisor, Ministry of Commerce
and Industry, Government of India, New Delhi
Note: For the application of this Clause index of
Construction Machinery has been chosen to represent the
Construction Machinery Group.
Adjustment for Other materials.:
(vii) Price adjustment for increase or decrease in the cost
of other materials other than cement, steel, bitumen and
Fuel and Lubricants, procured by the contractor shall be
paid in accordance with following formula:
VM=0.85 X PM/100 X R X (Mi-Mo)/Mo, Where
VM = Increase or decrease in the cost of work
during the quarter under consideration due to
- 17 -
COMAP No. 515 of 2025
changes in the rates for local materials other
than cement, steel, bitumen and Fuel and
Lubricants.
MO=The all India average wholesale price
index for all commodities for the quarter
preceding the date of opening of bids, as
published by the Office of the Economic
Advisor, Ministry of Commerce and Industry,
Government of India, New Delhi
Mi=The all India average wholesale price index
for all commodities for the quarter under
consideration as published by the Office of the
Economic Advisor, Ministry of Commerce and
Industry, Government of India, New Delhi
PM=Percentage of other material component
(Other than cement, steel, bitumen and Fuel
and Lubricants) of the work.
The following percentages will govern the price adjustment
for the entire contract:
1. Labour- PL
2. Cement -PC
3. Steel -Ps
4. Bitumen -PB
5. Fuel and Lubricants- PF6. Construction MachineryPCM
7. Other materials - PM
TOTAL
28%
4%
5%
13%
5%
20%
25%
100%
The liquidated damages for the whole of the works are
For Milestone 1: Rs 18945/- per day
For Milestone 2: Rs 18945/- per day
For Milestone 3: Rs 25200/- per day
The maximum amount of liquidated damages for the whole
of the works is 10% (ten percent) of final contract price
The amounts of the advance payment are:
Name of Advance
1. Mobilization
Amount (Rs.)
5%
of
the
Contract price
Conditions to be fulfilled
On
submission
of
unconditional Bank Guarantee,
- 18 -
COMAP No. 515 of 2025
(to be drawn before end of
20% of Contract period)
(The advance payment will be paid to the Contractor no
later than 30 days after fulfillment of the above conditions).
Repayment of advance payment for mobilization:
The advance loan shall be repaid with percentage
deductions from the interim payments certified by the
Engineer under the Contract. Deductions shall commence
in the next Interim Payment Certificate following that in
which the total of all such payments to the Contractor has
reached not less than 15 percent of the Contract Price or 3
months from the date of payment of first installment of
advance, whichever period concludes earlier, and shall be
made at the rate of 7.5% percent of the amounts of all
Interim Payment Certificates until such time as the loan
has been repaid, always provided that the loan shall be
completely repaid prior to the expiry of the original time for
completion pursuant to Clauses 17 and 26.
The date by which "as-built" drawings in 2 sets are required
is within 30 days of issue of certificate of completion of
Whole or Section of the Work as the case may be.
The date by which Operating and Maintenance Manuals
are required is within 30 days of issue of certificate of
completion of Whole or Section of the Work as the case
may be.
The amount to be withheld for failing to supply "as built"
drawings or supply of Operation and Maintenance Manuals
by the date required is 0.5 %of the contract value
The following events shall also be fundamental breach of
the contract:
1. The contractor has contravened Sub-clause 71 and
Clause 9 of CC. The percentage to apply to the value of
the work not completed representing the Employer's
additional cost for completing the Works shall be 30
percent."
- 19 -
COMAP No. 515 of 2025
21.
The learned Commercial Court had noted that there was a
conflict between Clause 40 and Clause 40.1 of the GCC. Whereas,
Clause 40.1, expressly provided that if the contract price would be
adjusted for increase or decrease in the rates and prices of labour,
materials, fuels and lubricants, Clause 40 referred to Government
Orders dated 26.11.2004 and 21.11.2008 in parenthesis.
22.
The relevant extract of the Government Order dated
21.11.2008 is set out in the impugned order, is reproduced below:
“In the circumstances explained in the preamble, in
modification of the Government Order dated 26-11-2004,
it is directed that the following price adjustment methods
are applicable hereafter.
a) For all works costing more than Rs. 50 lakhs, if the
period of execution is more than 12 months, the price
adjustment will be calculated as prescribed in Annexure to
G.O. No. FD-59 Pro-Cell 2004 dated 26-11-2004.
b) If the period of execution is more than 6 months but
less than or equal to 12 months, for work costing more
than Rs. 50 lakhs, star rates in respect of specified
material, (cement, steel and bitumen) only shall be
payable to the contractor based on the All India Average
Wholesale Price Index for the said materials. The star
rates adjustment shall be as per the increase or decrease
in the index as applicable to the said materials between
the last date for receiving bids and the date of execution
as per the approved program of work submitted by the
contractor at the time of execution of agreement which
shall mandatorily be part of the agreement.
(Emphasis Supplied)"
- 20 -
COMAP No. 515 of 2025
23.
The learned Commercial Court had held that in terms of the
said government order dated 21.11.2008, star rates were applicable
in respect to material (cement, steel and bitumen) only. However,
the respondent's case was that the contract, as required, should be
considered to be more than 12 months, as the period of execution
would also take into account the extension. Reference to Clause
40.1(a) clearly indicates that extensions granted are required to be
considered along with the initial terms of the contract. Admittedly, in
terms of Clause 40.1, the contract price is required to be adjusted
for an increase or decrease in rates and prices for labour, materials,
fuels and lubricants. Even if the Government Order dated
21.11.2008 is held to be applicable but the appellant's contention
that it was entitled to extension time is accepted, the appellant
would be entitled to price adjustment for labour, materials, fuels and
lubricants, and its claim could not be confined to material alone. The
appellant’s claim that it was entitled to an extension is based on its
assertion that the delay was attributable to the respondent. This
contention has been accepted by the Arbitral Tribunal.
24.
The formulae referred to in Clause 40.1 clearly provided price
adjustment for material, labour, fuel and plant and machinery.
- 21 -
COMAP No. 515 of 2025
25.
In our view, it is clear from the above that the question of
whether the appellant's claim was sustainable under the terms of
the contract could at best be a contentious issue. If this issue was
raised, the Arbitral Tribunal would be required to adjudicate the
same. However, as noted above, the respondent, despite the
opportunity, did not contest the claim before the Arbitral Tribunal. It
is clearly not open for the respondent to insist on fresh adjudication
of contentious question before the learned Commercial Court,
unless the Court finds that the award is ex-facie, vitiated by patent
illegality, the award cannot be set aside on that ground. The
illegality must be apparent on the face of the award and must go to
the root of the dispute. The jurisdiction of the learned Commercial
Court is confined to examining whether the arbitral award is required
to be set aside on the grounds as set out in Section 34 of the A&C
Act.
26.
It is difficult to accept that the impugned award is, ex facie,
contrary to the terms of the Agreement. As noted above, the
question at the very least would require interpreting the terms of the
Agreement. Concededly, the appellant’s claim is sustainable under
clause 40.1 of the GCC. The question as to whether there was a
conflict between Clause 40 and 40.1 of the GCC and the
- 22 -
COMAP No. 515 of 2025
interpretative exercise required for addressing the same, excludes it
from the scope of Section 34 of the A&C Act. We are unable to
accept that the impugned award is vitiated by patent illegality on its
face or is in conflict with the public policy of India.
27.
Before concluding, we may also note that the learned
Commercial Court had referred to the appellant’s letter, which
indicated that it had also claimed price variation in respect of plant
and machinery, which is not covered under Clause 40.1 of the COC.
However, the formulae referred to in clause 40.1 also provide for
variation on account of the plant and machinery component. In our
view, this at best would be a contentious issue. It may have
warranted examination before the Arbitral Tribunal if any such
dispute had been raised. It is not disputed that no such objection
had been raised in respect to the price variation bill raised by the
respondent at the material time.
28.
The learned counsel appearing for the respondent also stated
that there was no contemporaneous communication by the
respondent raising the said issue.
29.
As noted above, the application filed under Section 34 of the
A&C Act also does not mention any such ground. We are unable to
- 23 -
COMAP No. 515 of 2025
accept that any interference with the impugned award is warranted
under Section 34 of the A&C Act.
30.
The appeal is accordingly allowed, and the impugned order is
set aside.
31.
Parties are left to bear their own costs.
Sd/(VIBHU BAKHRU)
CHIEF JUSTICE
Sd/(C.M. POONACHA)
JUDGE
KPS
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review