IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on: 9th September, 2026
Judgment pronounced on: 18th November, 2026
#
CNR No. DLHC012087892017
+
W.P.(C) 3676/2017 with CM APPL. 16178/2017, CM APPL.
38319/2023 and CM APPL. 47390/2026
M/S R.B. SAXENA AND SONS
.....Petitioner
Through: Mr. Rajesh Vashisht and Mr. Piyush
Kumar, Advocates.
versus
EAST DELHI MUNICIPAL CORPORATION
& ORS
.....Respondents
Through: Mr. Sanjay Vashishtha, Standing
counsel for MCD with Mr. Siddhartha
Goswami and Mr. Aditya Sachdeva,
Advocates for MCD.
#
CNR No. DLHC011979802018
+
W.P.(C) 8294/2018 with CM APPL. 62590/2025
JOGINDER SINGH WADHAWA
.....Petitioner
Through: Mr. Vaibhav Agnihotri, Ms. Vagmi
Singh, Mr. Chaitanya Malhotra, Mr.
Jai Raj Maini and Ms. Yashi Pandey,
Advocates.
versus
EAST DELHI MUNICIPAL CORPORATION
& ORS
.....Respondents
Through: Mr. Sanjay Vashishtha, Standing
counsel for MCD with Mr. Siddhartha
Goswami and Mr. Aditya Sachdeva,
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
#
Advocates for MCD.
CNR No. DLHC010214632019
+
W.P.(C) 4824/2019
M/S S G CONSTRUCTIONS
.....Petitioner
Through: Ms. Chandrika Prasad Mishra, Mr.
Ankit Pandey, Ms. Swati Surbhi, Ms.
Prashasti Singh, Ms. Harshita
Bhardwaj, and Ms. Priyanshi Kumari,
Advocates.
versus
#
EAST DELHI MUNICIPAL CORPORATION
AND ORS.
.....Respondents
Through: Mr. Sanjay Vashishtha, Standing
counsel for MCD with Mr. Siddhartha
Goswami and Mr. Aditya Sachdeva,
Advocates for MCD.
CNR No. DLHC010216182019
+
W.P.(C) 4849/2019
KHAJAN SINGH
.....Petitioner
Through:
Ms. Chandrika Prasad Mishra, Mr.
Ankit Pandey, Ms. Swati Surbhi, Ms.
Prashasti Singh, Ms. Harshita
Bhardwaj, and Ms. Priyanshi Kumari,
Advocates.
versus
EAST DELHI MUNICIPAL
CORPORATION & ORS
Through:
#
.....Respondents
Mr. Sanjay Vashishtha, Standing
counsel for MCD with Mr. Siddhartha
Goswami and Mr. Aditya Sachdeva,
Advocates for MCD.
CNR No. DLHC010325972021
+
W.P.(C) 11919/2021 & CM APPL. 62325/2025
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
SAI INTERPRISES THROUGH ITS
PROPRIETOR UMESH KUMAR
.....Petitioner
Through: Mr. Vaibhav Agnihotri, Ms. Vagmi
Singh, Mr. Chaitanya Malhotra, Mr.
Jai Raj Maini and Ms. Yashi Pandey,
Advocates.
versus
EAST DELHI MUNICIPAL
CORPORATION & ANR.
Through:
.....Respondents
Mr. Sanjay Vashishtha, Standing
counsel for MCD with Mr. Siddhartha
Goswami and Mr. Aditya Sachdeva,
Advocates for MCD.
CORAM:
HON’BLE MR. JUSTICE AMIT BANSAL
JUDGMENT
AMIT BANSAL, J.
1.
The present writ petitions have been filed seeking directions to the
respondents to release amounts withheld and deducted from the bills of the
petitioners towards ‘Foul Condition’ charges, along with interest thereon.
The petitioners also seek quashing of the communications issued by the
respondent, East Delhi Municipal Corporation (‘EDMC’), whereby the
recovery of the aforesaid amounts was communicated to the petitioners.
2.
Since all the present writ petitions involve common issues arising out
of the withholding and recovery of ‘Foul Condition’ charges payable under
contracts awarded by EDMC, the petitions are being disposed of by way of a
common judgment. However, for the sake of convenience, the facts of
W.P.(C.) 8294/2018 are being noted.
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
3.
The petitioner is engaged in the business of providing vehicles with
auto-tipping facilities for lifting Municipal Solid Waste (‘MSW’), including
garbage and drain silt and dumping the same at designated sites.
4.
On 18th January, 2011, the Municipal Corporation of Delhi (‘MCD’)
issued a communication concerning the rates payable for the deployment of
labour under general and foul conditions. The rate per vehicle per day was
fixed at Rs.668/- under ‘General Purposes’ and Rs.835/- under ‘Foul
Condition’. The rate for one beldar was Rs.238/- per day under ‘General
Purposes’ and Rs.297/- per day under ‘Foul Condition’.
5.
On 22nd February, 2012, MCD issued Notice Inviting Tender (‘NIT’)
for hiring vehicles for lifting municipal solid waste, garbage and drain silt.
6.
The petitioner participated in the tender process and was one of the
successful bidders. The petitioner was allocated work in the Shahdara
(South) and Shahdara (North) Zones, involving the deployment of 70 autotipping vehicles.
7.
Before the work order could be issued, in March, 2012, MCD was
trifurcated into three separate municipal corporations, namely, North Delhi
Municipal Corporation (‘NDMC’), South Delhi Municipal Corporation
(‘SDMC’) and East Delhi Municipal Corporation (‘EDMC’). Consequently,
the work allocated to the petitioner in the Shahdara Zones came under the
jurisdiction of EDMC.
8.
During the period from 2012 to 2014, EDMC issued five work orders
in favour of the petitioner. However, the provision relating to the enhanced
rate for beldars deployed under foul conditions was specifically not
incorporated in the work orders issued by EDMC.
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
9.
From 2012 until February, 2016, EDMC released payments to the
petitioner, including amounts calculated at the rate applicable to foul
conditions.
10.
With effect from March 2016, without any prior notice or intimation,
the respondents began deducting 25% of the gross bill amount towards ‘Foul
Condition charges’ while releasing the payments to the petitioner.
11.
During 2016, the petitioner submitted representations seeking
payment of the amounts deducted and incorporation of the provision relating
to ‘Foul Condition charges’ in the work orders.
12.
Upon receiving no response, Joginder Singh Wadhwa [petitioner in
W.P.(C.) 8294/2018] filed a writ petition, W.P.(C.) 10376/2016, which was
disposed of on 4th November, 2016, directing EDMC to decide
his
representation dated 24th September, 2016, within six weeks.
13.
As no decision was taken, Joginder Singh Wadhwa filed another writ
petition, W.P.(C.) 385/2017. During the pendency of the writ petition, the
respondents passed an order rejecting the representation. Accordingly, on
16th January, 2017, the petition was disposed of with liberty to Joginder
Singh Wadhwa to challenge the said decision.
14.
Joginder Singh Wadhwa thereafter filed another writ petition,
W.P.(C.) 1326/2017, which was disposed of on 15th February, 2017,
permitting him to make a fresh representation to the respondents and
directing the respondents to decide the same within four weeks.
15.
On 22nd February, 2017, and 22nd May, 2017, Joginder Singh Wadhwa
submitted further representations. Since his representations were not being
decided, he instituted Cont. Cas. (C) No. 587/2017 against the respondents.
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
16.
By communication dated 21st August, 2017, EDMC rejected the
representations, inter alia, on the ground of delay. The petitioners contend
that the said communication did not address their grievance on merits.
17.
The contempt petition was disposed of on 23rd August, 2017, with
liberty to Joginder Singh Wadhwa to challenge the decision dated 21st
August, 2017, in accordance with law.
18.
By a common communication dated 12th February, 2018, EDMC
informed the affected contractors, including all the petitioners herein, that
excess payments had been made towards Foul Condition charges and that
the excess amounts were being recovered from their bills. The
communication enclosed statements setting out the amounts withheld from
the petitioners’ bills up to December 2017.
19.
Aggrieved therefrom, Joginder Singh Wadhwa has approached this
Court under Article 226 of the Constitution of India seeking the following
reliefs:
“(i) A Writ of Certiorari or any other writ, order or direction calling for
the records of the matter and peruse the same.;
(ii) A Writ of Certiorari or any other writ, order or direction thereby
quashing the impugned action of the respondents in making illegal,
arbitrary, discriminatory and malafide deductions from the petitioner's
payments under the garb of alleged recovery of 'Foul Condition' amount
which was earlier paid to the petitioner for most genuine and correct
reasons, as has been intimated to the petitioner vide letter dated
12.02.2018 together with detail of impugned deductions [ANNEXURE-P18 (Colly)];
(iii) A Writ of Certiorari or any other writ, order or direction thereby
quashing and setting aside the communication/ letter dated 21.08.2017
(ANNEXURE-P-16) issued by the respondents whereby petitioner's most
genuine and bonafide request to rectify an apparent and inadvertent
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
mistake occurred in the work orders issued by them has been rejected
without assigning any plausible and justifiable reason;
(iv) A Writ of Mandamus or any other writ, order or direction thereby
directing the respondents to rectify the mistakes occurred in the Work
Orders issued by them to the petitioner and incorporate the 'Foul
Condition' clause therein similar to the same existing in the work orders
issued by the other Municipal Corporations of Delhi and thereafter, to
pay the Foul Condition chargers to the petitioner, as was being paid
earlier;
(v) A Writ of Mandamus or any other writ, order or direction thereby
directing the respondents to refund/release the entire amount of the
petitioner illegally and arbitrarily withheld/deducted by them on account
of recovery of amount paid for ‘Foul Condition’ together with interest
thereon;”
20.
The petitioners in the other writ petitions have also filed petitions
seeking similar reliefs.
21.
A counter-affidavit has been filed on behalf of the respondents,
contending that the contracts awarded to the petitioners contained specific
terms for payment. There were excess payments made inadvertently, which
were subsequently detected pursuant to audit and vigilance objections,
following which such payments were discontinued and the excess amount
was recovered.
SUBMISSIONS ON BEHALF OF THE PETITIONERS
22.
The principal contention of the petitioners is that the deductions and
recoveries made by EDMC towards foul condition charges are arbitrary and
contrary to the terms governing the contracts awarded to them.
23.
It is submitted on behalf of the petitioners that the MCD had
prescribed a rate of Rs.297/- per day for labour deployed under foul
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
conditions, as against Rs.238/- per day for general conditions. The
petitioners contend that the work undertaken by them involved lifting and
transporting municipal solid waste, garbage and drain silt and, therefore, fell
within the category of work performed under foul conditions.
24.
The petitioners further submit that the respondents’ own affidavits
and internal records acknowledge that the work involved the lifting and
transportation of municipal waste under foul conditions and that the rate of
Rs.297/- was associated with such work. The respondent has merely
characterised such payments as inadvertent excess payments pursuant to
audit observations, without disputing the material factual assertions of the
petitioners. Accordingly, it is submitted that no substantial dispute of fact
survives for adjudication.
25.
It is further submitted that the work orders were issued pursuant to the
tender process initiated by the MCD and that the petitioners were paid foul
condition charges for approximately three-and-a-half to four years.
According to the petitioners, EDMC could not subsequently treat the
payments made in accordance with the contractual arrangement as excess
payments and recover the same unilaterally.
26.
It is also contended that the deductions commenced without any prior
notice or show-cause notice and without affording them an opportunity to
explain their position, hence, the impugned action is arbitrary and violative
of Article 14 of the Constitution of India.
27.
The NDMC and SDMC, which emerged from the trifurcation of the
MCD, continued to pay foul condition charges to contractors engaged in
similar work. It is contended that the differential treatment meted out to
contractors engaged by EDMC is discriminatory.
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
28.
On the objection of maintainability, the petitioners submit that the
mere existence of a contractual relationship does not bar the exercise of writ
jurisdiction under Article 226 of the Constitution of India, where the action
complained of is arbitrary and has been taken by a statutory authority.
Reliance is placed on the judgment of the Supreme Court in ABL
International Ltd. v. Export Credit Guarantee Corporation of India1 and
Union of India v. Tantia Construction2, and Kumari Shrilekha Vidyarthi
v. State of U.P3.
29.
With regard to limitation, the petitioners submit that the cause of
action arose when EDMC commenced withholding the foul condition
charges and, subsequently, when the recovery amount was communicated to
the petitioners on 12th February, 2018. It is contended that even though
deductions of 25% foul condition charges commenced only from March
2016, the communication to the petitioners from the respondents confirming
withheld amounts was issued only on 12th February, 2018, and that is the
earliest common cause of action crystallising the grievance for all
petitioners.
SUBMISSIONS ON BEHALF OF THE RESPONDENTS
30.
Per contra, the respondents oppose the writ petitions on the ground
that the claims raised by the petitioners arise out of concluded contractual
arrangements and are, therefore, not amenable to adjudication under Article
226 of the Constitution of India.
(2004) 3 SCC 553
(2011) 5 SCC 697
(1991) 1 SCC 212
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
31.
It is further submitted that the dispute involves the interpretation of
the contractual terms, the applicability of the rates prescribed under the
tender documents and the computation of the amounts allegedly payable or
recoverable under the respective work orders. According to the respondents,
such disputes ought to be agitated before the appropriate civil forum rather
than in proceedings under Article 226 of the Constitution.
32.
It is submitted that the work orders were issued between 2012 and
2014 and that the petitioners did not challenge their terms at the time of
issuance. According to the respondents, the ‘Foul Condition’ clause was
absent from the written terms of the work orders, unlike the work orders
issued by the other municipal corporations.
33.
The respondents contend that if the petitioners were aggrieved by the
omission of a specific ‘Foul Condition’ clause from the work orders, the
grievance ought to have been raised when the work orders were issued. The
petitioners cannot, after the contracts have expired by efflux of time, seek a
direction from this Court to incorporate a term into the contracts or to grant
monetary relief on that basis.
34.
The respondents further submit that the cause of action, at the latest,
arose in March 2016, when deductions from the petitioners’ bills
commenced. The petitioners were aware of the deductions but did not
approach this Court within a reasonable period.
35.
It is contended that the representations submitted by the petitioners
and the subsequent communications issued by EDMC do not give rise to a
fresh cause of action. The petitioners cannot extend the period for
approaching this Court by submitting successive representations and treating
the rejection of each representation as a fresh starting point for limitation.
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
Reliance is placed on Rabindra Nath Bose v. Union of India4, P.S.
Sadasivaswamy v. State of Tamil Nadu5, and Karnataka Power
Corporation Ltd. v. K. Thangappan6.
36.
The respondents also submit that the intervening writ and contempt
proceedings initiated by the petitioners did not determine the substantive
dispute on merits and did not grant any stay against the deductions. It is
contended that the liberty granted to the petitioners to pursue their remedies
in accordance with law did not revive any claim that had otherwise become
stale.
37.
On the merits of the dispute, the respondents rely upon their stand that
the payments made towards foul condition charges were in excess and were
liable to be recovered pursuant to the observations made by the audit
authorities. The respondents contend that the petitioners cannot rely solely
upon the fact that payments were made in the past to claim a continuing
entitlement to such payments.
ANALYSIS AND FINDINGS
38.
I have carefully considered the submissions made on behalf of the
parties and the examined the record of the writ petitions.
39.
Firstly, I shall deal with the merits of the case.
40.
MCD vide its communication dated 18th January, 2011 had declared
the rates for hiring charges of vehicles with auto tipping facilities to carry
out lifting of Municipal Solid Waste including garbage and drain silt from
the narrow lanes and roads of each ward of MCD, in terms of which, the
(1970) 1 SCC 84
(1975) 1 SCC 152
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
rates of vehicles per unit was fixed for Rs.668/- under ‘General Purposes’
and Rs.835/- under ‘Foul Condition’. The rate for ‘Foul Condition’ was 25%
higher than the rate for ‘General Purposes’. The said communication also
provided the differential rates payable in respect of a beldar, i.e. Rs. 238 for
‘General Purposes’ and Rs. 297/- for ‘Foul Condition’. The rate for ‘Foul
Condition’ was 25% higher than the rate for ‘General Purposes’.
41.
The tenders were issued by MCD in 2012 and the petitioners herein
were the successful tenderers. Thereupon, in March 2012, MCD was
trifurcated into three separate municipal corporations. The work allocated to
the petitioners came under the jurisdiction of EDMC.
42.
The petitioners, with effect from 2012, continued to receive work
orders from the respondents. Based on the aforesaid, the respondents
continued to pay the rates applicable to the Foul Condition Charges till
February, 2016.
43.
The grievance of the petitioners is that the respondents, with effect
from March 2016, began to unilaterally and arbitrarily deduct amounts that
were due to the petitioners on account of ‘Foul Condition’ Charges.
44.
Per Contra, respondents contend that there were excess payments
made inadvertently, which were subsequently detected pursuant to audit and
vigilance observations.
45.
Therefore, the issue to be decided in the present writ petition is
whether the respondents were justified in making deductions from the bills
of the petitioners, in respect of the amounts which had been paid towards the
Foul Condition Charges.
(2006) 4 SCC 322
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
46.
The respondents, in their counter-affidavit, have clearly admitted that
“the NIT was floated by the respondents inviting bids to provide auto
tippers with driver and helper for lifting and transport garbage i.e.
working on foul condition.” It is further admitted that the rate of Rs.297/was applicable for foul conditions. In fact, the respondents had duly paid to
the petitioners at the aforesaid rate of Rs.297/- from the date of contract/
work order, till March, 2016.
47.
It was only in March, 2016 that the respondents came to the
conclusion that they had made excess payments to the petitioners on account
of foul conditions and accordingly, stopped making the said payments and
sought to recover the excess amounts paid to the petitioners. There is no
justification or reasoning given by the respondents as to the basis of the
conclusion that excess amounts were paid by them to the petitioners. The
only justification for deducting the amounts is on account of audit/vigilance
objections.
48.
The respondents themselves recognized the difference in the rates to
be paid to labourers/beldars working under general conditions and those
working under foul conditions by providing that the labourers/beldars
working under foul conditions would be entitled to 25% higher
remuneration. In this regard, reference may be to the rates notified by MCD
in its communication dated 18th January, 2011 (Annexure P-1 to the W.P.(C)
8294/2018).
49.
EDMC, in its communication dated 9th August, 2012 (Annexure P-3
to the W.P.(C) 3676/2017) addressed to the petitioner in W.P.(C.)
3676/2017, invited the petitioner to submit a bid for the deployment of 70
additional LMVs in the Shahdara (South) and Shahdara (North) Zones, on
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
the revised terms and conditions of the contract. The said communication
also expressly recognized the differential rates applicable to beldars
deployed under general and foul conditions. The relevant extracts from the
said communication are set out below:
“Vehicles will be hired for a maximum period of 5 years from the date of
issue of the work order, on daily basis or as required by the department
and the escalation on the awarded rate due to increase/decrease in fuel
and minimum wages, will be paid as follows by considering the rates of
CNG @ 30/- per kg, petrol @ 63.70/- per lts. and minimum wage rate @
297/- per day (Rate of one beldar comes to Rs. 238/- and Rs. 297/- as on
date for general purpose and foul condition respectively).”
[emphasis supplied]
50.
This was reiterated in the subsequent communication of EDMC dated
19th February, 2014. (Annexure P-4 to the W.P. (C) 3676/2017).
51.
The EDMC in its subsequent notification dated 1st May, 2018
(Annexure P-6 to the W.P. (C) 8294/2018) has also notified different rates
for hiring charges for ‘General Purposes’ and ‘Foul Condition’.
52.
The objections of Vigilance Department of EDMC fail to provide any
justification as to why the petitioners are not entitled to the benefit of the
foul condition rates. In fact, in response to the subject audit report, the
Executive Engineer of EDMC has specifically stated that there was no
irregularity in the payments made to the Contractor on account of ‘Foul
Condition’ charges. It was explained that the basic labour rate was Rs.238/per day, to which an additional 25% was applicable for work under foul
conditions. The response further noted that the Special Audit Party had
failed to account for this additional component of extra 25% for working
under the ‘Foul Condition’. Thus, EDMC’s own response to the audit
objection recognized the distinction between the two rates and justified the
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
inclusion of the additional component for foul condition work. (Annexure P21 to the W.P. (C) 8294/2018). It is not even the case of MCD in the
counter-affidavit that the work performed by the petitioners did not relate to
foul conditions.
53.
Pertinently, the respondents did not even bother to issue a show cause
notice to the petitioners before they began to unilaterally deduct amounts
from the bills of the petitioners, with effect from March, 2016.
54.
It is noteworthy that NDMC and SDMC, the other units that emerged
pursuant to the split of MCD, did not make any such deductions in respect of
the contractors hired for similar work.
55.
On behalf of respondents, it has been contended that the work orders
issued by the respondents did not provide for a differential rate in respect of
foul conditions and therefore, the petitioners cannot claim parity in respect
of work orders issued by NDMC and SDMC, which specifically provided
for a differential higher rate for foul conditions.
56.
In my view, the aforesaid submission is completely devoid of merits.
The work orders were issued by different units of MCD, pursuant to the
trifurcation. However, they were based on the same NIT, which was issued
by a unified MCD. Different units of MCD arising out of the trifurcation
cannot follow differential payment norms in respect of the same tender.
57.
Therefore, in the opinion of this Court, not mentioning ‘Foul
Condition’ clause in the work orders issued by EDMC was nothing but an
inadvertent clerical mistake. The understanding of the petitioners as well as
the respondents was clear that a higher rate had to be paid in respect of ‘Foul
Condition’ work to be performed by the Contractors. This conclusion is also
fortified by the fact that EDMC continued to make payments towards foul
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
condition charges till February, 2016 and the payment was stopped only on
account of audit/vigilance objection, which as noted above, was completely
without any justification.
58.
Therefore, in the opinion of this Court, the action of the respondents
in deduction/recovery of the amounts from the payments due to the
petitioners is clearly unjust and arbitrary and violative of Article 14 of the
Constitution of India.
59.
Now I shall deal with the plea of limitation taken by the respondents.
60.
The filing dates of the present writ petitions are tabulated below:
Petitioner
Joginder Singh Wadhwa
(Lead Petition) (Prop. Of Ms.
Manmohan Singh Wadhwa)
M/s R.B. Saxena & Sons
M/s SG Constructions
Khajan Singh
Sailnterprise (Umesh Kumar)
61.
W.P. No.
W.P. (C) 8294/2018
Date of Filing
31.07.2018
W.P. (C) 3676/2017
W.P. (C) 4824/2019
W.P. (C) 4849/2019
W.P. (C) 11919/2021
27.04.2017
03.05.2019
03.05.2019
11.10.2021
The petitioner in W.P.(C) 8294/2018 immediately went to Court by
filing W.P.(C.) 10376/2016 and continued to file various writ petitions
before this Court on the same cause of action.
62.
Both W.P.(C) 8294/2018 and W.P.(C) 3676/2017 were filed within
the period of limitation even if the period of limitation is counted from
March, 2016, when first deduction/recovery was made by the respondents.
63.
In so far as the petitioners in W.P.(C.) 4824/2019 and W.P.(C.)
4849/2019 are concerned, the earliest communication made to the
petitioners from the respondents confirming the withheld amounts was
issued only in February, 2018. Accordingly, the cause of action crystallized
on 12th February, 2018, when the respondents quantified the alleged excess
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
payments and raised a demand for their recovery. The petitioners could not
have
effectively
challenged
the
quantified
demand
prior
to
its
communication. Therefore, W.P.(C.) 4824/2019 and W.P.(C.) 4849/2019,
which were filed in 2019, were within the period of limitation.
64.
In so far as the 5th petition, W.P.(C) 11919/2021, is concerned, the
petitioner therein is entitled to the benefit of limitation given by the Supreme
Court vide order dated 10th January, 2022 in Suo Motu W.P. (C) No. 3/2020,
titled Re: Cognizance for extension of limitation, wherein Supreme Court
noted that the period between 15th March, 2020 to 28th February, 2022
would be excluded for the purpose of limitation as may be prescribed under
any general or special laws in respect of judicial or quasi-judicial
proceedings.
65.
Hence, none of the writ petitions are barred by limitation/delay or
laches.
66.
Now, I shall deal with the aspect of maintainability of the present
petition.
67.
The respondents have objected to the maintainability of the writ
petitions on the ground that the writ petitions arise out of concluded
contractual arrangements and involve disputed questions of facts and
interpretation of contractual terms, which ought to be agitated before the
appropriate civil forum rather than in proceedings under Article 226 of the
Constitution.
68.
The Supreme Court in Shrilekha Vidyarthi (supra) has held that in
any sphere of activity, there cannot be any unfairness or unreasonableness in
actions of the State.
69.
The aforesaid judgement was followed by Supreme Court in ABL
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
International (supra), wherein it was held that merely because the dispute
arises out of a contract or involves disputed questions of fact cannot be a
ground to refuse to entertain a writ petition. It was further held that where
the State or its instrumentality acts arbitrarily, the writ court is empowered
to intervene. The relevant observations are set out below:
“27. From the above discussion of ours, the following legal principles
emerge as to the maintainability of a writ petition:
(a) In an appropriate case, a writ petition as against a State or an
instrumentality of a State arising out of a contractual obligation is
maintainable.
(b) Merely because some disputed questions of fact arise for
consideration, same cannot be a ground to refuse to entertain a writ
petition in all cases as a matter of rule.
(c) A writ petition involving a consequential relief of monetary claim is
also maintainable.”
70.
In Tantia Construction (supra), the Supreme Court, while dealing
with a contractual dispute, held that an alternative remedy is not an absolute
bar to invoke the writ jurisdiction of the High Court.
71.
The relevant paragraphs of the aforesaid judgment are set out below:
“33. Apart from the above, even on the question of maintainability of the
writ petition on account of the arbitration clause included in the
agreement between the parties, it is now well established that an
alternative remedy is not an absolute bar to the invocation of the writ
jurisdiction of the High Court or the Supreme Court and that without
exhausting such alternative remedy, a writ petition would not be
maintainable. The various decisions cited by Mr Chakraborty would
clearly indicate that the constitutional powers vested in the High Court
or the Supreme Court cannot be fettered by any alternative remedy
available to the authorities. Injustice, whenever and wherever it takes
place, has to be struck down as an anathema to the rule of law and the
provisions of the Constitution.
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
34. We endorse the view of the High Court that notwithstanding the
provisions relating to the arbitration clause contained in the agreement,
the High Court was fully within its competence to entertain and dispose
of the writ petition filed on behalf of the respondent Company. We,
therefore, see no reason to interfere with the views expressed by the High
Court on the maintainability of the writ petition and also on its merits.”
[emphasis supplied]
72.
In the light of the aforesaid decisions, the position in law is crystal
clear that there is no absolute bar for a party to invoke the writ jurisdiction
of the High Court under Article 226 of the Constitution of India, even in
respect of contractual matters. The State is required to act fairly, reasonably
and without arbitrariness in all spheres of its activity, including in the sphere
of contractual matters. Being a statutory body/local authority, the respondent
falls within the definition of ‘State’ under Article 12 of the Constitution of
India and therefore, its actions would be subject to Article 14 of the
Constitution of India.
73.
In the present case, as noted above, there are no disputed questions of
fact which require adjudication on the basis of evidence. The respondents in
their short affidavit have clearly admitted that the NIT was floated for ‘Foul
Condition’ work and the bids were accepted on that basis. Accordingly,
work orders were issued providing the rate of Rs.297/-. The petitions also do
not require any interpretation of contractual provisions.
74.
Applying the ratio of aforesaid judgements to facts of the present
case, there is no doubt in my mind that the respondents have acted in a
completely arbitrary, unreasonable and discriminatory manner and in
complete violation of Article 14 of the Constitution of India. In these
circumstances, there cannot be any bar to entertain the present writ petitions.
75.
In view of the discussion above, all the writ petitions deserve to be
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
allowed.
76.
Consequently, the communications issued by the respondents seeking
deduction/recovery of the amounts paid to the petitioners towards ‘Foul
Condition’ charges are hereby set aside.
77.
Resultantly, the respondents shall refund all amounts due to the
petitioners that had been wrongfully deducted/recovered by them along with
the interest @ rate of 8% per annum.
78.
The pending applications stand disposed of.
AMIT BANSAL
(JUDGE)
NOVEMBER 18, 2026
at
Digitally Signed
By:AANCHAL TAGGAR
12:04:47
W.P.(C) 3676/2017 and connected matters
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review