Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
IN THE HIGH COURT OF MEGHALAYA AT
SHILLONG
: JUDGMENT :
(1)
WRIT APPEAL No.49 of 2010
….. Appellant
M/s Power Carriers (India) Pvt. Ltd.
-VersusShri G.M Lanong and others
(2)
….. Respondents
WRIT APPEAL No.6 of 2011
The Meghalaya State Electricity Board
(now Meghalaya Energy Corporation Ltd.)
-VersusShri G.M Lanong and Another
Date of Judgment:
::
….. Appellant
….. Respondents
15th December, 2016
PRESENT
HON’BLE SHRI JUSTICE DINESH MAHESHWARI, CHIEF JUSTICE
HON’BLE SHRI JUSTICE S.R. SEN
Shri HS Thangkhiew, Senior Advocate with Shri PN Nongbri for the
appellant in WA No. 49 of 2010.
Shri KS Kynjing, Senior Advocate with Shri SM Suna
and Shri N Mozika for the appellant in WA No. 6 of 2011.
Shri S Chakrawarty, Senior Advocate with Ms. M Mahanta, for the
respondent/writ petitioner in both the appeals.
AFR
BY THE COURT: (per Hon’ble the Chief Justice)
Preliminary
These two appeals, directed against the same order dated
11.10.2010 as passed by the learned Single Judge in WP(C) No.295
(SH) of 2007, have been considered together; and are taken up for
disposal by this common judgment.
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
The respondent of these appeals
Shri G.M. Lanong
[hereinafter referred to as „the respondent‟ or „the writ petitioner‟]
preferred the writ petition aforesaid while stating grievance against
the actions of the appellant of Writ Appeal No. 6 of 2011, the
Meghalaya State Electricity Board [now the Meghalaya Energy
Corporation Limited – hereinafter referred to as „the appellant-Board‟
or „the Board‟] and its officers, where they invited tenders for a civil
works contract but later on, cancelled the tender process and then,
awarded the contract to the appellant of Writ Appeal No.49 of 2010,
Power Carriers (India) Pvt. Ltd. [hereinafter referred to as „the
appellant-Company‟].
In the impugned order dated 11.10.2010, the learned Single
Judge held that the Board and its officers had acted wholly unfair in
cancelling the tender process and then, awarding the contract in
question to the appellant-Company without inviting fresh tenders and
thereby, denying the writ petitioner an opportunity to participate.
However, in view of the fact that execution of the work under the
contract in question was already over, the learned Single Judge
found it illogical to set aside the decision of awarding the contract
and, instead, considered it justified that the writ petitioner be
compensated by the present appellants. Accordingly, the learned
Single Judge held the present appellants jointly and severally liable
to pay an amount of Rs.10,00,000/- (ten lakhs) as damages and
further an amount of Rs.50,000/- (fifty thousand) towards costs of
proceedings to the writ petitioner.
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
Aggrieved by the order so passed by the learned Single
Judge, the respondents of the writ petition i.e., the contractor who
was awarded the contract in question as also the principal who had
awarded the contract, have preferred these two separate appeals.
The background aspects; initial tender process
The relevant background aspects of the matter could be taken
note of in the following: By way of a Notice Inviting Tenders („NIT‟)
dated 01.03.2006, the appellant-Board invited sealed bids from
reputed
EHV
(Extra
High
Voltage)
Line
Construction
Contractors/Joint Venture Firms/Consortium of two or more Firms for
„Construction of 132KV Double Circuit Transmission Line on 220KV
Towers from Myntdu-Leshka Stage-I HEP to the 132 KV substation
at Khliehriat, Jaintia Hills, Meghalaya, India‟. The tender process
consisted of two-bid system, i.e., techno-commercial bid and
financial bid. In response to this NIT, the appellant-Board received
two offers, one by the writ petitioner and another by the appellantCompany.
The appellant-Board, however, took the view that the technocommercial bid of the writ petitioner was not meeting with the criteria
for consideration of the financial bid and hence, proceeded to open
the financial bid of the appellant-Company, who was found to be
fulfilling the requisite criteria. Having learnt that the financial bid of
the appellant-Company had been opened on 13.11.2006, the writ
petitioner sent a letter of protest dated 15.11.2006 to the Chief
Engineer of the Board. In response to this letter of protest, the writ
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
petitioner was informed by way of a letter dated 01.12.2006 from the
Superintending Engineer (G.T.) of the Board that his technocommercial bid was not fulfilling the requisite criteria. However, the
writ petitioner was called upon to submit certain documents for
placing his matter before the Tender Evaluation Committee like: (i)
Annual Turnover for last 5 years; (ii) Successful Commissioning
Certificates; (iii) Particular Experience Record; (iv) Current Contract
Commitments; and (v) Equipment Capabilities.
In response to the communication aforesaid, the writ petitioner
allegedly furnished all the requisite particulars under his letter dated
11.12.2006; and, while expressing concern that he had been asked
to provide certain particulars after a lapse of about seven months
since the date of opening of the techno-commercial bid and had not
been given any other information about the fate of its tender, the writ
petitioner reiterated the request for opening of his financial bid.
Thereafter, the said Superintending Engineer (Trans) issued a letter
dated 23.03.2007, addressed to both the writ petitioner as also the
appellant-Company,
to
the
effect
that
due
to
unavoidable
circumstances and in accordance with Clause (10) of the General
Conditions of Contract, the tender process had been cancelled and
the earnest money, amounting to Rs.6,00,000/-, was being returned
to each of them. As shall be noticed hereafter, this termination of
tender process under the NIT dated 01.03.2006 was not the end but
was the origination of dispute involved in this matter.
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
Award of contract to the appellant-Company
Even when the aforesaid tender process had been scrapped
and no new tenders had been invited, the appellant-Board
proceeded to award the contract for construction of towers and
transmission line to the appellant-Company. This led to the
grievance of the writ petitioner who, in the first place, instituted Title
Suit No.19 (T) of 2007 in the Court of Assistant to Deputy
Commissioner, Shillong for declaration and injunction with an
application under Order XXXIX Rules 1 and 2 of the Code of Civil
Procedure, seeking temporary injunction
that the appellant-
Company be restrained from executing the work in question. While
accepting this application for temporary injunction [Misc. Case
No.46(T) of 2007] by the order dated 30.05.2007, the learned Trial
Court restrained the appellant-Company from carrying out the
construction work of „132 KV double circuit transmission line on 220
KV tower from Myntdu-Leshka Stage-I HEP to the 132 KV Substation at Khliehriat, Jaintia Hills, Meghalaya‟.
Aggrieved by the aforesaid order dated 30.05.2007, the
appellant-Company preferred an appeal [FAO 2(T) of 2007] while
contending that the work so allotted to it was different from the one
in respect whereof the said NIT dated 01.03.2006 was issued in the
past and which was later on cancelled. It was also contended in the
appeal so filed against the order of temporary injunction that since
the work, which had been allotted to the appellant-Company, was a
new work and the allotment of the new work was not under
challenge, the question of granting injunction against execution
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
thereof did not arise. In this appeal, the learned Additional Deputy
Commissioner, Shillong, accepted the contention that the work
allotted to the appellant-Company was different from the one
covered by the earlier tender process and hence, by the order dated
26.07.2007, set aside the impugned injunction order dated
30.05.2007.
Assailing the aforesaid order dated 26.07.2007, the writ
petitioner preferred a revision petition in this Court [CR(P) No.49(SH)
of 2007] with the submissions, inter alia, that except change of the
capacity of towers, all other features of the work as awarded
remained the same as that of the work mentioned in the earlier NIT
dated 01.03.2006. In the order dated 21.09.2007, a learned Single
Judge of this Court, even while expressing doubts on the fairness of
the procedure adopted by the Board, observed that the petitioner
had not challenged the work order dated 16.05.2007, whereby the
contract was awarded in favour of the appellant-Company and,
hence, the said work order could not have been interfered with by
way of an injunction. The learned Single Judge did observe that
prima facie, the appellant-Board appeared to have adopted the
backdoor policy to allot the contract to the appellant-Company
without floating the tender but declined to interfere because the writ
petitioner had not challenged the work order issued to the appellantCompany and because there was a „marginal difference‟ in the work
that had been allotted to the appellant-Company and the one which
was in dispute in the suit. The learned Single Judge, while
dismissing the revision petition, of course, observed that the writ
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
petitioner could be suitably compensated in terms of damages, if
succeeding in the suit. The relevant part of the order dated
21.09.2007 reads as under:“I have already noted earlier that there is a minor change in the
Work Order. Since the petitioner did not challenge the Work Order
allotted to the respondent No.1 on 16.05.2007, there is no scope for
this Court to interfere with the impugned order passed by the
learned Additional Deputy Commissioner. No doubt, prima facie, it
appears to me that it is a case of showing undue favour to the
respondent No.1, inasmuch as, the original tender has been
cancelled/withdrawn after processing the same for long one year.
The grounds for scrapping the earlier tender also did not appeal to
me. It is also appears to me that the MeSEB has adopted a
backdoor policy to award the contract to the respondent No.1
without floating tender. Despite these facts, the impugned order
cannot be interfered with since there is marginal difference in the
Work Order, which has been allotted to respondent No.1 and the
one under dispute in civil suit. Hence, proper remedy for the
petitioner is to approach the Civil Court for seeking damages or for
any other appropriate relief.
Since the Work Order of the respondent No.1 is not materially the
one which has been challenged in the suit, it cannot be said that
the petitioner has a strong prima facie case. Besides this, the
petitioner can also be suitably compensated in terms of damages, if
he succeeds in the suit. Hence it is not a fit case to restore the
injunction order at this stage.”
The writ petition in this Court
Faced with the position that the Court had expressed the view,
though on an application for temporary injunction, that the work,
which had been allotted to the appellant-Company was different
from the one which had been covered by the tender process, the
respondent (writ petitioner) approached this Court by way of the writ
petition under Article 226 of the Constitution of India with the prayers
that the allotment of the new work to the appellant-Company be set
aside; and the appellant-Board be directed to float the tenders in
respect of the new work that had been allotted to the appellantCompany. It was contended in the writ petition that cancellation of
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
the earlier tender process was illegal, arbitrary, mala fide and without
any justifiable reason; that the allotment of new contract work with
marginal changes had only been in order to favour the appellantCompany; and that such an allotment, having been made without
inviting offers from all the interested eligible persons, was wholly
illegal and mala fide.
The appellant-Company contested the matter, inter alia, with
the submissions that the petition suffered from delay and laches
inasmuch as, the work in question had been allotted to it as back as
on 16.05.2007 whereas, the writ petition was filed only on
26.11.2007; and during this period of 5 months from the date of
allotment, substantial work had already been executed and any
interference by the Court in the ongoing work at the belated stage
would lead to enormous hardship. It was further contended that the
work allotted under the work order dated 16.05.2007 was different
from the one that had been abandoned after inviting tenders. In
support of this contention that the two works had been different, it
was alleged that the NIT dated 01.03.2006 had been floated for
construction of „220 KV towers‟ and drawing of „transmission line of
132 KV on the said 220 KV towers‟ but later on, the Board took a
policy decision to construct the towers of „132 KV‟ instead of „220
KV‟ and to draw „132 KV transmission line on 132 KV towers‟; and
that the technical specifications and the cost of construction of 220
KV towers were significantly different from that of 132 KV towers. It
was also contended that the Board, in its written statement filed in
T.S. No.19 (T) of 2007, had categorically stated that the work order
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
dated 16.05.2007 was for construction of „132 KV Double Circuit line
on 132 KV Towers‟ and not for construction of „132 KV Double
Circuit Line on 220 KV Towers‟. The appellant-Company further
elaborated that a comparative analysis of technical data sheet of
220 KV towers and 132 KV towers would show that the height,
weight, base area, foundation depth, pit size, excavation volume,
concreting volume of the two types of towers were significantly
different; and that the tendered cost of construction of the super
structures of 220 KV towers was about Rs. 3.59 Crores, whereas the
tendered cost of construction of 132 KV towers was 2.23 Crores.
The appellant-Company stated that by 25.11.2007, it had incurred
the expenditure under various head of accounts to the tune of
Rs.60,33,793/- and at the given juncture, the writ petitioner was not
entitled to seek interference in the ongoing work.
In regard to the Board‟s decision to allot the work without
inviting fresh tenders, it was contended that the work allotted was a
part of the Myntdu-Leshka Hydel Project, which had to be
commissioned by the month of June, 2008; and since calling for the
tenders was likely to delay the project, the policy decision was rightly
taken by the Board to allot the work to the appellant-Company on
the approved rates. It was also submitted that the appellantCompany was the only technically and financially competent EHV
contractor in the State of Meghalaya with requisite experience for the
work in question. It was emphasized that the work in question
related to a major public utility project for generation and
transmission of power that was required to be completed within time;
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
and hence, the Board was justified in taking into consideration the
interest of public and to allot the same to the appellant-Company
instead of going for the tender process afresh. It was also submitted
that the writ petitioner was not even qualified to execute the work in
question, as was found in the earlier tender process, because he did
not fulfill the eligibility criteria and had failed to furnish the relevant
documents when called upon to do so and hence, he had no locus
standi to challenge the allotment of work to the appellant-Company.
The appellant-Board and its officers, who were arrayed as
respondents No. 1, 2 and 3 in the writ petition, contended while
opposing the writ petition that the bid submitted by the writ petitioner
was not accepted due to his lack of experience and for his failing to
satisfy the requisite eligibility criteria. While justifying the allotment of
work to the appellant-Company, it was contended on behalf of the
Board that: (a) the project in question was a time bound one and
going for the fresh tender process would have taken excessive time
and thereby, the entire Hydel project, involving about Rs.600 crores,
would have been jeopardized; (b) that the appellant-Company was
the only EHV contractor in Meghalaya that was registered with the
Board and was having a long working experience with the Board
since the year 1988 and had successfully completed a number of
such works; and (c) that the work in question had been allotted to
the appellant-Company at the approved rates of the Board. It was
also contended that the final allotment of the construction work
pursuant to the tender process that was initiated by the NIT dated
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
01.03.2006 came to be abandoned due to the change in technical
specifications.
The observations, findings and directions in the order impugned
The learned Single Judge, however, rejected all the aforesaid
contentions of the present appellants and found no justifiable reason
for cancelling the earlier tender process and awarding of the contract
to the appellant-Company while observing, inter alia, as under:“35. The State respondents merely contend that the MeSEB
decided to change the specifications of the work and this was a
policy decision. Even if policy decision may not be open to judicial
review, the fact of the matter remains that when the tender had
already been floated for allotment of specified work, and the same
was, subsequently, abandoned, the State respondents ought to
have given satisfactory reasons, when questioned, before this
Court, as to why they had abandoned the tender process, and,
when no satisfactory and acceptable reason could be assigned by
the State respondents, then, the abandonment or cancellation of
the tender process must be held, and is hereby held, to be
motivated and arbitrary.
36. The only reason, as already indicated above, assigned by the
State respondents for abandoning the tender process, was change
in the policy. The State respondents have not assigned any reason,
far less convincing, as to why they changed the policy at all; what
was wrong with the earlier tender, which had been floated on
01.03.2006? The State respondents have also miserably failed to
show as to why the work, which has come to be, eventually,
awarded to the private respondents, was not the work in respect
whereof the earlier tender had been floated and at what stage and
on what consideration, it was decided that instead of pursuing the
project, covered by the earlier notice, it is the latter project, which
needs to be pursued. The cancellation of the tender process,
without any convincing reason having been assigned therefor,
cannot but be treated as arbitrary and denial of equal opportunity to
the petitioner, who has been alleged to have been found to be
unqualified in the earlier tender process, though no cogent reason
could be assigned for disqualification of the petitioner in the earlier
tender process too.
…..
…..
…..
38. Thus, the case of Raunaq International (supra), in no way,
applies to the facts of the present case inasmuch as Raunaq
International (supra) is a case, which arose out of a tender
process, where there were two bidders. In the present case, no
process of selection was adhered to by the State respondents.
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
Thus, the allotment of contract, in the present case, is nothing, but
arbitrary inasmuch as not even a semblance of selection process
was resorted to before the contract was awarded in favour of the
private respondent. This apart, the State respondents have also not
been able to lay before this Court any convincing reason, far less
convince, as to why they, initially, did not float Notice Inviting
Tender for the contract work, which has been subsequently
awarded to the private respondent. Strictly speaking, in the present
case, the State respondents excluded the petitioner from the
purview of consideration on the ground that in the previous tender
process, the petitioner had allegedly been found not technically
qualified, though, as already indicated above, no reason
whatsoever has been assigned by the State respondents for
branding the petitioner as a technically unqualified bidder. …”
The learned Single Judge also found that the alleged changes
in specifications were made only in order to award the contract in
favour of the appellant-Company and not in the interest of public;
and that there was nothing on record to justify the departure from the
normal rule of awarding of public contract by open invitation and
sustainable selection process. The learned Single Judge observed
and held as under:
“44. There is, therefore, clear room for taking the view that in the
facts and attending circumstances of the present case, changes, in
the specifications of the contract work, were made so as to award
the contract in favour of the private respondents and not in the
interest of the public, for, had the award of contract been in the
interest of public, the State respondents would have been able to
disclose as to why the notice inviting tenders had not been issued,
on 01-03-2006, for the work, which came to be subsequently
allotted to the private respondent.
45. In short, thus, no such fact has been disclosed by the
respondents, or discernible from the materials on record, which can
justify departure from the normal rule of awarding of a public
contract on the basis of sustainable selection process. There may
be extra-ordinary situations, which may require some departure
from the norms, but the authorities, under such circumstances, are
obliged
to
disclose
to
the
Court
the
compelling
circumstances/reasons, which necessitated exercise of discretion
contrary to the normal requirement of Article 14 of the Constitution
of India.
46. In the case at hand, the State respondents, having not been
able to assign, as already discussed above, reasons for holding the
petitioner technically disqualified and they, having failed to assign
the reason as to why, on what consideration, on what date and at
what stage, making of changes, in the specifications of the contract
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
work, were found to be necessary, and, further, why, while issuing
notice, on 01-03-2006, tenders were not invited for the work, which
has, eventually, come to be allotted to the private respondent or, in
other words, what had restrained the State respondents from
floating notice inviting tenders on 01-03-2006 itself in respect of the
contract work, which has been subsequently awarded to the private
respondent, one has no option but to hold that the State
respondents‟ action in changing the specifications of the contract
work is not bona fide and they failed to maintain the transparency,
required to be maintained by them, while awarding the contract to
the private respondent.
47. As stated above, in the instant case, the justification, offered for
not calling tender by the Meghalaya State Electricity Board, is no
justification in the eye of law.
While referring to several decisions and reiterating the basic
principles of the requirements of just, fair and transparent method for
awarding of the public contract, the learned Single Judge found that
the case at hand was disclosing rather disturbing features and the
alleged delay and laches were not the factors sufficient to decline
the writ jurisdiction in the matter while observing as under:“58. The law, relating to award of contract, by the State, its
Corporation and bodies, acting as the instrumentalities and
agencies of the Government, are more or less settled by judicial
pronouncements. The State can choose its own method in arriving
at a decision for awarding contract and it can fix its own terms of
invitation to tender. What is required is that while awarding the
contract or granting any right or privilege to others, it must be just,
fair, transparent, free from the vice of arbitrariness and in tune with
Art.14 of the Constitution. In a given case, the State can award
contract by negotiation, but such decision has to be free from bias,
discrimination and favouritism.
59. In the case at hand, the facts are really disturbing to say the
least. The State respondents issued tender, wherein both the
petitioner and the respondent No.4 (i.e., the private respondent)
participated. There is nothing on record to show that the technical
bid of the private respondent was opened for consideration. Without
disclosing any reason whatsoever as to why the private respondent
was disqualified, the authorities clandestinely awarded the contract
in favour of the private respondent and even when the petitioner
questioned the fairness, transparency and legality of the awarding
of contract in favour of the private respondent in this writ
proceeding, the State respondents have not been able to assign
any reason as to why the petitioner was held to be technically not
qualified. This apart, and as already indicated above, the State
respondents are also completely silent as to why they had not
floated tender, on 01-03-2006 itself, in respect of the contract work,
which came to be allotted subsequently to the private respondent.
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
60. It has also been contended, while resisting this writ petition, by
the respondents that the writ petition suffers from delay and
latches. When the contract has been awarded to the private
respondent without informing any one and even when the petitioner
had instituted the suit, the State respondents did not come forward
to contest the suit by disclosing that the contract had been awarded
on changed specification, the writ petition cannot be said to have
been suffering from delay and latches particularly, when the
allotment of contract was not publicly made known nor was the
petitioner informed about the allotment of the contract to the private
respondent. Later on, when the petitioner learnt that the contract
had stood awarded to the respondent No.4, the petitioner filed a
suit. The suit was dismissed, because there were some changes
made in the subject matter of the contract, which was not under
challenge in the suit. Thereafter, the petitioner filed the present writ
petition. In the face of these facts and attending circumstances, the
decisions, cited by the respondents, are of no help.”
After having, thus, found in no uncertain terms that the
procedure adopted by the Board was entirely illegal, mala fide and
arbitrary, with denial of opportunity to the writ petitioner, the learned
Single Judge observed that in the given circumstances, the award of
contract was required to be set aside. However, the other factors
given out before the Court at the time of hearing were that the
execution of the contract work was over and thus, the learned Single
Judge observed that it would be illogical to set aside the award of
contract at the given stage. The learned Single Judge, nevertheless,
observed that for having been kept out of selection process in an
unfair and illegal manner, the writ petitioner was required to be
compensated for the loss suffered. Thereafter, even while finding
that the writ petition may not be the appropriate proceeding for
awarding of damages, the learned Single Judge observed that the
respondents of the writ petition cannot be exonerated and they need
to be directed to pay, apart from the cost of proceedings, some
amount as public law damages to the writ petitioner, while referring
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
to the decision of the Hon‟ble Supreme Court in the case of
Subhash Projects and Marketing Ltd. vs. West Bengal Power
Development Corporation Ltd.: (2008) 3 SCC 438. With these
observations, the learned Single Judge proceeded to award an
amount of Rs.10,00,000/- (ten lakhs) to the writ petitioner while
holding the respondents of the writ petition jointly and severely liable
for the same and also awarded another amount of Rs.50,000/- (fifty
thousand) towards the costs of proceedings. The learned Single
Judge finally observed, held and directed as under:
“61. Because of what have been discussed and pointed out above,
I find that the decision making process of awarding the contract, in
question, was arbitrary and denial of opportunity to the petitioner to
participate in the tender process was wholly illegal, mala fide and
arbitrary. In such circumstances, the award of the contract needs to
be set aside. However, considering the fact that the execution of
the contract is over, it would be illogical to set aside the awarding
the contract to private respondent.
62. Considering, however, the fact that the petitioner was kept out
of the selection process of the contract, in question, by adopting
means, which were wholly unfair, illegal and arbitrary, the petitioner
deserves to be compensated of the loss, which the petitioner may
have suffered. This Court is, of course, required to determine of the
quantum of loss, which the petitioner might suffered. The present
writ petition is not the appropriate proceeding for awarding of
damages to the petitioner for the loss, which the petitioner has
suffered. He must, however, be compensated for denying him the
right to equal treatment under Article 14 of the Constitution. Neither
the State respondents nor can the private respondents be,
therefore, completely exonerated and they need to be directed to
pay, apart from the cost of the proceeding, some amount as a
public law damages to the petitioner. (See Subhas Projects and
Marketing Ltd. Vs. West Bengal Power Development
Corporation Ltd., reported in (2008) 3 SCC 438).
63. In the result and for the reasons discussed above, while
awarding of the contract, in question, to the private respondent is
not interfered with, this writ petition is disposed of with direction that
the petitioner be paid a sum of Rs.10,00,000/- (Rupees ten lakhs)
as damages. The damages, so directed, shall be payable by the
State respondents as well the private respondents. The State
respondents as well as the private respondents, who are jointly and
severely liable, shall also pay a sum of Rs.50,000/- as cost of the
proceeding.
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
64.
With the above observations and directions, this writ petition
shall stands disposed of.”
Aggrieved by the order so passed by the learned Single
Judge, the respondents of the writ petition i.e., the contractor as also
the principal have preferred these two separate appeals.
Rival contentions in appeals
Before taking note of the rival contentions, it may be indicated
that these appeals were heard on several occasions before different
Division Benches but were adjourned, while granting time to the
parties to make an endeavour to reach to an amicable settlement.
Lastly, on 31.03.2016, it was frankly given out by the learned
counsel for the parties that despite efforts, they had not been able to
reach to the negotiated settlement.
Having regard
to the
circumstances, we had proceeded with the hearing of the matter. Of
course, during the course of hearing, learned counsel for the
appellants have submitted in writing their offers for settlement
without prejudice to the submissions sought to be made in these
appeals. We shall refer to these proposals a little later and only after
examining the other contentions on the merits of the case.
Questioning the order impugned, learned counsel for the
appellant-Company has strenuously argued that the learned Single
Judge has erred in attaching illegitimacy to the contract awarded to
the appellant-Company though such a decision was taken by the
authorities of appellant-Board in fair discharge of their public duties,
particularly because of the urgency of execution of the public utility
project. With reference to the opinion of the Hon‟ble Supreme Court
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
in Special Reference No. of 1 of 2012: (2012) 10 SCC 1 and the
decision in Villianur Iyarkkai Padukappu Maiyam Vs. Union of
India and Ors: (2009) 7 SCC 561, the learned counsel would argue
that award of contract only after floating tenders is not the mandate
of law; and a contract awarded without open invitation to offer is not
to be regarded as unfair or arbitrary in every case. According to the
learned counsel, in the present case, the project in question being of
immense public utility and the matter being of urgency, the Chairman
had validly taken the decision to get the same executed by the
appellant-Company, the only qualified EHV contractor in the State of
Meghalaya; and the decision of the Chairman was duly ratified by
the Board. The learned counsel has also referred to the decision in
Raunaq International Ltd. Vs. IVR Construction Ltd. and others:
(1999) 1 SCC 492 to submit that even the relaxation of qualifying
criterion in the matter of award of contract has been held justified
when departure from the norms was made on valid principles and
overwhelming public interest.
Learned counsel for the appellant-Company has further
argued that the appellant did execute the work in question as
awarded to it in public interest by the appellant-Board on the
scheduled rates; and there had neither been any allegation of
collusion nor there was any ill-intent or motive on the part of the
appellant-Company so as to be penalized in this matter by award of
compensation to the respondent. Learned counsel has yet further
contended that the respondent was found disqualified even in the
earlier tender process for construction of towers and laying of 132
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
KV double circuit transmission line, and hence, as observed in
Raunaq International (supra), he could not have made any legal
grievance against the award of contract to the appellant-Company
and in any case, was not entitled to claim any compensation.
The learned counsel also submitted in the alternative that
without prejudice to its other submissions but looking to the nature
and quantum of contract and going by the method of quantification in
the case of Subhash Projects (supra), there was no justification in
awarding any compensation beyond a sum of Rs.4.34 lakhs, which
represents about 15% of the expected profit in the contract in
question; and the appellant-Company has, accordingly, made the
offer for settlement, which may be considered if at all its other
contentions are not accepted by the Court.
The learned counsel appearing for the appellant-Board has
further elaborated on the submissions that the work in question was
required to be executed due to urgency and else, the entire time
bound project would have been jeopardized; and in the given
circumstances, after scrapping of the earlier tender process, when
little or rather no time was left for floating of fresh tenders, a
reasonable decision was taken for getting the work executed from
the appellant-Company only on approved rates. According to the
learned counsel, the appellant-Company was rightly awarded the
contract in question for being the only qualified EHV line contractor
in the State of Meghalaya, who had executed various similar
contract works with the appellant-Board; and such a decision was
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
rightly ratified by the Board. Apart from the decisions cited by the
counsel for the other appellant, the learned counsel for the
appellant-Board has referred to and relied upon the decision in Ravi
Development Vs. Shree Krishna Prathisthan and Ors: (2009) 7
SCC 462. The learned counsel has yet further contended that even
on the principles as available in the case of Subhash Projects
(supra), there was no justification for awarding any amount of
compensation against the appellants. Apart from the foregoing,
learned counsel has made similar submissions in the alternative,
while placing on record the offer that was made by the appellantBoard for amicable settlement with the respondent (writ petitioner).
While opposing the contentions urged on behalf of the
appellants, learned counsel for the respondent (writ petitioner) has
emphasized on the submissions that there had not been any so
called urgency or emergency as sought to be canvassed before this
Court so as to award of contract in question to the appellantCompany without inviting offers. Learned counsel would submit that
in the earlier tender process, the bid of respondent was unfairly
avoided from consideration and upon his making representation and
answering to all the requirements, the tender process was cancelled
after about one year of issuance of NIT. Thus, according to the
learned counsel, there was no urgency in the matter and yet, without
inviting fresh offers and after some artificial changes in the
specifications, the work was awarded to the appellant-Company in a
wholly clandestine manner. The learned counsel has strenuously
argued that the submissions about ratification by the Board are of no
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
effect because the relevant facts pertaining to the contract in
question were not placed before the Board, as is evident from the
document Annexure-5 sought to be relied upon by the appellants.
Learned counsel has referred to the observations made by the
Hon‟ble Supreme Court in Special Reference No.1 of 2012 (supra)
to submit that the ordinary rule of public auction or tender cannot be
deviated at the whims of the authorities. Learned counsel submitted
that the allegation about his disqualification is entirely baseless
because even in the earlier tender process, the Board never held
him disqualified; and no tender was invited after scrapping of the
earlier tender process and thereby, he was deprived of the chance
to make his offer. The learned counsel has argued that the
respondent, who was deprived of the chance to submit his bid for
the contract in question, has rightly been awarded compensation
and costs of proceedings from the appellant-Company as also the
appellant-Board; and has referred to the decision of the Hon‟ble
Supreme Court in the case of U.P. State Electricity Board and
another Vs. OM Metals & Minerals (P) Ltd.: (2002) 9 SCC 512 to
submit that the compensation as awarded in the present case to the
tune of Rs.10 lakhs remains justified.
Having
given
thoughtful
consideration
to
the
rival
submissions and having examined the record, we are clearly of the
view that the learned Single Judge has rightly pronounced against
the process as adopted by the appellant-Board in awarding the
contract in question to the appellant-Company without floating
tenders and without inviting open offers; but, the amount of
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
compensation as awarded by the learned Single Judge would call
for interference, for the reasons indicated infra.
The Scope of judicial review and legality of the action in question
Apparent it is that the writ petition leading to this appeal was filed
by the respondent herein on his basic grievance that the NIT for the
work of erection of towers and laying of transmission lines from
Myntdu-Leshka Stage-I HEP to the 132 KV substation at Khliehriat,
Jaintia Hills, Meghalaya was earlier issued wherein, he too offered the
bids and submitted the documents as required but, the said tender
process was cancelled and then, with a slight modification of the
specification of towers, the same work was awarded to the appellantCompany without inviting tenders.
It remains trite that the judicial review of such an administrative
action of award of contract is essentially intended to prevent
irrationality, arbitrariness, unreasonableness and mala fides. In such a
matter, the Court is primarily concerned with the decision making
process and not the merits of the decision itself. In the case of Jagdish
Mandal Vs. State of Orissa and others: (2007) 14 SCC 517, the
Hon‟ble Supreme Court, after a survey of some of the celebrated
decisions like those in Sterling Computer Limited: (1993) 1 SCC 445,
Tata Cellular: (1994) 6 SCC 651 and Raunaq International (supra), has
summed up the principles as follows:“22. Judicial review of administrative action is intended to prevent
arbitrariness, irrationality, unreasonableness, bias and mala fides.
Its purpose is to check whether choice or decision is made
“lawfully” and not to check whether choice or decision is “sound”.
When the power of judicial review is invoked in matters relating to
tenders or award of contracts, certain special features should be
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
borne in mind. A contract is a commercial transaction. Evaluating
tenders and awarding contracts are essentially commercial
functions. Principles of equity and natural justice stay at a distance.
If the decision relating to award of contract is bona fide and is in
public interest, courts will not, in exercise of power of judicial
review, interfere even if a procedural aberration or error in
assessment or prejudice to a tenderer, is made out. The power of
judicial review will not be permitted to be invoked to protect private
interest at the cost of public interest, or to decide contractual
disputes. The tenderer or contractor with a grievance can always
seek damages in a civil court. Attempts by unsuccessful tenderers
with imaginary grievances, wounded pride and business rivalry, to
make mountains out of molehills of some technical/procedural
violation or some prejudice to self, and persuade courts to interfere
by exercising power of judicial review, should be resisted. Such
interferences, either interim or final, may hold up public works for
years, or delay relief and succour to thousands and millions and
may increase the project cost manifold. Therefore, a court before
interfering in tender or contractual matters in exercise of power of
judicial review, should pose to itself the following questions:
(i) Whether the process adopted or decision made by the authority
is mala fide or intended to favour someone;
OR
Whether the process adopted or decision made is so arbitrary and
irrational that the court can say: “the decision is such that no
responsible authority acting reasonably and in accordance with
relevant law could have reached”;
(ii) Whether public interest is affected.
…..”
It is noticed that in the present case, learned Single Judge
has, in fact, examined only the decision making process and has
found that no justification whatsoever was available on record for
abandoning the process under the NIT dated 01.03.2006 and for
later awarding of the contract to the appellant-Company without
open invitation to offer. In Special Reference No.1 of 2012 (supra),
the Hon‟ble Supreme Court has referred to the requirements of
procedural fairness, rationality and reasonableness in the matters of
State action related with grant of contract or distribution of largesse
in the following:-
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
“107. From scrutiny of the trend of decisions it is clearly perceivable
that the action of the State, whether it relates to distribution of
largesse, grant of contracts or allotment of land, is to be tested on
the touchstone of Article 14 of the Constitution. A law may not be
struck down for being arbitrary without the pointing out of a
constitutional infirmity as McDowell case has said. Therefore, a
State action has to be tested for constitutional infirmities qua Article
14 of the Constitution. The action has to be fair, reasonable, nondiscriminatory, transparent, non-capricious, unbiased, without
favouritism or nepotism, in pursuit of promotion of healthy
competition and equitable treatment. It should conform to the norms
which are rational, informed with reasons and guided by public
interest, etc. All these principles are inherent in the fundamental
conception of Article 14. This is the Mandate of Article 14 of the
Constitution of India.”
In the said case, the Hon‟ble Supreme Court has, however,
examined the question as to whether the process of auction could
be held as being mandatory for disposal of natural resources; and,
even while holding in the negative, has explained the parameters for
deviation from the process of public auction in the following:“129. Hence, it is manifest that there is no constitutional mandate in
favour of auction under Article 14. The Government has repeatedly
deviated from the course of auction and this Court has repeatedly
upheld such actions. The Judiciary tests such deviations on the
limited scope of arbitrariness and fairness under Article 14 and its
role is limited to that extent. Essentially, whenever the object of
policy is anything but revenue maximization, the executive is seen
to adopt methods other than auction.
….
….
….
146. To summarise in the context of the present Reference, it
needs to be emphasized that this Court cannot conduct a
comparative study of the various methods of distribution of natural
resources and suggest the most efficacious mode, if there is one
universal efficacious method in the first place. It respects the
mandate and wisdom of the executive for such matters. The
methodology pertaining to disposal of natural resources is clearly
an economic policy. It entails intricate economic choices and the
Court lacks the necessary expertise to make them. As has been
repeatedly said, it cannot, and shall not, be the endeavour of this
Court to evaluate the efficacy of auction vis-à-vis other methods of
disposal of natural resources. The Court cannot mandate one
method to be followed in all facts and circumstances. Therefore,
auction, an economic choice of disposal of natural resources, is not
a constitutional mandate. We may, however, hasten to add that the
Court can test the legality and constitutionality of these methods.
When questioned, the courts are entitled to analyse the legal
validity of different means of distribution and give a constitutional
answer as to which methods are ultra vires ad intra vires the
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
provisions of the Constitution. Nevertheless, it cannot and will not
compare which policy is fairer than the other, but, if a policy or law
is patently unfair to the extent that it falls foul of the fairness
requirement of Article 14 of the Constitution, the Court would not
hesitate in striking down.
149. Regard being had to the aforesaid percepts, we have opined
that auction as a mode cannot be conferred the status of a
constitutional principle. Alienation of natural resources is a policy
decision, and the means adopted for the same are thus, executive
prerogatives. However, when such a policy decision is not backed
by a social or welfare purpose, and precious and scarce natural
resources are alienated for commercial pursuits of profit maximising
private entrepreneurs, adoption of means other than those that are
competitive and maximise revenue may be arbitrary and face the
wrath of Article 14 of the Constitution. Hence, rather than
prescribing or proscribing a method, we believe, a judicial scrutiny
of methods of disposal of natural resources should depend on the
facts and circumstances of each case, in consonance with the
principles which we have culled out above. Failing which, the Court,
in exercise of power of judicial review, shall term the executive
action as arbitrary, unfair, unreasonable and capricious due to its
antimony with Article 14 of the Constitution.”
In the case of Raunaq International (supra), the concerned
State Electricity Board had awarded the works contract to the
appellant who was the lowest tenderer after relaxing the requisite
qualifying criteria as permissible under the terms of tender. However,
the respondent, who was another tenderer but who did not fulfill the
requisite qualifying criteria and whose tender was not preferred by
the experts, filed a writ petition in which, the High Court granted an
interim stay over issuance of letter of intent in favour of the
appellant. In the given fact situation and looking to the public
interest, the Hon‟ble Supreme Court found no justification for such
an interim stay. The Supreme Court also found that it was not a case
of mala fides of any member of the Board nor there was any
allegation of collateral motive; and that the relaxation was granted by
the Board on valid principles. It was further found that even if the
criteria could be relaxed both for the appellant and the respondent,
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
the offer of the appellant being the lower one, the decision of the
Board was not unjustified. The said decision has been considered by
the learned Single Judge and it has rightly been observed that the
said case fundamentally stand at a different footing because in the
present case, there was no invitation to offer at all.
Learned counsel for the appellant-Company has also relied
upon the following passages in the case of Villianur Jyarkkai
Padukappu Maiyam (supra):“164. The plea raised by the learned counsel for the appellants that
the Government of Pondicherry was arbitrary and unreasonable in
switching the whole public tender process into a system of personal
selection and, therefore, the appeals should be accepted, is devoid
of merits. It is well settled that non-floating of tenders or not holding
of public auction would not in all cases be deemed to be the result
of the exercise of the executive power in an arbitrary manner.
…
…
…
171. In a case like this where the State is allocating resources such
as water, power, raw materials, etc. for the purpose of encouraging
development of the port, this Court does not think that the State is
bound to advertise and tell the people that it wants development of
the port in a particular manner and invite those interested to come
up with proposals for the purpose. The State may choose to do so if
it thinks fit and in a given situation it may turn out to be
advantageous for the State to do so, but if any private party comes
before the State and offers to develop the port, the State would not
be committing breach of any constitutional obligation if it negotiates
with such a party and agrees to provide resources and other
facilities for the purpose of development of the port.”
Noticeable it is that in the aforesaid case of Villianur Jyarkkai
Padukappu Maiyam (supra), selection of a developer by the
Government of Pondicherry for development of Pondicherry Port on
BOT basis was sought to be questioned in High Court but therein,
the writ petitioners (appellants before the Supreme Court) had
conceded that they were not assailing the selection of the developer
but were concerned with possible environmental effect of the project.
In the circumstances, the Hon‟ble Supreme Court though found the
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
appeals not maintainable but, looking to the issues involved, still
considered the matter on merits; and after examining all the facts
and the relevant factors, held as under:“173. The terms and conditions of the contract entered into with
Respondent 11 as well as the surrounding circumstances show that
the State has acted bona fide and not out of improper or corrupt
motive or in order to promote the private interest of Respondent 11
at the cost of the State. Therefore, it is difficult to interfere and
strike down the State action as arbitrary, unreasonable or contrary
to public interest.
174. It is true that one of the methods of securing the public
interest, when it is considered necessary to dispose of a property,
is to sell the property by public auction or by inviting tenders. But as
noted earlier, this is not a case of sale of property by the State.
Though public auction or inviting of tenders is the ordinary rule in
case where the State Government proposes to dispose of a
property, it is not an invariable rule. There may be situations where
there are compelling reasons necessitating departure from the rule,
the reasons indicated in this case for the departure are shown to be
rational and are not suggestive of discrimination.”
Apparent it is that in the aforesaid decision, in the given facts
situation, the Hon‟ble Supreme Court found no reason to interfere
when the State had acted bona fide and not out of improper motive
or to promote the private interest of the developer.
In the case of Ravi Development (supra), the Hon‟ble
Supreme Court approved the methodology of award of an innovative
project plant to the originator of proposal by „Swiss Challenge
Method‟ whereby, the originator of the proposal is given the benefit
of matching the highest bid submitted. Finding the method as
adopted to be otherwise not against the Government revenue and
being transparent, the Hon‟ble Supreme Court found no reason that
such an executive decision of the Government be interfered with.
Though the aforesaid decisions have no direct application to
the facts of the present case but, in a summation of the principles
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
therein, it is noticed that the method of open invitation to offer is
generally accepted to be preferable method for award of the contract
by the State and its agencies that ensures fairness and transperacy
but, departure therefrom, by itself, is not of illegality, if the departure
is based on some valid and rational principles and conforms to the
requirements of fairness and reasonableness. However, a blithe
deviation is considered intolerable by the Courts, the ultimate test
being that of fairness of decision-making process and adequate
compliance of Article 14 of the Constitution of India.
While keeping the principles aforesaid in view, it could now be
examined if the impugned interrelated actions of the appellant-Board
i.e, of cancelling the process under the NIT dated 01.03.2006; and of
departure from the normal rule of inviting tenders while awarding the
contract to the appellant-Company stand the relevant tests of
reasonableness, rationality, fairness and transparency.
No reason why the earlier tender process was abandoned and
why tenders were not floated afresh; Unfairness self-evident
In the present case, it is not in dispute that the appellantBoard indeed invited offers from reputed EHV Line Construction
Contractors/Joint Venture Firms/Consortium of Firms by issuing NIT
dated 01.03.2006 for „Construction of 132KV Double Circuit
Transmission Line on 220KV Towers from Myntdu-Leshka Stage-I
HEP to the 132 KV substation at Khliehriat, Jaintia Hills, Meghalaya,
India‟. The appellant-Company and the respondent both submitted
their respective bids in response to this NIT dated 01.03.2006. The
process under this NIT was kept pending for an inexplicably long
length of time, for the reasons best known to the appellant-Board
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
alone. In any case, on 13.11.2006, only the bid of the appellantCompany was sought to be considered to which, the respondent
stated his protest by the letter dated 15.11.2006. Thereafter, the
respondent was addressed the letter dated 01.12.2006 wherein,
even while alleging that his techno-commercial bid was not fulfilling
the requisite criteria, the respondent was requested to submit certain
documents for placing the matter before the Tender Evaluation
Committee. The respondent indeed furnished the documents with
his letter dated 11.12.2006. However, thereafter, the tender process,
as initiated in the month of March, 2006, was cancelled in the month
of March, 2007, due to the alleged „unavoidable circumstances‟.
After examining the entire record, the learned Single Judge
has categorically held such a cancellation of the tender process was
without any convincing reason and, therefore, cannot be treated
anything but arbitrary. We have no hesitation in endorsing the
findings so reached by the learned Single Judge. It is very difficult to
find from the record any justification whatsoever that the tender
process that was taken up in the month of March, 2006 was
abandoned in the month of March, 2007; and the only reason
assigned for such cancellation of the tender process in the letter of
the Superintending Engineer (Trans) dated 23.03.2007 had been
that of the alleged „unavoidable circumstances‟. Obviously, no
specific reason was stated therein. In fact, no such specific reason
has been brought to the fore even before the Court.
In a desperate attempt to somehow justify this questionable
abandonment, the appellants have attempted to suggest that there
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
had been a so called change of policy decision by the Board
because of various technical and financial requirements that instead
of going ahead with 220 KV towers, the construction shall be of 132
KV towers. Such a suggestion has its own shortcomings and pitfalls.
In the first place, it is difficult to find from the material placed on
record if such a policy decision was indeed taken before issuance of
the aforesaid letter dated 23.03.2007 conveying abandonment of the
tender process due to „unavoidable circumstances‟. Secondly, it is
noticed that after such abandonment, it was proposed on
20.04.2007 that the appellant-Company be awarded the work of
„Construction of 132 KV double circuit line from Myntdu Leshka HEP
to the 132 KV Khliehriat S/S‟. The same particulars were stated in
the work order dated 16.05.2007. The specifications of towers were
nowhere stated in those propositions. It appears from the material
placed on record that only after such placing of the work order that
the Member Technical of the Board prepared the Agenda Note
dated 14.06.2007 (Annexure-5) suggesting as if construction of 220
KV Towers was not considered technically and financially feasible.
Only thereafter, the Board purportedly ratified the award of the work
„for construction/erection of 132 KV line on 132 KV double circuit
towers from MLHEP-I to the 132 KV Khliehriat Sub-Station‟ in its
meeting dated 15.06.2007.
In an overall comprehension of the record, it is but clear that
the suggestion as made before the Court that the work was
abandoned because of the change of specifications of towers is not
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
supported by the material available on record; and is rather
contradicted by the surrounding factors.
We would hasten to observe at this stage itself that if it were a
simple case of abandonment of a particular tender process only,
may be the decision as such could not have been questioned by the
respondent/writ petitioner nor the Court would have taken an
exception against the same. However, what had transpired before
and after such abandonment leaves nothing to doubt that the
cancellation of earlier tender process was lacking in bona fides and
was only a maneuver to somehow avoid the respondent and to
award the contract to the appellant-Company.
As noticed, both the appellant-Company and the respondent
were the bidders in response to the NIT dated 01.03.2006 but then,
there had been the attempts in the very first place that the
consideration of the bid of the respondent be avoided. However, the
respondent stated his protest and submitted the documents as
called for. Then, the tender process was abandoned on 23.03.2007.
However, thereafter, the same work was immediately offered to the
appellant-Company by way of the letter dated 20.04.2007 and then,
this very work of erection of towers and laying of transmission lines
from Myntdu-Leshka Stage-I HEP to the 132 KV substation at
Khliehriat, Jaintia Hills, Meghalaya was awarded to the appellantCompany by the work order dated 16.05.2007. Thereafter, the
decision was ratified by the Board only on 15.06.2007 with insertion
of the expression suggestive that the towers would be „132 KV
double circuit towers‟. While awarding the work to the appellant-
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
Company in this manner, the appellant-Board chose not to issue the
NIT nor adopted any other method of competitive bidding by the
interest and eligible persons.
It is noticed that the appellants suggested the justifications for
departure from the ordinary rule of tender process in the manner that
(i) there had been change in the specifications; (ii) it was a matter of
urgency inasmuch as the project in question was a time bound
project of public utility; (iii) the appellant-Company was the only EHV
contractor in Meghalaya, registered with the Board having a long
working experience with the Board; and (iv) the work in question was
allotted to the appellant-Company at the approved rates of the
Board.
Though learned counsel for the appellants have not suggested
the bogus ground of change of specifications as any justification for
not inviting offers in these appeals before us but, the fact that such a
ground was suggested in the first place before the Court when the
respondent took up the litigation clearly shows that the appellants
was seeking to put forward nothing but pretentions to justify the
apparently questionable method adopted by them. As noticed, even
such change of specification of towers does not appear to be a
reason for scrapping the earlier tender process. In any case, even if
it be assumed that the specifications of the towers had been
changed,
the
work
essentially remained
that
of
laying
of
transmission lines from Myntdu-Leshka Stage-I HEP to the 132 KV
substation at Khliehriat. It beats imagination as to how such alleged
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
change of specifications of towers could have been any justification
for not inviting competitive offers.
In an attempt to justify the award of work to the appellantCompany without invitation to offers, it has been strenuously argued
that the project in question was that of public utility and was time
bound; and that the same would have been jeopardized by invitation
of such offers. This justification is also nothing but a hollow pretext.
As noticed, for this work, an NIT was issued earlier in the month of
March, 2006 but the process itself dragged on for an inordinate
length of time and in fact, the respondent, who was one of the
bidders and was sought to be disqualified, made his protest in the
month of November, 2006 whereupon, he was requested to submit
certain documents; and the respondent indeed submitted the
documents in the month of December, 2006. Thereafter, the
appellant-Board chose to sit over the matter for another three
months and then, cancelled the tender process only in the month of
March, 2007. As noticed, no plausible reason for scrapping of the
said process has been brought on record. If at all it were a matter of
urgency, it is left to everyone‟s guess as to why the earlier tender
process was kept pending for more than one year and then, why the
same was scrapped at all? In this regard, again, even if we assume
that scrapping of earlier tender process was not an oblique decision,
it is difficult to find any rationale or any justification that after
scrapping, the appellant-Board suddenly found it to be a matter of
urgency and then, chose to offer the work to the appellant-Company
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
without adopting any such method which would have ensured
competitive biddings.
We are at one with learned Single Judge that no compelling
circumstances or reasons had been assigned for not inviting offers,
even if it was suddenly found to be a matter of urgency. Although,
the urgency suggestion itself is clearly pretentious for, as observed
above, the earlier tender process was kept pending for more than a
year without any reason.
The other specious justification as put forward by the
appellants for awarding of the contract without open invitation in the
manner that the appellant-Company was the only EHV contractor in
the State of Meghalaya, having a long working experience with the
Board, in fact, clinches the issue that the entire exercise had been
wanting in bona fides and was intended only to award the contract to
the appellant-Company alone. Even if the appellant-Company was
having a so called „long working experience with the Board‟, it had
not acquired the status of an exclusive contractor with the Board
who could have a monopoly over the contracts. It is not the case,
and we are unable to find any logic in any such proposition, that only
the EHV contractor in the State of Meghalaya could have been
considered qualified for the work in question. Unless an open
invitation was made and offers were received, there was no
occasion for the Board to assume that the appellant-Company alone
was to be awarded the contract in question. Noticeable in this regard
is the fact that the respondent had indeed made the offer pursuant to
the earlier NIT issued and even submitted the documents later on
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
required. There had not been any final decision on the offer made by
him that he was disqualified. The learned Single Judge has found,
and rightly so, that the appellant-Board had not been able to assign
any reason as to why the respondent was sought to be considered
as disqualified. We have no hesitation in finding the action of the
Board wanting in bonafide because without inviting any offer after
scrapping of the earlier tender process, the Board could not have
assumed that the appellant-Company alone was to be awarded the
contract in question.
The other justification stated on behalf of the appellants
sounds rather preposterous. It is suggested that work in question
was allotted to the appellant-Company at the approved rates of the
Board. The very fundamental of inviting competitive bids is that such
a process best serves the interest of revenue. Without inviting other
bidders, the Board could not have assumed that awarding of the
contract on its suggested rates was best serving the interest of
revenue and there could not have been any better proposal serving
the finances.
When we find that there had been no justification in
abandonment of the earlier tender process and no justification in
awarding the contract thereafter to one of the bidders in the earlier
tender process but without inviting offers, we have no hesitation in
affirming the findings of the learned Single Judge in this regard and
in holding that the impugned action of the appellant-Board was
lacking in fairness and reasonableness; and was intended only to
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
provide a backdoor entry to the appellant-Company. The action of
the appellant-Board could only be deprecated and disapproved.
The writ petitioner’s right to relief
In the ordinary course, the consequence of the findings
against the validity of the process in question would have been of
setting it aside but then, it cannot be said that as a further
consequence thereof, the work would have been awarded to the
respondent alone. Then, the fact of the matter had been that even
when the writ petition was filed, a substantial part of the work in
question had already been executed and by the time the writ petition
was decided, the execution was complete. In the given set of facts
and circumstances, though the respondent could be considered as
one of the potential bidders who had indeed offered the bid earlier
and who might have been interested in offering the bid if tenders
were floated afresh but then, it is difficult to say that the respondent
alone would have the only person entitled to be awarded the
contract in question. Taking an overall view of the matter, we are of
the view that only a reasonable amount of compensation could have
been considered available for the respondent (writ petitioner) and
not beyond.
Quantification of compensation and offers for settlement
After it is found that the respondent (writ petitioner) could have
been awarded a reasonable amount of compensation, the question
arises as regards quantification of such compensation. It is noticed
that the respondent has not given out all the factors requisite for
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
making a fair assessment of compensation in this matter. The
learned Single Judge had rightly observed in the first place that the
writ petition was not the appropriate proceedings for awarding of
damages to the petitioner for the loss which he had suffered.
However, thereafter, the learned Single Judge observed that the writ
petitioner was required to be compensated for having been denied
the right to equal treatment under Article 14 of the Constitution.
Thereafter, the learned Single Judge referred to the decision in the
case of Subhash Projects (supra) and then, straightway awarded an
amount of Rs.10 lakhs to the writ petitioner. With respect, we are
unable to endorse such awarding of a lump sum to the respondent
(writ petitioner) and that too to the tune of Rs.10 lakhs. No basis for
arriving at this figure of Rs.10 lakhs had been indicated in the order
impugned except a reference to the decision in the case of Subhash
Projects. However, in the case of Subhash Projects (supra), the
reasons for awarding compensation to the tune of Rs.1 crore to the
writ petitioner therein have been indicated at the outset by the
Hon‟ble Supreme Court in the introduction of the case in paragraph
1 of the judgment as follows:“….. This was on the finding that the contract based on the tender
floated by Respondent No.1, the West Bengal Power Development
Corporation Limited (hereinafter referred to as “the Power
Corporation”) ought to have been awarded to the writ petitioner L &
T and the award of the same to Respondent 11 Subhash Projects
was illegal, but it was inexpedient at that stage to set aside the
award of the contract and the least that should be done was to
direct Subhash Projects to disgorge at least some portion of the
profit it would have earned out of the illegally awarded contract and
make over the same as compensation to the writ petitioner L & T,
who ought to have been awarded the contract…...”
(underlining supplied for emphasis)
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
In the present case, as noticed, all the relevant factors for
quantification of compensation are not available on record and in
any case, it cannot be said that the contract in question ought to
have been awarded to the writ petitioner alone, as was the finding in
the case of Subash Projects. Of course, the process as adopted by
the appellant-Board is thoroughly disapproved and it is also found
that the unfair and unquestionable process was adopted essentially
in order to provide backdoor entry to the appellant-Company but
then, these findings by themselves do not lead to the result that the
writ petitioner alone was to get the contract in question. In any case,
the learned Single Judge has not indicated any basis for awarding
the lump sum of Rs.10 lakhs. The decision in Om Metals (supra) is
also of no help to the respondent because therein, compensation
was awarded per the terms of contract for excess period of work.
The respondent is of course entitled to be awarded a
reasonable amount of compensation particularly when the first
tender process was cancelled in an unfair manner and thereafter, no
tenders were invited and the contract was awarded to the appellantCompany. Having said thus, we would have considered taking up
the process for arriving at a reasonable amount of compensation
while compelling the appellant-Company to disgorge some portion of
profit earned out of illegally awarded contract and the appellantBoard also to share such burden for having conducted the
proceeding in an unfair manner. However, such a process does not
appear necessary in this matter for the reasons that during the
course of hearing, the appellants have placed before us by way of
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
alternative submissions, their offers, as were earlier made to the
respondent but were not accepted by him. Now and at this juncture,
we may take note of such offers. On behalf of the appellantCompany, the offer for settlement has been stated as under:“1. The instant appeal has been filed by the Appellant challenging
the Judgment and Final Order dated 11.10.2010 passed by the
learned Single Bench in WP(C) No.295 of 2007.
2. That the Appellant is willing to part with an amount of Rs.2.17
lacs (Rupees two lakhs and seventeen thousand) only, towards
compensation/damages to be paid to the private respondent.
3. That it is prayed that this Hon‟ble Court may kindly consider the
proposed amount of Rs.2.17 lacs (Rupees two lakhs and seventeen
thousand) only towards compensation/damages to be paid to the
private respondent.”
On behalf of the Board, its efforts for settlement and matching
offer made for the purpose have been indicated as follows:“1. That the Appellant/MeECL have preferred an appeal and the
same was registered as W.A. No.6 of 2011.
2. That the Appellant/MeECL begs to state that on the 30.03.2016
the Appellant/MeECL with the permission of this Hon‟ble Court had
again made an effort for settlement and the Appellant/MeECL was
ready to part with Rs.2,17000/- (Rupees two lakhs seventeen
thousand) only towards compensation/quantum for the loss/injury
suffered by the Respondent.
3. That the Appellant begs to state that the amount of Rs.2,17000/(Rupees two lakhs seventeen thousand) only proposed by the
Appellant/MeECL was not accepted and denied by the Respondent.
4. That this Application is filed bonafidely for the ends of justice to
bring on record the outcome of the settlement effort made by the
MeECL/Appellant.”
In an overall comprehension of the matter, we find the offers
aforesaid just and proper and the resultant amount payable to the
respondent i.e., a sum of Rs.4,34,000/- (Rupees four lakhs thirty four
thousand) to be that of fair amount of compensation in this case.
Having regard to the circumstances of the case, we find no reason to
interfere with the award of costs in this matter but shall not make any
further order towards costs of these appeals.
Writ Appeal No. 49 of 2010 &
Writ Appeal No. 6 of 2011
Conclusion
Accordingly, and in view of the above, these appeals are
partly allowed to the extent and in the manner indicated. The
findings as regards the process adopted by the appellant-Board in
awarding the contract in question to the appellant-Company are
affirmed; however, the amount of compensation as awarded in the
order impugned is modified and the respondent (writ petitioner) is
held entitled to an amount of Rs.4,34,000/- (Rupees four lakhs thirty
four thousand) towards compensation. The respondent (writ
petitioner) shall be further entitled to the amount of Rs.50,000/(Rupees fifty thousand) towards costs of proceedings as awarded by
the learned Single Judge. The amount so payable shall be borne in
equal proportion by the appellant-Company and the appellant-Board.
JUDGE
Lam
CHIEF JUSTICE
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review