IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 23RD DAY OF FEBRUARY, 2026
PRESENT
THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
AND
THE HON'BLE MR. JUSTICE C.M. POONACHA
WRIT APPEAL NO. 1825 OF 2025 (GM-KEB)
BETWEEN:
1.
Digitally
signed by
SRIDEVI S
Location:
High Court
of Karnataka
M/S. PERFECT ELECTRICALS
A PARTNERSHIP FIRM,
REGISTERED UNDER THE INDIAN
PARTNERSHIP ACT, 1932,
PLOT NO. 152, SOMPURA 1ST STAGE,
KIADB INDUSTRIAL AREA,
DABASPET, NELAMANGALA TALUK,
BENGALURU-562 111,
REPRESENTED BY ITS MANAGING PARTNER,
SRI. P. V. KUMARASWAMY,
AGED ABOUT 65 YEARS,
S/O. LATE VEERABHADRAPPA.
…APPELLANT
(BY SRI. SIDDHARTH SUMAN, ADVOCATE)
AND:
1.
MANGALORE ELECTRICITY SUPPLY COMPANY
(MESCOM)
A GOVERNMENT OF KARNATAKA UNDERTAKING
REGISTERED UNDER THE COMPANIES ACT, 1956,
HAVING ITS REGISTERED OFFICE AT 2ND FLOOR,
MESCOM BHAVANA, KAVOOR CROSS ROAD,
BEJAI, MANGALURU-575 004,
REPRESENTED BY ITS MANAGING DIRECTOR.
-2NC: 2026:KHC:12553-DB
WA No. 1825 of 2025
HC-KAR
2.
SUPERINTENDING ENGINEER (ELE)
O & M CIRCLE, MESCOM,
HAVING REGISTERED OFFICE AT
KUNJIBETTU, UDUPI-576 102.
3.
THE EXECUTIVE ENGINEER (ELE)
O & M DIVISION, MESCOM,
MARUTHI VITHIKA,
UDUPI-576 101.
4.
THE EXECUTIVE ENGINEER (ELE)
O & M DIVISIONS, MESCOM,
KARKALA-574 104.
5.
THE EXECUTIVE ENGINEER (ELE)
O & M DIVISION, MESCOM,
NANASAHEB ROAD,
KUNDAPURA-576 201.
…RESPONDENTS
(BY SRI. AMRUTHA VARSHINI M.,ADVOCATE)
WRIT APPEAL FILED U/S 4 OF THE KARNATAKA HIGH
COURT ACT PRAYING TO SET ASIDE THE ORDER DATED
10/10/2025 PASSED BY THE LEARNED SINGLE JUDGE IN WP
NO.7513/2025 DISMISSING THE SAID WRIT PETITION AND TO
CONSEQUENTLY ALLOW THE WP NO.7513/2025 FILED BY
THE APPELLANT AS PRAYED FOR AND TO AWARD COSTS
AND GRANT SUCH OTHER RELIEFS.
THIS
APPEAL,
COMING
ON
FOR
PRELIMINARY
HEARING, THIS DAY, JUDGMENT WAS DELIVERED THEREIN
AS UNDER:
-3NC: 2026:KHC:12553-DB
WA No. 1825 of 2025
HC-KAR
CORAM: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
and
HON'BLE MR. JUSTICE C.M. POONACHA
ORAL JUDGMENT
(PER: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE)
1.
The appellant has filed the present appeal impugning an
order dated 10.10.2025 passed by the learned Single Judge of this
Court in WP.No.7513/2025 (GM-KEB). The learned Single Judge
had declined to entertain the said writ petition on the ground that
disputed questions of fact were involved, and therefore it would not
be apposite to consider the same in the proceedings under Article
226 of the Constitution of India.
2.
The appellant had filed the said writ petition, inter alia,
praying as under:
"a. to issue a writ of certiorari or such other
appropriate writ or orders directions, quashing the
notice No.AaEm(V)/UDUPI/KaNiEm(V)Sakaniem2/Ka-78/1/118201/2024 dated 2.12.2024 issued by
the Respondent No. 1 i.e., Annexure - J as
arbitrary, illegal and unjust;
b. to issue a writ of mandamus directing the
Respondents to refund the security deposit
amounting to Rs.13,89,558/-, which has been
unlawfully withheld by the Respondent;
-4NC: 2026:KHC:12553-DB
WA No. 1825 of 2025
HC-KAR
c. to issue a writ of mandamus directing the
Respondent to refund the amount unlawfully
obtained by invoking the Petitioner's Bank
Guarantee amount of Rs.12,15,000/-;
d. To issue a Writ of Mandamus directing the
Respondent to release the outstanding dues
payable to the Petitioner for the repair works
undertaken on faulty transformers, Invoice No. KL007 dated 30.03.2024 for an amount of
Rs.9,49,960/- and Invoice No.UP-005 dated
28.03.2024 for an amount of Rs.24,65,886/-."
3.
Mangalore Electricity Supply Company [MESCOM] had
invited tenders for the repair and reconditioning of failed distribution
transformers on a buy-back basis for the Udupi O&M Circle. The
scope of work under the said tender included release of
transformer oil; removal of high-voltage (HV) and low voltage (LV)
coils along with other unserviceable components; repair of the
transformer by incorporating new high-tension (HT) and lowtension (LT) coils; painting; replacement of bushing and other
necessary parts; refilling the transformer with Extra High Voltage
(EHV) grade new or reclaimed transformer oil procured from
approved vendors; and conducting testing of the repaired
transformers in accordance with the stipulated terms.
-5NC: 2026:KHC:12553-DB
WA No. 1825 of 2025
HC-KAR
4.
The appellant's bid pursuant to the notice inviting tenders
was accepted, and a Rate Contract Award dated 03.01.2023 was
issued to the appellant.
Additionally, the Contract Agreement
dated 03.01.2023 was entered into between the concerned parties.
The appellant states that the agreement was for a period of two
(02) years. However, the extension for the second year was subject
to successful completion of the work during the first year. The
appellant claims that it was successful in performance during the
first year, and therefore the respondents reissued the tender to the
appellant for the second year as well. However, the appellant did
not accept the same. Subsequently, the appellant claimed that it
duly repaired the faulty transformers in accordance with the terms
under the guarantee clause – clause 8.01 of the Agreement. The
said clause is reproduced below:
"8.01 GUARANTEE:
8.01.1 The repaired Transformer shall be
guaranteed for satisfactory operation against failure
due to bad workmanship (repair) for a period of
18 months from the date of delivery or 12 months
from the date of Commissioning of transformer
whichever is earlier. The Contractor shall repair the
Transformers at his own cost that fails during the
guarantee period. In case where repaired
Transformer fails within guarantee period the same
shall be collected within 7days from the date of
intimation by the concerned Divisional stores and
-6NC: 2026:KHC:12553-DB
WA No. 1825 of 2025
HC-KAR
shall be returned duly repaired within 15 days from
the receipt of intimation, failing which next batch of
faulty Transformers will not be issued for repairs.
Further, in case repaired transformer on
commissioning fails again within 1 year from the
date of commissioning, the same will have to be
repaired at his own cost and returned to stores
within 10 days.
8.01.2. The repairer shall repair all the transformers
failed within guarantee period within stipulated
period failing which cost of the repairs of
Transformers failed within guarantee period will be
deducted out of the security deposit held for the
purpose. If the security deposit held for that
particular batch falls short, the remaining amount
will be recovered out of either the security deposit
held for the other batches or the running bills on
hand whichever is feasible. No Explanations/Claims
will be entertained in this regard."
5.
The appellant claims that in terms of the aforesaid clause, it
had duly repaired all faulty distribution transformers and the
repaired transformers were delivered to their respective divisional
stores. The appellant claims that it had sought for the test reports in
respect of repaired and reconditioned transformers. The reports
indicated the transformers repaired by the appellant had passed
the tests, and its repair and reconditioning work had been accepted
without any reservation. Thereafter, the appellant had raised
invoices for the same.
-7NC: 2026:KHC:12553-DB
WA No. 1825 of 2025
HC-KAR
6.
The appellant states that during the joint inspection, certain
transformers that were within the guarantee period, were found not
working, as all three coils were burnt. The appellant claims that this
failure could not be attributed to bad workmanship but was due to
factors beyond the appellant's control. However, the respondents
contend that the appellant has failed to perform his obligation.
Paragraph 8 of the writ petition, which gives a glimpse of the
disputes between the parties is set out below:
"8. In reference to the letters sent by the Petitioner,
the Respondents issued a notice dated 17.08.2024,
directing the Petitioner to repair all transformers that
failed within the guarantee period at its own cost.
The notice further stated that even after the expiry
of the contract period, the Petitioner was obligated
to repair any pending transformers that failed within
the guarantee period, at its own cost, within its own
workshop. It was alleged that certain transformers
had failed within the guarantee period and remained
pending repair at the Petitioner's end. The
Respondents claimed that repeated requests were
made via telephone and official letters, urging the
Petitioner to repair and return the failed
transformers at the earliest. However, the
Petitioner, in its response, maintained that the
guarantee applied only to defects arising from
defective workmanship and that the transformers in
question had failed due to factors beyond its
control, including natural calamities (such as rain,
heavy winds, and lightning), overload due to
unauthorized connections, power failures, and
single-phasing power supply. The Respondents
further asserted that the Petitioner had falsely
-8NC: 2026:KHC:12553-DB
WA No. 1825 of 2025
HC-KAR
claimed that certain failed transformers were jointly
inspected by AEE, MT, Udupi, and declared as
having three (3) coils burnt, thereby classifying
them as failures occurring after the guarantee
period ("AGP failure"). According to the
Respondents, the report furnished by AEE, MT,
Udupi, did not indicate that such an inspection had
taken place or that transformers were declared as
three (3) coils burnt. Additionally, the Respondents
rejected the Petitioner's contention that the stated
causes of failure exempted it from repair
obligations, asserting that normal monsoon
conditions did not constitute natural calamities and
that no unauthorized loads were responsible for the
failures. The notice concluded by directing the
Petitioner to repair and return all failed transformers
without further delay. A copy Notice bearing No.SE
(E)/UDP/EE(O)AEE-2/F-78/1/104070/2024
dated
17.08.2024 of the respondent is herewith produced
as ANNEXURE - E."
7.
It is clear from the above that the disputes between the
parties are contractual in nature and involve disputed questions of
fact. We concur with the learned Single Judge that it would not be
apposite to entertain such disputes in proceedings under Article
226 of the Constitution of India.
8.
The appeal is, accordingly, dismissed.
9.
We, however, clarify that this order would not preclude the
appellant from availing other remedies, in accordance with law.
-9NC: 2026:KHC:12553-DB
WA No. 1825 of 2025
HC-KAR
10.
Pending application stands disposed of.
Sd/(VIBHU BAKHRU)
CHIEF JUSTICE
Sd/(C.M. POONACHA)
JUDGE
SD
List No.: 2 Sl No.: 16
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review