2026:CGHC:26230-DB
NAFR
HIGH COURT OF CHHATTISGARH AT BILASPUR
WPC No. 3135 of 2026
M/s Pearl India Marketing Services Private Limited Through Its Authorized
Signatory/representative, Having Its Office At Plot No. F-281, Behind
Gumber Petrol Pump, Vyapar Vihar, Bilaspur, Chhattisgarh, 495001
... Petitioner
versus
1 - State Of Chhattisgarh Through The Secretary, Department Of Energy,
Mahanadi Bhawan, Mantralaya, Naya Raipur, Chhattisgarh- 492002
2 - Chhattisgarh State Renewable Energy Development Agency (C R E D A)
Through Its Chief Executive Officer, C.R.E.D.A, V I P Road, Raipur,
Chhattisgarh - 492006
3 - Superintendent Engineer R E -1, C R E D A, V I P Road, Raipur,
Chhattisgarh - 492006
4 - Executive Engineer R E -V, C.R.E.D.A. V I P Road, Raipur, Chhattisgarh
- 492006
... Respondents
(Cause title taken from Case Information System)
VED
PRAKASH
DEWANGAN
Digitally signed
by VED
PRAKASH
DEWANGAN
Date:
2026.06.30
10:50:53 +0530
For Petitioner
:
Mr. Ayush Mittal, Advocate
For Respondents/State
:
Mr. Shashank Thakur, Addl. A.G.
Hon'ble Shri Ramesh Sinha, Chief Justice
Hon'ble Shri Ravindra Kumar Agrawal, Judge
Order on Board
Per Ramesh Sinha, Chief Justice
29/06/2026
1.
Heard Mr. Ayush Mittal, learned counsel appearing for the petitioner.
Also heard Mr. Shashank Thakur, learned Additional Advocate
General appearing for the State/respondent No.1.
2.
By way of the present writ petition filed under Article 226 of the
Constitution of India, the petitioner has called in question the legality
and
validity
of
the
Notice
Inviting
Tender
(NIT)
Ref.
No.
2708/CREDA/SPVHLS/2026-27 dated 08.06.2026 and the E-Bid
Document No. 192875/CREDA/SPVHLS/2026-27 dated 09.06.2026,
issued
by
respondent-CREDA
for
supply,
installation
and
commissioning of 753 Solar Photovoltaic Home Lighting Systems, to
the extent the respondents have sought to re-tender the very same
753 systems which were earlier allotted to the petitioner and whose
work order was subsequently cancelled, contending that such retendering during the pendency of the petitioner's contractual dispute
resolution proceedings is arbitrary, unfair and violative of Article 14 of
the Constitution of India.
3.
The present petition has been filed by the petitioner seeking for the
following reliefs:“In view of the facts pleaded, documents relied
upon and grounds urged, the petitioner most
respectfully prays that this Hon'ble Court be
pleased to:
A. Issue an appropriate writ, order or
direction quashing and setting aside the
impugned
fresh
NIT
Ref.
2708/CREDA/SPVHLS/2026-27
No.
dated
08.06.2026 and E-Bid Document No.
192875/CREDA/SPVHLS/2026-27 dated
09.06.2026, to the extent the same
seeks to re-tender the 753 Solar Home
Light Systems earlier allotted to and
thereafter cancelled from the Petitioner;
B. In the alternative, issue an appropriate
writ, order or direction restraining the
Respondents
from
finalising
the
impugned tender, issuing LOI/work order,
or creating any third-party rights pursuant
to
NIT
Ref.
No.
2708/CREDA/
SPVHLS/2026-27 dated 08.06.2026 / EBid
Document
No.
192875/CREDA/
SPVHLS/2026-27 dated 09.06.2026, till
the
Petitioner's
invoked
contractual
dispute resolution proceedings in respect
of cancellation of 753 systems are
considered in accordance with law;
C. Hold that the action of RespondentCREDA in re-tendering the same 753
Solar Home Light Systems, while the
Petitioner's remedy against cancellation
of the said systems has already been
invoked and is pending/available, is
arbitrary,
unfair,
colourable,
self-
contradictory and violative of Article 14 of
the Constitution of India;
D. Direct the Respondents not to treat
the Petitioner as blacklisted, debarred or
disqualified
on
the
basis
of
the
blacklisting orders dated 05.05.2025 and
20.04.2026, both of which have already
been quashed by this Hon'ble Court;
E. Call for the entire records relating to
issuance of the impugned fresh tender,
including note-sheets, approval records,
decision-making
specifications,
file,
technical
comparison
with
the
earlier tender, and reasons for retendering the same 753 Solar Home
Light Systems;
F. Direct the Respondents to decide the
Petitioner's
representation/
pre-bid
objection dated..2026 by a reasoned
order before taking any further final step
pursuant to the impugned tender;
G. Grant any other relief/order/direction
which this Hon'ble Court may deem fit
and
proper
in
the
facts
and
circumstances of the case, in the interest
of justice.”
4.
The facts, in brief, are that respondent No.2/CREDA had floated
Tender No. 155945 dated 10.07.2024 for supply, installation and
commissioning of Solar Home Lighting Systems of 300 Wp capacity
under the PM-JANMAN Scheme. The petitioner participated in the
tender process and was awarded the work. According to the
petitioner, after submission and approval of the requisite sample
system and technical documents by CREDA, it commenced execution
of the work in accordance with the tender conditions. Subsequently,
disputes arose between the parties regarding the specifications of the
systems supplied by the petitioner, particularly concerning the alleged
deviation in the 68-cell/72-cell solar module configuration and Isection/C-channel mounting structure. Based on such allegations,
CREDA initially passed an order dated 05.05.2025 blacklisting the
petitioner, which came to be quashed by this Court in WPC No. 2677
of 2025 vide order dated 03.12.2025, while leaving the contractual
disputes to be resolved before the appropriate forum. Thereafter,
CREDA again passed a fresh order dated 20.04.2026 blacklisting the
petitioner and, on the same date, cancelled the work order relating to
753 unexecuted Solar Home Lighting Systems. The petitioner
questioned the said orders in WPC No. 2310 of 2026, wherein this
Court, by order dated 08.05.2026, set aside the fresh blacklisting
order but relegated the petitioner to avail the contractual dispute
resolution mechanism with regard to the cancellation of the work
order.
5.
It is the further case of the petitioner that, pursuant to the liberty
granted by this Court, it has already invoked the contractual dispute
resolution mechanism by issuing an arbitration notice challenging the
cancellation of the aforesaid 753 systems. During the pendency of the
said
contractual
impugned
proceedings,
NIT Ref.
No.
respondent-CREDA
issued
2708/CREDA/SPVHLS/2026-27
the
dated
08.06.2026 and E-Bid Document No. 192875/CREDA/SPVHLS/202627 dated 09.06.2026 inviting fresh bids for supply, installation and
commissioning of the very same 753 Solar Photovoltaic Home
Lighting Systems. According to the petitioner, the impugned re-tender
is arbitrary and amounts to a colourable exercise of power, as it seeks
to create third-party rights over the subject matter of the pending
contractual dispute, thereby rendering the petitioner's contractual
remedy illusory. It is further pleaded that the earlier action against the
petitioner was founded upon alleged deficiencies relating to the 72cell module configuration and C-channel mounting structure, whereas
the impugned tender does not expressly prescribe those very
requirements. Aggrieved thereby, the petitioner has filed the present
writ petition seeking quashment of the impugned tender, or in the
alternative, a restraint against its finalisation pending adjudication of
the contractual dispute.
6.
Learned counsel for the petitioner would submit that the impugned
tender has been floated for the very same 753 Solar Home Lighting
Systems, which were earlier allotted to the petitioner and whose work
order came to be cancelled by respondent-CREDA. It is contended
that although this Court, while deciding WPC No. 2310 of 2026,
relegated the petitioner to avail the contractual dispute resolution
mechanism in respect of the cancellation of the work order, the
petitioner has already invoked the arbitration clause by issuing a
notice invoking arbitration. According to him, during the pendency of
the said contractual proceedings, the respondents could not have
proceeded to issue a fresh tender in respect of the same work, as
such action would create irreversible third-party rights and virtually
render the contractual remedy available to the petitioner nugatory and
illusory.
7.
It is further argued that the impugned action is arbitrary, unfair and hit
by Article 14 of the Constitution of India. Learned counsel would
contend
that
the
earlier
cancellation
and
blacklisting
were
substantially founded on the alleged deviation regarding the 72-cell
module configuration and C-channel mounting structure; however, the
impugned tender does not prescribe those very requirements, thereby
demonstrating a self-contradictory approach on the part of the
respondents. It is also submitted that both the blacklisting orders
passed against the petitioner have already been quashed by this
Court and, therefore, the petitioner cannot be treated as a defaulting
or disqualified contractor. It is thus prayed that the impugned tender,
to the extent it pertains to the aforesaid 753 systems, deserves to be
quashed, or in the alternative, the respondents be restrained from
finalising the tender till the contractual dispute is adjudicated.
8.
Per contra, learned State counsel as well as learned counsel
appearing for respondent-CREDA would oppose the writ petition and
submit that the dispute raised by the petitioner essentially emanates
from the cancellation of a contractual work order and, therefore, is
purely contractual in nature. It is contended that this Court, in the
earlier round of litigation, has already relegated the petitioner to avail
the contractual dispute resolution mechanism insofar as the
cancellation of the work order is concerned, and accordingly the
petitioner has already invoked arbitration. Once the contractual
remedy has been invoked, the petitioner cannot seek to indirectly
challenge the consequences of such cancellation by questioning a
subsequent and independent tender process in exercise of the writ
jurisdiction under Article 226 of the Constitution of India.
9.
It is further submitted that the respondents, being instrumentalities of
the State, are duty-bound to ensure timely implementation of the PMJANMAN Scheme and supply of the Solar Home Lighting Systems for
the benefit of the intended beneficiaries. The issuance of a fresh
tender is stated to be an administrative and commercial decision
taken in public interest after cancellation of the earlier work order, and
the petitioner has no vested or enforceable right to insist that the work
should remain unallotted pending adjudication of its contractual
claims. It is argued that no mala fides, arbitrariness or violation of any
statutory provision has been demonstrated in the decision-making
process warranting interference in judicial review. It is, therefore,
prayed that the writ petition, being devoid of merits, deserves to be
dismissed.
10.
We have heard learned counsel for the parties and considered their
rival submissions made herein above and also gone through the
entire records of the case with utmost circumspection.
11.
Having heard learned counsel for the parties and having perused the
material available on record, this Court finds that the principal
challenge in the present writ petition is directed against the fresh
Notice Inviting Tender dated 08.06.2026 and the E-Bid Document
dated
09.06.2026
issued
by
respondent-CREDA
for
supply,
installation and commissioning of 753 Solar Photovoltaic Home
Lighting Systems. The petitioner's grievance is that the fresh tender
pertains to the very same 753 systems whose work order had earlier
been cancelled and that, since the petitioner has already invoked the
contractual dispute resolution mechanism pursuant to the liberty
granted by this Court in the earlier writ proceedings, the respondents
ought not to have proceeded with the re-tendering process until the
contractual dispute is adjudicated.
12.
At the outset, it deserves to be noticed that the cancellation of the
work order dated 20.04.2026 was specifically left open by this Court to
be questioned before the appropriate contractual forum while deciding
WPC No.2310 of 2026. Admittedly, the petitioner has already invoked
the arbitration clause in terms of the contract. Therefore, the legality
and consequences of the cancellation of the work order, together with
the rights and obligations flowing therefrom, are matters which are
already sub judice before the forum agreed upon by the parties under
the contract. The present writ petition cannot be permitted to become
an indirect means of adjudicating or protecting contractual rights
which are required to be determined in the arbitral proceedings.
13.
It is well settled that judicial review in matters relating to award of
contracts or tenders is concerned with the decision-making process
and not with the merits of the commercial decision itself. Unless the
decision is shown to be arbitrary, mala fide, irrational, intended to
favour a particular bidder, or in violation of statutory provisions,
constitutional courts ordinarily refrain from interfering in matters
involving commercial wisdom of the employer. In Tata Cellular v.
Union of India, the Hon'ble Supreme Court held that the Court does
not sit as an appellate authority over administrative decisions in
contractual matters and judicial restraint is the governing principle.
14.
The aforesaid principle has consistently been reiterated by the
Hon'ble Supreme Court in Jagdish Mandal v. State of Orissa,
wherein it was held that interference in tender matters is warranted
only where the decision is actuated by mala fides or arbitrariness to
the extent that no responsible authority acting reasonably could have
arrived at such decision, and where overwhelming public interest
requires judicial intervention. Similarly, in Michigan Rubber (India)
Ltd. v. State of Karnataka, it has been held that fixation of tender
conditions and decisions relating to award of contracts essentially lie
within the domain of the employer and the scope of judicial review
remains extremely limited.
15.
Applying the aforesaid principles to the facts of the present case, this
Court is unable to find any infirmity in the decision-making process
adopted by respondent-CREDA in issuing the impugned tender. The
mere fact that the fresh tender relates to the same quantity of systems
whose work order had earlier been cancelled does not, by itself,
establish arbitrariness or mala fides. Once the earlier work order stood
cancelled, respondent-CREDA, being an implementing agency
entrusted with execution of a public welfare scheme, cannot be
compelled to indefinitely withhold procurement merely because the
erstwhile contractor has chosen to invoke arbitration. Public projects
cannot remain suspended until conclusion of arbitral proceedings,
which may consume considerable time.
16.
The submission of the petitioner that finalisation of the impugned
tender would render the arbitral proceedings infructuous also does not
merit acceptance. The scope of arbitration would continue to remain
intact for adjudication of the legality of cancellation of the work order
and the consequential contractual reliefs, including such reliefs as
may be permissible in law. The possibility that the nature of relief
ultimately available to the petitioner may undergo a change owing to
subsequent events cannot furnish a ground for restraining the
employer from proceeding with a fresh procurement undertaken in
public interest.
17.
Equally untenable is the submission founded upon the quashing of the
earlier blacklisting orders. It is true that the blacklisting orders passed
against the petitioner were set aside by this Court. However, the
present tender has not been challenged on the ground that the
petitioner has been declared ineligible or has been excluded from
participation by treating it as a blacklisted contractor. The controversy
in the present case relates to the issuance of a fresh tender after
cancellation of the earlier work order, which constitutes a distinct
cause of action. The quashing of the blacklisting orders, therefore,
does not confer upon the petitioner any enforceable right to insist that
the respondents must keep the work unexecuted until the contractual
disputes are finally resolved.
18.
The contention that the technical specifications contained in the fresh
tender differ from the specifications which formed the basis of the
earlier dispute likewise does not persuade this Court to exercise its
extraordinary jurisdiction. Prescription or modification of technical
specifications in a tender document falls within the realm of
commercial and technical policy of the procuring authority. Unless
such
specifications
are
shown
to
be
manifestly
arbitrary,
discriminatory or tailor-made to favour a particular bidder, the Court
would not substitute its own opinion for that of the technical experts.
Reference in this regard may also be made to the decisions of the
Hon'ble Supreme Court in Afcons Infrastructure Ltd. v. Nagpur
Metro Rail Corporation Ltd. and Silppi Constructions Contractors
v. Union of India, wherein it has been emphasised that courts must
exercise
considerable
restraint
in
matters
involving
technical
evaluation and commercial decisions of the tendering authority.
19.
This Court is also of the considered opinion that the petitioner has
failed to demonstrate violation of any statutory provision or
infringement of any legal or fundamental right so as to warrant
interference under Article 226 of the Constitution of India. The
grievance projected by the petitioner essentially arises out of
contractual rights flowing from the earlier agreement, the adjudication
whereof has already been relegated to arbitration. The existence of
such contractual disputes cannot, by itself, invalidate a subsequent
tender issued by the employer for execution of public work.
20.
In view of the aforesaid discussion and in the light of the law laid down
by the Hon'ble Supreme Court in Tata Cellular (supra), Jagdish
Mandal (supra), Michigan Rubber (supra), Afcons Infrastructure
(supra) and Silppi Constructions (supra), this Court finds no
arbitrariness, mala fides, favouritism or procedural illegality in the
issuance of the impugned tender warranting exercise of the
extraordinary jurisdiction under Article 226 of the Constitution of India.
The petitioner is at liberty to pursue its contractual remedies before
the competent arbitral forum, where all questions relating to the
legality of cancellation of the earlier work order and the consequential
reliefs shall be decided on their own merits, uninfluenced by any
observation made in the present order.
21.
Accordingly, finding no merit in the writ petition, the same deserves to
be and is hereby dismissed. No order as to costs.
Object 1
ved
Sd/(Ravindra Kumar Agrawal)
Judge
Sd/(Ramesh Sinha)
Chief Justice
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review