Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
CGHC010372122019
2026:CGHC:43659-DB
NAFR
HIGH COURT OF CHHATTISGARH AT BILASPUR
Reserved for Judgment on : 23.09.2026
Judgment Delivered on : 08.10.2026
Judgment Uploaded on : 09.10.2026
ARBA No. 57 of 2019
M/s Orissa Concrete And Allied Industries Ltd. Through Its Authorized
Signatory, Mr. Banshi Chowdhury, S/o Late Ramrenu Chowdhury, Age 60
Years, At Plot No.53, Bhanpuri Industries Area, Post Office Birgaon, Raipur,
Chhattisgarh., District : Raipur, Chhattisgarh
--- Appellant
versus
The Union Of India Through, Its General Manager (Engineering) South East
Central Railway, Bilaspur, Chhattisgarh.
--- Respondent
____________________________________________________________
For Appellant
: Mr. Chandresh Shrivastava, Advocate with
Ms. Mahi Pandey, Advocate
For Respondent
: Mr. R.K. Mishra, DSGI with
Mr. Rishabh Dev Singh & Ms. Shweta Rai,
Advocates
Division Bench
BALRAM
PRASAD
DEWANGAN
Hon'ble Shri Parth Prateem Sahu, Judge
Hon'ble Smt. Sushma Sawant, Judge
Digitally signed
by BALRAM
PRASAD
DEWANGAN
CAV Judgment
Per Parth Prateem Sahu, J
1.
Appellant has filed this arbitration appeal U/s. 37 (1) (C) of the
Arbitration and Conciliation Act, 1996 (In short ‘the Act, 1996’) read
with Section 13 of the Commercial Court Act, 2015 (In short ‘the Act,
2015’) questioning the legality and sustainability of the order dated
30.08.2019, passed in MJC No.34 of 2018, whereby learned
Commercial Court (District Level), Atal Nagar, District – Raipur (C.G.)
has dismissed the application filed U/s. 34 (2) (b) (ii) of the Act, 1996
affirming the arbitral award 21.09.2016, wherein the Sole Arbitrator
rejected the claim of appellant holding it to be barred by limitation.
2.
Brief facts of the case are that appellant firm M/s. Orissa Concrete &
Allied Industries Ltd. is engaged in the manufacture of Concrete Mono
Block Sleepers. Respondent/South Easter Center Railway, Bilaspur
floated a tender vide NIT dated 07.02.2006 for manufacture and
supply of Mono Block Pre-Stressed Concrete (PSC) Sleepers.
Appellant participated in the said tender and, being the successful
bidder, was awarded the work for manufacture and supply of 3,50,779
units of PSC Sleepers at the rate of Rs. 865/- per unit, within the
stipulated period of two years and one month commencing from
26.12.2005. During subsistence of contract, due to certain variation in
the contractual quantity under the terms of contract,
appellant
supplied 2,54,445 units of PSC Sleepers out of 3,50,779 units to
respondent.
3.
On 24.02.2009, contract between the parties came to be terminated. In
May, 2009, respondent demanded liquidated damages to the tune of
Rs.54,20,100/- from appellant. Being disgruntled by demand of
liquidated damages, appellant invoked the arbitration clause stipulated
in the agreement vide letter dated 27.06.2009. The Arbitrator entered
into reference on 09.10.2009 to decide the legality of termination of
contract, which is still pending for adjudication. As per appellant, bills
of appellant regarding payments against supplied sleepers and other
heads were passed and paid by respondent. Payments related to
inspection charges, excise duty on PVC bills, entry tax on cement etc.
were made in installments and last such payment was made by
respondent to appellant on 15.02.2010. It is case of appellant that
apart from bills paid by respondent, certain claims were due for
payment. Appellant wrote various letters requesting for payment of
bills pending towards respondent but his request was denied and last
denial for payment by respondent against the PVC bills raised by
appellant was vide letter dated 07.01.2013. Being disgruntled by
denial of payments of alleged dues, appellant invoked the arbitration
clause on 25.04.2013 and requested the respondent to appoint an
Arbitrator and pursuant thereto Mr. A.K. Pandey, Chief Engineer (Con.)
SECR, Nagpur was appointed as Sole Arbitrator. Appellant filed its
Statement of Claim before the learned Sole Arbitrator, raising seven
claims/bills aggregating to a total amount of Rs. 2,36,46,182/-, along
with interest at the rate of 18% per annum on the respective amounts
from the dates of the respective bills.
4.
Respondent filed reply to the claim of appellant pleading that all the
payments claimed by appellant in contract were finalized before
March, 2009. It was further pleaded that minor amount of
miscellaneous bills like insert inspection charges to RITES, service tax
on insert inspection charges, excise duty on last PVC bills and entry
tax on cement were submitted and passed on 24.04.09, 24.07.09,
24.07.09, 21.01.10 and 15.02.10. Appellant/claimant was advised in
May, 2009 to deposit liquidated damages. Being aggrieved with the
recovery of liquidated damages, appellant/claimant had sought
arbitration pursuant thereto arbitration tribunal was constituted on
24.07.2009. The Arbitrator entered into reference on 09.10.2009,
which is still under adjudication. It was further pleaded that
appellant/claimant
sought
another
arbitration
under
the
same
agreement on 25.04.2013. It was further pleaded in the reply that
under doctrine of constructive res-judicata that appellant cannot be
allowed to relitigate the matter again as one arbitration reference is
pending consideration on the same contract. He submits that after
passing of the bills only, there can be cause of action. Therefore, all
the claims should have been raised together as splitting of cause of
action is not allowed under the doctrine of constructive res-judicata. It
was pleaded that appellant’s application for appointment of an
arbitrator was made after expiry of three years from the accrual of
cause of action and was, therefore, barred by limitation. It was pleaded
that the last supply was made by appellant in March 2009, whereas
the payment against the bills raised by the appellant had already been
made by 23.12.2008. Despite this, appellant submitted its application
seeking appointment of an arbitrator only on 25.04.2013, i.e., after the
expiry of the prescribed period of limitation and prays for rejection of
claim of appellant.
5.
After hearing both parties, learned Sole Arbitrator, vide arbitral award
dated 21.09.2016, rejected the appellant’s claim as barred by
limitation. The Arbitrator held that cause of action arose upon
termination of contract on 24.02.2009, and that application for
appointment of an arbitrator was required to be made within three
years thereof. Since appellant submitted the application only on
25.04.2013, the claim was held to be beyond the prescribed period of
limitation.
6.
Being aggrieved by rejection of its claim by learned Arbitrator,
appellant filed an application under Section 34(2)(b)(ii) of the Act,
1996, before the Commercial Court (District Level), Atal Nagar, Raipur.
The said application also came to be dismissed vide impugned order,
whereby the learned Commercial Court dismissed the application
under Section 34 of the Act of 1996 observing that there is no merit.
7.
Learned counsel for appellant would submit that the impugned order
passed by Sole Arbitrator rejecting the claim of appellant on the
ground of limitation, which has subsequently been affirmed by the
Commercial Court is erroneous, contrary to the facts and law. He
submits that the impugned order passed by Sole Arbitrator as well as
by Commercial Court is illegal and violates the principles of natural
justice, as the Arbitrator decided the issue of limitation, which is a
mixed question of law and facts, without giving the parties an
opportunity to produce evidence. He next contended that learned
Commercial Court has wrongly treated 15.02.2010, the date of the last
payment, as the date from which the limitation period should be
counted.
He submits that although last payment was made by
respondent on 15.02.2010, however certain other claims of appellant
remained due and payable. Appellant, from time to time, addressed
letters to the respondent requesting for payment of outstanding claims.
However, the respondent repeatedly returned the said letters without
making payment. Ultimately, respondent, vide its communication dated
07.01.2013, denied the appellant for payment in respect of the bills
raised. He next contended that, after denial by respondent on
07.01.2013, the appellant, within the period of limitation from the date
of such denial, requested for appointment of an Arbitrator for resolution
of the dispute, therefore, claim of appellant is well within limitation. In
support of his contention, he placed reliance upon the judgment of
High Court of Andhra Pradesh at Hyderabad in case of State of
Andhra Pradesh Vs. P. Somasekhara Rao and Ors., reported in
1997 SCC OnLine AP 256 and also the decision of Hon’ble Supreme
Court in case of Major (Retd.) Inder Singh Rekhi Vs. Delhi
Development Authority, reported in (1988) 2 SCC 338. He also
submits that before final payment made on 15.02.2010, respondent
had not decided/denied any of claims raised by appellant, therefore,
the date of final payment could not be treated as the date for counting
the limitation period of all the claims.
8.
Learned counsel for respondent opposes the submission made by
learned counsel for appellant and supports the impugned order. He
submits that appellant failed to supply the quantity of the Sleeper as
per the contract, agreement was terminated and as per Clause 3 of
the purchase order, penalty of liquidated damages of Rs.54,20,100/was imposed upon appellant. He submits that appellant has invoked
the arbitration clause against imposition of liquidated damages as also
against termination of contract and that arbitration proceeding is still
pending adjudication. Appellant was free to raise his further dues and
claims during the course of the said arbitral proceedings, however, he
failed to do so and after expiry of three years from the date of
termination of contract, appellant has again moved an application for
appointment of Arbitrator on 25.04.2013, which is barred by limitation.
He submits that period of limitation for invocation of arbitration clause
would start from the date when the last payment was made to the
appellant
i.e.
15.02.2010,
however,
appellant
requested
for
appointment of Arbitrator for adjudication of the demanded bills on
25.04.2013, which is after three years from the receiving of last
payment. Accordingly, the claim of appellant is beyond the prescribed
period of limitation.
9.
We have heard learned counsel for parties and also perused the
record.
10.
Undisputedly, the parties entered into contract agreement for work of
supply of Mono Block Pre-stressed Concrete Sleeper (Pre Tensioned
Type) for board gauge against tender No. CS-156 of 2005 vide
contract agreement No. Engg./TP/OCAIL/Bhanpuri/CS-156/1008 DT.
07.02.2006 for completion of work upto two year one month w.e.f.
26.12.2005 i.e. up to 25.01.2008. According to the terms of
agreement, 350779 nos of concrete sleeper were to be supplied at a
rate of Rs.865/- per sleeper. Value of above agreement was
Rs.30,34,23,835/-. The period of supply was extended up to
10.09.2008 vide letter dated 18.01.2008. Contract was terminated by
respondent on 24.02.2009. Claimant submitted application for
appointment of Arbitrator on 25.04.2013. The sole Arbitrator entered
into reference on 22.10.2013 and thereafter, the statement of claim
was submitted on 18.11.2013 to which respondent also submitted its
statement of defence 28.01.2014.
11.
Respondents made prayer for rejection of claim on 19.02.2014 on the
ground that all payments claimed by claimant in the contract were
finalized before March, 2009. Minor amount miscellaneous bills like
insert inspection charges to RITES, service tax on insert inspection
charges, excise duty on last PVC bill and entry tax on cement were
submitted and passed on 24.04.2009, 24.07.2009, 24.07.2009,
21.01.2010 and 15.02.2010, hence, application for arbitration
submitted on 25.04.2013 is barred by limitation. One of the ground
which is taken for rejection of claim is that after passing of final bill
there can only be one cause of action therefore, all the claims could
have been raised together, as splitting of cause of action is not allowed
under the doctrine of constructive res-judicata. The sole Arbitrator
upon considering the rival submission made by parties based on the
documents placed in the arbitral proceedings, has taken into
consideration the fact that contract was terminated on 24.02.2009,
therefore, the claimant could have raised the claim as raised in the
arbitration proceedings before the Arbitrator earlier appointed on
24.07.2009. The cause of action has been taken from the date of
termination of contract and taking period of limitation to be three years
from the date of cause of action, dismissed the claim.
12.
Award passed by the Arbitrator was put to challenge by appellant
herein by filing application U/s. 34 of the Act, 1996 in particular Section
34 (2) (b) (ii) of the Act, 1996, before the Commercial Court and the
Commercial Court by impugned order has dismissed the application
holding that according to the facts and circumstances of the case and
the law of limitation, conclusion arrived by the learned Arbitrator that
claim of claimant was barred by limitation cannot be said to be
erroneous and no ground is made out to interfere with the findings of
learned Arbitrator. Learned Commercial Court for arriving at such
conclusion as observed thus :“33.
The law is trite, limitation under Article 137 of
Limitation Act, 1963 begins to run from the time when
the right to apply accrues. The expression "when the
right to apply accrues" in its ordinary connotation to
mean when the right to apply first accrues. Ignorance of
the accrual of the right in his favour on the applicant's
part, will not postpone the starting point of limitation.
34.
In the instant case, the cause of arbitration first
arose when the final supply bill was passed by the
Railways (non-applicant) on dated 02.01.2009, then
secondly arose when the contract was terminated by
the non-applicant on 24.02.2009, thereafter again arose
when final PVC bill was passed on 19.03.2009 and
finally arose when miscellaneous bill like insert
inspection charges to RITES, service tax on insert
inspection charge, excise duty on last PVC bill and
entry tax on cement dated 24.04.2009, 24.07.2009,
24.07.2009, 21.01.2010 and 15.02.2010 were passed
by the non-applicant and received by applicant without
any demur. Quite naturally, while receiving the above
payments, the applicant was well aware about the fact
that some bills, as sought by him in arbitration
proceeding, were not passed or paid to him. Therefore,
the right to claim those bills accrued finally on
15.02.2010 when the last payment was made to the
applicant and hence the limitation started from the date
15.02.2010 and the period of three years shall be
counted from 15.02.2010 and elapsed on 15.02.2013.
35.
It is settled law that once the period of limitation
begins to run, it does not stop. The letters and
remainders sent by the applicant to the non-applicant
does not stop and save limitation. Therefore, the
commencement of Arbitration (25.04.2013) in this
matter is barred by limitation in view of Article 137 of
schedule of limitation Act which prescribes limitation
period of three years from time when right to apply
accrues.
36.
The applicant invoked Arbitration clause on
25.04.2013 which is after three years of the last
payment to the applicant e.g. dated 15.02.2010. Apart
from that, the applicant has not even filed an application
for condonation of delay before the Learned Arbitrator
regarding his claims.
37.
In view of the aforesaid reasons, none of the
judgments on the point of limitation, relied upon by the
learned counsel for applicant are of any avail to it,
because the facts and circumstances of the case in
hand are quite distinguishable from the citations relied
upon by the applicant.”
13.
So far as the grounds raised by learned counsel for appellant that
learned Commercial Court while exercising his jurisdiction under
Section 34 of the Act,1996 could not have dismissed the application
under Section 34 of the Act, 1996 on other ground is concerned that
Arbitrator has dismissed the claim observing that claim is barred by
limitation. Upon minute perusal of the award enclosed along with this
appeal would show that the objection is raised by respondent
therein/respondents herein of the claim to be beyond period of
limitation, has clearly mentioned the dates and events, of the
submission of minor amount miscellaneous bills like insert inspection
charges to RITES, service tax on insert inspection charges, excise
duty on last PVC bill and entry tax on cement were submitted and
passed on 24.04.2009, 24.07.2009, 24.07.2009, 21.01.2010 and
15.02.2010, whereas application for arbitration was submitted on
25.04.2013, which is beyond the period of limitation prescribed under
Section 137 of the Limitation Act, 1963 (In short ‘the Act, 1963’).
14.
The law applicable with regard to the limitation for claiming arbitration
and disputes are governed by provisions under Section 43 of the Act,
1996 and Article 137 of the Act, 1963.
15.
Under the Act, 1996, a dispute is to be referred for arbitration which
means a claim asserted by one party and its denial by repudiation by
other. In the facts of the case it has been considered by Arbitrator as
also the Commercial Court in exercise of powers under Section 34 of
the Act, 1996 and arrived at a conclusion that claim is barred by
limitation as it is beyond the period of limitation of three years.
16.
Learned Commercial Court in para 24 of its order impugned has
considered that contract was terminated on 24.02.2009, final bill for
the supply of sleepers was passed on 02.01.2009 and final PVC bill
(including freight charges) was passed on 19.03.2009. The said fact
has been recorded based on the arbitral record available before the
Arbitrator and it further taken note of the submission of minor
miscellaneous bills, last bill, paid is dated 15.02.2010, therefore, from
the aforementioned facts it is apparent that from the records as
submitted by the parties before the Arbitrator, all the payments
made/bills passed was of either 15.02.2010 or prior to it, therefore, the
period of limitation with regard to last bill passed would be 15.02.2013
by latest, whereas the arbitration application has been filed on
25.04.2013 after period of three years.
17.
It is also not in dispute that after passing of final bill and termination of
contract, claimant/appellant has invoked the arbitration clause by
submitting an application for appointment of Arbitrator vide letter dated
27.06.2009 and pursuant thereto, Arbitral Tribunal was constituted by
competent authority vide its letter dated 24.07.2009. The Arbitrator
entered into reference on 09.10.2009. Perusal of the claim would show
that PVC bills for the period from March, 2005 to December, 2005 was
claimed. In reply/Statement of defence, there is clear pleading that
letter of acceptance was issued on 12.01.2006 as the alleged supply
was prior to the letter of acceptance and further PVC formula is not
applicable to sleepers manufactured and supplied prior to the date of
acceptance, it is pleaded that claim to that head is not admissible. The
date of letter of acceptance is not disputed by learned counsel for
appellant. Copy of letter of acceptance is also forming part of the
record of arbitration. The terms and conditions as mentioned in the
letter of acceptance would not be made applicable to the railway
sleepers manufactured prior to issuance of letter of acceptance. Letter
exchanged between parties is also part of records. Transaction, after
the contract agreement will only be governed under the terms and
conditions of that contract agreement.
18.
From perusal of the records it is apparent that the Arbitrator as also the
Commercial Court in the proceeding under Section 34 of the Act, 1996
clearly observed that claim of appellant is barred by limitation. A plain
reading of Article 137 of the Act, 1963 would make it clear that period
of limitation in cases covered by Article 137 is three years and the said
period would began to run when the right to apply accrues.
19.
Section 9 of the Act, 1963 talks of continuous running of time and it
provides that “Where once time has begun to run, no subsequent
disability or inability to institute a suit or make an application stops it”.
Under proviso to Section 9 it is provided that where letters of
administration to the estate or creditor have been granted to his
debtor, the running of the period of limitation for a suit to recover the
debt shall be suspended while the administration continues.
20.
Hon’ble Supreme Court in case of Inder Singh Rekhi v. DDA, (1988)
2 SCC 338, while dealing with the issue with regard to starting point of
limitation has observed thus :“4. Therefore, in order to be entitled to order of
reference under Section 20, it is necessary that there
should be an arbitration agreement and secondly,
difference must arise to which this agreement applied.
In this case, there is no dispute that there was an
arbitration agreement. There has been an assertion of
claim by the appellant and silence as well as refusal in
respect of the same by respondent. Therefore, a
dispute has arisen regarding non-payment of the
alleged dues of the appellant. The question is for the
present case when did such dispute arise. The High
Court proceeded on the basis that the work was
completed in 1980 and therefore, the appellant
became entitled to the payment from that date and the
cause of action under Article 137 arose from that date.
But in order to be entitled to ask for a reference under
Section 20 of the Act there must not only be an
entitlement to money but there must be a difference or
dispute must arise. It is true that on completion of the
work a right to get payment would normally arise but
where the final bills as in this case have not been
prepared as appears from the record and when the
assertion of the claim was made on 28-2-1983 and
there was non-payment, the cause of action arose from
that date, that is to say, 28-2-1983. It is also true that a
party cannot postpone the accrual of cause of action
by writing reminders or sending reminders but where
the bill had not been finally prepared, the claim made
by a claimant is the accrual of the cause of action. A
dispute arises where there is a claim and a denial and
repudiation of the claim. The existence of dispute is
essential for appointment of an arbitrator under Section
8 or a reference under Section 20 of the Act. See Law
of Arbitration by R.S. Bachawat, first edition, page 354.
There should be dispute and there can only be a
dispute when a claim is asserted by one party and
denied by the other on whatever grounds. Mere failure
or inaction to pay does not lead to the inference of the
existence of dispute. Dispute entails a positive element
and assertion of denying, not merely inaction to accede
to a claim or a request. Whether in a particular case a
dispute has arisen or not has to be found out from the
facts and circumstances of the case.”
21.
Hon’ble Supreme Court in case of Geo Miller & Co. (P) Ltd. v.
Rajasthan Vidyut Utpadan Nigam Ltd., (2020) 14 SCC 643, has
considered that what will be the breaking point at which any
reasonable party would have abandoned efforts at arriving at a
settlement and contemplated referral of the dispute for arbitration and
observed thus :“28. Having perused through the relevant precedents,
we agree that on a certain set of facts and
circumstances, the period during which the parties
were bona fide negotiating towards an amicable
settlement may be excluded for the purpose of
computing the period of limitation for reference to
arbitration under the 1996 Act. However, in such cases
the entire negotiation history between the parties must
be specifically pleaded and placed on the record. The
Court upon careful consideration of such history must
find out what was the “breaking point” at which any
reasonable party would have abandoned efforts at
arriving at a settlement and contemplated referral of
the dispute for arbitration. This “breaking point” would
then be treated as the date on which the cause of
action arises, for the purpose of limitation. The
threshold for determining when such a point arises will
be lower in the case of commercial disputes, where the
party's primary interest is in securing the payment due
to them, than in family disputes where it may be said
that the parties have a greater stake in settling the
dispute amicably, and therefore delaying formal
adjudication of the claim.
29. Moreover, in a commercial dispute, while mere
failure to pay may not give rise to a cause of action,
once the applicant has asserted their claim and the
respondent fails to respond to such claim, such failure
will be treated as a denial of the applicant's claim
giving rise to a dispute, and therefore the cause of
action for reference to arbitration. It does not lie to the
applicant to plead that it waited for an unreasonably
long period to refer the dispute to arbitration merely on
account of the respondent's failure to settle their claim
and because they were writing representations and
reminders to the respondent in the meanwhile.”
22.
In the case at hand, one of the argument raised based on the facts
that subsequently miscellaneous claims have also been made, which
came to be rejected in the year 2011-12 etc., however, those claims
were denied earlier as pleaded in the statement of defence. Hence,
submitting multiple repeated applications thereafter will not make out
such claim within the period of limitation, stating that lastly the claim
has been rejected on 07.01.2013
23.
Hon’ble Supreme Court in case of BSNL v. Nortel Networks (India)
(P) Ltd., (2021) 5 SCC 738, had an occasion to consider about the
several communications have been exchanged between petitioners
and respondents ever since the dispute has arisen between the
parties, regarding non-payment of amounts due under the tender
document and observed thus :“51. The period of limitation for issuing notice of
arbitration would not get extended by mere exchange of
letters, [S.S. Rathore v. State of M.P., (1989) 4 SCC 582
: 1990 SCC (L&S) 50; Union of India v. Har Dayal,
(2010) 1 SCC 394; CLP (India) (P) Ltd. v. Gujarat Urja
Vikas Nigam Ltd., (2020) 5 SCC 185] or mere
settlement discussions, where a final bill is rejected by
making deductions or otherwise. Sections 5 to 20 of the
Limitation Act do not exclude the time taken on account
of settlement discussions. Section 9 of the Limitation
Act makes it clear that:“where once the time has begun
to run, no subsequent disability or inability to institute a
suit or make an application stops it.” There must be a
clear
notice
invoking
arbitration
setting
out
the
“particular dispute” [ Section 21 of the Arbitration and
Conciliation Act, 1996.] (including claims/amounts)
which must be received by the other party within a
period of 3 years from the rejection of a final bill, failing
which, the time bar would prevail.
24.
In appeal filed under Section 37 of the Act,1996, this Court have very
limited jurisdiction to interfere with the order U/s. 34 and award.
Interference is permissible only on the grounds as provided under
Section 34 of the Act, 1996 is made out. The grounds enumerated for
interference in the award
under Section 34 is extracted below for
ready reference :“34. Application for setting aside arbitral award.-(1)
Recourse to a Court against an arbitral award may be
made only by an application for setting aside such
award in accordance with sub-section (2) and subsection (3).
(2) An arbitral award may be set aside by the Court
only if(a) the party making the application [establishes on
the basis of the record of the arbitral tribunal that](i)
the party was under some incapacity,
(ii)
the arbitration agreement is not valid under
the law to which the parties have subjected it or,
failing any indication thereon, under the law for the
time being in force,
(iii)
the party making application was not given
proper notice of the appointment of an arbitrator or
of the arbitral proceedings or was otherwise unable
to present his case,
(iv)
the arbitral award deals with a dispute not
contemplated by or not falling within the terms of
the submission to arbitration or it contains decisions
on matters beyond the scope of the submission to
arbitration.
Provided that, if the decisions on
matters submitted to arbitration can be separated
from those not so submitted, only that part of the
arbitral award which contains decisions on matters
not submitted to arbitration may be set aside; or
(v)
the composition of the arbitral tribunal or the
arbitral procedure was not in accordance with the
agreement of the parties, unless such agreement
was in conflict with a provision of this Part from
which the parties cannot derogate, or, failing such
agreement, was not in accordance with this Part; or
(b)
the Court finds that(i) the subject-matter of the dispute is not capable of
settlement by arbitration under the law for the time
being in force, or
(ii) the arbitral award is in conflict with the public
policy of India.
25.
Hon’ble Supreme Court in case of Rajasthan State Mines & Minerals
Ltd. v. Eastern Engg. Enterprises, (1999) 9 SCC 283, has explained
the scope of Section 34 of the Act, 1996 and observed thus :“44. From the resume of the aforesaid decisions, it can
be stated that:
(a) It is not open to the court to speculate, where no
reasons are given by the arbitrator, as to what
impelled the arbitrator to arrive at his conclusion.
(b) It is not open to the court to admit to probe the
mental process by which the arbitrator has reached
his conclusion where it is not disclosed by the terms
of the award.
(c) If the arbitrator has committed a mere error of fact
or law in reaching his conclusion on the disputed
question submitted for his adjudication then the court
cannot interfere.
(d) If no specific question of law is referred, the
decision of the arbitrator on that question is not final,
however much it may be within his jurisdiction and
indeed essential for him to decide the question
incidentally. In a case where a specific question of
law touching upon the jurisdiction of the arbitrator
was referred for the decision of the arbitrator by the
parties, then the finding of the arbitrator on the said
question between the parties may be binding.
(e) In a case of a non-speaking award, the jurisdiction
of the court is limited. The award can be set aside if
the arbitrator acts beyond his jurisdiction.
(f) To find out whether the arbitrator has travelled
beyond his jurisdiction, it would be necessary to
consider the agreement between the parties
containing the arbitration clause. The arbitrator acting
beyond his jurisdiction is a different ground from the
error apparent on the face of the award.
(g) In order to determine whether the arbitrator has
acted in excess of his jurisdiction what has to be seen
is whether the claimant could raise a particular claim
before the arbitrator. If there is a specific term in the
contract or the law which does not permit or give the
arbitrator the power to decide the dispute raised by
the claimant or there is a specific bar in the contract
to the raising of the particular claim then the award
passed by the arbitrator in respect thereof would be
in excess of jurisdiction.
(h) The award made by the arbitrator disregarding the
terms of the reference or the arbitration agreement or
the terms of the contract would be a jurisdictional
error which requires ultimately to be decided by the
court. He cannot award an amount which is ruled out
or prohibited by the terms of the agreement. Because
of a specific bar stipulated by the parties in the
agreement, that claim could not be raised. Even if it is
raised and referred to arbitration because of a wider
arbitration clause such claim amount cannot be
awarded as the agreement is binding between the
parties and the arbitrator has to adjudicate as per the
agreement. This aspect is absolutely made clear in
Continental Construction Co. Ltd. [(1988) 3 SCC 82 :
(1988) 3 SCR 103] by relying upon the following
passage from Alopi Parshad v. Union of India [AIR
1960 SC 588 : (1960) 2 SCR 793] which is to the
following effect: (SCC p. 88, para 5)
“There it was observed that a contract is not
frustrated merely because the circumstances in which
the contract was made, altered. The Contract Act
does not enable a party to a contract to ignore the
express covenants thereof, and to claim payment of
consideration for performance of the contract at rates
different from the stipulated rates, on some vague
plea of equity. The parties to an executory contract
are often faced, in the course of carrying it out, with a
turn of events which they did not at all anticipate, a
wholly abnormal rise or fall in prices, a sudden
depreciation of currency, an unexpected obstacle to
execution, or the like. There is no general liberty
reserved to the courts to absolve a party from liability
to perform his part of the contract merely because on
account of an uncontemplated turn of events, the
performance of the contract may become onerous.”
(i) The arbitrator could not act arbitrarily, irrationally,
capriciously or independently of the contract. A
deliberate departure or conscious disregard of the
contract not only manifests the disregard of his
authority or misconduct on his part but it may
tantamount to mala fide action.
(j) The arbitrator is not a conciliator and cannot ignore
the law or misapply it in order to do what he thinks
just and reasonable; the arbitrator is a tribunal
selected by the parties to decide the disputes
according to law.”
26.
In Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd., (2019) 20
SCC 1, Hon’ble Supreme Court while considering the scope of
interference of Court under the Act, 1996 has observed thus :“25. Moreover, umpteen number of judgments of this
Court have categorically held that the courts should not
interfere with an award merely because an alternative
view on facts and interpretation of contract exists. The
courts need to be cautious and should defer to the view
taken by the Arbitral Tribunal even if the reasoning
provided in the award is implied unless such award
portrays perversity unpardonable under Section 34 of
the Arbitration Act.”
27.
In case of Somdatt Builders-NCC-NEC (JV) v. NHAI, (2025) 6 SCC
757, Hon’ble Supreme Court has relied upon its earlier decision, has
observed thus :-
“45. In MMTC Ltd. v. Vedanta Ltd. [MMTC Ltd. v.
Vedanta Ltd., (2019) 4 SCC 163 : (2019) 2 SCC (Civ)
293] , this Court held that as far as Section 34 is
concerned, the position is well settled that the Court
does not sit in appeal over an arbitral award and may
interfere on merits only on the limited ground provided
under Section 34(2)(b)(ii) i.e. if the award is against the
public policy of India. Even then, the interference would
not entail a review on the merits of the dispute but
would be limited to situations where the findings of the
arbitrator are arbitrary, capricious or perverse or when
the conscience of the Court is shocked or when the
illegality is not trivial but goes to the root of the matter.
An arbitral award may not be interfered with if the view
taken by the arbitrator is a possible view based on
facts. As far as interference with an order made under
Section 34 by the Court under Section 37 is concerned,
it has been held that such interference under Section 37
cannot travel beyond the restrictions laid down under
Section 34. In other words, the Court cannot undertake
an independent assessment of the merits of the award
and must only ascertain that the exercise of power by
the Court under Section 34 has not exceeded the scope
of the provision.”
28.
Hon’ble Supreme Court in case of Consolidated Construction
Consortium Ltd. v. Software Technology Parks of India, (2025) 7
SCC 757, has held that the arbitral award is not liable to be interfered
with only on the ground that the award is illegal or is erroneous in law
which would require re-appraisal of the evidence adduced before the
Arbitral Tribunal. If two views are possible, there is no scope for the
court to re-appraise the evidence and to take the view other than the
one taken by the arbitrator. The view taken by the Arbitral Tribunal is
ordinarily to be accepted and allowed to prevail. Thus, the scope of
interference in arbitral matters is only confined to the extent envisaged
under Section 34 of the Act. The court exercising powers under
Section 34 has per force to limit its jurisdiction within the four corners
of Section 34. It is a restrictive jurisdiction and has to be invoked in a
conservative manner.
29.
Considering the facts of the case as discussed above in light of the
decision of Hon’ble Supreme Court we are of the considered view that
no case is made out for interference with the order passed by the
Commercial Court (District Level) dated 30.08.2019 as well as with the
award passed by the Arbitrator.
30.
Accordingly, the appeal being sans merit is liable to be and it is hereby
dismissed.
Sd/(Parth Prateem Sahu)
Judge
Balram
Sd/(Sushma Sawant)
Judge
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review