HIGH COURT OF JUDICATURE FOR RAJASTHAN
BENCH AT JAIPUR
D.B. Civil Miscellaneous Appeal No. 1170/2022
CNR: RJHC020401512022 | URN: CMA / 1994U / 2022
M/s Kamal Autotech Private Limited, Kamal And Company
Premises Opposite G.p.o, M.I. Road, Jaipur-302001 (Rajasthan)
Through Its Director/ Authorized Signatory- Mr. Aditya Kasliwal.
----Appellant
Versus
1.
Rajasthan State Industrial Development And Investment
Corporation Limited (RIICO), Udyog Bhavan, Tilak Marg,
Jaipur- 302005 (Raj.) Through Its Chairman.
2.
Rajasthan State Industrial Development And Investment
Corporation Limited (RIICO), EPIP, Sitapura Industrial
Area, Jaipur- 302022 (Raj.) Through Its Sr. Regional
Manager.
3.
Sole Arbitrator Hon'ble Mr. Justice S.N. Bhargava (Retd.),
20/46, Ambedkar Marg, Renu Path, Mansarovar, Jaipur.
----Respondents
For Appellant(s)
:
Ms. Sukriti Kasliwal, Adv.
Mr. Nareshwar Shekhawat, Adv.
For Respondent(s)
:
Mr. Chandra Shekhar, Adv.
Mr. Devendra Singh. Adv.
HON'BLE MR. JUSTICE ARUN MONGA
HON'BLE MR. JUSTICE ASHUTOSH KUMAR
Order(Oral)
Reportable
30/07/2026
Per: Arun Monga, J.
1.
This appeal is directed against the order dated 31.03.2022 passed
by the learned Commercial Court, whereby, in exercise of jurisdiction
under Section 34 of the Arbitration and Conciliation Act, 1996 (for short
“the Act of 1996”), the objections preferred by the respondent–
Corporation were allowed and the arbitral award dated 12.02.2018
made by the learned Sole Arbitrator was set aside.
2.
The appellant company applied to the Rajasthan State Industrial
Development and Investment Corporation Ltd. (RIICO) for allotment of
(2 of 16)
[2026:RJ-JP:29646-DB]
[CMA-1170/2022]
an industrial plot for establishing a unit for “Service Station & Body
Building of Executive CC”. By allotment letter dated 14.12.2011, RIICO
allotted Plot No. SP-2033(B), admeasuring 4834.35 square metres,
situated at Ramchandrapura, EPIP, Sitapura Industrial Area, Jaipur,
under Rule 3(W) of the RIICO Disposal of Land Rules, 1979 (for short
“the Rules of 1979”). The allotment obliged the appellant to complete
construction and commence commercial production within the stipulated
period, and to raise construction in conformity with the approved site
plan and the applicable building bye-laws. Possession of the plot was
delivered on 09.04.2012, and a lease deed for a period of ninety-nine
years was executed between the parties on 27.09.2012.
2.1
Even before taking possession, the appellant, by its letter dated
20.12.2011, pointed out discrepancies in the original site plan, stating
that the setbacks depicted therein rendered the project unviable. RIICO
thereupon issued a revised site plan on 31.08.2012, modifying the
setbacks. The industrial area was subsequently declared a “Developed
Area” by RIICO vide office order dated 07.08.2013. In the interregnum,
RIICO addressed communications to the appellant regarding progress of
construction, including letters dated 08.11.2012 and 17.04.2013, while
the appellant’s request for extension of time made by letter dated
30.05.2013 was declined by RIICO on 15.07.2013.
2.2
RIICO thereafter issued a show cause notice dated 20.04.2014
proposing cancellation of the allotment. Disputes having arisen, the
appellant
invoked
the
arbitration
clause
contained
in
the
lease
agreement and also instituted proceedings under Section 9 of the Act of
1996, in which interim protection was granted by the competent court
vide orders dated 28.05.2015 and 03.05.2016. The named arbitrator
not having entered upon the reference, the appellant filed an application
(3 of 16)
[2026:RJ-JP:29646-DB]
[CMA-1170/2022]
under Section 11 of the Act of 1996, and this Court, by order dated
03.06.2016, appointed Hon’ble Justice S.N. Bhargava (Retd.) as the
Sole Arbitrator.
2.3
Before the learned Sole Arbitrator, the appellant challenged the
wake-up notice and the show cause notices issued by RIICO and
sought, inter alia, a declaration as to the date from which the
contractual period for completion of construction and commencement of
production was to be reckoned. RIICO contested the claims. By award
dated 12.02.2018, the learned Sole Arbitrator held that the stipulated
period was to be reckoned from the date of issuance of the revised site
plan, namely 31.08.2012, and allowed the claims accordingly.
2.4
Aggrieved, RIICO instituted proceedings under Section 34 of the
Act of 1996 before the Commercial Court, which, by the impugned order
dated 31.03.2022, allowed the objections and set aside the award.
Hence, this appeal.
3.
Ms. Sukriti Kasliwal, learned counsel for the appellant submits
that the learned Commercial Court exceeded the limited jurisdiction
conferred by Section 34 of the Act of 1996. It re-appreciated the
evidence, examined the merits of the dispute and substituted its own
interpretation of the contractual terms, as though exercising appellate
jurisdiction. The award, it is urged by her, was a reasoned award
rendered upon consideration of the pleadings, the evidence and the
issues framed. It could not have been disturbed unless a ground under
Section 34(2) or (2A), such as patent illegality or conflict with public
policy, was made out.
3.1
It is next submitted by her that the Commercial Court erred in
framing
new
points
of
determination,
concerning
the
allegedly
premature character of the arbitration and the absence of a cause of
[2026:RJ-JP:29646-DB]
(4 of 16)
[CMA-1170/2022]
action, which were never the respondent’s objections. This Court, while
exercising jurisdiction under Section 11, had already satisfied itself of
the existence of live disputes and appointed the Sole Arbitrator by order
dated 03.06.2016, an order which neither party ever challenged. The
question of arbitrability or the existence of disputes could not,
therefore, be reopened in proceedings under Section 34.
3.2
She further submits that the dispute referred was, in essence, one
of interpretation of the contractual provisions the determination of the
date from which the period for completion of construction and
commencement of production was to run, and the reliefs seeking
quashing of RIICO’s notices were merely consequential. The arbitration
clause embraced every dispute arising out of or relating to the
agreement, and nothing in it required the appellant to await a final
order of cancellation or recovery before invoking arbitration.
3.3
It is also urged that RIICO acted throughout as a contracting
party under the lease agreement and not in exercise of any statutory
adjudicatory power; the Commercial Court therefore erred in observing
that the arbitration sought to obstruct the functioning of a statutory
authority. The dispute was purely contractual, governed by the terms of
the agreement, the Rules of 1979 and the Act of 1996.
3.4
Lastly, Ms. Kasliwal submitted that the learned Sole Arbitrator
considered all relevant clauses, correspondence and material before
holding that the prescribed period was to be computed from the
issuance of the revised site plan; the interpretation so adopted was a
possible view and hence immune from interference under Section 34.
The impugned order, travelling beyond the permissible limits of judicial
scrutiny, is liable to be set aside.
[2026:RJ-JP:29646-DB]
4.
(5 of 16)
[CMA-1170/2022]
Per contra, Mr. Chandra Shekhar, learned counsel for the
respondent submits that the impugned order is based on rational logic
and warrants no interference and the arbitral award has rightly been set
aside. He would rely on the reasoning assigned in the impugned order
passed by the commercial court in support of his contention.
5.
Having heard the rival contentions and perused the record
including the impugned order passed by the learned commercial court
as well as the impugned award, we shall now proceed to render our
opinion.
6.
First and foremost, for sake of better structuring our discussion
and analysis, in our view following three questions arise for our
consideration:
(i) whether the learned Commercial Court, in setting aside the award,
remained within the confines of Section 34 of the Act of 1996;
(ii) whether it was open to the Commercial Court to hold the reference
to arbitration premature for want of a cause of action, when no such
objection had been taken by the respondent at any stage;
And
(iii) whether the award is vitiated for insufficiency of reasons.
7.
Adverting first to the third question, ibid. Since the sufficiency of
the Arbitrator’s reasoning is squarely in issue, it is apposite to notice the
operative discussion in the award dated 12.02.2018, the relevant
portion whereof reads as under:
“44. I have considered the pleadings brought on record, perused all the
documents and evidence led by each party and considered the arguments
advanced orally as well as by way of written submissions, and based upon
all I decide the issues as under.
[2026:RJ-JP:29646-DB]
(6 of 16)
[CMA-1170/2022]
ISSUE NO. 1:
Whether the Claimant Company has committed any breach of the terms and
conditions of the allotment made vide Allotment Letter No. U(25)-3(SP2033(B))/2011/3994 dated 14.12.2011 and the Lease Deed dated
27.09.2012 in its favour and, if so, what would be the effect?
The burden to prove this issue was on the Non-claimant Corporation.
During the course of arguments the Non-claimant Corporation raised the
following contentions in support of this issue:—
(i) The allotment was made under Rule 3(W) of the RIICO Disposal of
Land Rules, which is a preferential allotment.
(ii) Before the subject land was allotted, the Claimant Company was
aware that only 38% of the area would be available as per the
setbacks; reliance was placed on the Minutes of the Meeting dated
30.11.2011.
(iii) At the time of allotment the Claimant Company had given an
undertaking to complete construction within a period of 2 years from
the date of allotment.
(iv) As per Term Nos. 6 and 9 of the allotment letter as well as the
Rules of 1979, the Claimant Company was required to complete
construction within 2 years from the date of allotment and make capital
investment of Rs. 21.89 Crores, which the Claimant Company failed to
do and has therefore committed breach of the terms and conditions of
the allotment.
(v) On account of breach of the terms and conditions, the Claimant
Company is liable to pay either retention charges or get the allotment
cancelled.
The Claimant Company in reply submitted that—
(i) the Claimant Company never participated in the Sub-Committee
Meeting held on 30.11.2011 (Annexure R-2), as is evident from the
minutes not having been signed by the Claimant Company, nor was any
representative present in the said meeting;
(ii) had the Claimant Company been told that, out of the land proposed
to be allotted, only 38% utility area would be available after leaving
the setbacks, it would not have gone ahead with the proposed project,
as it would have been unviable;
(iii) it was only when the allotment letter dated 14.12.2011 (Annexure2/Exhibit-3 at Page 22) was issued that the Claimant Company got the
site plan with the given setbacks;
(iv) as more than 60% of the land was going in setbacks, the Claimant
Company, immediately and before taking possession of the land, by its
letter dated 20.12.2011 (Annexure-R6/Exhibit-5 at Page 288),
requested RIICO to issue a revised site plan, explaining the difficulty;
(v) Clause 15 of the letter of allotment clearly stipulates that the
Claimant Company is to construct the building according to the bye-
[2026:RJ-JP:29646-DB]
(7 of 16)
[CMA-1170/2022]
laws of RIICO; as the application of the Claimant Company for
reconsideration of the setbacks was under consideration, the Claimant
Company could not commence construction activity;
(vi) moreover, possession of the said land was handed over to the
Claimant Company only on 09.04.2012 (Annexure-4/Exhibit-6 at Page
29) and the lease deed for the subject land came to be executed on
27.09.2012 (Annexure-9/Exhibit-8 at Page 31); without possession and
without transfer of the land in its favour, the Claimant Company could
not commence construction activity on site;
(vii) Terms 2(d) and 2(p) are material terms of the lease agreement,
which also clearly stipulate that construction has to be made in
accordance with the applicable Rules, and the applicable Rules clearly
require setbacks to be left while commencing construction;
(viii) in fact, even the revised site plan dated 31.08.2012 (Annexure3/Exhibit-7), issued eight months after the letter of allotment, stipulates
that construction has to be made in accordance with the given site
plan;
(ix) the Claimant Company completed construction and commenced
production activity within the stipulated period reckoned from receipt
of the revised site plan from RIICO; as such, the Claimant Company
did not commit breach of any term or condition of the letter of
allotment or the lease deed;
(x) the Claimant Company began construction on the allotted land
immediately after receipt of the revised site plan and finished the same
within two years therefrom; production on the allotted land was also
started, as informed to the Non-claimant Corporation by letter dated
29.08.2014 (Annexure-25), and the completion of the factory and
commencement of production are evident from the site report dated
08.09.2014 (Annexure-26/Annexure R-15) annexed with the reply of the
Non-claimant Corporation itself;
(xi) in the light of the aforesaid, it is clear that the Claimant Company
functioned in complete conformity with the terms of the allotment letter
and the lease deed.
I have considered the submissions made by both the parties and I am of the
considered view that, in the facts and circumstances, the period of two
years has to be reckoned from the date of the revised site plan. In view of
this, Issue No. 1 is decided in favour of the Claimant Company.
ISSUE NO. 2:
Whether the terms of allotment and the Lease Deed are subject to the
RIICO Disposal of Land Rules, 1979 and, if so, what would be the effect of
the same on the terms and conditions incorporated in the Letter of
Allotment and the Lease Deed?
The allotment letter dated 14.12.2011 contains certain clauses which make
it compulsory for the allottee Claimant Company to act in conformity with
[2026:RJ-JP:29646-DB]
(8 of 16)
[CMA-1170/2022]
the RIICO Disposal of Land Rules, 1979. The relevant clauses are
reproduced hereunder for ready reference:
‘The allottee shall abide by the RIICO Disposal of Land Rules, 1979
and its amendments made thereunder from time to time. That you will
construct the building after leaving prescribed setbacks as per enclosed
site plan and in accordance with the building bye-laws as provided in
the RIICO Disposal of Land Rules, 1979.’
The lease agreement dated 27.09.2012 (Annexure-9/Exhibit-8) itself
declares, at the title page, that it is drafted under Rule 11 of the RIICO
Disposal of Land Rules, 1979. Furthermore, Clause 2(p) of the lease
agreement mandates the lessee to abide by the provisions of the Rules of
1979, and is reproduced hereunder:
‘2(p) That the Lessee shall also abide by the terms and conditions of
the letter of allotment, RIICO Disposal of Land Rules, 1979 and
amendments made therein from time to time. The letter of allotment
shall form part and parcel of the Lease Agreement.’
From the afore-stated it is clear that both the terms of the allotment letter
and the lease deed are subject to the provisions of the RIICO Disposal of
Land Rules, 1979 and, in case of any contradiction, the Rules of 1979 shall
prevail.
ISSUE NO. 3:
Whether the Non-claimant Corporation is responsible for the delay of eight
months caused in the commencement of construction work and, if so, what
would be its effect?
The Claimant Company contended, firstly, that there has been no delay in
completion of construction, as the period of two years mentioned in the
letter of allotment read with the Note to Rule 21 clearly demonstrates that
the period would be reckoned from 07.08.2013 (when the area was declared
‘developed’), and construction was completed well within two years
therefrom; and, secondly, that if the period of two years is calculated from
the date of allotment, i.e. 14.12.2011, then a period of eight months should
be excluded, as the delay, if any, was attributable only to the Non-claimant
Corporation, for which the Claimant Company cannot be held responsible.
The delay occurred at the following stages:
(i) delay in handing over possession;
(ii) delay in releasing the revised site plan;
(iii) delay in execution of the lease deed in favour of the Claimant
Company.
The Claimant Company further contended that RIICO in some cases allots
industrial lands after fully developing the industrial areas and in some
cases soon after acquiring the agricultural lands. If allotments are made
under Rule 3(W) in developed areas, conditions can always be imposed to
start construction within the given time; but where allotments are made in
undeveloped industrial areas, the period of two years can be reckoned only
[2026:RJ-JP:29646-DB]
(9 of 16)
[CMA-1170/2022]
after the industrial area is declared ‘developed’. In the instant case, the
allotment was made in an undeveloped industrial area having no roads, no
electricity, no water mains, no sewerage, etc., and it was therefore not
possible to complete construction on agricultural land, bereft of the
infrastructure required for construction, and to commence production
within two years from the date of allotment. A distinction has therefore to be
drawn between allotments made under the Rule 3(W) scheme in a
developed industrial area and in an undeveloped industrial area.
The related facts are as under:—
(i) Delay in handing over possession: although the Non-claimant
Corporation issued the letter of allotment dated 14.12.2011 (Annexure2/Exhibit-3) and was considering the application dated 20.12.2011
(Annexure-R6/Exhibit-5) for a revised site plan, it handed over
possession of the subject premises only on 09.04.2012 (Annexure4/Exhibit-6), i.e. after a period of more than four months. Without
possession of the subject premises, the Claimant Company could not
have commenced construction activity on the plot.
(ii) Delay in releasing the revised site plan: the Claimant Company
applied for allotment of 5000 sq. metres of land for developing a
service station and body building industrial unit by its letter dated
10.01.2011 (Annexure-R1), in the bona fide belief that, after leaving
setbacks (approx. 1800 sq. metres), it would be able to utilise 3200 sq.
metres, which would suffice for the proposed project. However, by
letter dated 12.12.2011 (Annexure-R3), RIICO informed the Claimant
Company that its application had been accepted, but that in place of
5000 sq. metres, land admeasuring only 4834.35 sq. metres could be
allotted. It was only when the allotment letter dated 14.12.2011 was
issued along with the site plan that the Claimant Company realised
that, looking to the odd shape of the offered land and after leaving the
setbacks as depicted in the site plan, it would be left with barely 38–
40% usable area, as out of 4834.35 sq. metres, 2934 sq. metres was
going in setbacks. Immediately thereafter, the Claimant Company wrote
the letter dated 20.12.2011 requesting RIICO to revise the site plan.
From 20.12.2011 to 30.08.2012 the site plan remained under
reconsideration, and the revised site plan was issued only on
31.08.2012 (Annexure-3/Exhibit-7). As the letter of allotment (Term No.
15) and the lease deed (Terms 2(d) and 2(p)) clearly stipulated that
construction had to be in accordance with the site plan, the Claimant
Company could not have commenced construction until it received the
revised site plan. The circumstances were thus beyond its control. The
Claimant Company even requested the Non-claimant Corporation to
reckon the period of two years from the date of issuance of the revised
site plan, but the request was declined. The Claimant Company, in all
bona fides, proceeded with the construction and completed it within
two years from the date of the revised site plan. The delay, if any, is
attributable only to the Non-claimant Corporation, which took an
inordinate time of eight months in issuing the revised site plan.
[2026:RJ-JP:29646-DB]
(10 of 16)
[CMA-1170/2022]
(iii) Delay in execution of the lease deed: after the allotment of
14.12.2011 and handing over of possession on 09.04.2012, the lease
deed came to be executed between the parties only on 27.09.2012
(Annexure-9/Exhibit-8), i.e. after the revised site plan was released on
31.08.2012. As a result, the Claimant Company could commence
construction activity only after receiving the revised site plan on
31.08.2012.
As the delay is not attributable to the Claimant Company, it cannot be held
liable to pay any penalty or retention charges, as mentioned in the contract
or the applicable Rules, for the delay, if any, in completion of construction
within the stipulated period. The Claimant Company has also placed
reliance on Section 54 of the Indian Contract Act, which stipulates the
‘Effect of default as to that promise which should be first performed, in
contract consisting of reciprocal promises’, and which reads:
‘When a contract consists of reciprocal promises, such that one of them
cannot be performed, or that its performance cannot be claimed till the
other has been performed, and the promisor of the promise last
mentioned fails to perform it, such promisor cannot claim the
performance of the reciprocal promise, and must make compensation
to the other party to the contract for any loss which such other party
may sustain by the non-performance of the contract.’
This issue is also decided in favour of the Claimant Company.
x-x-x-x-x-x-x
ISSUES NOS. 5 & 6:
Whether the Claimant Company is entitled to a declaration to the effect that
the period of two years for completion of construction and commencement
of production shall be reckoned from the date the allotted area is declared a
‘developed area’ in accordance with the Industrial Development Committee
decision, and whether the allotted area has been so declared and, if yes,
when, and with what effect?
The Note appended to Clause 3 of the allotment letter dated 14.12.2011
clearly stipulates that the Industrial Area Ramchandrapura (Sitapura
Extension) was not developed at the time the allotment letter was issued to
the Claimant Company. The said industrial area was declared developed by
Office Order No. U(25)3/2013-14/1988 dated 07.08.2013 (Annexure15/Exhibit-14). A bare perusal of the RIICO Disposal of Land Rules, 1979
shows that Rule 21 provides the ‘time period for commencement and
completion of construction activities and commencement of production
activities’. As per the IDC decision dated 20.05.2004, the following Note
was inserted in Rule 21 and made applicable to all allotments, including
preferential allotments made under Rule 3(W):
‘Note: In cases where lease-deed of plot has been executed or
possession of plot is taken over/deemed, prior to declaration of area as
developed then, the period for commencement of construction
activities, completion of construction activities and commencement of
[2026:RJ-JP:29646-DB]
(11 of 16)
[CMA-1170/2022]
production activities will be considered from the date of declaration of
area as “Developed”.’
The aforesaid Note applied even to preferential allotments made under Rule
3(W) and is therefore applicable to the allotment made in favour of the
Claimant Company on 14.12.2011. As such, the time period of two years for
completion of construction and commencement of production should be
reckoned w.e.f. 07.08.2013, and the Claimant Company is entitled to a
declaration to that effect. These two issues are decided in favour of the
Claimant Company.
ISSUE NO. 7:
Whether the Claimant Company is entitled to a declaration to the effect that
there is no time limit fixed for making an investment to the tune of Rs. 21.89
Crores on the land allotted by the Non-claimant Corporation?
The preferential allotment under Rule 3(W) was made as the Claimant
Company wanted to construct a big service station for CC executive class
cars by investing Rs. 21.89 Crores. Neither the application seeking
allotment, nor the undertaking, nor even the allotment letter anywhere
mentions that the investment of Rs. 21.89 Crores was to be made within two
years of issuance of the allotment letter. Though making an investment of
Rs. 21.89 Crores was a pre-condition for allotment under Rule 3(W), no
time period was prescribed for making the investment. Moreover, at the time
of allotment, i.e. on 14.12.2011, the Note to Rule 21(6) was not in existence,
having been inserted sometime in May 2012. Learned counsel for the
Claimant Company has placed reliance on Zile Singh v. State of Haryana,
(2004) 8 SCC 1, wherein it has been held that it is a cardinal principle of
construction that every statute is prima facie prospective unless it is
expressly or by necessary implication made to have retrospective
operation.”
8.
We have, examined the award, and, with due respect we may say
that we do not propose to gloss over its imperfections. The findings on
Issue Nos. 1 and 2, may not be happily worded, viz., the learned
Arbitrator has set out the rival submissions at length and after, what
seems to be, accepting the arguments of the claimant, thus recorded
his conclusions in favour of the claimant. It gives the impression on first
blush, as if they are without an independent discussion of his own.
However, were those findings to stand alone, the criticism of want of
reasons might have carried weight.
9.
But they do not stand alone. An arbitral award is not to be read
necessarily with a fault-finding eye. The award must be read fairly, as a
[2026:RJ-JP:29646-DB]
(12 of 16)
[CMA-1170/2022]
whole and cumulatively. So read, the discussion under Issue No. 3,
which traverses the same ground as Issues Nos. 1 and 2, supplies the
reasoning that sustains the findings on the earlier issues read further
with the discussion and analysis contained under issues no.5 to 7.
Thereunder, the learned Arbitrator has examined the delay at each of
the three stages, delivery of possession, issuance of the revised site
plan and execution of the lease deed, with reference to Clause 15 of the
allotment letter, Clauses 2(d) and 2(p) of the lease deed, the Note to
Rule 21 of the Rules of 1979 and Section 54 of the Indian Contract Act,
and has thus concluded that the appellant could not, in law or in fact,
have commenced construction before the revised site plan was issued
on 31.08.2012. It was held that the contractual stipulations themselves
required construction to conform to the site plan. The reasons, though,
if we may say so, are economically expressed, but at the same time are
intelligible and disclose due application of mind to the pleadings and the
evidence adduced by both parties.
10.
The conclusion, which the above reasoning yields, is that the
period for completion of construction was to be reckoned from
31.08.2012, when the revised site plan was issued, or, alternatively,
from 07.08.2013, when the area was declared developed. Said
conclusion is thus anchored in the contract and the Rules.
11.
Au contraire, the construction adopted by the learned Arbitrator
is, at the lowest, a possible view, and it is trite that the availability of
another possible view furnishes no ground for the Section 34 court to
interfere as though it were a court of first appeal. In preferring its own
interpretation after re-appreciating the evidence and reframing the
points for determination, the learned Commercial Court exceeded the
jurisdiction which the statute confers.
[2026:RJ-JP:29646-DB]
12.
(13 of 16)
[CMA-1170/2022]
Now, adverting still further to the commercial court. What has to
be borne in mind is that the parameters of interference under Section
34 are well settled and need no elaborate restatement. The court
examining objections to an arbitral award does not sit in appeal over it.
Neither it re-appreciates the evidence nor substitutes its own view for
that of the arbitrator. The construction of the terms of a contract lies
primarily within the arbitrator’s domain. Where the view taken is a
possible one, the award must stand even if another, may be even
better, view was available. Interference is confined to the grounds
enumerated in Section 34(2) and (2A), and “patent illegality” denotes
an illegality going to the root of the matter, not a mere erroneous
procedural deficiency of law or perceived misappreciation of evidence.
13.
For testing the settled principles noticed above vis-à-vis the
impugned order passed by the learned commercial court, let us first see
what weighed on its mind. It, in fact, framed two legal questions which
are reproduced here in below :“26. That in the light of the aforesaid aspect of the matter as argued by
the objector/ non-clairmant this court is constrained to determine the
following legal questions:1. Whether the claimant got the cause of action by mere receipt of the
'show cause notices' to get the same adjudicated through arbitration,
even before passing of final order in the form of cancellation of allotment
or recovery of retention charges against the claimant?
2. Whether the premature adjudication merely on the show cause notices
in an arbitral proceeding has led to disrobing the statutory authority from
its powers under the rules and regulations?”
14.
On perusal of the impugned order passed by the learned
commercial court, we find that it traversed on a path, what it thought
was the central question, i.e. whether mere receipt of show cause
notices gave the claimant a cause of action to invoke arbitration before
any final order (such as cancellation of allotment or recovery of
[2026:RJ-JP:29646-DB]
(14 of 16)
[CMA-1170/2022]
retention charges) was passed by RIICO. The commercial court held it
did not.
14.1
It, inter alia, held that, RIICO, as a statutory authority, had
merely issued a wake-up notice (17.07.2013) and show cause notices
(including the final one dated 09.04.2015), which only afforded the
claimant an opportunity to explain or seek extension of time. Instead of
replying or applying for extension as advised, the claimant invoked
arbitration and sought quashing of the notices, an exercise the court
described as premature and driven by an ulterior motive to obstruct and
pre-empt any final order by the authority.
14.2
The learned commercial court felt that judicial authority must not
interfere at the show cause notice stage, since a show cause notice by
itself infringes no rights. It held that a grievance arises only upon a final
adverse order. Adjudicating on mere notices amounted to usurping the
powers of the statutory authority. Thus it held that the award therefore
fell foul of the "fundamental policy of Indian law" under Section 34(2)
(b)(ii) read with Explanation 1 and the resultant setting aside of the
same.
15.
Having applied our mind to the reasoning and approached
adopted by the learned commercial court, we are of the opinion that the
same cannot be sustained, for it suffers from three fundamental
infirmities. Let us see how.
16.
First,
the
learned
Commercial
Court
travelled
beyond
the
objections before it. It framed for itself new “legal questions”, whether
the reference to arbitration was premature and whether any cause of
action existed. Not to suggest that it could not have chartered that path
and/or there is any legal bar on that, but atleast these ought to have
(15 of 16)
[2026:RJ-JP:29646-DB]
[CMA-1170/2022]
been on the basis of the arguments and/or grounds raised by the
respondent/RIICO
in
its
objection
petition.
Objection
petition
proceedings ought to be decided on the grounds pleaded within the
limited parameters envisaged under Section 34 of the Act. The
commercial court should not construct for the objector a case which the
objector itself never made. The respondent’s objections, as the record
shows, were directed entirely at the merits of the claimant’s grievance,
i.e. the delay in delivery of possession of the plot and revision of the
site plan enabling commencement of construction. These are matters,
which the learned Arbitrator dealt with under Issue No. 1 and the other
connected issues.
16.1
Secondly, even assuming, arguendo, that the question of
prematurity could have been examined, even taken the conclusion
reached is untenable. The Commercial Court proceeded on the footing
that the dispute had been referred to arbitration merely on the basis of
the show cause notice dated 20.08.2014. The order dated 03.06.2016,
by which this Court allowed the application under Section 11 of the Act
of 1996, belies that assumption. It was passed after hearing both sides,
in the presence of their respective counsel, and upon a satisfaction that
a live dispute subsisted between the parties travelling beyond the show
cause notice, in particular, the dispute arising from RIICO’s refusal to
extend the two-year period for completion of construction, which fell
squarely within the arbitration clause. That order was never challenged
by either party and attained finality. It was not open to the Commercial
Court to sit in collateral judgment over it in proceedings under Section
34.
16.2
Moreover, in this context, even the RIICO/respondent’s conduct
places the matter beyond doubt. At no stage did the respondent
[2026:RJ-JP:29646-DB]
(16 of 16)
[CMA-1170/2022]
contend that the reference was premature. Neither before this Court
when the Section 11 application was allowed; nor susbequently before
the learned Arbitrator, where any plea touching jurisdiction was required
to be raised at the threshold. Furthermore, it was never pleaded so
even in its objection petition under Section 34. An objection never taken
by the party could not have been conceived of and answered by the
Court on its behalf in exercise of the limited jurisdiction vested under
section 34, ibid.
16.3
Thirdly, the learned Commercial Court re-appreciated the
evidence and substituted its own interpretation of the contractual terms
for that of the Arbitrator, an exercise which is the hallmark of firstappellate jurisdiction and is precisely what Section 34 forbids.
17.
As an upshot of our discussion, the answers to the question in
para-6, ibid, are all in negative. Resultantly, the appeal is allowed. The
impugned order dated 31.03.2022 passed by the learned Commercial
Court is set aside, and the award dated 12.02.2018 is restored to its
original position, with consequences to follow.
18.
All pending application(s) stand disposed of.
(ASHUTOSH KUMAR),J
10-/Ashwani
(ARUN MONGA),J
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review