M/S Kamal Autotech Private Limited vs Rajasthan State Industrial Development and Investment Corporation Limited (Riico)

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Rajasthan High Court
Date
30 July 2026
Case No.
CMA 1170/2022
Result
Allowed
Bench
Arun Monga, Ashutosh Kumar
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

17. As an upshot of our discussion, the answers to the question in para-6, ibid, are all in negative. Resultantly, the appeal is allowed. The impugned order dated 31.03.2022 passed by the learned Commercial Court is set aside, and the award dated 12.02.2018 is restored to its original position, with consequences to follow.

Filed under

Arbitration and Conciliation Act, 1996 Section 34, Arbitration and Conciliation Act, 1996 Arbitration and Conciliation Act

Guides on this topic, in plain language:

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

[2026:RJ-JP:29646-DB] HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR D.B. Civil Miscellaneous Appeal No. 1170/2022 CNR: RJHC020401512022 | URN: CMA / 1994U / 2022 M/s Kamal Autotech Private Limited, Kamal And Company Premises Opposite G.p.o, M.I. Road, Jaipur-302001 (Rajasthan) Through Its Director/ Authorized Signatory- Mr. Aditya Kasliwal. ----Appellant Versus 1. Rajasthan State Industrial Development And Investment Corporation Limited (RIICO), Udyog Bhavan, Tilak Marg, Jaipur- 302005 (Raj.) Through Its Chairman. 2. Rajasthan State Industrial Development And Investment Corporation Limited (RIICO), EPIP, Sitapura Industrial Area, Jaipur- 302022 (Raj.) Through Its Sr. Regional Manager. 3. Sole Arbitrator Hon'ble Mr. Justice S.N. Bhargava (Retd.), 20/46, Ambedkar Marg, Renu Path, Mansarovar, Jaipur. ----Respondents For Appellant(s) : Ms. Sukriti Kasliwal, Adv. Mr. Nareshwar Shekhawat, Adv. For Respondent(s) : Mr. Chandra Shekhar, Adv. Mr. Devendra Singh. Adv. HON'BLE MR. JUSTICE ARUN MONGA HON'BLE MR. JUSTICE ASHUTOSH KUMAR Order(Oral) Reportable 30/07/2026 Per: Arun Monga, J. 1. This appeal is directed against the order dated 31.03.2022 passed by the learned Commercial Court, whereby, in exercise of jurisdiction under Section 34 of the Arbitration and Conciliation Act, 1996 (for short “the Act of 1996”), the objections preferred by the respondent– Corporation were allowed and the arbitral award dated 12.02.2018 made by the learned Sole Arbitrator was set aside. 2. The appellant company applied to the Rajasthan State Industrial Development and Investment Corporation Ltd. (RIICO) for allotment of (2 of 16) [2026:RJ-JP:29646-DB] [CMA-1170/2022] an industrial plot for establishing a unit for “Service Station & Body Building of Executive CC”. By allotment letter dated 14.12.2011, RIICO allotted Plot No. SP-2033(B), admeasuring 4834.35 square metres, situated at Ramchandrapura, EPIP, Sitapura Industrial Area, Jaipur, under Rule 3(W) of the RIICO Disposal of Land Rules, 1979 (for short “the Rules of 1979”). The allotment obliged the appellant to complete construction and commence commercial production within the stipulated period, and to raise construction in conformity with the approved site plan and the applicable building bye-laws. Possession of the plot was delivered on 09.04.2012, and a lease deed for a period of ninety-nine years was executed between the parties on 27.09.2012. 2.1 Even before taking possession, the appellant, by its letter dated 20.12.2011, pointed out discrepancies in the original site plan, stating that the setbacks depicted therein rendered the project unviable. RIICO thereupon issued a revised site plan on 31.08.2012, modifying the setbacks. The industrial area was subsequently declared a “Developed Area” by RIICO vide office order dated 07.08.2013. In the interregnum, RIICO addressed communications to the appellant regarding progress of construction, including letters dated 08.11.2012 and 17.04.2013, while the appellant’s request for extension of time made by letter dated 30.05.2013 was declined by RIICO on 15.07.2013. 2.2 RIICO thereafter issued a show cause notice dated 20.04.2014 proposing cancellation of the allotment. Disputes having arisen, the appellant invoked the arbitration clause contained in the lease agreement and also instituted proceedings under Section 9 of the Act of 1996, in which interim protection was granted by the competent court vide orders dated 28.05.2015 and 03.05.2016. The named arbitrator not having entered upon the reference, the appellant filed an application (3 of 16) [2026:RJ-JP:29646-DB] [CMA-1170/2022] under Section 11 of the Act of 1996, and this Court, by order dated 03.06.2016, appointed Hon’ble Justice S.N. Bhargava (Retd.) as the Sole Arbitrator. 2.3 Before the learned Sole Arbitrator, the appellant challenged the wake-up notice and the show cause notices issued by RIICO and sought, inter alia, a declaration as to the date from which the contractual period for completion of construction and commencement of production was to be reckoned. RIICO contested the claims. By award dated 12.02.2018, the learned Sole Arbitrator held that the stipulated period was to be reckoned from the date of issuance of the revised site plan, namely 31.08.2012, and allowed the claims accordingly. 2.4 Aggrieved, RIICO instituted proceedings under Section 34 of the Act of 1996 before the Commercial Court, which, by the impugned order dated 31.03.2022, allowed the objections and set aside the award. Hence, this appeal. 3. Ms. Sukriti Kasliwal, learned counsel for the appellant submits that the learned Commercial Court exceeded the limited jurisdiction conferred by Section 34 of the Act of 1996. It re-appreciated the evidence, examined the merits of the dispute and substituted its own interpretation of the contractual terms, as though exercising appellate jurisdiction. The award, it is urged by her, was a reasoned award rendered upon consideration of the pleadings, the evidence and the issues framed. It could not have been disturbed unless a ground under Section 34(2) or (2A), such as patent illegality or conflict with public policy, was made out. 3.1 It is next submitted by her that the Commercial Court erred in framing new points of determination, concerning the allegedly premature character of the arbitration and the absence of a cause of [2026:RJ-JP:29646-DB] (4 of 16) [CMA-1170/2022] action, which were never the respondent’s objections. This Court, while exercising jurisdiction under Section 11, had already satisfied itself of the existence of live disputes and appointed the Sole Arbitrator by order dated 03.06.2016, an order which neither party ever challenged. The question of arbitrability or the existence of disputes could not, therefore, be reopened in proceedings under Section 34. 3.2 She further submits that the dispute referred was, in essence, one of interpretation of the contractual provisions the determination of the date from which the period for completion of construction and commencement of production was to run, and the reliefs seeking quashing of RIICO’s notices were merely consequential. The arbitration clause embraced every dispute arising out of or relating to the agreement, and nothing in it required the appellant to await a final order of cancellation or recovery before invoking arbitration. 3.3 It is also urged that RIICO acted throughout as a contracting party under the lease agreement and not in exercise of any statutory adjudicatory power; the Commercial Court therefore erred in observing that the arbitration sought to obstruct the functioning of a statutory authority. The dispute was purely contractual, governed by the terms of the agreement, the Rules of 1979 and the Act of 1996. 3.4 Lastly, Ms. Kasliwal submitted that the learned Sole Arbitrator considered all relevant clauses, correspondence and material before holding that the prescribed period was to be computed from the issuance of the revised site plan; the interpretation so adopted was a possible view and hence immune from interference under Section 34. The impugned order, travelling beyond the permissible limits of judicial scrutiny, is liable to be set aside. [2026:RJ-JP:29646-DB] 4. (5 of 16) [CMA-1170/2022] Per contra, Mr. Chandra Shekhar, learned counsel for the respondent submits that the impugned order is based on rational logic and warrants no interference and the arbitral award has rightly been set aside. He would rely on the reasoning assigned in the impugned order passed by the commercial court in support of his contention. 5. Having heard the rival contentions and perused the record including the impugned order passed by the learned commercial court as well as the impugned award, we shall now proceed to render our opinion. 6. First and foremost, for sake of better structuring our discussion and analysis, in our view following three questions arise for our consideration: (i) whether the learned Commercial Court, in setting aside the award, remained within the confines of Section 34 of the Act of 1996; (ii) whether it was open to the Commercial Court to hold the reference to arbitration premature for want of a cause of action, when no such objection had been taken by the respondent at any stage; And (iii) whether the award is vitiated for insufficiency of reasons. 7. Adverting first to the third question, ibid. Since the sufficiency of the Arbitrator’s reasoning is squarely in issue, it is apposite to notice the operative discussion in the award dated 12.02.2018, the relevant portion whereof reads as under: “44. I have considered the pleadings brought on record, perused all the documents and evidence led by each party and considered the arguments advanced orally as well as by way of written submissions, and based upon all I decide the issues as under. [2026:RJ-JP:29646-DB] (6 of 16) [CMA-1170/2022] ISSUE NO. 1: Whether the Claimant Company has committed any breach of the terms and conditions of the allotment made vide Allotment Letter No. U(25)-3(SP2033(B))/2011/3994 dated 14.12.2011 and the Lease Deed dated 27.09.2012 in its favour and, if so, what would be the effect? The burden to prove this issue was on the Non-claimant Corporation. During the course of arguments the Non-claimant Corporation raised the following contentions in support of this issue:— (i) The allotment was made under Rule 3(W) of the RIICO Disposal of Land Rules, which is a preferential allotment. (ii) Before the subject land was allotted, the Claimant Company was aware that only 38% of the area would be available as per the setbacks; reliance was placed on the Minutes of the Meeting dated 30.11.2011. (iii) At the time of allotment the Claimant Company had given an undertaking to complete construction within a period of 2 years from the date of allotment. (iv) As per Term Nos. 6 and 9 of the allotment letter as well as the Rules of 1979, the Claimant Company was required to complete construction within 2 years from the date of allotment and make capital investment of Rs. 21.89 Crores, which the Claimant Company failed to do and has therefore committed breach of the terms and conditions of the allotment. (v) On account of breach of the terms and conditions, the Claimant Company is liable to pay either retention charges or get the allotment cancelled. The Claimant Company in reply submitted that— (i) the Claimant Company never participated in the Sub-Committee Meeting held on 30.11.2011 (Annexure R-2), as is evident from the minutes not having been signed by the Claimant Company, nor was any representative present in the said meeting; (ii) had the Claimant Company been told that, out of the land proposed to be allotted, only 38% utility area would be available after leaving the setbacks, it would not have gone ahead with the proposed project, as it would have been unviable; (iii) it was only when the allotment letter dated 14.12.2011 (Annexure2/Exhibit-3 at Page 22) was issued that the Claimant Company got the site plan with the given setbacks; (iv) as more than 60% of the land was going in setbacks, the Claimant Company, immediately and before taking possession of the land, by its letter dated 20.12.2011 (Annexure-R6/Exhibit-5 at Page 288), requested RIICO to issue a revised site plan, explaining the difficulty; (v) Clause 15 of the letter of allotment clearly stipulates that the Claimant Company is to construct the building according to the bye- [2026:RJ-JP:29646-DB] (7 of 16) [CMA-1170/2022] laws of RIICO; as the application of the Claimant Company for reconsideration of the setbacks was under consideration, the Claimant Company could not commence construction activity; (vi) moreover, possession of the said land was handed over to the Claimant Company only on 09.04.2012 (Annexure-4/Exhibit-6 at Page 29) and the lease deed for the subject land came to be executed on 27.09.2012 (Annexure-9/Exhibit-8 at Page 31); without possession and without transfer of the land in its favour, the Claimant Company could not commence construction activity on site; (vii) Terms 2(d) and 2(p) are material terms of the lease agreement, which also clearly stipulate that construction has to be made in accordance with the applicable Rules, and the applicable Rules clearly require setbacks to be left while commencing construction; (viii) in fact, even the revised site plan dated 31.08.2012 (Annexure3/Exhibit-7), issued eight months after the letter of allotment, stipulates that construction has to be made in accordance with the given site plan; (ix) the Claimant Company completed construction and commenced production activity within the stipulated period reckoned from receipt of the revised site plan from RIICO; as such, the Claimant Company did not commit breach of any term or condition of the letter of allotment or the lease deed; (x) the Claimant Company began construction on the allotted land immediately after receipt of the revised site plan and finished the same within two years therefrom; production on the allotted land was also started, as informed to the Non-claimant Corporation by letter dated 29.08.2014 (Annexure-25), and the completion of the factory and commencement of production are evident from the site report dated 08.09.2014 (Annexure-26/Annexure R-15) annexed with the reply of the Non-claimant Corporation itself; (xi) in the light of the aforesaid, it is clear that the Claimant Company functioned in complete conformity with the terms of the allotment letter and the lease deed. I have considered the submissions made by both the parties and I am of the considered view that, in the facts and circumstances, the period of two years has to be reckoned from the date of the revised site plan. In view of this, Issue No. 1 is decided in favour of the Claimant Company. ISSUE NO. 2: Whether the terms of allotment and the Lease Deed are subject to the RIICO Disposal of Land Rules, 1979 and, if so, what would be the effect of the same on the terms and conditions incorporated in the Letter of Allotment and the Lease Deed? The allotment letter dated 14.12.2011 contains certain clauses which make it compulsory for the allottee Claimant Company to act in conformity with [2026:RJ-JP:29646-DB] (8 of 16) [CMA-1170/2022] the RIICO Disposal of Land Rules, 1979. The relevant clauses are reproduced hereunder for ready reference: ‘The allottee shall abide by the RIICO Disposal of Land Rules, 1979 and its amendments made thereunder from time to time. That you will construct the building after leaving prescribed setbacks as per enclosed site plan and in accordance with the building bye-laws as provided in the RIICO Disposal of Land Rules, 1979.’ The lease agreement dated 27.09.2012 (Annexure-9/Exhibit-8) itself declares, at the title page, that it is drafted under Rule 11 of the RIICO Disposal of Land Rules, 1979. Furthermore, Clause 2(p) of the lease agreement mandates the lessee to abide by the provisions of the Rules of 1979, and is reproduced hereunder: ‘2(p) That the Lessee shall also abide by the terms and conditions of the letter of allotment, RIICO Disposal of Land Rules, 1979 and amendments made therein from time to time. The letter of allotment shall form part and parcel of the Lease Agreement.’ From the afore-stated it is clear that both the terms of the allotment letter and the lease deed are subject to the provisions of the RIICO Disposal of Land Rules, 1979 and, in case of any contradiction, the Rules of 1979 shall prevail. ISSUE NO. 3: Whether the Non-claimant Corporation is responsible for the delay of eight months caused in the commencement of construction work and, if so, what would be its effect? The Claimant Company contended, firstly, that there has been no delay in completion of construction, as the period of two years mentioned in the letter of allotment read with the Note to Rule 21 clearly demonstrates that the period would be reckoned from 07.08.2013 (when the area was declared ‘developed’), and construction was completed well within two years therefrom; and, secondly, that if the period of two years is calculated from the date of allotment, i.e. 14.12.2011, then a period of eight months should be excluded, as the delay, if any, was attributable only to the Non-claimant Corporation, for which the Claimant Company cannot be held responsible. The delay occurred at the following stages: (i) delay in handing over possession; (ii) delay in releasing the revised site plan; (iii) delay in execution of the lease deed in favour of the Claimant Company. The Claimant Company further contended that RIICO in some cases allots industrial lands after fully developing the industrial areas and in some cases soon after acquiring the agricultural lands. If allotments are made under Rule 3(W) in developed areas, conditions can always be imposed to start construction within the given time; but where allotments are made in undeveloped industrial areas, the period of two years can be reckoned only [2026:RJ-JP:29646-DB] (9 of 16) [CMA-1170/2022] after the industrial area is declared ‘developed’. In the instant case, the allotment was made in an undeveloped industrial area having no roads, no electricity, no water mains, no sewerage, etc., and it was therefore not possible to complete construction on agricultural land, bereft of the infrastructure required for construction, and to commence production within two years from the date of allotment. A distinction has therefore to be drawn between allotments made under the Rule 3(W) scheme in a developed industrial area and in an undeveloped industrial area. The related facts are as under:— (i) Delay in handing over possession: although the Non-claimant Corporation issued the letter of allotment dated 14.12.2011 (Annexure2/Exhibit-3) and was considering the application dated 20.12.2011 (Annexure-R6/Exhibit-5) for a revised site plan, it handed over possession of the subject premises only on 09.04.2012 (Annexure4/Exhibit-6), i.e. after a period of more than four months. Without possession of the subject premises, the Claimant Company could not have commenced construction activity on the plot. (ii) Delay in releasing the revised site plan: the Claimant Company applied for allotment of 5000 sq. metres of land for developing a service station and body building industrial unit by its letter dated 10.01.2011 (Annexure-R1), in the bona fide belief that, after leaving setbacks (approx. 1800 sq. metres), it would be able to utilise 3200 sq. metres, which would suffice for the proposed project. However, by letter dated 12.12.2011 (Annexure-R3), RIICO informed the Claimant Company that its application had been accepted, but that in place of 5000 sq. metres, land admeasuring only 4834.35 sq. metres could be allotted. It was only when the allotment letter dated 14.12.2011 was issued along with the site plan that the Claimant Company realised that, looking to the odd shape of the offered land and after leaving the setbacks as depicted in the site plan, it would be left with barely 38– 40% usable area, as out of 4834.35 sq. metres, 2934 sq. metres was going in setbacks. Immediately thereafter, the Claimant Company wrote the letter dated 20.12.2011 requesting RIICO to revise the site plan. From 20.12.2011 to 30.08.2012 the site plan remained under reconsideration, and the revised site plan was issued only on 31.08.2012 (Annexure-3/Exhibit-7). As the letter of allotment (Term No. 15) and the lease deed (Terms 2(d) and 2(p)) clearly stipulated that construction had to be in accordance with the site plan, the Claimant Company could not have commenced construction until it received the revised site plan. The circumstances were thus beyond its control. The Claimant Company even requested the Non-claimant Corporation to reckon the period of two years from the date of issuance of the revised site plan, but the request was declined. The Claimant Company, in all bona fides, proceeded with the construction and completed it within two years from the date of the revised site plan. The delay, if any, is attributable only to the Non-claimant Corporation, which took an inordinate time of eight months in issuing the revised site plan. [2026:RJ-JP:29646-DB] (10 of 16) [CMA-1170/2022] (iii) Delay in execution of the lease deed: after the allotment of 14.12.2011 and handing over of possession on 09.04.2012, the lease deed came to be executed between the parties only on 27.09.2012 (Annexure-9/Exhibit-8), i.e. after the revised site plan was released on 31.08.2012. As a result, the Claimant Company could commence construction activity only after receiving the revised site plan on 31.08.2012. As the delay is not attributable to the Claimant Company, it cannot be held liable to pay any penalty or retention charges, as mentioned in the contract or the applicable Rules, for the delay, if any, in completion of construction within the stipulated period. The Claimant Company has also placed reliance on Section 54 of the Indian Contract Act, which stipulates the ‘Effect of default as to that promise which should be first performed, in contract consisting of reciprocal promises’, and which reads: ‘When a contract consists of reciprocal promises, such that one of them cannot be performed, or that its performance cannot be claimed till the other has been performed, and the promisor of the promise last mentioned fails to perform it, such promisor cannot claim the performance of the reciprocal promise, and must make compensation to the other party to the contract for any loss which such other party may sustain by the non-performance of the contract.’ This issue is also decided in favour of the Claimant Company. x-x-x-x-x-x-x ISSUES NOS. 5 & 6: Whether the Claimant Company is entitled to a declaration to the effect that the period of two years for completion of construction and commencement of production shall be reckoned from the date the allotted area is declared a ‘developed area’ in accordance with the Industrial Development Committee decision, and whether the allotted area has been so declared and, if yes, when, and with what effect? The Note appended to Clause 3 of the allotment letter dated 14.12.2011 clearly stipulates that the Industrial Area Ramchandrapura (Sitapura Extension) was not developed at the time the allotment letter was issued to the Claimant Company. The said industrial area was declared developed by Office Order No. U(25)3/2013-14/1988 dated 07.08.2013 (Annexure15/Exhibit-14). A bare perusal of the RIICO Disposal of Land Rules, 1979 shows that Rule 21 provides the ‘time period for commencement and completion of construction activities and commencement of production activities’. As per the IDC decision dated 20.05.2004, the following Note was inserted in Rule 21 and made applicable to all allotments, including preferential allotments made under Rule 3(W): ‘Note: In cases where lease-deed of plot has been executed or possession of plot is taken over/deemed, prior to declaration of area as developed then, the period for commencement of construction activities, completion of construction activities and commencement of [2026:RJ-JP:29646-DB] (11 of 16) [CMA-1170/2022] production activities will be considered from the date of declaration of area as “Developed”.’ The aforesaid Note applied even to preferential allotments made under Rule 3(W) and is therefore applicable to the allotment made in favour of the Claimant Company on 14.12.2011. As such, the time period of two years for completion of construction and commencement of production should be reckoned w.e.f. 07.08.2013, and the Claimant Company is entitled to a declaration to that effect. These two issues are decided in favour of the Claimant Company. ISSUE NO. 7: Whether the Claimant Company is entitled to a declaration to the effect that there is no time limit fixed for making an investment to the tune of Rs. 21.89 Crores on the land allotted by the Non-claimant Corporation? The preferential allotment under Rule 3(W) was made as the Claimant Company wanted to construct a big service station for CC executive class cars by investing Rs. 21.89 Crores. Neither the application seeking allotment, nor the undertaking, nor even the allotment letter anywhere mentions that the investment of Rs. 21.89 Crores was to be made within two years of issuance of the allotment letter. Though making an investment of Rs. 21.89 Crores was a pre-condition for allotment under Rule 3(W), no time period was prescribed for making the investment. Moreover, at the time of allotment, i.e. on 14.12.2011, the Note to Rule 21(6) was not in existence, having been inserted sometime in May 2012. Learned counsel for the Claimant Company has placed reliance on Zile Singh v. State of Haryana, (2004) 8 SCC 1, wherein it has been held that it is a cardinal principle of construction that every statute is prima facie prospective unless it is expressly or by necessary implication made to have retrospective operation.” 8. We have, examined the award, and, with due respect we may say that we do not propose to gloss over its imperfections. The findings on Issue Nos. 1 and 2, may not be happily worded, viz., the learned Arbitrator has set out the rival submissions at length and after, what seems to be, accepting the arguments of the claimant, thus recorded his conclusions in favour of the claimant. It gives the impression on first blush, as if they are without an independent discussion of his own. However, were those findings to stand alone, the criticism of want of reasons might have carried weight. 9. But they do not stand alone. An arbitral award is not to be read necessarily with a fault-finding eye. The award must be read fairly, as a [2026:RJ-JP:29646-DB] (12 of 16) [CMA-1170/2022] whole and cumulatively. So read, the discussion under Issue No. 3, which traverses the same ground as Issues Nos. 1 and 2, supplies the reasoning that sustains the findings on the earlier issues read further with the discussion and analysis contained under issues no.5 to 7. Thereunder, the learned Arbitrator has examined the delay at each of the three stages, delivery of possession, issuance of the revised site plan and execution of the lease deed, with reference to Clause 15 of the allotment letter, Clauses 2(d) and 2(p) of the lease deed, the Note to Rule 21 of the Rules of 1979 and Section 54 of the Indian Contract Act, and has thus concluded that the appellant could not, in law or in fact, have commenced construction before the revised site plan was issued on 31.08.2012. It was held that the contractual stipulations themselves required construction to conform to the site plan. The reasons, though, if we may say so, are economically expressed, but at the same time are intelligible and disclose due application of mind to the pleadings and the evidence adduced by both parties. 10. The conclusion, which the above reasoning yields, is that the period for completion of construction was to be reckoned from 31.08.2012, when the revised site plan was issued, or, alternatively, from 07.08.2013, when the area was declared developed. Said conclusion is thus anchored in the contract and the Rules. 11. Au contraire, the construction adopted by the learned Arbitrator is, at the lowest, a possible view, and it is trite that the availability of another possible view furnishes no ground for the Section 34 court to interfere as though it were a court of first appeal. In preferring its own interpretation after re-appreciating the evidence and reframing the points for determination, the learned Commercial Court exceeded the jurisdiction which the statute confers. [2026:RJ-JP:29646-DB] 12. (13 of 16) [CMA-1170/2022] Now, adverting still further to the commercial court. What has to be borne in mind is that the parameters of interference under Section 34 are well settled and need no elaborate restatement. The court examining objections to an arbitral award does not sit in appeal over it. Neither it re-appreciates the evidence nor substitutes its own view for that of the arbitrator. The construction of the terms of a contract lies primarily within the arbitrator’s domain. Where the view taken is a possible one, the award must stand even if another, may be even better, view was available. Interference is confined to the grounds enumerated in Section 34(2) and (2A), and “patent illegality” denotes an illegality going to the root of the matter, not a mere erroneous procedural deficiency of law or perceived misappreciation of evidence. 13. For testing the settled principles noticed above vis-à-vis the impugned order passed by the learned commercial court, let us first see what weighed on its mind. It, in fact, framed two legal questions which are reproduced here in below :“26. That in the light of the aforesaid aspect of the matter as argued by the objector/ non-clairmant this court is constrained to determine the following legal questions:1. Whether the claimant got the cause of action by mere receipt of the 'show cause notices' to get the same adjudicated through arbitration, even before passing of final order in the form of cancellation of allotment or recovery of retention charges against the claimant? 2. Whether the premature adjudication merely on the show cause notices in an arbitral proceeding has led to disrobing the statutory authority from its powers under the rules and regulations?” 14. On perusal of the impugned order passed by the learned commercial court, we find that it traversed on a path, what it thought was the central question, i.e. whether mere receipt of show cause notices gave the claimant a cause of action to invoke arbitration before any final order (such as cancellation of allotment or recovery of [2026:RJ-JP:29646-DB] (14 of 16) [CMA-1170/2022] retention charges) was passed by RIICO. The commercial court held it did not. 14.1 It, inter alia, held that, RIICO, as a statutory authority, had merely issued a wake-up notice (17.07.2013) and show cause notices (including the final one dated 09.04.2015), which only afforded the claimant an opportunity to explain or seek extension of time. Instead of replying or applying for extension as advised, the claimant invoked arbitration and sought quashing of the notices, an exercise the court described as premature and driven by an ulterior motive to obstruct and pre-empt any final order by the authority. 14.2 The learned commercial court felt that judicial authority must not interfere at the show cause notice stage, since a show cause notice by itself infringes no rights. It held that a grievance arises only upon a final adverse order. Adjudicating on mere notices amounted to usurping the powers of the statutory authority. Thus it held that the award therefore fell foul of the "fundamental policy of Indian law" under Section 34(2) (b)(ii) read with Explanation 1 and the resultant setting aside of the same. 15. Having applied our mind to the reasoning and approached adopted by the learned commercial court, we are of the opinion that the same cannot be sustained, for it suffers from three fundamental infirmities. Let us see how. 16. First, the learned Commercial Court travelled beyond the objections before it. It framed for itself new “legal questions”, whether the reference to arbitration was premature and whether any cause of action existed. Not to suggest that it could not have chartered that path and/or there is any legal bar on that, but atleast these ought to have (15 of 16) [2026:RJ-JP:29646-DB] [CMA-1170/2022] been on the basis of the arguments and/or grounds raised by the respondent/RIICO in its objection petition. Objection petition proceedings ought to be decided on the grounds pleaded within the limited parameters envisaged under Section 34 of the Act. The commercial court should not construct for the objector a case which the objector itself never made. The respondent’s objections, as the record shows, were directed entirely at the merits of the claimant’s grievance, i.e. the delay in delivery of possession of the plot and revision of the site plan enabling commencement of construction. These are matters, which the learned Arbitrator dealt with under Issue No. 1 and the other connected issues. 16.1 Secondly, even assuming, arguendo, that the question of prematurity could have been examined, even taken the conclusion reached is untenable. The Commercial Court proceeded on the footing that the dispute had been referred to arbitration merely on the basis of the show cause notice dated 20.08.2014. The order dated 03.06.2016, by which this Court allowed the application under Section 11 of the Act of 1996, belies that assumption. It was passed after hearing both sides, in the presence of their respective counsel, and upon a satisfaction that a live dispute subsisted between the parties travelling beyond the show cause notice, in particular, the dispute arising from RIICO’s refusal to extend the two-year period for completion of construction, which fell squarely within the arbitration clause. That order was never challenged by either party and attained finality. It was not open to the Commercial Court to sit in collateral judgment over it in proceedings under Section 34. 16.2 Moreover, in this context, even the RIICO/respondent’s conduct places the matter beyond doubt. At no stage did the respondent [2026:RJ-JP:29646-DB] (16 of 16) [CMA-1170/2022] contend that the reference was premature. Neither before this Court when the Section 11 application was allowed; nor susbequently before the learned Arbitrator, where any plea touching jurisdiction was required to be raised at the threshold. Furthermore, it was never pleaded so even in its objection petition under Section 34. An objection never taken by the party could not have been conceived of and answered by the Court on its behalf in exercise of the limited jurisdiction vested under section 34, ibid. 16.3 Thirdly, the learned Commercial Court re-appreciated the evidence and substituted its own interpretation of the contractual terms for that of the Arbitrator, an exercise which is the hallmark of firstappellate jurisdiction and is precisely what Section 34 forbids. 17. As an upshot of our discussion, the answers to the question in para-6, ibid, are all in negative. Resultantly, the appeal is allowed. The impugned order dated 31.03.2022 passed by the learned Commercial Court is set aside, and the award dated 12.02.2018 is restored to its original position, with consequences to follow. 18. All pending application(s) stand disposed of. (ASHUTOSH KUMAR),J 10-/Ashwani (ARUN MONGA),J

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Rajasthan HC judgments →

Arbitration & Mediation advocates near the Rajasthan High Court

Dealing with a similar matter? Send a free enquiry to advocates who handle it. Fees are agreed with the advocate directly.

All Arbitration & Mediation advocates in India