Judgments
LegalFirms.in Judgments · legalfirms.in/judgments/m-s-jalaram-transport-angul-vs-mcl-sambalpur-20260204/ · Printed 24 Nov 2026
Constitutional

M/S. Jalaram Transport, Angul vs Mcl, Sambalpur

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Orissa High Court
Date
4 February 2026
Case No.
WP(C) 37718/2023
Result
Disposed
Bench
Harish Tandon (Cj), Murahari Sri Raman
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

9. In view of the facts as discussed above, we do not find any justification in the action of the authorities in imposing the penalty and demanding the recovery thereof from the different contracts. The same is hereby quashed and set aside. The authorities are directed to release the retention money within six weeks from the date of the communication of this order, to the petitioner.

10. The writ petition is, thus, disposed of. I agree. (Murahari Sri Raman) Judge (Harish Tandon) Chief Justice S.K. Guin/PA Reason: Authentication Location: High Court of Orissa, Cuttack W.P.(C) No. 37718 of 2023

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

IN THE HIGH COURT OF ORISSA AT CUTTACK W.P.(C) No.37718 of 2023 M/s. Jalaram Transport …. Petitioner …. Opposite Parties -VersusMahanadi Coalfields Limited and others Advocates appeared in this case: For Petitioner : Mr. Avijit Patnaik, Advocate For Opp. Parties : Mr. Haripad Mohanty, Advocate CORAM: HON’BLE THE CHIEF JUSTICE AND HON’BLE MR. JUSTICE MURAHARI SRI RAMAN JUDGMENT -------------------------------------------------------------------------------Date of Hearing : 12th November, 2025 Date of Judgment : 04th February, 2026 -------------------------------------------------------------------------------HARISH TANDON, CJ. 1. The petitioner challenges the notice of demand dated 12th November, 2023 issued by opposite parties-MCL to recover a sum of Rs.9,15,980.70 from the running contract of the petitioner under NIT-843 dated 25th February, 2022 of Ananta OCP, Jagannath Area on account of penalty. W.P.(C) No. 37718 of 2023 2. A prelude to the litigation is required to be adumbrated to consider the points raised in the instant litigation. The Notice Inviting Tender (NIT) was floated on 20th March, 2012 for transportation of crushed coal by tippers from feeder breaker of Jagannath colliery to siding I, III and IV of Jagannath Area for a total quantity of 38 lakh Tes. The petitioner was adjudged as the successful bidder and deposited the bank guarantee as earnest money and two further guarantees towards the performance security and the security deposit with opposite party No.1. The period of completion of the entire work was fixed for 365 days. Pursuant to the said NIT and the petitioner having adjudged as a successful bidder, the letter of acceptance was issued on 13th June, 2012 followed by a work order dated 21st June, 2012. The date of completion of work was fixed at 3rd July, 2013, which according to the petitioner was duly executed and the payments were released from time to time except a paltry sum of Rs.3,28,398/-. 2.1. It is stated in the petition that after a lapse of ten years, the impugned demand is raised without assigning any reason therefor, nor adhering to the principle of natural justice. It is averred in the writ petition that Clause 6.2 of the General Terms and Conditions W.P.(C) No. 37718 of 2023 (GTC) of the Contract clearly provides that the penalties shall be calculated on a monthly basis and in order to give an opportunity to the contractor to make up the shortfall in succeeding three months within the stipulated time of completion and on fulfilling the said shortfall, the said penalty shall be released. On the basis of the said Clause, it is a specific case of the petitioner that once the entire amount has been released except the said paltry sum, the imposition of penalty after a gap of ten years is whimsical, arbitrary and also in violation of the terms and conditions embodied in the contract. 2.2. On the other hand, the opposite parties took a stand that the petitioner failed to comply the safety terms and conditions of the contract and also to deploy those tippers which have a requisite safety features. A notice was issued to the petitioner on 9th October, 2012 with an advice to deploy those tippers which have safety features, but the same was challenged by the petitioner in W.P.(C) No.20844 of 2012 before this Court. In the said writ petition, the petitioner challenged sub-clause (1) (i) (vi) and (xviii) of Clause39.00 as illegal and inoperative. The interim order was passed in the said petition until 12th April, 2019 when the petitioner withdrew the same. It is averred in the counter affidavit that because of the interim W.P.(C) No. 37718 of 2023 order being operative, no further steps could be taken. Responding to Clause 6.2 of the GTC, it is averred that the hindrance register maintained jointly by the management and the contractor would indicate not only the daily progress, but the shortfall, if any, and, therefore, imposition of penalty for such shortfall in terms of the said Clause cannot be said to be perverse and illegal. Lastly, it is averred that since the petitioner is also awarded other contract, the said amount can be recovered from the RA bills which in fact has been indicated in the impugned letter. 3. While admitting the instant writ petition, an interim order was passed on 12th February, 2024 restraining the opposite parties from making any further recovery from the petitioner’s account on the basis of the said impugned demand notice. 4. Mr. Avijit Patnaik, learned counsel for the petitioner has submitted that the impugned demand notice dated 12th November, 2023 is bad, infirm and illegal as no opportunity of hearing was given to the petitioner before imposition of penalty. It is further submitted that in terms of Clause 6.2 of the GTC, the penalty shall be calculated on a monthly basis and can only be withheld for the limited purpose of giving an opportunity to the contractor to make W.P.(C) No. 37718 of 2023 up the shortfall within three months and, therefore, after the release of all the payments including the bank guarantees, such imposition/demand is per se beyond the terms and conditions of the contract. It is further submitted that once the work has already been completed and the bills raised by the petitioner were paid up, the imposition of penalty after a gap of ten years is not only imaginary, but otherwise not sustainable in law. The reliance is placed upon a judgment of the apex Court in case of M.P. Power Management Company Limited v. Sky Power Southeast Solar India Private Limited, (2023) 2 SCC 703 that there is no absolute fetter on the part of the writ Court to interfere in a contractual field, if the action or inaction of the authority is perceived from the contract and such decision is per se arbitrary. Learned counsel for the petitioner has further relied upon a judgment of the apex Court rendered in case of Mohinder Singh Gill v. The Chief Election Commissioner, New Delhi, (1978) 1 SCC 405 in support of the contention that the party shall not be permitted to take a new plea in the litigation, if such plea is not reflected in the impugned decision of the authority. 5. Per contra, Mr. Haripad Mohanty, learned counsel for opposite parties-MCL has vociferously submitted that the delay in W.P.(C) No. 37718 of 2023 raising a demand was because of an intervening interim order passed in the earlier writ petition filed by the petitioner and, therefore, it cannot be said that there is unexplained delay in imposing the penalty. It is further submitted that since the entire work could not be completed, the time was extended which was duly rectified by the petitioner that it will not charge any escalation of price which shows that the petitioner did not complete the work within the time frame. It is, thus, submitted that after withdrawal of the said writ petition, the penalty was calculated on the basis of a hindrance register and a decision is taken to recover the said amount from the other contract awarded to the petitioner. 6. On the conspectus of the aforesaid rival stands taken by the parties, the question we frame for consideration is whether the impugned demand notice issued after a lapse of a decade can be said to be perverse, arbitrary and illegal being not in consonance with the terms and conditions of the contract. 7. It is not in dispute that the tender was floated for transportation of crushed coal by tippers from the feeder breaker of Jagannath colliery to the different sidings in a time bound manner. The agreement was executed between the parties which undeniably W.P.(C) No. 37718 of 2023 includes a GTC as a part of the contract and, there is no incongruity in perceiving the terms and conditions embodied therein having its applicability and binding on the parties. Clause-6.2 of the GTC, which has been heavily relied upon by the petitioner postulates as under: “6.2 In the event of the contractor's failure to comply with the required progress in terms of the agreed time and progress chart or to complete the work and clear the site on or before the date of completion of contract or the extended date of completion, he shall without prejudice to any other right or remedy available under the law to the company on account of such breach, shall become liable to pay for penalty as under: a) If the average daily progress of work during the calendar month is less than the stipulated rate indicated in the detailed tender notice, penalty as detailed below will be levied. i) If the average daily progress of work executed during the calendar month is more than 80% and less than 100% of stipulated rate of progress, penalty equal to 10% of the contract value of the shortfall in work shall be levied. ii) If the average daily progress of work executed during the calendar month is less than 80% of stipulated rate, W.P.(C) No. 37718 of 2023 penalty equal to 20% of contract value of the shortfall in work shall be levied. iii) The aggregate of the penalties so levied shall not exceed 20% of the total contract value. Penalties will be calculated every month and withheld. The contractor shall be allowed to make up the shortfall in the succeeding three months within the stipulated time of completion. Once the shortfall is fully made up the so withheld penalty will be released. b) The defaulters i.e. the Contractors who do not commence the work after issue of LOA shall not be allowed to participate in the re-tendering for the same work.” 8. A bare look of the above quoted Clause leaves no ambiguity that in the event of a failure on the part of the contractor to meet the required progress within the stipulated time shall become liable to pay further penalty. The incidence is also jotted down therein in the sub-clause appended thereto and, therefore, the penalty can only be imposed in the event no incidences are patent and apparent on the face of the record. It further provides that in the event any shortfall is noticed in a month, an opportunity should be given to the contractor to make up the shortfall in succeeding three months and W.P.(C) No. 37718 of 2023 in the event the contractor fulfils such obligations, penalty so withheld shall be released. 8.1. It would not be incongruous in perceiving the intention of the contracting parties from the above Clause that the shortfall must be communicated to the contractor on a monthly basis and an opportunity should be given to make up such shortfall in the succeeding three months. The said agreement further provides for maintenance of the hindrance register jointly at the site which is found during the course of an execution, giving further opportunity to the contractor to make good the delay by putting his endeavors constantly to the satisfaction of the Engineer-in-Charge. Though Clause 8.8 of the GTC bestowed power upon the opposite parties to recover and enforce the recovery of any over-payments detected after the payments as a result of a post payment audit or the technical examination or by any other means, but such Clause has to be read conjointly and in relation to Clause 6.2 of the said GTC. 8.2. Though the nature of the interim order passed in an earlier writ petition is not lucidly and/or explicitly disclosed by both the parties, but from the nature of the reliefs claimed therein, it does not appear to us that there was any interdiction in ascertaining the W.P.(C) No. 37718 of 2023 shortfall leading to the imposition of the penalty. Even the stand of the opposite parties-MCL cannot be accepted for the reason that once the said writ petition was withdrawn in the year 2019, yet there was a complete silence for a considerable period and the demand was issued after a lapse of more than three years. The record would reveal that the hindrance register was prepared in the year 2022 though Clause 6.2 postulates the same to be maintained on a monthly basis and an opportunity should be given to the contractor/transporter to make up the shortfall within three months succeeding such perceived shortfall. 8.3. There is no iota piece of paper produced by either parties that any shortfall on a monthly basis was ever communicated to the petitioner and opportunity was given to make up the said shortfall within the succeeding three months period. It is no longer res integra that the parties to the contract are bound by the terms and conditions thereof. In the event, it is aggrieved by the parties that the shortfall should be detected on a monthly basis and an opportunity is to be given to make up the said shortfall within the stipulated time, it is unjust that one of the contracting parties would raise a demand de hors the said Clause. A plea of demur was taken that the writ W.P.(C) No. 37718 of 2023 petition raising an issue in relation to a contract is not maintainable which does not appear to be an absolute fetter in view of the judgment rendered by the apex Court in M.P. Power Management Company Limited (supra) in the following: “82. We may cull out our conclusions in regard to the points, which we have framed: 82.1. It is, undoubtedly, true that the writ jurisdiction is a public law remedy. A matter, which lies entirely within a private realm of affairs of public body, may not lend itself for being dealt with under the writ jurisdiction of the Court. 82.2. The principle laid down in Bareilly Development Authority [Bareilly Development Authority v. Ajai Pal Singh, (1989) 2 SCC 116] that in the case of a nonstatutory contract the rights are governed only by the terms of the contract and the decisions, which are purported to be followed, including Radhakrishna Agarwal [Radhakrishna Agarwal v. State of Bihar, (1977) 3 SCC 457] , may not continue to hold good, in the light of what has been laid down in ABL [ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd., (2004) 3 SCC 553] and as followed in the recent judgment in Sudhir Kumar Singh [State of U.P. v. Sudhir Kumar Singh, (2021) 19 SCC 706 : 2020 SCC OnLine SC 847] . 82.3. The mere fact that relief is sought under a contract which is not statutory, will not entitle the respondent State in a case by itself to ward off scrutiny of its action or inaction under the contract, if the complaining party is able to establish that the action/inaction is, per se, arbitrary. 82.4. An action will lie, undoubtedly, when the State purports to award any largesse and, undoubtedly, this relates to the stage prior to the contract being entered W.P.(C) No. 37718 of 2023 into (see Ramana Dayaram Shetty [Ramana Dayaram Shetty v. International Airport Authority of India, (1979) 3 SCC 489] ). This scrutiny, no doubt, would be undertaken within the nature of the judicial review, which has been declared in the decision in Tata Cellular v. Union of India [Tata Cellular v. Union of India, (1994) 6 SCC 651] . 82.5. After the contract is entered into, there can be a variety of circumstances, which may provide a cause of action to a party to the contract with the State, to seek relief by filing a writ petition. 82.6. Without intending to be exhaustive, it may include the relief of seeking payment of amounts due to the aggrieved party from the State. The State can, indeed, be called upon to honour its obligations of making payment, unless it be that there is a serious and genuine dispute raised relating to the liability of the State to make the payment. Such dispute, ordinarily, would include the contention that the aggrieved party has not fulfilled its obligations and the Court finds that such a contention by the State is not a mere ruse or a pretence. 82.7. The existence of an alternate remedy, is, undoubtedly, a matter to be borne in mind in declining relief in a writ petition in a contractual matter. Again, the question as to whether the writ petitioner must be told off the gates, would depend upon the nature of the claim and relief sought by the petitioner, the questions, which would have to be decided, and, most importantly, whether there are disputed questions of fact, resolution of which is necessary, as an indispensable prelude to the grant of the relief sought. Undoubtedly, while there is no prohibition, in the writ court even deciding disputed questions of fact, particularly when the dispute surrounds demystifying of documents only, the Court may relegate the party to the remedy by way of a civil suit. 82.8. The existence of a provision for arbitration, which is a forum intended to quicken the pace of dispute resolution, is viewed as a near bar to the entertainment of a writ petition [see in this regard, the view of this Court W.P.(C) No. 37718 of 2023 even in ABL [ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd., (2004) 3 SCC 553] explaining how it distinguished the decision of this Court in State of U.P. v. Bridge & Roof Co. (India) Ltd. [State of U.P. v. Bridge & Roof Co. (India) Ltd., (1996) 6 SCC 22] , by its observations in SCC para 14 in ABL [ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd., (2004) 3 SCC 553] ]. 82.9. The need to deal with disputed questions of fact, cannot be made a smokescreen to guillotine a genuine claim raised in a writ petition, when actually the resolution of a disputed question of fact is unnecessary to grant relief to a writ applicant. 82.10. The reach of Article 14 enables a writ court to deal with arbitrary State action even after a contract is entered into by the State. A wide variety of circumstances can generate causes of action for invoking Article 14. The Court's approach in dealing with the same, would be guided by, undoubtedly, the overwhelming need to obviate arbitrary State action, in cases where the writ remedy provides an effective and fair means of preventing miscarriage of justice arising from palpably unreasonable action by the State. 82.11. Termination of contract can again arise in a wide variety of situations. If for instance, a contract is terminated, by a person, who is demonstrated, without any need for any argument, to be the person, who is completely unauthorised to cancel the contract, there may not be any necessity to drive the party to the unnecessary ordeal of a prolix and avoidable round of litigation. The intervention by the High Court, in such a case, where there is no dispute to be resolved, would also be conducive in public interest, apart from ensuring the fundamental right of the petitioner under Article 14 of the Constitution of India. When it comes to a challenge to the termination of a contract by the State, which is a nonstatutory body, which is acting in purported exercise of the powers/rights under such a contract, it would be over simplifying a complex issue to lay down any inflexible W.P.(C) No. 37718 of 2023 rule in favour of the Court turning away the petitioner to alternate fora. Ordinarily, the cases of termination of contract by the State, acting within its contractual domain, may not lend itself for appropriate redress by the writ court. This is, undoubtedly, so if the Court is dutybound to arrive at findings, which involve untying knots, which are presented by disputed questions of facts. Undoubtedly, in view of ABL [ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd., (2004) 3 SCC 553] , if resolving the dispute, in a case of repudiation of a contract, involves only appreciating the true scope of documentary material in the light of pleadings, the Court may still grant relief to an applicant. We must enter a caveat. The Courts are today reeling under the weight of a docket explosion, which is truly alarming. If a case involves a large body of documents and the Court is called upon to enter upon findings of facts and involves merely the construction of the document, it may not be an unsound discretion to relegate the party to the alternate remedy. This is not to deprive the Court of its constitutional power as laid down in ABL [ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd., (2004) 3 SCC 553] . It all depends upon the facts of each case as to whether, having regard to the scope of the dispute to be resolved, whether the Court will still entertain the petition. 82.12. In a case the State is a party to the contract and a breach of a contract is alleged against the State, a civil action in the appropriate forum is, undoubtedly, maintainable. But this is not the end of the matter. Having regard to the position of the State and its duty to act fairly and to eschew arbitrariness in all its actions, resort to the constitutional remedy on the cause of action, that the action is arbitrary, is permissible (see in this regard Shrilekha Vidyarthi v. State of U.P. [Shrilekha Vidyarthi v. State of U.P., (1991) 1 SCC 212 : 1991 SCC (L&S) 742] ). However, it must be made clear that every case involving breach of contract by the State, cannot be dressed up and disguised as a case of arbitrary State action. While the concept of an arbitrary action or W.P.(C) No. 37718 of 2023 inaction cannot be cribbed or confined to any immutable mantra, and must be laid bare, with reference to the facts of each case, it cannot be a mere allegation of breach of contract that would suffice. What must be involved in the case must be action/inaction, which must be palpably unreasonable or absolutely irrational and bereft of any principle. An action, which is completely mala fide, can hardly be described as a fair action and may, depending on the facts, amount to arbitrary action. The question must be posed and answered by the Court and all we intend to lay down is that there is a discretion available to the Court to grant relief in appropriate cases. 82.13. A lodestar, which may illumine the path of the Court, would be the dimension of public interest subserved by the Court interfering in the matter, rather than relegating the matter to the alternate forum. 82.14. Another relevant criteria is, if the Court has entertained the matter, then, while it is not tabooed that the Court should not relegate the party at a later stage, ordinarily, it would be a germane consideration, which may persuade the Court to complete what it had started, provided it is otherwise a sound exercise of jurisdiction to decide the matter on merits in the writ petition itself. 82.15. Violation of natural justice has been recognised as a ground signifying the presence of a public law element and can found a cause of action premised on breach of Article 14. (See Sudhir Kumar Singh [State of U.P. v. Sudhir Kumar Singh, (2021) 19 SCC 706 : 2020 SCC OnLine SC 847] ).” 8.4. Apart from the same, we notice that the impugned demand does not reflect any grounds while imposing the penalty except the shortfall amount required to be recovered. It has been highlighted in the constitution Bench decision rendered in Mohinder Singh Gill W.P.(C) No. 37718 of 2023 (supra) that it is not open to the authorities to take a different route, to what has not been taken in the administrative order nor can be improved by filing a counter affidavit before Court. The authority cannot wriggle out of the grounds taken in the impugned action and ultimately taking a different route to justify such action was deprecated. 9. In view of the facts as discussed above, we do not find any justification in the action of the authorities in imposing the penalty and demanding the recovery thereof from the different contracts. The same is hereby quashed and set aside. The authorities are directed to release the retention money within six weeks from the date of the communication of this order, to the petitioner. 10. The writ petition is, thus, disposed of. I agree. (Murahari Sri Raman) Judge (Harish Tandon) Chief Justice Digitally Signed Signed by: SUBASH KUMAR GUIN S.K. Guin/PA Reason: Authentication Location: High Court of Orissa, Cuttack Date: 05-Feb-2026 13:37:43 W.P.(C) No. 37718 of 2023

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Orissa HC judgments →