M/s Jai Mata Di Construction Company vs The State of Bihar

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Patna High Court
Date
1 October 2026
Case No.
CWJC 16232/2023
Result
Disposed
Bench
Smt. G. Anupama Chakravarthy
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

16. In view of the aforesaid facts, the dispute is essentially confined to the remaining 150 metres and the consequential claim relating to the maintenance period. Since the said portion has also admittedly been completed, the petitioner is entitled to consideration and payment of the maintenance amount for the period for which the maintenance was actually carried out, in accordance with the terms of the agreement and the measurement recorded by the competent authority. The actual date of completion of work has to be strictly adhered by the respondent for the commencement of the maintenance work for computing it for five years.

17. Accordingly, the respondents are directed to verify the relevant Measurement Book Patna High Court CWJC No.16232 of 2023 dt.01-10-2026 10/10 and other departmental records and make payment of the admissible maintenance dues relating to the said 150 metres, after completion of the stipulated five-year period, in accordance with the agreement and applicable rules, within a period of three months from the date of receipt/production of a copy of this order.

18. Interlocutory Application(s), if any, shall stand disposed of. (G. Anupama Chakravarthy, J) Spd/AFR/NAFR Uploading Date Transmission Date

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

IN THE HIGH COURT OF JUDICATURE AT PATNA Civil Writ Jurisdiction Case No.16232 of 2023 CNR No. BRHC011042852023 ====================================================== M/s Jai Mata Di Construction Company through its Partner Sanjeev Kumar, having its registered office at Professor Colony, Power house Road, Begusarai, Sanjeev Kumar, male, aged about 48 years, S/o- Digambar Prasad Singh, R/o- Ward no. 08, Chandaur, P.O.- Chandaur, P.S.- Bhagwanpur, District- Begusarai. 1. ... ... Petitioner/s Versus The State of Bihar through Principal Secretary Rural works Department, Government of Bihar, Patna. 2. The Principal Secretary, Rural works Department Government of Bihar, Patna. 3. The Engineer-in-Chief, Rural works Department Governemnt of Bihar, Patna. 4. The Chief Engineer-2 and 4 Rural works Department Government of Bihar, Patna. 5. The Superintending Engineer, (Monitoring and Data Cell), Rural works Department, Work Circle, Saharsa. 6. The Superintending Engineer, Local Area Project Planning and Development Department, Bihar Disaster Rehabilitation and Reconstruction Society, 1st floor, Indira RC Singh, Boring Canal Road, Patna-800001. 7. The Executive Engineer, Rural Works Department, Work Division, Saharsa. ... ... Respondent/s ====================================================== Appearance : For the Petitioner/s : For the Respondent/s : M/s Rajendra Narayan, Sr. Advocate Alok Ranjan, Advocate M/s Rakesh Kumar, G.A. 4 Rajan, AC to GA 4 ====================================================== CORAM: HONOURABLE JUSTICE SMT. G. ANUPAMA CHAKRAVARTHY ORAL JUDGMENT Date : 01-10-2026 1. The petitioner has filed the instant application for the following reliefs: “ I. For directing and commanding the responding authorities for making Patna High Court CWJC No.16232 of 2023 dt.01-10-2026 2/10 payment of the work done and successesfully completed by the petitioner to the respondent authorities satisfaction pursuant of to agreement no. 38/M.B.D/15-16 along with maintenance of 5 years. Vide Package no. BKBDP, SA-II, Name of the work-1- PWD Road to Nandlali Muslim tola and-2- Pachgachhiya (Rajanjee Residence) to Sattar village via Medha Tola. II. For further directing and commanding the respondent authorities for making payment of the work done by the petitioner taking into consideration the fact that pursuant to policy decision Government, of the Central GST has been implemented and the same has been increased from 12% to 18%, and also considering the fact that now provision of GST is applicable in place of VAT. III. For amount making of the payment work of entire done of maintenance of the road for five years and successfully completing the same by the petitioner, along with penal interest @ 18% from date it became dues till actual date of payment and Patna High Court CWJC No.16232 of 2023 dt.01-10-2026 3/10 also directing the respondent authority for making payment of amount of Security deposit to the petitioner. IV. For making payment of cost of litigation taking into consideration the fact that after completion of the work allotted to the petitioner payments have not been made to the petitioner, on one pretext or the other (due to paucity of funds) and petitioner has been compel to approach before this Hon'ble court. V. For any other relief or reliefs for which the petitioner is entitled under law in the facts and circumstances of the present case. VI). For quashing and setting aside the letter no. 799 dated 19.04.2021 issued under the signature of Executive Engineer RWD work Division Saharsa, whereby and where under the authority in a very arbitrary and illegal manner, erroneously has mentioned the date of completion of work as 20.01.2020 whereas, it has been mentioned by the senior authority of the department that the petitioner has already completed the work assigned to the petitioner in the stretch of 12.4.2018 itself. land available on Patna High Court CWJC No.16232 of 2023 dt.01-10-2026 4/10 VII) For taking appropriate action against the authorities who are trying to frustrate the legitimate claims of the petitioner on one pretext or the other, since their illegal demands have not been fulfilled by the petitioner. 2. The brief facts culled out of the Writ petition are that the petitioner is a Class-I registered contractor, was awarded the work under Agreement No. 38/MBD/2015-16 for construction and five years' maintenance of two roads under the Bihar Kosi Basin Development Project. The petitioner commenced the work and, despite certain initial hindrances in availability of the work site, completed the construction work under the supervision of the departmental authorities, for which extension of time was also granted. 3. The work executed by the petitioner was duly recorded in the Measurement Book and the completion of the work was acknowledged by the Engineer-in-charge. However, despite repeated representations, the respondents did not release the petitioner's outstanding dues. The petitioner Patna High Court CWJC No.16232 of 2023 dt.01-10-2026 5/10 has also raised claims arising out of reduced work front, delay maintenance attributable work, to delayed the employer, release of retention/security amounts and other contractual dues, including applicable interest. 4. The petitioner approached this Court, seeking for appropriate direction for consideration and payment of his lawful contractual dues, in accordance with the agreement and the applicable rules. 5. The Learned counsel for the petitioner submits that the petitioner has completed the work entrusted to him to the satisfaction of the departmental authorities and that the work so executed has also been duly recorded in the Measurement Book. It is submitted that, despite the same the admitted dues have not been paid to the petitioner. 6. The Learned counsel for the petitioner further submits that the petitioner's claims arise out of the terms of the contract, particularly the provisions relating to compensation events and Patna High Court CWJC No.16232 of 2023 dt.01-10-2026 6/10 release of retention amounts, and therefore the respondents are required to take a decision on the petitioner's pending claims in accordance with the agreement and law. 7. A counter affidavit has been filed on behalf of the respondents. The Learned counsel for the respondents submits that the construction work has already been completed and the petitioner has been paid Rs.6,83,45,113/- towards the construction cost. It is submitted that, so far as the maintenance work is concerned, the petitioner carried out maintenance for a period of three years only and thereafter stopped the same. His claim for maintenance for the entire five-year period is, therefore, not acceptable. 8. The Learned counsel for the respondents further submits that the authorities have already initiated steps for payment of the maintenance dues, for the three years actually executed by the petitioner by seeking allotment of the requisite funds. It is also submitted that the petitioner has not raised any claim towards GST and, as the Patna High Court CWJC No.16232 of 2023 dt.01-10-2026 7/10 stipulated five-year maintenance period has not been completed, the claim for release of the security deposit is not presently payable under the agreement. 9. The Learned counsel for the respondents further submits that necessary steps have already been taken by the respondents for redressal of the petitioner's genuine claim in accordance with the terms of the agreement. 10. A rejoinder to the counter affidavit has been filed on behalf of the petitioner. The Learned counsel for the petitioner submits that the departmental records themselves show that the work had substantially been completed in 2017-18, and that the respondents have not controverted the earlier departmental communications acknowledging such completion. 11. The Learned counsel for the petitioner further submits that the petitioner had already raised his claim for GST and had also completed the maintenance work, but the same has not been paid despite repeated representations. It is Patna High Court CWJC No.16232 of 2023 dt.01-10-2026 8/10 submitted that the subsequent stand of the respondents disputing these claims is contrary to the earlier departmental records. 12. The Learned counsel for the petitioner, therefore, submits that the petitioner’s pending claims, including maintenance charges, GST and release of the security deposit, may be considered and paid in accordance with the terms of the agreement and the relevant departmental records. 13. Heard the Learned counsel for the parties. 14. Having considered the pleadings and the materials on record, it is evident that the construction work was substantially completed and the same was duly recorded by the departmental authorities. The records further indicate that the initial hindrance related only to a portion of the road, and out of the disputed portion, 200 metres were subsequently completed on 15.03.2019, leaving only 150 metres, which was completed on 20.01.2020. 15. The earlier departmental Patna High Court CWJC No.16232 of 2023 dt.01-10-2026 9/10 communications, including 16.09.2020 the and the letter subsequent dated completion certificate, support the fact that the work was ultimately completed. The respondents have also admitted completion of the work and payment of the construction cost. 16. In view of the aforesaid facts, the dispute is essentially confined to the remaining 150 metres and the consequential claim relating to the maintenance period. Since the said portion has also admittedly been completed, the petitioner is entitled to consideration and payment of the maintenance amount for the period for which the maintenance was actually carried out, in accordance with the terms of the agreement and the measurement recorded by the competent authority. The actual date of completion of work has to be strictly adhered by the respondent for the commencement of the maintenance work for computing it for five years. 17. Accordingly, the respondents are directed to verify the relevant Measurement Book Patna High Court CWJC No.16232 of 2023 dt.01-10-2026 10/10 and other departmental records and make payment of the admissible maintenance dues relating to the said 150 metres, after completion of the stipulated five-year period, in accordance with the agreement and applicable rules, within a period of three months from the date of receipt/production of a copy of this order. 18. Interlocutory Application(s), if any, shall stand disposed of. (G. Anupama Chakravarthy, J) Spd/AFR/NAFR CAV DATE Uploading Date Transmission Date NAFR NA 05.10.2026

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Patna HC judgments →

Corporate & Commercial advocates near the Patna High Court

Dealing with a similar matter? Send a free enquiry to advocates who handle it. Fees are agreed with the advocate directly.

All Corporate & Commercial advocates in India