HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT SRINAGAR
Reserved on: 14.05.2026
Pronounced on 22.05.2026
Uploaded on
22.05.2026
Whether the operative part or full
judgment is pronounced: Full judgment.
Arb P No. 53/2025
M/s Hassan Roads Construction Company …Petitioner(s)/Appellant(s)
Private Limited
Through:
Mr. Z. A. Qureshi, Sr. Advocate with
M/s. Rehana, Babar Billal Malik and Muzaam
Nasir, Advocates
v/s
J&K Economic Reconstruction Agency
(ERA) and ors.
Through:
…. Respondent(s)
Mr. Illyas Nazir Laway, GA
CORAM: HON’BLE MR. JUSTICE SANJAY DHAR, JUDGE.
JUDGMENT
1.
The present petition under Section 11(6) of the Jammu and Kashmir
Arbitration and Conciliation Act, 1996 (hereinafter referred to as the Act
of 1996) has been filed by the petitioner-company seeking appointment of
an Arbitrator to adjudicate the disputes and differences that have arisen
between the parties out of contract dated 07.08.2021 relating to “the
Construction of Cenral Control Building for Housing Emergency
Operation Centre and SCADA System at Ompora, Budgam”.
2.
Arb P No. 53/2025
According to the petitioner-company, pursuant to the NIT issued by the
respondent, J&K Economic Reconstruction Agency (hereinafter referred
as “ERA”), for the aforesaid work, the petitioner submitted its bid on
16.03.2021 and was declared as the lowest bidder. Consequently, a letter
of acceptance letter dated 30.06.2021 was issued by respondent-ERA,
whereby the work was allotted to the petitioner-company at a contract cost
of Rs. 29,88,70,430/- plus Rs. 5,00,00,000/- (provisional sum). Pursuant
thereto, a contract agreement was executed between the parties on
07.08.2021.
3.
According to the petitioner-company, it had completed about 90% of the
allotted work and, for completion of the remaining work, certain electrical
and mechanical items were required, which were approved by respondentERA for procurement vide communication dated 22.08.2025. It has been
submitted that the said items were thereafter procured by the petitioner
from the companies defined by the respondents in terms of the contract. It
has further been submitted that the execution of the work got delayed on
account of lapses attributable to the respondents for one reason or the
other, regarding which various communications were exchanged between
the parties from time to time.
4.
It has also been submitted that the respondents issued a letter terminating
the contract, which constrained the petitioner to approach the Court of
learned Additional District Judge, Srinagar, by way of a civil suit. The
said suit came to be disposed of by the learned Additional District Judge,
Srinagar, with a direction to the respondents to consider the representation
Arb P No. 53/2025
of the petitioner seeking extension of time for completion of the balance
work. Pursuant thereto, the petitioner submitted a representation dated
21.08.2025 before the respondents, whereafter extension of 90 days came
to be granted in its favour.
5.
It has been submitted that the petitioner filed a petition under Section 9 of
the Act of 1996 before the Court of Addl. District Judge, Srinagar on
10.04.2025 seeking an injunction against the encashment of bank
guarantee. However, the said petition came to be dismissed vide order
dated 06.10.2025. The petitioner challenged the said order by way of an
appeal under Section 37 of the Act of 1996 before the Commercial
Appellate Division of this Court, which is stated to be pending
adjudication. The petitioner is stated to have invoked arbitration
agreement as contained in Clause 24.4 of the agreement vide its letter
dated 30.09.2025 requesting the respondents to name the arbitrator. It has
been submitted that in the said letter the petitioner has named Sh.Rafiq
Ahmad Rafiq, Ex Chief Engineer as its arbitrator, but the respondents
despite receipt of the notice did not respond.
6.
According to the petitioner, it is entitled to the following claims:
S.
No.
1.
3.
4.
Description of item
IIPC-21st (Bill period 11.06.2025 to
14.07.2025
Variation No.3
Non-BOQ items executed at site
Retention money held with
department
Bank
Performance security
Guarantees
Valid till 22.10.2026
Amount in Rupees
4,64,44,734
1,32,02,210
3,05,70,235
1,04,48,189
1,74,43,522
Addl. Performance
security Valid till
31.12.2025
7.
ESHS performance
Valid till 31.12.2025
Compensation due to late release of
payments
Compensation in terms of condition
42 of the contract (compensation
events)
Expenditure of legal proceedings
Arb P No. 53/2025
2,79,04,085
34,88,705
44,49,007
For last 5 IPCs
5,97,74,086
25,00,000
It has been submitted that the contract could not be completed because of
the default of the respondents and the respondents have terminated the
contract of the petitioner despite their fault, as a result of which the Bank
was not ready to give Bank guarantees to the petitioner unless 100%
security in the form of deposits is furnished to it. This has caused damage
to the tune Rs. 300 lacs to the petitioner.
8.
The respondents have filed their reply to the petition, wherein it has been
submitted that the person who has instituted the petition on behalf of the
petitioner-company is not duly authorized to do so. It has further been
submitted that the petitioner has not invoked the arbitration clause in the
manner contemplated under the agreement. The respondents have also
contended that no arbitrable dispute exists between the parties and,
therefore, the matter is not eligible to be referred to an Arbitral Tribunal.
9.
According to the respondents, the petitioner has already filed a civil suit
regarding the subject matter before the learned Munsiff, Panthachok and
has obtained ex parte order dated 25.08.2025. It has further been
submitted that the petition filed by the petitioner under Section 9 of the
Act of 1996 before the designated Commercial Court, Srinagar, stands
Arb P No. 53/2025
dismissed vide judgment dated 06.10.2025, against which the petitioner
has preferred an appeal. It has also been submitted that the petitioner has
filed another writ petition bearing WP(C) No. 40/2026 in relation to the
same subject matter.
10.
According to the respondents, the petitioner failed to fulfill its contractual
obligations and could not complete the critical disaster management
project even after the lapse of half a decade, despite the stipulated period
of completion being only 12 months. It has been submitted that the
contract, which is the subject matter of the present petition, was awarded
to the petitioner for an amount of Rs. 34,88,70,430/- with the objective of
providing services to the general public during emergency and disaster
situations. According to the respondents, the original completion period
under the contract was 12 months and the scheduled date of completion
was 20.09.2022; but despite grant of four extensions up to 31.10.2024, the
petitioner failed to complete the work.
11.
It has been submitted that, in view of the persistent non-performance and
fundamental breach of obligations under Clause 57.2 of the General
Conditions of Contract (GCC), the contract came to be terminated vide
communication dated 01.04.2025, whereafter post-termination measures,
including takeover of the site, forfeiture of securities and re-tendering of
the balance work, were initiated. It has further been submitted that,
pursuant to the order dated 07.05.2025 passed by the learned Additional
District Judge, Srinagar, the termination order was revoked vide
communication dated 02.06.2025 after approval from the competent
Arb P No. 53/2025
authority, and the petitioner was granted a further period of 90 days to
complete the work. According to the respondents, the petitioner failed to
fulfill the terms and conditions of the revocation order dated 02.06.2025
and did not complete the balance work within the stipulated period. As a
consequence thereof, and in terms of the explicit conditions contained in
the revocation order, the contract automatically stood terminated upon
expiry of the extended period of 90 days. It has also been submitted that
vide communication dated 01.09.2025, it was confirmed that the contract
awarded to the petitioner stood terminated with effect from 31.08.2025
and actions, including encashment of the bank guarantee, initiation of
post-termination proceedings and re-tendering of the balance work, were
undertaken by the respondents.
12.
On the basis of the aforesaid submissions, the respondents have contended
that the appointment of an Arbitrator would be unnecessary and it would
entail an unwarranted financial burden upon the respondent-organization
on account of the arbitral proceedings.
13.
I have heard learned counsel for the parties and perused the record of the
case including contract/documents executed by the parties on 07.08.2021.
14.
The objection raised by the respondents about the authority of the person
who has filed the petition on behalf of the petitioner has been addressed
by the petitioner by placing on record copy of the Board resolution dated
01.07.2021, whereby signatory to the petition stands authorized to
institute and pursue the instant petition on behalf of the petitionercompany.
15.
Arb P No. 53/2025
That takes us to the merits of the case. In this regard, learned counsel
appearing for the respondents, Mr. Illyas Nazir Laway, Government
Advocate, has contended that in terms of Clauses 23 and 24 of the GCC,
the petitioner has not taken resort to reference of the disputes to the
Adjudicator/Dispute Review Expert (DRE) before seeking reference of
the disputes to the Arbitral Tribunal. It has been contended that, without
adhering to the aforesaid procedure, which has been agreed upon by the
parties under the contract, it was not open to the petitioner to invoke the
arbitration clause.
16.
In order to determine the merits of the aforesaid contention raised by
learned counsel for the respondents, it would be necessary to notice the
covenants contained in Clauses 23 and 24 of the GCC:
23. Appointment 23.1. The Adjudicator/Dispute Review Expert (DRE) named in
of the Adjudicator
PCC shall be appointed jointly by the Employer and the
Contractor, at the time of the Employer‟s issuance of the
or Dispute Review
Expert
Letter of Acceptance. If, in the Letter of Acceptance, the
Employer does not agree on the appointment of the
Adjudicator/DRE, the Employer will request the Appointing
Authority designated in the PCC, to appoint the
Adjudicator/DRE within 14 days of receipt of such request.
23.1.1 The Adjudicator/DRE should be in position before “notice to
proceed with work” is issued to the Contractor and an
agreement should be signed with the Adjudicator/DRE
jointly by the Employer and the Contractor in the form
attached – Appendix 3.
23.2
Should the Adjudicator/DRE resign or die, or should the
Employer and the Contractor agree that the
Adjudicator/DRE is not functioning in accordance with the
provisions of the Contract; a new Adjudicator/DRE shall be
jointly appointed by the Employer and the Contractor. In
case of disagreement between the Employer and the
Contractor, within 30 days, the Adjudicator/DRE shall be
designated by the Appointing Authority designated in the
PCC at the request of either party, within 14 days of receipt
of such request.
24. Procedure for 24.1 If the Contractor believes that a decision taken by the Project
disputes.
Arb P No. 53/2025
Manager was either outside the authority given to the
Project Manager by the Contract or that the decision was
wrongly taken, the decision shall be referred to the
Adjudicator/DRE within 14 days of the notification of the
Project Manager‟s decision.
24.2 The Adjudicator/DRE shall give a decision in writing within
28 days of receipt of a notification of a dispute.
34.3
The Adjudicator/DRE shall be paid daily at the rates
specified in the PCC, together with reimbursable expenses
of the types specified in the PCC, and the cost shall be
divided equally between the Employer and the Contractor.
Whatever decision is reached by the Adjudicator/DRE,
either party may refer that decision to an Arbitrator within
28 days of the Adjudicator‟s/DRE‟s written decision. If
neither party refers the dispute to arbitration within the
above 28 days, the Adjudicator‟s/DRE‟s decision shall be
final and binding.
24.4 The arbitration shall be conducted in accordance with the
arbitration procedures published by the institution named
and in the place specified in the PCC.
The Arbitrator(s) shall give a decision in writing within
120 days of start of the proceedings unless otherwise agreed
to by the Parties. The Arbitrators shall entertain only those
issues which have been earlier referred to the
Adjudicator/Dispute Review Expert and either party is
dissatisfied with the decision given by the
Adjudicator/Dispute Review Expert.
17.
It would also be pertinent to refer to relevant covenants of Particular
Conditions of the Contract (PCC), which relate to appointment of
adjudicator/DRE and the procedure for arbitration:
GCC 23.1 &
GCC 232.
Sh. Mohd Iqbal (Retd) Chief Engineer PWD
Appointing authority for the Adjudicator/Dispute Review Expert:
Chairman, Institution of Engineers Srinagar Chapter.
GCC 24.3
Daily rate and types of reimbursable expenses to be paid to the
Adjudicator/Dispute Review Expert: INR 5000/day
GCC 24.4.
Arb P No. 53/2025
The procedure for adhoc arbitration will be as follow:
(a) In case of dispute or difference arising between the Employer
and a Contractor relating to any matter arising out of or
connected with this agreement, such dispute or difference
shall be settled in accordance with the Arbitration and
Conciliation Act, 1996. The arbitral tribunal shall consist of 3
Arbitrators one each to be appointed by the Employer and the
Contractor. The third Arbitrator shall be chosen by the two
Arbitrators so appointed by the Parties and shall act as
Presiding Arbitrator. In case of failure of the two Arbitrators
appointed by the parties to reach upon a consensus within a
period of 30 days from the appointment of the Arbitrator
appointed subsequently, the Presiding Arbitrator shall be
appointed by the Chairman of the Institution of Engineers
(Srinagar Chapter). If one of the parties fails to appoint its
Arbitrator in pursuance of sub-clause (a) above within 30
days after receipt of the notice of the appointment of its
Arbitrator by the other party, Chairman of the Institution of
Engineers (Srinagar Chapter), shall appoint the Arbitrator. A
certified copy of the order of the Chairman of the Institution
of Engineers (Srinagar Chapter), making such an
appointment shall be furnished to each of the parties.
(b) Arbitration may be commenced prior to or after completion of
the Works, provided that the obligations of the Employer, the
Project Manager, the Contractor and the Adjudicator shall not
be altered by reason of the arbitration being conducted during
the progress of the Works.
(c) Arbitration proceedings shall be held at Srinagar, and the
language of the arbitration proceedings and that of all
documents and communications between the parties shall be
English.
(d) The decision of the majority of Arbitrators shall be final and
binding upon both parties. The cost and expenses of
Arbitration proceedings will be paid as determined by the
arbitral tribunal. However, the expenses incurred by each party
in connection with the preparation, presentation, etc. of its
proceedings as also the fees and expenses paid to the Arbitrator
appointed by such party or on its behalf shall be borne by each
party itself.
(e) The Arbitrator should give final award within 180 days of
starting of the proceedings.
(e) Performance under the contract shall continue during the
arbitration proceedings and payments due to the contractor by
the Employer shall not be withheld, unless they are the subject
matter of the arbitration proceedings.
Arb P No. 53/2025
18.
Reference is also required to be made to Clause-2 of General Conditions
of Contract, which relates to interpretation:
Interpretation
2.1. In interpreting these GCC, words indicating one gender
include all genders. Words indicating the singular also
include the plural and words indicating the plural also include
the singular. Headings have no significance. Words have
their normal meaning under the language of the Contract
unless specifically defined. The Project Manager shall
provide instructions clarifying queries about these GCC.
2.2 If sectional completion is specified in the PCC, references in
the GCC to the Works, the Completion Date, and the
Intended Completion Date apply to any Section of the Works
(other than references to the Completion Date and Intended
Completion Date for the whole of the Works).
2.3
The documents forming the Contract shall be interpreted in
the following order of priority:
a) Agreement,
b) Letter of Acceptance,
c) Contractor‟s Bid & Priced Bill of Quantities,
d) Particular Conditions of Contract,
e) General Conditions of Contract including Appendices,
f) Specifications,
g) Drawings, and
h) Joint Venture Agreement [where applicable]
i) Any other document listed in the PCC as forming part of
the Contract.
19.
A perusal of Clause 23 of the GCC, as reproduced above, reveals that the
parties had agreed that an Adjudicator/DRE would be appointed jointly by
the Employer and the Contractor and, in the event the Employer did not
agree to such appointment, a request was to be made to the appointing
authority designated in the PCC for appointment of an Adjudicator. In this
regard, the PCC contains a stipulation to the effect that Sh. Mohd. Iqbal,
retired
Chief
Engineer
(PWD),
had
been
appointed
as
the
Adjudicator/DRE by the parties. Clause 23.1.1 as quoted above, inter alia,
provides that an agreement should be signed with the Adjudicator/DRE
Arb P No. 53/2025
jointly by the Employer and the Contractor in the form attachedAppendix-3.
20.
Learned counsel for the petitioner has produced original contract
executed between the parties. However, this Court could not find the
document in Appendix-3 in the said contract, nor the respondents have
placed on record or pleaded execution of any such document by the
Employer and the Contractor with the named Adjudicator/DRE. Thus, it
has to be presumed that agreement between the Adjudicator/DRE with the
Employer and the Contractor has not been executed by the parties.
21.
As per Clause 24.1 of GCC, if the Contractor believes that a decision
taken by the Project Manager was either outside the authority given to the
Project Manager or that the decision was wrong, the said decision has to
be referred to the Adjudicator/DRE within 14 days, whereupon the
Adjudicator/DRE has to take a decision in writing within 28 days. As per
Clause 24.3 of the GCC, either parties may refer the decision to the
Arbitrator within a period of 28 days from the decision of
Adjudicator/DRE and if the same is not done, decision of the
Adjudicator/DRE would become final and binding.
22.
In the present case, admittedly, the petitioner has not referred any
decision of the Project Manager to the Adjudicator/DRE. The question
that arises for determination is whether, in these circumstances, the
petitioner is entitled to invoke the Arbitration Clause directly without first
availing the remedy of approaching the Adjudicator/DRE. The whole
thrust of arguments of learned counsel for the respondents is on this
Arb P No. 53/2025
aspect of the matter. He has contended that without approaching the
adjudicator/DRE, the petitioner could not have invoked the arbitration
clause and it is only the decision of the Adjudicator/DRE, which can be
referred to arbitration, and not any other decision.
23.
The argument raised by the learned counsel for the respondents, at its first
blush, appears to be attractive but upon its detailed examination, it prima
facie appears that resort to the mechanism of approaching the
Adjudicator/DRE was not feasible and suitable for the petitioner in the
facts and circumstances of the present case. Firstly, because no agreement
appears to have been executed between the Adjudicator/DRE jointly with
respondent-ERA and the petitioner/contractor. Therefore, condition
stipulated in Clause 23.1.1 of the GCC has not been satisfied in the
present case, as such, the forum of Adjudicator/DRE was not available to
the petitioner.
24.
There is yet another aspect of the matter, which is required to be noticed
by this Court. The petitioner is primarily aggrieved of the action of the
respondents in terminating the contract and consequential measures taken
thereafter, which include encashment of bank guarantee, initiation of post
termination proceedings as per the clauses of the contract agreement and
re-tendering of the balance work at the risk and cost of the petitioner. All
these actions have been taken by the Employer and not by the Project
Manager. The Project Manager is an authority distinct from the Employer
and cannot be equated with the Employer. As per clause 4 of GCC, the
Arb P No. 53/2025
Project Manager is decision making authority on contractual matters
between the Employer and the contractor.
25.
In terms of clause 24 of the GCC, it is only the decision taken by the
Project Manager, which can be brought before the Adjudicator/DRE by a
Contractor, if he is aggrieved of the said decision. Any decision taken by
the Employer, including a decision relating to terminating of the contract
and subsequent actions initiated against the Contractor in terms of the
covenants of the contract, cannot be made subject matter of deliberation
before the Adjudicator/DRE. Thus, the petitioner could not have raised
the disputes which are subject matter of the present petition before the
Adjudicator/DRE in terms of the Clause 24 of the GCC.
26.
It is true that in terms of Clause 24.3 of GCC, only the decisions taken by
the Adjudicator/DRE can be referred to the arbitration by the aggrieved
party, but if we have a look at the arbitration clause contained in the PCC,
it is comprehensive in nature, inasmuch as, it provides that in case of
disputes or differences arising between the Employer and the Contractor
relating to any matter, arising out of or connected with the agreement,
such disputes or differences have to be settled in accordance with the
provisions of the Arbitration and Conciliation Act 1996. The arbitration
clause contained in the PCC is of wide amplitude. Therefore, any dispute
arising between the Employer and the Contractor, which does not fall
within the realm of disputes referable to the Adjudicator/DRE, can also be
referred to arbitration.
27.
Arb P No. 53/2025
Besides this, a perusal of the documents placed on record, which include
the communications exchanged between the parties among themselves
would make it abundantly clear that settlement between them through the
medium of an Adjudicator/DRE was not possible. Therefore, the
condition in the contract providing for arbitration of only those disputes
which have been referred to the Adjudicator/DRE is not possible,
particularly on account of decision relating to termination of contract
having been taken by the respondents. Therefore, no pre-arbitration
procedure available to the petitioner, could have been exhausted by it
prior to seeking appointment of the Arbitrator.
28.
In the above context, I am supported by the ratio laid down by the
Supreme Court in the case of Visa International Limited vs.
Continental Resources (USA) ltd. (2009) 2 SCC 55 and a decision of the
Bombay High Court in the case of Quick Heal Technologies ltd. vs.
NCS Computech Pvt and Anr. 2020 SCC Online Bombay 687.
Relying upon the ratio laid down in the aforesaid cases, the Bombay High
Court in the case of Generic Engineering Construction and Project ltd.
vs. Maharashtra Maritime Board, 2026 SCC Online Bom 2733 has
held that in a case where few other clauses in the contract may be slightly
inconsistent or may be in conflict with the main arbitration clause, the
Courts will have to rule in favour of the arbitration rather than giving
weightage to those confusing or conflicting clauses. The Court held that
once there is clear agreement to arbitrate, the courts would tend to ignore
other clauses of contract which may create confusion about existence of
Arb P No. 53/2025
arbitration agreement. It was observed that arbitration is aimed at
declogging the overburdened courts and therefore courts need to
necessarily rule in favour of arbitration rather than concentrating on other
inconsistent clauses for holding that specific arbitration clause present in
the contract would get nullified by those clauses.
29.
In view of the aforesaid position of law, despite there being mechanism
provided in the GCC for reference of the decision of the Project Manager
to the Adjudicator/DRE, this Court having regard to the wide scope of the
arbitration clause contained in PCC, is inclined to hold that the present
petition is maintainable. In fact the Supreme Court in the case of
Maharashtra State Electricity Distribution Company Limited
(MSEDCL) v. R Z Malpani, 2026 LiveLaw (SC) 356, has held that
courts should follow the principle of „When in doubt, do refer‟ and lean
towards referring matters to arbitration when the arbitration agreement is
prima facie existent. Apart from this, in terms of Section 16 of the
Arbitration and Conciliation Act, 1996, the arbitral tribunal is competent
to rule upon its own jurisdiction. Therefore, it shall be open to the
respondents to raise the issue of jurisdiction before the arbitral tribunal
itself.
30.
For the forgoing discussions, this Court is of the prima facie opinion that
the disputes between the parties are arbitrable in nature and that the
remedy of arbitration is available to the petitioner in the facts and
circumstances of the case.
31.
Arb P No. 53/2025
In view of the above, the petition is disposed of by referring all the
disputes and differences covered by the agreement to the learned Sole
Arbitrator in the following terms:
(i)
Hon‟ble Mr. Justice Ali Mohammad Magrey, former Chief Justice,
High Court of J&K and Ladakh is appointed as the Sole Arbitrator
to adjudicate upon the disputes and differences between the parties
arising out of and in connection with the agreement referred to
above.
(ii)
A copy of this order be communicated to the learned Sole
Arbitrator by the Registry of this Court within a period of ten days
from today.
(iii)
The learned Sole Arbitrator is requested to forward the statutory
statement of disclosure under Section 11(8) read with Section 12(1)
of the Act of 1996 to the parties within a period of two weeks from
the date of receipt of this order.
(iv)
The parties shall appear before the learned Sole Arbitrator on a date
and place to be fixed by the learned Sole Arbitrator.
(v)
All the arbitral costs and fee of the Arbitral Tribunal shall be borne
by the parties equally and shall be subject to final award that may
be passed by the learned Arbitrator in relation to the costs.
(SANJAY DHAR)
JUDGE
SRINAGAR
22.05.2026
Karam Chand
Whether the order is speaking: Yes
Whether the order is reportable: Yes
KARAM CHAND
2026.05.22 14:36
I attest to the accuracy and
integrity of this document
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review