The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
66. 1 (b), the Contractor may within fifteen days after receiving notice of such decision, give notice in writing to the Chief Engineer, requiring that the matter be submitted to arbitration and furnishing detailed particulars of this dispute or difference specifying clearly the point of issue. If the Contractor fails to give such notice to the Chief Engineer within the period of 15 days as stipulated above, the decision of the Chief Engineer, shall be final and conclusive and binding on the Contractor. Thereafter such issues shall not be subjected to arbitration. d) Arbitration shall be affected by an arbitration Board consisting of two members. One selected by the Corporation and the other by the contractor. The provisions of the Indian Arbitration Act, 1940 and the rules thereunder shall apply for appointment of Umpire and all matters relating to the arbitration proceedings. e) No arbitration proceedings shall be commended without settling the specific terms of reference. f) The cost of such arbitration shall be borne by the parties or party as decided by the Arbitration Board.” From the material placed on record, it is clear that the petitioner indeed made the requests to the respondent to proceed for arbitration in accordance with the said arbitration agreement but the respondents failed to take the necessary steps. In the totality of circumstances and for the reason of failur…
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
ARB.P. No.3/2017
M/s Gammon India Ltd. v. NEEPCO Ltd.
IN THE HIGH COURT OF MEGHALAYA AT
SHILLONG
: ORDER :
ARB.P. No.3 of 2017
….. Petitioner
M/s Gammon India Ltd.
- Versus –
North Eastern Electric Power Corporation
Ltd.
….. Respondent
Date of Order:
26th April, 2017
::
PRESENT
HON’BLE SHRI JUSTICE DINESH MAHESHWARI, CHIEF JUSTICE
Shri HL Shangreiso, for the petitioner
Shri VK Jindal, Sr.Adv with Ms. MK Marak, for the respondent
BY THE COURT: (Oral)
By way of this application under Section 11 (6) of the Arbitration
and Conciliation Act, 1996, the petitioner has made the request for
appointment of arbitrator to adjudicate upon and decide its dispute with
the respondent arising out of, and relating to, the contract work of
“construction of 68 Meters High Concrete Diversion Dam of Ranganadi
Hydro Electric Project”.
In this application, while making a reference to the formal
agreement between the parties dated 02.02.1996 and while asserting
its claim against the respondent to the tune of Rs.30,75,64,920/(Rupees thirty crores seventy five lakhs sixty four thousand nine
hundred and twenty) excluding interest in relation to the contract work
aforesaid, the petitioner has stated the background aspects as follows:-
ARB.P. No.3/2017
M/s Gammon India Ltd. v. NEEPCO Ltd.
“And an agreement was executed on 02.02.1996. The work which was
required to be completed within 48 months but due to various reasons
not attributable to the claimant, it was not completed on 20.07.1999
and was extended from time to time by the Respondent until it was
finally completed on 30.06.2002 as certified by the Respondent vide
letter dated 10.03.2003. Extension of time granted for completion of
work without levy of any penalty upto 30.06.2002. During the
execution of work certain disputes arose between the parties and the
same could not be resolved by mutual discussions at different levels.
And several meetings were also held in Shillong in connection with the
various issues/ pending payments against the work executed by the
Petitioner Company at RHEP and DHEP. The final bill was submitted
by the Petitioner vide letter dated 28.03.2005 for net amount of Rs.
37,36,09,974/- only but despite repeated requests the Respondent did
not make the payment of final bill. The Petitioner requested vide letter
dated 10.10.2005 to expedite the final bill payment and to intimate to
the Petitioner a probable date by which to expect the payment. It was
intimated to the Respondents that the work had been completed for
the past four years but that legitimate payments amounting to Rs.
34.22 Crores was yet to be released. And several other
correspondences were exchanged and meetings held between
14.08.2006-2009 in regards to payment of the final bill but no payment
was initiated. Aggrieved by the non-responsive attitude and inordinate
delay in clearing the Petitioner’s outstanding bill, the Petitioner vide its
letter dated 07.12.2011 submitted a Notice under clause 47 & 48 of
the General Condition of Contract for making payment of legitimate
dues along with interest from due date of payment within 21 days from
the receipt of the said notice failing which necessary action as per the
provisions of the contract would be taken. The Respondent till date
has failed to initiate complete payment towards the work completed by
the Petitioner and the delay seems to be designed to delay the arbitral
proceedings and frustrate the claims of the petitioner.”
It is submitted that on the failure of the respondent to take the
necessary steps as required, the petitioner is left with no alternative but
to make this request for appointment of arbitrator. It is submitted that
as per Clause 34 of the agreement, the application is of the jurisdiction
of this Court, as the Headquarter of the respondent-Corporation is
situated at Shillong.
It is submitted on behalf of the respondent-Corporation that the
claim as sought to be levied by the petitioner is grossly barred by time
and further that the pre-requisite of arbitration clause has not been
followed by the petitioner inasmuch as the petitioner has not
approached the Engineering-in-Charge in the first place.
ARB.P. No.3/2017
M/s Gammon India Ltd. v. NEEPCO Ltd.
In response to the objection raised on behalf of the respondent, it
is submitted on behalf of the petitioner that its claim is not barred by
time and further that the matter got delayed only because the
respondent kept on repeatedly calling the petitioner for negotiations.
Having heard the learned counsel for the parties and having
examined the record, this Court is clearly of the view that on the limited
aspects required to be considered in this application, the submissions
regarding the question of limitation are not to be adjudicated and
decided by this Court. So far this application is concerned, the
consideration herein is confined to the question as to whether there
exists an arbitration agreement between the parties.
In fact, the
existence of arbitration agreement in this matter is not in dispute. The
arbitration Clause, being Clause 66 of the agreement, reads as under:“Clause 66: Arbitration:
66.1 a) The agreement authority for this contract is the North Eastern
Electric Power Corporation and is represented by Chief Engineer, as
far as this contract is concerned. The Chief Engineer is represented at
site of work by Superintending Engineers, Executive Engineer, SubDivisional Officers, Assistant Engineers, Junior Engineers and other
subordinate staff. These officers at site are delegated with certain
powers regarding execution, measurement and payment of works.
The commitments made by those officers at site and the Chief
Engineer, are based on interpretation of agreement made by them. It
may sometimes happen that the Corporation/Chief Engineer, does not
agree with the views of its/his subordinate to officers and may have an
entirely different view as far as the interpretation of a clause in this
agreement is concerned. In such cases, the Corporation/Chief
Engineer, shall have the full right to revoke the decisions made by
each/his subordinate officers and direct adjustments in payment
based on the final decisions of Corporation/Chief Engineer, such
decisions of the Corporation/Chief Engineer, shall be communicated
to the contractor under title “Decision revoked by Chief
Engineer/Corporation” and shall be binding on the contractor.
b) Subject to the above stipulations, if the contractor consider
any record or ruling of the Corporation/Chief Engineer of its/his
subordinate so authorized in respect of any of the provisions of this
contract to be not in accordance with provisions of this agreement or
considers any work demanded of him by the Chief engineer, to be
outside the requirements of the Contract, he shall immediately upon
such of ruling being made or such work being demanded, as in writing
ARB.P. No.3/2017
M/s Gammon India Ltd. v. NEEPCO Ltd.
for written instructions or decisions on receipt whereof he shall
proceed without delay to conform to the record or to perform the work
demanded, at within 15 days after the date of receipt of the written
instructions or decisions he may file written protest with the Chief
Engineer, stating clearly and in detail the basis of his objection. Except
for such protests or objections; as are made on record in the manner
herein specified, and within the time limit stated, the records rulings,
instructions or decisions of the Corporation of Chief Engineer, shall be
final and conclusive. Instructions and/or decisions of the Chief
Engineer contained in the (illegible) to the contractor shall be
considered (illegible) instructions or decisions, subject to protest……
c) If the Contractor is dissatisfied with the final decisions of the
Chief Engineer, or Corporation on the protest or objection made by the
Contractor in accordance with the procedure prescribed in paragraph
66.1 (b), the Contractor may within fifteen days after receiving notice
of such decision, give notice in writing to the Chief Engineer, requiring
that the matter be submitted to arbitration and furnishing detailed
particulars of this dispute or difference specifying clearly the point of
issue. If the Contractor fails to give such notice to the Chief Engineer
within the period of 15 days as stipulated above, the decision of the
Chief Engineer, shall be final and conclusive and binding on the
Contractor. Thereafter such issues shall not be subjected to
arbitration.
d) Arbitration shall be affected by an arbitration Board
consisting of two members. One selected by the Corporation and the
other by the contractor. The provisions of the Indian Arbitration Act,
1940 and the rules thereunder shall apply for appointment of Umpire
and all matters relating to the arbitration proceedings.
e) No arbitration proceedings shall be commended without
settling the specific terms of reference.
f) The cost of such arbitration shall be borne by the parties or
party as decided by the Arbitration Board.”
From the material placed on record, it is clear that the petitioner
indeed made the requests to the respondent to proceed for arbitration
in accordance with the said arbitration agreement but the respondents
failed to take the necessary steps. In the totality of circumstances and
for the reason of failure of the procedure for appointment of arbitrator, it
is just and proper that an independent arbitrator be appointed to
adjudicate upon and decide the dispute between the parties including
their claims, counter claims and objections.
ARB.P. No.3/2017
M/s Gammon India Ltd. v. NEEPCO Ltd.
During the course of submissions, learned senior counsel Mr. VK
Jindal appearing for the respondent has submitted that looking to the
limited scope of enquiry in this application, irrespective of other
objections, he has conferred with Hon’ble Dr. Justice Mukundakam
Sarma, a former Judge of Supreme Court of India residing at Bungalow
No.105 New Motibagh, New Delhi-23, who has agreed to take up the
arbitration in this matter. Mr. HL Shangreiso, learned counsel
appearing for the petitioner has not objected to the suggestion made
by the learned counsel for the respondent except stating his
reservations about the cost factor for conducting the arbitration at New
Delhi.
Looking to the overall facts and circumstances of the case where
the registered office of the company is said to be situated at Mumbai,
situs of the Arbitrator at New Delhi cannot be said to be working to the
prejudice of the petitioner. All other aspects relating to the cost of
proceedings and fees are left to be determined by the arbitrator while
keeping in view the law applicable, including the provisions contained
in Fourth Schedule to the Arbitration and Conciliation Act, 1996, [as
amended by the Arbitration and Conciliation (Amendment) Act, 2015].
With
the
observations
foregoing,
Hon’ble
Dr.
Justice
Mukundakam Sarma, a former Judge of Supreme Court of India is
appointed to act as the Sole Arbitrator to adjudicate upon and decide
all the disputes between the parties including their claims, counter
claims and objections relating to the contract in question. The
requirements of the Arbitration and Conciliation Act, 1996, [as
amended by the Arbitration and Conciliation (Amendment) Act, 2015]
shall be complied with by all concerned.
ARB.P. No.3/2017
M/s Gammon India Ltd. v. NEEPCO Ltd.
This arbitration petition stands disposed of accordingly.
Needless to observe that all the questions arising between the
parties in this matter shall remain open for determination in the
arbitration proceedings.
CHIEF JUSTICE
Lam
Item No.3
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.