The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
8. Leamed counsel for the respondent company has relied upon Clause 5.9.4.3 of the General Terms and Conditions of Supply to contend that the sard dues are recoverable pursuant to the notice of termination of HT Service Connection dated 30.06.2025. The question of adjudication of the outstanding dues should not be gone into by this Court in exercise of writ jurisdiction in the present Writ Appeal. This dispute may be agitated by the appellant before the Consumer Grievance Redressal Forum having jurisdiction over the srtbject.
9. Therefore, upon heanng the learned counsel for the parties and after going through the relevant records and the proceedings dated I I .12.2025 whereby sanction has been accorded in favour of IWs. Al- .w HCJ (AKIS, 4 &, GMM, J W.A-No-,r65 of 2026 Meezan Metal Industry to undertake quarrying operations, we are of the opinion that the appellant shall make a fresh application for HT Service Connection to its premises as per the conditions of the General Terms and Conditions of Supply which require payment of outstanding dues against the previous Service Connection. If the apptlllant makes the said I payment, the respondent company would consider grant of fresh electricity Service Connection in favour of the appellant without any delay subject to other formalities and compliance being made by the appellant. However, the dispute on the computation of the bill totalling to Rs.27 ,47 ,730/- be raised by the appellant before the Consumer Grievance Redressal Forum. The deposit of Rs.27,47,7301- would be subject to the outcome of the decision of the Consumer Grievance Redressal Forum. Having said so, we are of the opinion that the observations made by the leamed writ Court as to deliberate suppression of facts for not disclosing the communication dated 12.12.2024 of the Assistant Director of Mines and Geology were not warranted as there was no communication of the letter dated 13.12.2024 …
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
*Fn -
[ 3488 ]
IN THE HIGH COURT FOR THE STATE OF TELANGANA
AT HYDERABAD
THURSDAY, THE TWENTY THIRD DAY OF APRIL
TWO THOUSAND AND TWENTY SIX
PRESENT
THE HONOURABLE THE CHIEF JUSTICE SRI APARESH KUMAR SINGH
AND
THE HONOURABLE SRI JUSTICE G.M. MOHIUDDIN
WRIT AP PEAL NO: 466 OF 2026
writ Appeal under clause 15 of the Letters Patent Against order Dated
28t11t2025 in WP No 23764 of 2025. on the file of the High Court.
Between:
M/s Bismilla and Shakthi Metal lndustries, Previously M/s Venkateswara Metal
Crushing Bearing HT Service No MDK2521 At Sy No 132 Lingareddypet Village
Manohaiabad Mindal Medak District Rep by its Managing Partner Ghouse Khan
sic Sri Qutbuddin Khan aged about 40 years occBusiness Rl/o H. No. 944lBl8l1
NFS Colony, Hakeempet, Tolichowki, Hyderabad
...APPELLANT
AND
1. Telangana state Southern Power Distribution company Limited, Vidyut Soudha
Somajiguda Hyderabad Rep by its Chairman and Managing Director'
2. Telangana state southern Power Distribution company Limited corporate
officel tospoCl, Mint Compound, Hyderabad. Rep. by its Chief General
Manager (Revenue).
3. Telangana State Southern Power Distribution Company Limited, TGSPDCL,
Tooprin, Medak District. Rep. by its Divisional Engineer (Operation)'
4. Telangana state southern Power Distribution company Limited TGSPDCL,
Tooprln, Medak District, Rep. by its Superintending Engineer (Operation)'
...RESPONDENTS
q:?
l.A. NO: 2 OF 2026
Petition under Section 151 CPC praying that in the circumstances stated in the
affidavit filed in suppo( of the petition, the High Court may be pleased to suspend the
lmpugned Order in W.P.No. 23764 of 2025 dated. 28-11-2025 passed by the Learned
Single Judge pending disposal of Writ Appeal.
l.A. NO: 3 OF 2026
Petition under section 151 cPC praying that in the circumstances stated in the
affidavit filed in support of the petition, the High court may be pleased to direct the
respondents to restore power supply to the Appellant / Petitioner HT Service No.
MDK2521 by suspend the impugned notice vide Lr.No. SE/O.P. No./MD[(SAO/IAOHT/F NO MDL-2521|D.N0 422125-26 Dated.30-06-2025 issued by the 4th respondent,
pending disposal of the Writ Appeal.
Counsel for the Appellant : SRI AMARAGANT MALSOOR
Counsel for Respondents: SRI N.SREEDHAR REDDY,
SC FOR TSSPDCL
The Court made the following: JUDGMENT
E*::;*i ^
IN THE HIGH COURT FOR TIIE STATE OF TEI-A]\IGANA
ATHYDERABA.D
THE HON'BLE THE CHIEF JUSTICE SRI APARESH KT]MAR SINGH
AND
TIIE HON'BLE SRI JUSTICE G.M.MOTIITJDDIN
WRIT APPEAL No.466 of 2026
DATED :23.04.2026
Between:
IWs. Bismilla and Shakthi Metal Industries
... Appellant
A-N[D
Telangana State Southern Power
Distribution Company Limited and four others
.., Respondents
JT]DGMENT:
Sri Amaragani Malsoor Goud, leamed counsel appears for
appellant.
Sri N. Sreedhar Reddy, leamed Standing Counsel for Telangana
State Southem Power Distribution Company Limited appears for
respondents.
2.
The appellant is the petitioner who filed Writ Petition No.23764
of 2025 challenging the notice of termination of its electricity HT
Service Connection and for restoration thereof. The said Writ Petition
was dismissed on grounds of suppression of facts and misleading the
Court.
3.
The appellant had HT Service Connection bearing No.
MrDK252L.Its electricity connection was disconnected with effect from
HCJ {AIGS. JI & GMM. J
W.A.No 466 of 2O26
13.12.2024 on account of non-pa)ment of dues. Writ Petition No.l201
of 2025 assailing thc said disconnection of electric power supply to the
appellant was disposcd of with a direction to the appellant to deposit an
amount of Rs.2,43,153/- pertaining to the second instalment as per the
proceedings dated 13.12.2024 within a period of one week from
20.01.2025 and upon its depositing the said due amount, the respondent
Company shall forthwith restore the power supply to HT Service
Comection belonging to the appellant's crushing unit situated in the
land in Survey No. 132 of Lingareddypet Village, Manoharabad Mandal,
Medak District. The appellant was also directed to comply with the
instructions issued in the proceedings dated 11.12.2024 and pay the third
instalment of Rs.2,43,153/- on or before 12.02.2025, failing which, the
respondent Company shall take due course of action against the
appellant
4.
The appellant claims to have deposited the first instalment of
Rs.3,00,000/- which, according to him, did not lead to restoration of its
electricity connection. Thereafter, as per the case of the respondent
company, based on the lefter dated 12.12.2024 addressed by the
Assistant Director of Mines and Geology, Medak, the electric power
supply to HT Service Connection of the appellant was disconnected for
not having any EC, CFO and CFE for operating the stone crusher unit.
The respondent company has taken a plea that after deposit of the first
instalment, pursuant to the order of the leamed writ Court in the earlier
B€ffii,
HcJ lAKrs, J} & cMM, J
w.A- No.rt6,6 of 2026
round, its electriciry connection was restored and thereafter,
disconnected with effect from 23.12.2024. This is a disputed question in
view of the stand of the parties. The disconnection of electric power
supply remained all along till the notice was issued on 30.06.2025. This
was made subject matter of W.P.No.23764 of 2025.
5.
In the said Writ Petition, based on the counter-affidavit filed by
the respondent company, vide order under appeal dated 28.11.2025, the
learned writ Court concluded that the appellant has invoked the writ
jurisdiction by misrepresentation and suppression of facts wasting
judicial time. Therefore, the appellant was not entitled to any relief. The
said Writ Petition was dismissed with costs of Rs.2,00,000/- to be
deposited with the three different associations of this High Court.
6.
Learned counsel for the appellant has pointed out that after
dismissal of the Writ Petition by the leamed writ Court vde order under
appeal dated 28.11.2025, the Assistant Director of Mines and Geology,
Medak, vide proceedings dated I 1.12.2025 accorded sanction to
M/s. Al-Meezan Metal Industry to continue the quarrying operations for
building stone and road metal over an extent of 1.00 Hebtare in Suwey
No.t32 of Lingareddypet Village, Manoharabad Mandal, Medak
District, for a further period of twenty (20) years with effect from
30.07 .2021 to 29.07 .2041 subject to the satisfaction
of all terms and
conditions laid down in Telangana Minor Mineral Concession Rules,
1966, and subsequent Government Orders and executive instructions
HCJ (AKiS, J)& CMM, J
W.A-No 456 of 2026
from time to time. This letter is taken on record. Be it also indicated here
that though the lettcr dated 12.12.2024 of the Assistant Director of
Mines and Geology, Medak, was communicated to the respondent
company, there was no officral communication of the said letter to the
appellant as is apparent from perusal of the said letter and there was no
specific averment to that effect in the counter-affidavit.
7.
On the other hand, there is a dispute about restoration of electric
pou.er supply to HT Service Connection of the appellant after the order
passed in Writ Petition No,l201 of 2025. The appellant contends that a
bill for pal,rnent of outstanding dues of Rs.27,47,7301- has been raised
during the period ,rf disconnection of power supply without actual
consumption.
8.
Leamed counsel for the respondent company has relied upon
Clause 5.9.4.3 of the General Terms and Conditions of Supply to
contend that the sard dues are recoverable pursuant to the notice of
termination of HT Service Connection dated 30.06.2025. The question
of adjudication of the outstanding dues should not be gone into by this
Court in exercise of writ jurisdiction in the present Writ Appeal. This
dispute may be agitated by the appellant before the Consumer Grievance
Redressal Forum having jurisdiction over the srtbject.
9.
Therefore, upon heanng the learned counsel for the parties and
after going through the relevant records and the proceedings dated
I I .12.2025 whereby sanction has been accorded in favour of IWs. Al-
.w
HCJ (AKIS, 4 &, GMM, J
W.A-No-,r65 of 2026
Meezan Metal Industry to undertake quarrying operations, we are of the
opinion that the appellant shall make a fresh application for HT Service
Connection to its premises as per the conditions of the General Terms
and Conditions of Supply which require payment of outstanding dues
against the previous Service Connection. If the apptlllant makes the said
I
payment, the respondent company would consider grant of fresh
electricity Service Connection in favour of the appellant without any
delay subject to other formalities and compliance being made by the
appellant. However, the dispute on the computation of the bill totalling
to Rs.27 ,47 ,730/- be raised by the appellant before the Consumer
Grievance Redressal Forum. The deposit of Rs.27,47,7301- would be
subject to the outcome of the decision of the Consumer Grievance
Redressal Forum. Having said so, we are of the opinion that the
observations made by the leamed writ Court as to deliberate suppression
of facts for not disclosing the communication dated 12.12.2024 of the
Assistant Director of Mines and Geology were not warranted as there
was no communication of the letter dated 13.12.2024 to the appellant by
either the Assistant Director of Mines and Geology or the respondent
company. The observation of the leamed writ Court in respect of
deliberate suppression of fact by the appellant deserves to be removed.
Therefore, in view of the nature of the order passed today, the
observation of the leamed writ Court as regards the suppression of fact
and the imposition of costs of Rs.2,00,000/- are set aside.
I
I
HCJ {^Krs, Jl & GMM, J
W.A.No 466 of 2026
The Writ Appeal is disposed of in the aforesaid terms. There shatl
be no order as to costs
Miscellaneous applications, if any pending, shall stand closed.
SD/. A.V.S. PRASAD
D PUTY REGISTRAR
//TRUE COPY//
ECTION OFFICER
To,
Southern
The Chairman and Managing Director' Telangana State
Hyderabad'
Power
OirtriOrtion Company Limitei' Vidyut Soudha Somajiguda
Telangana State Southern Power
2 The Chief General Manager (Revenue)
Mint Compound'
Distribution Company fimiiJ Corporate Office' TGSPDCL'
Hyderabad..
State Southern Power
J . The Divisional Engineer (Operation) Teiangana.
District '
Di.tribrtion Company Limitea, ICSpOCL, Toopran' Medak
State Southern
. The Superintending Engineer (Operation), Telangana
Medak District'
Oi.iriOrtion Company Li;ited TGSPDCL' Toopran'
t . One CC to SRI AMARAGANI MALSOOR' Advocate' [OPUCI
( SC FOR TGSPDCL) [OPUC]
6 . One CC to SRI N.SREEDHAR REDDY
7 Two CD CoPies
BSK
GJP
q*
Power
HIGH COURT
DATED: 2310412026
(_: .
)
,
JUDGMENT
WA.No.466 of 2026
DISPOSING OF THE WRIT APPEAL
WITHOUT COSTS
J
rot
s
lr :
,,
u ri ,:.t: I -tr:
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.