IN THE HIGH COURT OF JAMMU& KASHMIR AND LADAKH
AT SRINAGAR
…….
WP (C) No. 2009/2020
1. Kulsooma D/O Gh. Rasool Bhat.
2. Kazim Bhat S/O Mohammad Bhat
Both residents of Shariefabad, Budgam.
3. Asgar Dar S/O Mohammad Dar
R/O Durbal, Budgam.
……. Appellant(s)/Petitioner(s)
Through: Mr. Tasaduq H. Khawja, Advocate with
Mr. Iman Abdul Muizz and
Mr. Naseer Ul Akbar, Advocates .
Versus
1. Union Territory of Jammu and Kashmir through Secretary
to Government, Public Works Department, Irrigation and Flood
Control Civil Secretariat, Srinagar/Jammu.
2. Chief Engineer, Irrigation and Flood Control Civil Secretariat,
Srinagar.
3. Executive Engineer, Flood Spill channel (FSC) Division Narbal.
4. Collector, Land Acquisition, PHE, Irrigation and Flood Control,
Kashmir.
5. Dy. Commissioner cum District Collector, Budgam, Kashmir.
6. Tehsildar, Budgam.
……Respondent(s)
Through: Mr. Bikramdeep Singh, Dy. AG with
Ms. Nowbahar Khan, Assisting counsel
CORAM: HON’BLE MR. JUSTICE JAVED IQBAL WANI, JUDGE
JUDGMENT
07.03.2025.
(Oral)
1. The petitioners in the instant petition have implored for the following
reliefs:(i)
(ii)
Abdul Rashid Ganaie
I attest to the accuracy and
authenticity of this
document
“A writ of the nature of mandamus or any other appropriate
writ commanding the respondents to take all necessary steps
for payment of compensation, either by way of compulsory
acquisition mode or by private negotiation
for the
remaining portion of land falling in then Khasra No.
330,331 and 309 in estate Bemina that has been taken over
by respondents in connection with Flood Spill Channel but
for which no compensation has been paid as yet.
In alternative an appropriate writ directing the respondents
to return the possession of land back to petitioners after
removing the earth-filling there from and pay adequate
WP ( C ) No. 2009/2020
compensation at the rate of RS. 10,000/ per kanal per year
on account of damage caused to property as also on account
of use and occupation of petitioners’ land by the
respondents during the intervening period”.
2. The facts under the shade and cover of which the aforesaid reliefs have
been prayed and as are stated in the petition are that the petitioners 1 & 2
claimed to have jointly owned and possessed 14 Kanal and 17 marlas of
land covered under Survey No. 330 and 331 in estate Bemina, District
Budgam, out of which 4 Kanals and 13 Marlas were in Survey No. 330 and
remaining 10 Kanals and 4 marlas were in Survey No. 331, having been
devolved upon the petitioners by inheritance.
It is being next state that the petitioner 3 with his co-sharers as well owned
and possessed 14 Kanals and 5 marlas of land in Survey No. 309, which
consisted of 19 Kanals and 09 marlas, in estate Bemina, Budgam.
It is being further stated that somewhere in 1988-89, the Government of
Jammu and Kashmir initiated a process of construction of leftover portion
of Jhelum Flood Spill Channel in estate Bemina and onwards which flood
channel have had been conceived and constructed many decades back to
avoid floods in the Srinagar city, and the construction of the portion from
Bemina District Budgam towards north side up to Zainakote, Srinagar, of
the proposed Flood Spill Channel had been left midway to be completed
in future and in furtherance thereof the said process for completion of
leftover portion was initiated somewhere in 1988-89.
It is next stated by the petitioners that out of the aforesaid land, owned and
possessed by them some land had already been acquired for the
construction of the Flood Channel in question and that out of Survey No.
309, land measuring 10 Kanals and 14 Marlas was supposed to come under
Abdul Rashid Ganaie
I attest to the accuracy and
authenticity of this
document
WP ( C ) No. 2009/2020
the construction of Flood
Channel and
was formally sought to be
acquired, whereas, similarly, land measuring 1 Kanal and 18 marlas, and 7
Kanals and 02 marlas was sought to be formally acquired from Survey
No. 330 and 331, respectively.
It is being further stated that somewhere in the year 1989, the petitioners
were paid compensation qua the land acquired by the respondents,
measuring 10 Kanals and 14 marlas out of Survey No. 309, 01 Kanal and
18 marlas from Survey No. 330 and 07 Kanals and 02 marlas from Survey
No. 331, however, the remaining land then owned by the petitioners
being 03 Kanals and 11 marlas in Survey No. 309, 02 Kanals and 15
marlas in Survey No. 330 and 03 Kanals and 02 marlas in Survey No. 331,
was not acquired
by the respondents and the petitioners , as such
continued to remained in possession thereof as owners.
It is being further stated that though the land was acquired by the
respondents and the compensation to the land owners including the
petitioners was paid in the year 1988-89 and that no further construction at
ground level of the Flood Channel upto Zainakot was undertaken, a
process thereof however, came to be initiated by the respondents in the
year 2007-08 and the land acquired in the year 1988-89 of the petitioners
by the respondents was actually taken over by the respondents in this
regard.
It is being next stated by the petitioners that while constructing the Flood
Channel in question, the respondents did not restrict the construction of the
Channel over the already acquired land, but also took over the remaining
Abdul Rashid Ganaie
I attest to the accuracy and
authenticity of this
document
WP ( C ) No. 2009/2020
portion of the land owned and possessed by the petitioners in order to have
the smooth alignment of the Flood Channel.
It is being further stated by the petitioners that the said remaining land of
the petitioners was however taken over without following any formal
acquisition proceedings and that the petitioners part with the said land only
upon the assurance of the respondents
that since formal acquisition
proceedings are likely to take some time yet compensation qua the land
would be paid to them, as a consequence whereof the petitioners did not
object to either taking over of the land in question or the process of the
construction of the Flood Channel.
It is being next stated by the petitioners that though the respondents
initiated a process for payment of compensation for the land in question in
favour of the petitioners and in this regard a report was drawn by
respondent 3, detailing out therein the total land over which the Flood Spill
Channel had been constructed as also the area of the land for which the
compensation had been paid to the land owners as well as remaining land
for which compensation had not been paid.
It is being further stated by the petitioners that while the construction of the
Flood Spill Channel was in progress, settlement proceedings were
undertaken by the Revenue Department to update its record and in order to
bring it at par to the ground realities and before compensation, qua the land
in question would be paid by the respondents to the petitioners, said
settlement proceedings got concluded.
It is next being stated by the petitioners that the Flood Channel stands
constructed during the course of the settlement proceedings and a separate
Abdul Rashid Ganaie
I attest to the accuracy and
authenticity of this
document
WP ( C ) No. 2009/2020
survey number came to be carved out in the said settlement proceedings,
qua the land in question, being survey No. 659 qua the land measuring
142 Kanals and 10 marlas, however, on account of the settlement
proceedings the said land was shown in possession of the Flood Control
Department instead of the original, actual owners including the petitioners
herein.
It is next stated by the petitioners that on account of the settlement
proceedings the new survey numbers to the entire land, not only included
the land earlier acquired by the respondents for construction of the Flood
Channel, but also included the land in question which was taken over by
the respondents from the petitioners in the year 2007-08 upon which the
petitioners and the other land owners had the absolute title as owners
thereof.
It is being further stated by the petitioners that since the leftover land in
question of the petitioners was taken over by the respondents without any
compensation, the petitioners approached the respondents for payment of
compensation thereof, however, the respondents did not pay the same to
the petitioners while taking note of the fact that the land in question stands
recorded in the name of State during settlement proceedings and not in the
name of the petitioners.
It is being stated by the petitioners that faced with the said situation they
approached the respondents 6 for clarification in this regard, whereupon
respondent 6 solicited a report providing therein that while the petitioners
have been given compensation to some portion of their land, the remaining
portion of the land of the petitioners has been recorded in the name of State
Abdul Rashid Ganaie
I attest to the accuracy and
authenticity of this
document
WP ( C ) No. 2009/2020
during settlement proceedings, even though no compensation had been
paid to them for the said remaining land.
It is being stated that being satisfied that the compensation had been paid
for the land acquired from the petitioners, the respondent 6 took up the
matter with respondent 4 for payment of compensation to the petitioners
for the land in question which had been taken over by the respondents in
the year 2007-08 without formally acquiring the same during the process
of settlement.
It is further stated by the petitioners that since the revenue authorities were
not sure about the area of the land for which the compensation have been
paid to the petitioners and the other land owners, as such, an information
in this regard came to be sought from the respondent 4, in response
whereof the respondents 3 & 4 furnished the details of compensation paid
to the land owners including the petitioners, confirming that the
compensation stands paid in respect of land measuring 01 Kanal 18 marlas
in Survey No. 330, 07 Kanals 02 in Survey No. 331 and 10 Kanals 14
marlas in Survey No. 309 in favour of the petitioners.
It is being further stated that though it had been conclusively established
that the petitioners had been paid compensation for the land which had
been acquired by the respondents formally and not for the land in question
taken over by the respondents in the year 2007-08, the petitioners expected
the payment of compensation for the land in question to them which
however, was not paid, leaving no option open to the petitioners except to
seek the indulgence of this Court through the medium of instant petition on
the premise that the non-payment of compensation to them for their
Abdul Rashid Ganaie
I attest to the accuracy and
authenticity of this
document
WP ( C ) No. 2009/2020
proprietary land by the respondents in essence amounts to refusal of
payment of compensation to them against their immoveable property taken
over by the respondents without formally acquiring the same and, thus,
constituting violation of their right to property.
3. Objections have been filed by the respondents 1 to 3 and 6 to the petition.
4. In the objections filed by the respondents 1-3, it is being admitted by the
respondents that the petitioners were paid compensation for the land which
came to be acquired formally, however, the compensation sought by the
petitioners for the land in question is not payable to them, in that, the
petitioners are not recorded as the owners of the said land as the land in
question is recorded as “Gair Mumkin Flood Channel”.
5. In the objections filed by respondent 6, a similar stand has been taken as
has been taken by the respondents 1-3.
Heard the learned counsel for the parties and perused the record.
6. Insofar as, the specific plea of the petitioners raised in the petition, qua the
land measuring 03 Kanals and 11 marlas in Survey No. 309, 02 Kanals and
15 marlas in Survey No. 330 and 03 Kanals and 02 marlas in Survey No.
331, is concerned, the same was not acquired by the respondents in the
year 1988-89 and the petitioners, as such, continued to remain in
possession thereof as owners and continued to be recorded as owners
thereof in the relevant revenue records which however after the settlement
proceedings came to be shown as “Maqbooza Mehkamui Flood Control as
Gair Mumkin Flood Channel”.
7. Record reveals that the respondents have not specifically and in explicit
terms denied that the petitioners are and were not the recorded owners of
Abdul Rashid Ganaie
I attest to the accuracy and
authenticity of this
document
WP ( C ) No. 2009/2020
the land in question and, as such, are not entitled to the compensation
thereof. What is being disputed and denied by the respondents in the
aforesaid reply(s) filed to the petition is that the land in question is
recorded in the revenue records as “Maqbooza Mehkamui Flood Control
as Gair Mumkin Flood Channel”, which however goes in conflict with the
specific reports of the respondents 3,4 & 6, that the land in question, in
fact, has been and is owned by the petitioners notwithstanding its having
been recorded as “Gair Mumkin Flood Channel” under the occupation of
the Irrigation and Flood Control, Department. Thus in presence of this
position obtaining in the matter qua the land in question on any premise
including on account of applicability of SRO 154 of March 1986 and SRO
109 of 1987, pressed into service by the respondents, the effect of which
SRO’s have been taken cognizance of
and considered by the two
Coordinate Benches of this Court in case titled as “Raja Bano v. Union
Territory of Jammu and Kashmir” being WP( C) No. 177/2023, decided
on 12.08.2024, and “Ghulam Ahmad Bhat & Others v. State of J&K &
Others”, being OWP No. 1441/2012, decided on 22.12.2023, wherein it
has been inter alia held that merely recording the land as “Gair Mumkin
Nala” would not ipso facto transfer the title of the land from the petitioners
therein to the respondents therein while relying upon the settled position of
law that the right of property is a constitutional right, enshrined in Article
300-A of the Constitution and a person can be divested of ownership of the
property only in accordance with the provisions of law entitling the land
owners to the payment of compensation while relying upon the judgment
passed by the Apex Court in case titled Vidya Devi vs. State of Himachal
Abdul Rashid Ganaie
I attest to the accuracy and
authenticity of this
document
WP ( C ) No. 2009/2020
Pradesh & Others, reported as (2020)2 SCC 569, which being relevant
germane herein is also referred and relied in the instant case as well
hereunder:“12.1. The appellant was forcibly expropriated of her property
in 1967, when the right to property was a fundamental right
guaranteed by Article 31 in Part III of the Constitution. Article
31 guaranteed the right to private property, which could not be
deprived without due process of law and upon just and fair
compensation.
12.2. The right to property ceased to be a fundamental right by
the 9 Constitution (Forty-Fourth Amendment) Act, 1978,
however, it continued to be a human rights in a welfare State,
and a constitutional right under Article 300-A of the
Constitution. Article 300-A provides that no person shall be
deprived of his property save by authority of law. The State
cannot dispossess a citizen of his property except in accordance
with the procedure established by law. a The obligation to pay
compensation, though not expressly included in Article 300-A,
can be inferred in that Article.
12.3. To forcibly dispossess a person of his private property,
without following due process of law, would be violative of a
human right, as also the Constitutional right under Article 300A of the Constitution. Reliance is placed on the judgment in
Hindustan Petroleum Corpn. Lid. v. Darius Shapur Chenal
wherein this Court held that: (SCC p. 634, para 6) "6.... Having
regard to the provisions contained in Article 300-A of the
Constitution, the State in exercise of its power of "eminent
domain" may interfere with the right of property of a person by
acquiring the same but the same must be for a public purpose
and reasonable compensation therefore must be paid."
(emphasis supplied)
12.4. In N. Padmamma v. S. Ramakrishna Reddy, this Court
held that: (SCC p. 526, para 21) "21. If the right of property is a
human right as also a constitutional right, the same cannot be
taken away except in accordance with law. Article 300-A of the
Constitution protects such right. The provisions of the Act
seeking to divest such right, keeping in view of the provisions of
Article 300-A of the Constitution of India, must be strictly
construed."
(emphasis supplied)
12.5. In Delhi Airtech Services (P) Ltd. v. State of U.P., this
Court recognised the right to property as a basic human right in
the following words: (SCC p. 379, para 30) "30. It is accepted in
every jurisprudence and by different political thinkers that some
Abdul Rashid Ganaie
I attest to the accuracy and
authenticity of this
document
WP ( C ) No. 2009/2020
amount of property right is an indispensable safeguard against
tyranny and economic oppression of the Government. Jefferson
was of the view that liberty cannot long subsist without the
support of property.
"Property must be secured, else liberty cannot
subsist" was the opinion of John Adams. Indeed the
view that property itself is the seed-bed which must
be conserved if other constitutional values are to
flourish, is the consensus among political thinkers
and jurists."
(emphasis supplied)
12.6. In Jilubhai Nanbhai Khachar v. State of Gujarat, this
Court held as follows: (SCC p. 627, para 48) "48. ... In other
words, Article 300-A only limits the powers of the State that no
person shall be deprived of his property save by authority of
law. There has to be no deprivation without any sanction of law,
Deprivation by any other mode is not acquisition or taking
possession under Article 300-A. In other words, if there is no
law, there is no a deprivation."
(emphasis supplied)
12.7. In this case, the appellant could not have been forcibly
dispossessed of her property without any legal sanction, and
without following due process of law and depriving her payment
of just compensation, being a fundamental right on the date of
forcible dispossession in 1967.
12.8. The contention of the State that the appellant or her
predecessors had "orally” consented to the acquisition is
completely baseless. We find complete lack of authority and
legal sanction in compulsorily divesting the appellate of her
property by the State.
12.9. In a democratic polity governed by the rule of law, the
State could not have deprived a citizen of their property without
the sanction of law. Reliance it placed on the judgment of this
Court in Tukaram Kana Joshi v. MIDCS wherein it was held
that the State must comply with the procedure for acquisition,
requisition, or any other permissible statutory mode, The State
being a welfare State governed by the rule of law cannot
arrogate to itself a status beyond what is provided by the
Constitution.
12.10. This Court in State of Haryana v. Mukesh Kumari held
that the right to property is now considered to be not only a
constitutional or statutory right, but also a human right. Human
rights have been considered in the realm of individual rights
such as right to shelter, livelihood, health, employment, etc.
Human rights have gained a multi-faceted dimension…..”
Abdul Rashid Ganaie
I attest to the accuracy and
authenticity of this
document
WP ( C ) No. 2009/2020
8. Viewed thus, for what has been observed, considered and analyzed
hereinabove, the instant petition succeeds.
9. Accordingly, the petition is allowed and the Respondent-Irrigation and
Flood Control Department is commanded to send an indent to the
competent authority for initiating the process of acquisition of the land in
question of the petitioners, detailed out in the preceding paragraphs within
a period of six weeks from the date a copy of this judgment is served upon
them, whereupon the competent authority upon receipt of such indent shall
proceed with the acquisition of the land in question in accordance with
present applicable law and pass appropriate award in accordance with law.
10. It is made clear that the respondents, if they chose so, may take recourse to
the private negotiation in the matter instead of taking recourse to the
formal acquisition proceedings under the relevant law.
11. The respondents shall conclude the aforesaid process, preferably within a
period of three months from the date of passing of this judgment.
12. Disposed of along with connected CM(s).
13. Record produced by the learned counsel for the respondents is returned
back in the open Court.
(Javed Iqbal Wani)
Judge
Srinagar
07.03.2025.
“Ab. Rashid PS”
Whether the judgment/order is speaking;
Yes/No
Whether the judgement/order is reportable; Yes/No
Abdul Rashid Ganaie
I attest to the accuracy and
authenticity of this
document
This page is for informational and research purposes only and does not constitute legal advice.