[2026:JHHC:2563]
IN THE HIGH COURT OF JHARKHAND AT RANCHI
W.P. (C) No. 5606 of 2011
------
Jharkhand State Electricity Board through its Law Officer, Mithilesh
Kumar S/o Sri R.B. Choudhary, resident of Sector- II Dhurwa, P.O.
Dhurwa, P.S. Jagarnathpur, District-Ranchi officiating near Jharkhand
State Electricity Board, near Nepal House, P.O. & P.S. Doranda, District
Ranchi.
... Petitioner
Versus
M/s. Mangalam Plastics having its work place at Hardag, Hatia through
its proprietor Jacob Mathew, S/o. Sri M.P. Mathew, R/o- 3/50 Birsa
Nagar, P.O. Hatia, P.S. Jagarnathpur, Ranchi, Jharkhand.
... Respondent
CORAM : HON’BLE MR. JUSTICE SUJIT NARAYAN PRASAD
------
For the Petitioner
For the Respondent
: Mr. O.P. Tiwari, Advocate
: Mr. Dhananjay Kr. Pathak
-----st
11/Dated: 21 January, 2026
1. The instant writ petition has been filed under Article 226 of the
Constitution of India directed against the order passed by the Vidyut
Upbhokta Shikayat Niwaran Forum, (herein referred as VUSNF)
Ranchi dated 24.02.2011 in case no. 13 of 2010 by which the bills
issued for the month of November 2009 to February 2010 have been
quashed and JSEB (writ petitioner herein)
was directed to
refund/adjust the amount charged and recovered to the tune of Rs.
83455/- with interest. Further, the quashing of the order dated
19.07.2011 passed by the Electricity Ombudsman in appeal has also
been sought for by which order dated 24.02.2011 has been
confirmed.
[2026:JHHC:2563]
2. The brief facts of the case as per the pleading made in the writ
petition reads as:
(i)
The writ petitioner is a deemed licensee cum transmission
utility which is engaged in the business of generation,
transmission and distribution of electricity to its consumers
within the territorial jurisdiction of the State of Jharkhand and
the respondent(petitioner before VUSNF) is a consumer of the
writ petitioner JSEB and had taken an electrical connection
bearing Consumer no. HK 5429 under HTS-1 Mode of tariff
having contract demand of 105 KVA and the supply of electricity
has commenced w.e.f. 04.09.2007.
(ii)
The HT agreement to that effect was executed between the writ
petitioner and the respondent namely M/s. Mangalam Plastics
on 25.07.2007.
(iii) It is the case of respondent before the VUSNF that maximum
demand of consumer for the month of November, 2009 was
recorded more than the 115% of the contract dermanl therefore
the petitioner/JSEB charged the maximum demand on the basis
of actual recorded K.V.A. i.c. 128.85 K.V.A. because if the said
exceeded demand was supposed to be treated as contract
demand of the respondent, the only burden which would have
been imposed upon the consumer/complainant/respondent is
the maximum demand/KVA charges and nothing else.
(iv) It is further case of the respondent/consumer that the aforesaid
[2026:JHHC:2563]
bill for the month of November, 2009 of consumer/respondent
was arbitrarily charged Rs. 12.262/- without any basis under the
heading "correction if any”. Similarly, the petitioner/JSEB in the
same arbitrarily fashion has charged in the bills of December,
2009, January, 2010 and February, 2010 amounting to Rs.
22,894, Rs 21,710/- and Rs. 26,589/- respectively under the
(v)
heading “correction if any”.
Consequently, the respondent had approached the writ
petitioner/ JSEB for redressal of its grievances and the writ
petitioner/ JSEB replied that the aforesaid amounts have been
charged under the heading correction if any "on energy units by
calculating the guarantee charges on the basis of exceeded KVA".
(vi) But according to the consumer/respondent no guarantee energy
charges would have been raised on that basis of the contract
demand
of
HT
consumer.
According
to
the
respondent/consumer if any consumer exceeds its sanctioned
load, the exceeded load shall be treated as contract demand for
the purpose of maximum demand charges for six months and its
impact would come only upon KVA charges and minimum
monthly charges.
(vii) It is the case of the respondent that the writ petitioner/JSEB has
already charged maximum demand charges on the basis of
exceeded load every month from November, 2009 to February,
2010 besides the unit charges recorded in the meter and as such
[2026:JHHC:2563]
the maximum realizable charge by way of demand charges and
unit
charges
has
consumer/respondent
already
been
exceeding
charged
the
from
contract
the
demand.
Therefore, there was no occasion to further charge any unit
charges under the heading correction if any.
(viii) It has further been stated that respondent
has himself
approached the petitioner/JSEB for enhancement of his contract
demand which was allowed by the writ petitioner/JSEB and a
fresh agreement was also executed for the same.
(ix) The respondent only aggrieved with the petitioner /JSEB for
charging energy charges as gurantee in the aforesaid bills which
could not have been raised in view of the tariff order, 2003-04 of
Jharkhand State Electricity Regulatory Commission (In short to
be referred as J.S.E.R.C.).
(x)
The consumer/respondent has taken the ground before the
VUSNF that JSEB (Writ petitioner herein) has overlooked the
provision of clause 16.5 of 1993 tariff as well as clause1.4 of
tariff order 2003-04, because there is specific provision to deal
with the situation where the HT consumer excedds its contract
demand by more than 110 percent, therefore the writ
petitioner/JSEB has illegally realized the amount in question by
treating it unauthorized use of electricity.
(xi) The writ petitioner JSEB appeared before Vidyut Upbhokta
Shikayat Niwaran Forum(VUSNF), Ranchi and filed its counter
[2026:JHHC:2563]
affidavit denying the contentions raised by the consumer by
taking the ground that the bills in question have been raised in
accordance with law and existing tariff. Further ground has been
taken that the contract demand of consumer/respondent was
105 K.V.A. and during that period the consumer has exceeded
115% of the contract demand i.e. 128.85 K.V.A., therefore
charges were levied in the concerned monthly energy bills and
the maximum demand of the consumer was recorded more than
115% of contract demand which comes under the category of
unauthorized
use
of
electricity
and
as
such
the
consumer/complainant is liable to pay energy charges and K.V.A.
charges twice the rate on the above 115% exceeded of the
contract demand.
(xii) The Learned VUSNF by appreciating the contention vide order
dated 24.02.2011 passed in case no. 13/2010, disposed of the
said petition filed by the respondent/consumer by deciding in
favour of the respondent
and directed the JSEB board to
refund/adjust the illegal amount charged and recovered from
the respondent to the tune of 83,455/- with interest as per
supply code.
(xiii) Then JSEB filed an appeal against the said orders dated
24.02.2011 passed in case no. 13/2010 by VUSNF before the
Electricity Ombudsman and the same was registered as case no.
EOJ/02/2011.
[2026:JHHC:2563]
(xiv) The Electricity Ombudsman vide judgment dated 19.07.2011
upheld the order/judgment dated 24.02.2011 passed by VUSNF
in case no. 13/2010 and the appeal filed by the appellant JSEB
was dismissed and against the said orders the present writ has
been preferred by the JSEB.
(xv) Therefore, the instant writ petition has been filed for setting aside
the above-mentioned order dated 19/07/2011 passed by the
Electricity Ombudsman, Jharkhand and the order dated
24/02/2011 passed by the Vidyut Upbhokta Shikayat Niwaran
Forum, Ranchi.
3. It is evident from the factual aspect that the respondent-consumer
was granted an electric connection for 105KVA load at 11 K.V. supply
voltage for running its plastic industry under HTS-I tariff. The date of
commencement of supply was 04.09.2007. It has been alleged that in
the month of November 2009, the maximum demand of the
petitioner recorded more than 115% of the contract demand. i.e.,
128.85 K.V.A. The writ petitioner, the licensee has charged recorded
128.85 K.V.A along with the extra amount of Rs. 12,262/- without
any basis and contrary to the provisions of the tariff of 2003–2004.
4. Likewise, for the month of December 2009, January 2010, and
February 2010, the maximum demand recorded was more than
115% of the contact demand and on the aforesaid pretext, the
licensee has charged the extra amount in the bill dated 05.01.2010,
08.02.2010 and 05.03.2010.
[2026:JHHC:2563]
5. The consumer, the respondent writ petitioner has challenged the
said bills before the forum.
The licensee has appeared and
substantiated the bill inter alia on the ground that the Board has
rightly charged the surcharge amount, on consideration of the fact
that, the contract demand of the consumer exceeds 115% in the
month as per Clause 16.5 of the tariff 1993, which has been saved in
tariff order 2003–2004.
6. The writ petitioner, based upon the applicability of the provision of
Clause 1.4 of the tariff, 1993 saved in tariff of 2003–2004, therefore
has taken the ground that there is no infirmity in the bills as and as
such the complaint so made on behalf of the consumer, maybe
dismissed.
7. The forum, on appreciating the grounds/arguments advanced on
behalf of the parties, has formulated two issues;
(i)
Whether the consumer is liable for payment of surcharge
amount for 6 months even after he has covered MMC charges
for those months in case maximum demand exceeds 115% of
the contract demand.
(ii)
Whether the bills raised for the said months are liable to be
quashed
and
amount
so
recovered
are
fit
to
be
refunded/adjusted with interest.
8. The Forum has taken into consideration the tariff notification of
1993 of the Bihar State Electricity Board (BSEB), as it then was, for
the purpose of consideration of the Issue no. 1.
[2026:JHHC:2563]
9. The reference of Clause 1.4 of the tariff notification of 1993, which
has been saved in tariff notification 2003–2004, has been taken into
consideration wherein it was provided by revising the clause of
surcharge vide Notification No. 5058 dated 29.08.2022 and has
increased the limit of exceeding maximum demand from 110% to
115% and reduced months from 12 months to 6 months.
10. The Forum, based upon the applicability of the Clause 1.4 of the
tariff notification 2003–2004, has come out with the conclusion that
the bill raised by the respondent, the writ petitioner herein, from
November 2009 to February 2010 are not as per norms of the tariff
and are illegal and arbitrary. Such finding was given on the backdrop
of the fact that the petitioners exceeded maximum demand in four
consecutive months, i.e., from November 2009 to February 2010 and
maximum KVA was recorded in the month of February 2010, i.e., 135
K.V.A. As such, 135 K.V.A. should be the revised maximum demand
chargeable for six months that is from September 2009 to January
2010, as the surcharge for February 2010 has already been charged
and recovered with current bill of that month.
11. The Tribunal, based upon the aforesaid reason, has interfered with
the bill and the same has been quashed and set aside with the
direction upon the writ petitioner to refund the amount to the tune
of Rs. 83,455/- with interest as per supply code.
12. The said order has been challenged by the licensee by preferring an
appeal before the Ombudsman. The Ombudsman has also declined
[2026:JHHC:2563]
to interfere with the decision so taken by the Forum (VUSNF) by
coming out with the conclusive finding that as per Clause 1.4, as was
available in tariff notification 2003–2004, the bill which has been
issued on the presumption of surcharge has rightly been interfered
with.
13. Both the orders are the subject matter of this petition.
Submission of the learned counsel for the petitioner:
14. Learned counsel appearing for the petitioner has submitted that the
order passed by the appellate authority as well as VUSNF is
absolutely improper since the same has been passed without taking
into consideration the actual consumption, as has been consumed by
the consumer.
15. It has been contended that VUSNF and the Electricity Ombudsman in
the impugned judgment(s) dated 24.02.2011 & 19.07.2011 have
failed to appreciate that the Tariff notification of 1993 provides for
raising surcharge bill when the contract demand of the consumer
exceeds 110% of the contract load and the same recorded value
would be the contract demand for the whole financial year and
energy charge shall be payable. The same has been saved in Tariff
Notification 2003-04 issued by the Jharkhand State Electricity
Regulatory Commission in clause 1.4. It has further stated that the
JSEB had subsequently revised the surcharge clause vide notification
no. 5058 dated 29.08.2002 and the exceeded limit was increased
from 110% to 115%.
[2026:JHHC:2563]
16. It has been contended that the electricity ombudsman failed to
appreciate that the maximum demand of the consumer was
recorded more than 115 percent of the contract demand which
comes under the category of unauthorized use of electricity and
hence the respondent/ consumer is liable to pay the energy charges
and KVA charges twice the rate on above 115 percent of the contract
demand.
17. Further the VUSNF as well as appellate authority has not taken into
consideration that the tariff notification issued by the Jharkhand
State Electricity Regulatory Commission contained the saving clause
for pre-existing condition contained the saving clause for preexisting condition in clause 1.4.
18. It has further been contended that VUSNF and the Electricity
Ombudsman further failed to appreciate that the respondent
consumer had increased the requisite contracted load and the
recorded maximum contracted load was the contract demand for the
said financial year and the consumer was bound to pay the minimum
monthly charges and other charges for the required period. Thus,
both the courts below erred in observing that no other chargeable
except the balance of K.V.A. is chargeable. Moreover, exceeding KVA
beyond 115% is considered as unauthorized extraction of power.
19. On the basis of the aforesaid ground the learned counsel for the writ
petitioner has submitted that the impugned orders dated
24.02.2011 & 19.07.2011 passed by VUSNF and the Electricity
[2026:JHHC:2563]
Ombudsman respectively may be quashed and set-aside.
Submission of the learned counsel for the respondent:
20. Mr. D.K. Pathak, learned counsel appearing for the respondent has
taken the following ground by defending the orders passed by the
original as also the appellate authority.
21. It has been contended that there is no error in the concurrent order
passed by the VUSNF as well as Appellate authority and the said
orders have been passed by taking into consideration the specific
provision as carved out under Clause 1.4 of the tariff notification of
the year 2003–2004.
22. It has been contended, while responding to the submission/ground
raised on behalf of the petitioner, that the Clause 16.5 of the tariff
notification of 1993 has not been taken into consideration. The
submission has been made that provision has been made out in tariff
notification of 2003–2004 as available in Clause 1.4 by which the
condition which has been made available Clause 16.5 of the year
1993 has been saved, and as such, whatever the amount was to be
charged, that is in pursuance of Clause 16.5 of the tariff notification
of the year 1993, and as per the provision contained therein, the
billing since has not been made, and on taking into consideration the
aforesaid fact, the Forum has given a specific finding that the billing
ought to have been made on the basis of the consumption shown
made for a particular month and if it is found that the consumption
is more than of the other months, then the billing is to be made on
[2026:JHHC:2563]
the basis of highest consumption shown for a particular month of
the period in question with respect to KVA charges.
23. The learned counsel for the respondent therefore has submitted that
what is being contended that it is contrary to the provision as
contained under Clause 16.5 of the tariff notification of 1993 is not
fit to be accepted, rather whatever consideration has been made by
both the authorities concerned by giving a concurrent finding, the
same is based only upon the tariff notification of 1993 having been
saved in the tariff notification of 2003–2004, as per the provision
made to that effect of Clause 1.4.
24. Learned counsel, based upon the aforesaid ground, has submitted
that the impugned order passed by the VUSNF which has been
confirmed by the appellate authority requires no interference.
Analysis
25. We have heard the learned counsel for the parties and have gone
through the finding recorded by the learned Forum as also the
Ombudsman.
26. We are conscious that the moment order passed by the original
authority has been carried to the appellate authority, and if the
appellate authority declined to interfere with the finding, then on
the basis of the principle of merger, the order passed by the original
authority will be said to be merged upon the order passed by the
higher forum (herein electricity ombudsman). The principle of
merger is well settled that the moment the order passed by the
[2026:JHHC:2563]
lower forum is being affirmed by the higher forum, the order passed
by the lower forum will lose its existence due to its merger with the
order passed by the higher forum. Reference in this regard be made
to judgment rendered by the Hon’ble Apex Court in the case of
Kunhayammed & Ors. Vrs. State of Kerala and Anr. (2000) 6 SCC
359, has appreciated the principle of merger wherefrom, it is
evident that the Hon'ble Apex Court has delved upon the issue on
doctrine of merger and after taking aid of the judgment rendered in
U.J.S. Chopra Vrs. State of Bombay, AIR 1955 SC 633, wherein it has
been held:
"A judgment pronounced by the High Court in the exercise of its
appellate or revisional jurisdiction after issue of a notice and a full
hearing in the presence of both the parties... would replace the
judgment of the lower court, thus constituting the judgment of the
High Court the only final judgment to be executed in accordance with
law by the court below.'' Further reference of the judgment has been
made rendered in the case of S.S. Rathore Vrs. State of M.P., (1989) 4
SCC 582, wherein, a larger Bench of the Hon'ble Apex Court (Seven
Judges) has been pleased to hold that the distinction made between
courts and tribunals as regards the applicability of doctrine of merger
is without any legal justification; where a statutory remedy was
provided against an adverse order in a service dispute and that remedy
was availed, the limitation for filing a suit challenging the adverse
order would commence not from the date of the original adverse order
but on the date when the order of the higher authority disposing of the
statutory remedy was passed.
"12. The logic underlying the doctrine of merger is that there cannot
be more than one decree or operative orders governing the same
subject-matter at a given point of time. When a decree or order
passed by an inferior court, tribunal or authority was subjected to a
remedy available under the law before a superior forum then,
though the decree or order under challenge continues to be effective
[2026:JHHC:2563]
and binding, nevertheless its finality is put in jeopardy. Once the
superior court has disposed of the lis before it either way -- whether
the decree or order under appeal is set aside or modified or simply
confirmed, it is the decree or order of the superior court, tribunal or
authority which is the final, binding and operative decree or order
wherein merges the decree or order passed by the court, tribunal or
the authority below. However, the doctrine is not of universal or
unlimited application. The nature of jurisdiction exercised by the
superior forum and the content or subject-matter of challenge laid
or which could have been laid shall have to be kept in view.
44. To sum up, our conclusions are:
(i) Where an appeal or revision is provided against an order passed
by a court, tribunal or any other authority before superior forum
and such superior forum modifies, reverses or affirms the decision
put in issue before it, the decision by the subordinate forum merges
in the decision by the superior forum and it is the latter which
subsists, remains operative and is capable of enforcement in the eye
of law.
(ii) -----(iii) The doctrine of merger is not a doctrine of universal or
unlimited application. It will depend on the nature of jurisdiction
exercised by the superior forum and the content or subject-matter of
challenge laid or capable of being laid shall be determinative of the
applicability of merger. The superior jurisdiction should be capable
of reversing, modifying or affirming the order put in issue before it. ---
27. The decision in Kunhayammed v. State of Kerala (Supra) was
followed by a three-Judge Bench decision of Hon'ble Apex Court in
Chandi Prasad v. Jagdish Prasad reported in (2004) 8 SCC 724,
wherein at paragraphs 23 and 24 it has been held which read
hereunder as:"23. The doctrine of merger is based on the principles of propriety in
the hierarchy of the justice delivery system. The doctrine of merger
does not make a distinction between an order of reversal, modification
or an order of confirmation passed by the appellate authority. The said
[2026:JHHC:2563]
doctrine postulates that there cannot be more than one operative
decree governing the same subject-matter at a given point of time.
24. It is trite that when an appellate court passes a decree, the decree
of the trial court merges with the decree of the appellate court and
even if and subject to any modification that may be made in the
appellate decree, the decree of the appellate court supersedes the
decree of the trial court. In other words, merger of a decree takes place
irrespective of the fact as to whether the appellate court affirms,
modifies or reverses the decree passed by the trial court."
28. It is evident from the aforesaid judgment that doctrine of merger is
not a doctrine of universal or unlimited application rather it will
depend upon the nature of jurisdiction exercised by the superior
forum and the content or subject-matter of challenge laid or capable
of being laid shall be determinative of the applicability of merger.
The superior jurisdiction should be capable of reversing, modifying
or affirming the order put in issue before it.
29. This court, in order to appreciate the argument, first needs to
appreciate the applicability of the tariff. There is no dispute that the
period of bill is of the month of November 2009 to February 2010,
which is after coming into effect of the tariff notification of the 20032004. Prior to coming into effect, the tariff notification of 2003-2004,
there was tariff notification of the year 1993. The tariff notification
of 1993 contains a Clause as under Clause 16.5, for ready reference
the same is being referred herein which reads as under:
16.5 - "If during any month in a financial year (April to March next
year) the actual maximum demand of a consumer exceeds 110 percent
of the contract demand then the highest demand so recorded shall be
treated as the contract demand for that financial year and the
minimum base charges, both in respect of maximum demand and
[2026:JHHC:2563]
energy charge shall be payable on that basis"
30. It is evident from aforesaid clause that during any month in financial
year (April to March next year), the actual maximum demand of a
consumer exceeds 110% of the contract demand., then the highest
demand so recorded shall be treated as the contract demand for the
financial year and the minimum base charges, both in respect of
maximum demand and energy charges shall be payable on that
basis, meaning thereby, in a particular financial year, the bill will be
on the basis of the actual maximum demand of a consumer if
exceeds 110% of the contact demand. The tariff notification of the
year 1993 has been superseded by the tariff notification of the Year
2003–2004.
31. The relevant clause in the present lis is Clause 1.4, for ready
reference the same is being quoted as under:
“All other terms and conditions in respect of meter rent, supply at
lower voltage, capacitor charge, circuit-Breaker charge, electricity
duty, rebate, security deposit, surcharge for exceeding contract
demand etc shall remain the same as existing in the state.”
32. Thus, from the said clause it is evident that all other terms and
conditions in respect of meter rent, supply at lower voltage,
capacitor charge, circuit breaker charge, electricity duty, rebate,
security deposit, surcharge for exceeding contract demand, etc. shall
remain the same as existing in the State.
33. The fact about the said saving clause has not been disputed reason
being that there is no clause, as has been brought in force in the tariff
notification of 2003–2004 in supersession to Clause 16.5 of the tariff
[2026:JHHC:2563]
notification, 1993.
34. Thus, from aforesaid factual aspect, the seminal issue involve herein
is that whether the Forum has passed the order, said to be in
consonance with the Clause 16.5, as contained in tariff notification of
1993, being saved under Clause 1.4 of the tariff notification of 2003–
2004.
35. The law is well-settled that if the earlier provision is being amended
by bringing the subsequent law/rule/regulation, then the amended
provision, either of law/rule/regulation, will prevail upon as per the
principle of supersession, but if there is no provision said to be
existing in the earlier rules and regulations of the policy decision
and if the new rule has come out with the saving clause, then on the
principle, as provided under section 6 of the General Clause Act, will
prevail even after coming into effect of the amended policy decision
or the rule or the regulation, as the case may be.
36. Exactly, the case is herein, since, as provided under Clause 16.5 of
the tariff notification of the 1993, where it has been provided that
during any month in financial year (April to March next year), the
actual maximum demand of a consumer exceeds 110% of the
contract demand., then the highest demand so recorded shall be
treated as the contract demand for the financial year and the
minimum base charges, both in respect of maximum demand and
energy charges shall be payable on that basis.
37. Further there is no provision formulated in the tariff notification of
[2026:JHHC:2563]
the year 2003-2004, said to be in supersession to the provision
already available in Clause 16.5 of the tariff notification of the year
1993, rather, the provision which was there in Clause 16.5 of the
tariff notification 1993, has been said to be same in view of the
specific saving clause as provided under Clause 1.4 of the tariff
notification of the year 2003-2004.
38. This Court now is proceeding to examine the consideration so made
by the forum as to whether the findings so recorded by the Forum is
on consideration of the Clause 16.5 of the tariff notification of the
year 1993 saved also in the tariff notification of the year 2003–2004.
39. It has been provided in tariff Clause 16.5 of the tariff notification of
1993 saved in the notification of 2003-2004 that in case the
maximum demand of a consumer exists 110%, then the billing is to
be done on the basis of the increased demand on the presumption
that the contract demand will be said to the electricity used to that
extent. Herein, for a month it has been shown to be 135 KVA and as
such, the billing ought to have been done by taking into
consideration the maximum consumption treating the contract
demand to be exceeded 128.85 KVA, but the billing was not in
consequence with the Clause 16.5. The provision as contained in
clause 16.5, however has been amended to the extent that the 110%
has been shown to be exceeded to 115% and the period of 12
months have been reduced to the period of six months in the year
2002.
[2026:JHHC:2563]
40. The whole limb of argument is that the calculation which has been
made by taking the maximum contract load by treating the same to
be the maximum load on the basis of the excess consumption in a
particular month is to be assessed on the basis of the 12 months, as
is being referred in Clause 16.5 of the tariff notification of the year
1993 but the learned counsel appearing for the writ petitioner has
failed to answer the query which has been put upon him with
respect to the implication of the Notification No. 5058 dated
29.08.2022 by which the exceeded limit was increased from 110% to
115% and the period of 12 months has been reduced to the period
of 06 months.
41. It is very surprising, although the licensee is before this Court by
filing this petition, but without making any pleading regarding the
implication of Notification No. 5058 dated 29.08.2022, the present
writ petition has been filed while the thoughtful consideration has
been given by the Forum with respect to the consequence of the
Notification No. 5058 dated 29.08.2022, as would be evident from
the paragraph-6 of the order so made by the Electricity Ombudsman
wherein the genuineness of the calculation of the bill has been tested
by considering the implication of Notification No. 5058 dated
29.08.2022 issued by the J.S.E.B. revising the clause of surcharge by
which the exceeding limit has been increased from 110% to 115%
and reduced from 12 months to 06 months. For ready reference
Para-6 of the order passed by the Electricity Ombudsman is being
[2026:JHHC:2563]
referred herein which reads as:
“6. I find myself in agreement in the aforesaid contentions of the
learned Counsel of consumer/respondent and I am also of the view that
the
appellant/JSEB
has
illegally
raised
the
bills
of
consumer/respondent from November, 2009 to February, 2010 against
the tariff and therefore the learned VUSNF has rightly quashed the
aforesaid bills. I also find myself in agreement with the findings of the
learned VUSNF that there is provision for raising surcharge bill in the
tariff notification of 1993 where a maximum demand of a consumer
exceeds 110% of the contract demand and the same recorded value
will be the contract demand for the whole financial year and the
minimum base charge, both in respect of maximum demand and
energy charge shall be payable on that basis. This provision has also
been saved in the tariff notification of 2003-04 of J.S.E.R.C in Cause 14.
This
is an admitted fact in between both the parties that the
appellant/JSEB had revised the clause of surcharge vide notification
no. 5058 dated 29/08/2002 by which the exceeding limit has been
increased from 110 to 115% and reduced from twelve month to six
months.”
42. The question which requires consideration is that if any
consideration of any valid notification issued by the competent
authority has been made the basis of adjudication, then how can the
writ petition be filed without going through the proper implication
of such notification as the facts of the present writ petition is.
43. The writ petitioner ought to have filed this writ petition by coming
out with the specific pleading by carving out the interpretation along
with the proper and just implication of the Notification No. 5058
dated 29.08.2022 which is the basis of passing of an order by the
Forum (VUSNF) and that has also been taken into consideration by
the Ombudsman.
44. Further from record it is apparent that consumer's/respondent’s
[2026:JHHC:2563]
maximum demand exceeded in four consecutive months from
November, 2009 to February, 2010 and maximum K.V.A. is recorded
in the month of February, 2010 which is 135 K.V.A., therefore 135
K.V.A. should be the revised maximum demand chargeable for six
months as the surcharge for February, 2010 has already been
charged and realized from the consumer/respondent with current
bill of that month.
45. The learned Electricity ombudsman taking into consideration the
aforesaid
factual
aspect
has
observed
that
the
consumer/complainant/respondent herein has covered the monthly
minimum charge in all these months, therefore, no other charges is
chargeable except the balance of K.V.A. charges from September,
2009 to January, 2010 and accordingly directed the writ
petitioner/appellant/JSEB to revise or adjust the amount so charged
and recovered from the respondent Mangalam Plastics.
46. On the basis of the aforesaid factual aspect, it is considered view of
this Court that finding arrived by the learned appellate authority i.e.
Electricity Ombudsman by which order passed by the Original
Authority has been affirmed, is based upon the cogent reasoning and
hence requires no interference.
47. Further It needs to refer herein that the issuance of the writ of
certiorari, is very limited and the same can only be issued in a
situation where there is any jurisdictional error of the violation of
principle of natural justice or if the order suffers from error
[2026:JHHC:2563]
apparent on the face of the of the order. Reference in this regard be
made to the judgment rendered by the Hon’ble Apex Court in the
case of West Bengal Central School Service Commission & Ors Vrs.
Abdul Halim & Ors., reported in (2019) 18 SCC 39, wherein, at
paragraph-30 it has been held as under:“30. In exercise of its power of judicial review, the Court is to see
whether the decision impugned is vitiated by an apparent error of law.
The test to determine whether a decision is vitiated by error apparent
on the face of the record is whether the error is self-evident on the face
of the record or whether the error requires examination or argument
to establish it. If an error has to be established by a process of
reasoning, on points where there may reasonably be two opinions, it
cannot be said to be an error on the face of the record, as held by this
Court in Satyanarayan vs. Mallikarjuna reported in AIR 1960 SC 137. If
the provision of a statutory rule is reasonably capable of two or more
constructions and one construction has been adopted, the decision
would not be open to interference by the writ Court. It is only an
obvious misinterpretation of a relevant statutory provision, or
ignorance or disregard thereof, or a decision founded on reasons which
are clearly wrong in law, which can be corrected by the writ Court by
issuance of writ of Certiorari.”
48. Likewise, the Hon’ble Apex Court in the case of T.C. Basappa v. T.
Nagappa, reported in (1955) 1 SCR 250, it has been held as under:“An error in the decision or determination itself may also be amenable
to a writ of certiorari but it must be a manifest error apparent on the
face of the proceedings, e. g. when it is based on clear ignorance or
disregard of the provisions of law. In other words, it is a patent error
which can be corrected by certiorari but not a mere wrong decision.”
49. This Court, in view of the aforesaid and considering the parameter to
be followed and also applying the principle laid down in the
aforesaid cases and based upon the discussion made hereinabove, is
of the view that neither of the condition is available so that the writ
of certiorari be issued for quashing the impugned orders passed by
the VUSNF and Electricity Ombudsman dated 24.02.2011 and
[2026:JHHC:2563]
19.07.2011 respectively.
50. This Court, in view of the above and having gone through the
concurrent finding recorded by the VUSNF and Electricity
Ombudsman, is of the view that it is not a fit case where writ of
certiorari is to be issued.
51. Accordingly, the instant writ petition being W.P. (C) No. 5606 of 2011
is dismissed and as such disposed of.
52. Pending interlocutory application(s), if any, also stands disposed of.
(Sujit Narayan Prasad, J.)
21st January, 2026
Samarth
AFR
Uploaded on: 02.02.2026
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review