Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
+
O.M.P. (COMM) 408/2022
JHARKHAND ROAD PROJECTS IMPLEMENTATION
.....Petitioner
Through:
Mr. Kaushik Laik, Mr. Ashay
Kaushik, Mr. Shashank Tiwari, and
Mr. H. N. Thangal, Advocates
versus
SADBHAV ENGINEERING LIMITED
.....Respondent
Through: Mr. Sarojanand Jha, Mr. Suraj Malik,
Ms. Rajreeta Ghosh, Mr. Rahul
Kumar and Ms. Muskan Saxena,
Advocates
CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
%
I.A. 424/2026
1.
ORDER
09.01.2026
This application has been filed by the Petitioner for withdrawal of the
present Petition in terms of the Settlement Agreement dated 25.08.2025.
2.
The present Petition was filed by the Petitioner under Section 34 of
the Arbitration & Conciliation Act, 1996 challenging the Award dated
06.08.2020.
3.
It is stated that during the pendency of the present Petition, the parties
have entered into a Settlement Agreement dated 25.08.2025. The entire
Settlement Agreement is reproduced herein and the same reads as under:
“SETTLEMENT AGREEMENT This Settlement
Agreement (“Agreement”) is made and entered into on
O.M.P. (COMM) 408/2022
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 13/01/2026 at 13:12:10
this 25th day of 2025, at Mumbai, Maharashtra, by and
between: 8 JHARKHAND ROAD PROJECTS
IMPLEMENTATION COMPANY LIMITED, a
company incorporated under the Companies Act, 1956,
having its registered office at IL&FS li Transportation
Networks Limited, The IL&FS Financial Centre, 3rd
Floor, G Block, Plot C-22, Bandra Kurla Complex,
Bandra (E), Mumbai 400 051 (hereinafter referred to
as “JRPICL” or the “Company”), acting through its
authorized signatory, Mr. Vineet Chaubey, Manager;
AND
GKC PROJECTS LIMITED, a company incorporated
under the Companies Act, 1956, having its office at Sy.
No. 9 (P), CII Green Building Lane, Kondapur, Hitech
City, Hyderabad, represented by Mr. K. V. Raja
Sekhar, Chief Executive Officer (hereinafter referred to
as “GKC”)
AND
SADBHAV ENGINEERING LIMITED, a company
incorporated under the Companies Act, 1956, having
its office at Sadbhav House, Opp. Law Garden Police
Chowki, Ellisbridge, Ahmedabad, represented by Mr.
Vikramjeet Singh, Senior Vice President (hereinafter
referred to as “SEL”). JRPICL, GKC and SEL are
hereinafter individually referred to as a “Party” and
collectively as the “Parties”.
WHEREAS:
A.
SEL was engaged by JRPICL as an EPC
contractor in connection with the Ranchi Ring Road
Project (“Project”). The Project was successfully
completed by SEL with the support of GKC (as subcontractor) on 21.09.2012. Based on non-fulfilment by
O.M.P. (COMM) 408/2022
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 13/01/2026 at 13:12:10
JRPICL to the terms of the contract executed between
JRPICL and SEL, SEL initiated arbitration
proceedings against JRPICL in July 2014. This dispute
pertained to the Project, wherein SEL claimed a sum of
Rs. 251 Crores. JRPICL had also lodged its
counterclaims for Rs. 44.24 Crores.
B.
During the pendency of the said arbitration
proceedings, the Hon’ble National Company Law
Appellate Tribunal (“NCLAT”) by its order dated
October 15, 2018 (“October 15 Order”), stayed the
initiation and / or continuation of all proceedings
(including arbitration proceedings) and recovery
actions against Infrastructure Leasing & Financial
Services Limited (“IL&FS”) and its group entities
(collectively, “IL&FS Group Entities”), including
JRPICL, in the larger public interest.
C.
Thereafter, the arbitration proceedings were
permitted to be continued by the NCLAT vide an order
dated January 11, 2019 (“January 11 Order”) with a
direction that any award that may be passed by the
Arbitral Tribunal against IL&FS or its group entities
shall be kept in a sealed cover.
D.
By its judgment dated March 12, 2020 (“March
12 Judgment”), the Hon’ble NCLAT confirmed the
continuation of the October 15 Order and approved the
resolution framework for IL&FS Group Entities, as
proposed by the Union of India (“Resolution
Framework”).
E.
Under the Resolution Framework, all creditor
claims stood frozen and crystallised as of October 15,
2018 (the “Cut-Off Date”), and payments are to be
made only in respect of admitted claims as verified by
the claims management consultant, Grant Thornton
Bharat LLP (“Grant Thornton”).
O.M.P. (COMM) 408/2022
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 13/01/2026 at 13:12:10
F.
Grant Thornton was appointed as an
independent claims management consultant to manage
claims for certain IL&FS Group Entities (including
JRPICL) and invited submissions through a claims
window opened on June 6, 2019, which was extended
multiple times.
G.
Pursuant to the January 11 Order, the
arbitration proceedings resumed and an award dated
August 6, 2020 was passed by all three members of the
Arbitral Tribunal unanimously in favour of SEL,
however, the same was kept in a sealed cover (in terms
of the January 11 Order).
H.
SEL thereafter, filed an application before
NCLAT for de-sealing of the award and release of the
same to the parties, wherein the NCLAT passed an
order dated May 26, 2022 (“May 26 Order”)
permitting the award to be opened from the sealed
cover and release the same to the parties; further
observing that all rights and contentions shall be open
to parties to be taken in accordance with law.
I.
Thereafter, the award was unsealed and
released to the parties on June 6, 2022. SEL has been
awarded Rs. 72.65 crores plus interest at 10% per
annum from the date of claim (“Award”).
J.
After the release of the Award, JRPICL filed a
challenge to the Award under Section 34 ' the
Arbitration and Conciliation Act, 1996 before Hon’ble
High Court of Delhi. Enforcement proceedings were
subsequently initiated by SEL before the Commercial
Court. Ranchi.
K.
Meanwhile, , JRPICL had filed an application
before NCLAT being IA No.1288 seeking various
O.M.P. (COMM) 408/2022
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 13/01/2026 at 13:12:10
reliefs including a permanent injunction against SEL
from enforcing the Award. SEL also filed an
application before NCLAT being IA No.3262 seeking
various reliefs including a declaration that SEL was
entitled to seek enforcement of the Award.
L.
The Hon’ble NCLAT, by its interim order dated
August 28, 2024, clarified that the October 15 Order
remains in force and that the May 26 Order did not
authorize enforcement of the Award. The NCLAT,
however, kept the IA No.1288 and IA No.3262 pending
for considering the other prayers therein.
M.
During the pendency and adjudication of the
aforesaid IA No.1288 and IA No. 3262 before the
NCLAT, the NCLAT, vide Order dated April 3, 2025
granted liberty to the Parties to explore the possibility
of settlement pursuant to which SEL issued the letter
dated April 12, 2025 expressing its intention to explore
the possibility of settlement of its claims under the
Award, without prejudice to its rights and contentions.
N.
In response thereto, JRPICL vide its email dated
May 19, 2025, called SEL for a meeting to discuss an
amicable settlement. Accordingly, a virtual meeting
was held between the representatives of SEL and the
JRPICL on May 21, 2025, at 4 pm wherein parties
discussed the nuances of the proposed settlement of
claims of SEL under the Award.
O.
SEL, in terms of its letter dated May 23, 2025,
without prejudice to its rights and contentions,
provided its consent to JRPICL to consider its claims
under the Award in accordance with the Resolution
Framework.
Meanwhile, an assignment agreement dated July 11,
2025 was entered in to between SEL and GKC
O.M.P. (COMM) 408/2022
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 13/01/2026 at 13:12:10
(“Assignment Agreement”), wherein SEL has
unconditionally and irrevocably assigned and
transferred all its rights, title, benefits, obligations and
interest under the Award (including to pursue
realisation of amounts due thereunder) in favour of
GKC, with effect from the date of the Assignment
Agreement.
NOW, THEREFORE, in consideration of the mutual
promises and covenants set forth herein, the Parties
agree as follows:
1. ACKNOWLEDGEMENT OF AWARD AMOUNT
The Parties agree and acknowledge that:
(a) an arbitral award dated August 6, 2020, was
passed in favour of SEL in connection with the Ranchi
Ring Road Projects (RRR I & RRR II), awarding an
amount of Rs. 72,65,00,000 (Indian Rupees SeventyTwo Crores and Sixty Five Lakhs Only) plus interest at
10% per annum from the date of claim;
(b) GKC (the assignee of SEL’s rights, title, benefits,
obligations and interest in terms of the v. Assignment
Agreement) has claimed that the total amount,
including all components awarded aggregates to Rs.
153,67,40,259 as of August 25, 2025. The verification
and admission of the said claim under the IL&FS
Group Resolution Framework shall be carried out by
Grant Thornton
(c) the total amount of the claim, inclusive of all
components of the Award, shall be independently
verified and admitted, solely upon reconciliation by
Grant Thornton, in terms of the Resolution
Framework.
O.M.P. (COMM) 408/2022
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 13/01/2026 at 13:12:10
2. RESOLUTION FRAMEWORK SUBMISSION
2.1 GKC agrees to submit its claim exclusively to
Grant Thornton pursuant to the Resolution
Framework, and in accordance with directions issued
by the Hon’ble NCLAT.
2.2 The Company, along with IL&FS, shall facilitate
the reopening of the claim window and enable GKC to
lodge its claim under the Award, notwithstanding the
expiration of the original timelines for claim
submission. It is clarified that any payment to GKC
against the claims under the Award shall be processed
through the mechanisms prescribed under the
Resolution Framework.
3.
STEPS
TOWARDS
SETTLEMENT
WITHDRAWAL OF LITIGATION & WAIVER
AND
The Parties agree that the process of settlement shall
be effectuated in the following sequence and manner:
3.1 Upon the claims window being opened by Grant
Thornton, GKC shall submit its claims under the
Award to Grant Thornton, for formal verification and
admission as per the Resolution Framework, within a
period of ten (10) days from the date of this Agreement,
unless extended by Grant Thornton;
3.2 Within a period of fifteen (15) days of the
submission of the claims to Grant Thornton by GKC
and/or formal confirmation towards admission of the
relevant claims (in full or in part) under the Award by
the Grant Thornton, the Parties shall simultaneously
undertake the following actions:
(a) GKC and/ or SEL shall withdraw its enforcement
proceedings being Commercial Execution Case No
O.M.P. (COMM) 408/2022
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 13/01/2026 at 13:12:10
13/2023 in respect of the Award as pending before the
Commercial Court, Ranchi;
(b) JRPICL shall withdraw its petition under Section
34 of the Arbitration and Conciliation Act, 1996 being
OMP (Comm.) No 408/ 2022 challenging the Award
before the High Court of Delhi.
(c) upon withdrawal of the proceedings set out in (a)
and (b) above, the Parties shall send an intimation to
Grant Thornton with a copy to the other Parties.
3.3 Upon completion of each of the steps set out in
paragraph 3.2 above, the Parties shall within a period
of ten (10) days thereof, file a joint application before
the NCLAT for withdrawal of the pending applications
as listed in Annexure A concerning the Award, in
pursuance of the present settlement.
3.5 GKC and SEL further agree that upon
completion of the steps mentioned in paragraphs 3.1 to
3.2 above and save and except as provided under this
Agreement, neither GKC nor SEL shall initiate or
pursue, directly or indirectly, any future legal, arbitral,
judicial or enforcement proceedings against JRPICL,
IL&FS Group Entities, or their representatives, in
relation to the Award, the underlying contract(s)
resulting in the grant of the Award, or any matter
governed by or falling within the scope of the
Resolution Framework, whether in India or abroad.
Notwithstanding the above, SEL and GKC shall retain
their rights in law to challenge any downward revision
of their claims under the Award by Grant Thornton
3.6 Failure by either Party to comply with the
obligations under this clause within the stipulated
period shall entitle the other Party to treat this
Agreement and all actions taken in pursuant thereto as
O.M.P. (COMM) 408/2022
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 13/01/2026 at 13:12:10
void ab initio, without prejudice to any other rights or
remedies available in law.
3.7 Any steps taken by any party in pursuance of the
present Agreement until all of the steps/ terms of the
Agreement have been fully complied, shall not be
treated as a waiver of the right of such party to seek
appropriate remedy including for revival of any
proceedings which may have been withdrawn in
pursuance of the present Agreement.
4. NO FURTHER CLAIMS
Subject to the fulfilment of the provisions set out in
paragraph 3.1 to 3.2 above, SEL and GKC hereby
release JRPICL and its affiliates from all past, present,
and future claims (other than its bonus entitlement
from the Government of Jharkhand towards early
completion of the Project, which the GKC/ SEL is
pursuing before appropriate forum/ authority) related
to the Award. Notwithstanding the above, SEL and
GKC shall retain their rights in law to challenge any
downward revision of their claims under the Award by
Grant Thornton (GT).
5. REPRESENTATIONS AND WARRANTIES
Each of GKC and SEL hereby represent and warrant
to the Company that:
5.1 it has granted the requisite authority to the persons
executing this Agreement to execute this Agreement,
and this Agreement is binding upon it;
5.2 it is duly organized and validly existing under the
laws of its jurisdiction of incorporation;
5.3 it has all requisite corporate power, authority, and
O.M.P. (COMM) 408/2022
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 13/01/2026 at 13:12:10
consents to execute and deliver this Agreement and to
consummate the transactions contemplated herein.
5.4 the Assignment Agreement (a) constitutes legal,
valid and binding obligations of each of GKC and SEL
enforceable against each of GKC and SEL on the terms
contained in the Assignment Agreement; and (b)
continues to remain effective at all times;
5.5 No notice has been received in respect of any
revocation or cancellation or termination or injection
of the Assignment Agreement.
6. GOVERNING LAW AND JURISDICTION.
This Agreement shall be governed by and construed in
accordance with the laws of India. The courts at New
Delhi shall have exclusive jurisdiction, subject to the
supervisory jurisdiction of the Hon’ble NCLAT in
accordance with applicable laws.
7. ENTIRE AGREEMENT
This Agreement constitutes the full and final
understanding between the Parties regarding the
subject matter herein. It supersedes all prior
discussions, letters, or representations.”
4.
The present Application has been filed for withdrawal of the present
Petition in terms of the Settlement Agreement dated 25.08.2025.
5.
For the reasons stated in the application, the same is allowed.
6.
The present Petition is disposed of as withdraw in terms of the
Settlement Agreement dated 25.08.2025.
7.
It is made clear that both the parties are bound by the terms of the
Settlement Agreement dated 25.08.2025.
O.M.P. (COMM) 408/2022
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 13/01/2026 at 13:12:10
8.
The date already fixed, i.e. 13.03.2026 stands cancelled.
SUBRAMONIUM PRASAD, J
JANUARY 09, 2026
Rahul
O.M.P. (COMM) 408/2022
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 13/01/2026 at 13:12:10
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review