Judgments
LegalFirms.in Judgments · legalfirms.in/judgments/jaipur-vidyut-vitran-nigam-limited-vs-m-s-uttam-bharat-electricals-limited-20260916/ · Printed 28 Nov 2026
Civil

Jaipur Vidyut Vitran Nigam Limited vs M/S Uttam (Bharat) Electricals Limited

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Rajasthan High Court
Date
16 September 2026
Case No.
CMA 3299/2019
Result
Dismissed
Bench
Arun Monga, Anuroop Singhi
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

34. Consequently, the present appeal stands dismissed and the arbitral award dated 26.04.2011 so also the order passed by the learned Commercial Court dated 27.02.2019 is upheld.

Filed under

Arbitration and Conciliation Act, 1996 Section 37, Arbitration and Conciliation Act, 1996 Arbitration and Conciliation Act

Guides on this topic, in plain language:

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

[2026:RJ-JP:37655-DB] HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR D.B. Civil Miscellaneous Appeal No. 3299/2019 CNR: RJHC020564742019 | URN: CMA / 5153U / 2019 1. Jaipur Vidyut Vitran Nigam Limited registered office situated at Vidyut Bhawan, Jyoti Nagar, Jaipur 2. Superintendent Engineer (SPO-V) Jaipur Vidyut Vitran Nigam Limited, Purana Power House, Near Ram Mandir, Jaipur Both through Officer In Charge Executive Engineer (SPO V), Jaipur Vidyut Vitran Nigam Limited, Purana Power House, Near Ram Mandir, Jaipur. ----Appellants Versus M/s Uttam (Bharat) Electricals Limited, B-189, Road No. 9 (F) V.K.I. Area, Jaipur. ----Respondent For Appellant(s) : Mr. Sarvesh Jain For Respondent(s) : Mr. Shivangshu Naval with Ms. Akanksha Noval, Mr. Jatin Soni and Mr. Aarav Jain HON'BLE MR. JUSTICE ARUN MONGA HON'BLE MR. JUSTICE ANUROOP SINGHI Order 16/09/2026 PER :- HON'BLE MR. JUSTICE ANUROOP SINGHI CHALLENGE: 1. The subject matter of impugnment in the present appeal filed under Section 13 of the Commercial Courts Act, 2015 read with Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act of 1996”), is the order dated 27.02.2019 passed by the Commercial Court No.3, Jaipur Metropolitan, in Arbitration Application No.156/2018, whereby the objections preferred by the appellants against the arbitral award dated 26.04.2011, came to be rejected. [2026:RJ-JP:37655-DB] (2 of 11) [CMA-3299/2019] FACTUAL BACKGROUND: 2. The controversy between the parties arises out of a contract entered into between the appellants and the claimant-respondent pursuant to the acceptance of claimant-respondent’s bid in response to appellants’ tender for supply of 36 numbers of 3.15 MVA, 33/11 KV Copper Wound Power Transformers along with fittings and accessories. The bid of the claimant-respondent was accepted vide acceptance letter dated 14.02.2005 and the agreement between the parties came to be executed on 27.04.2005. 3. Certain disputes thereafter arose between the parties with regard to the payment of amount towards price variation under the contract. In terms of the arbitration clause contained in the agreement, the dispute was referred to an Arbitral Tribunal comprising of three learned Arbitrators. 4. The learned Arbitral Tribunal, by a majority of 2:1, passed the arbitral award dated 26.04.2011 in favour of the claimant-respondent, aggrieved by which the appellants preferred objections before the learned Commercial Court under Section 34 of the Act of 1996. The said objections came to be rejected vide order dated 27.02.2019, unsatisfied thereof, the present appeal has been filed. SUBMISSIONS ON BEHALF OF THE APPELLANTS: 5. Mr. Sarvesh Jain, learned counsel appearing for the appellants submits that the impugned order is being assailed principally on the ground that the learned Commercial Court failed to appreciate that the arbitral award is contrary to the agreed terms and conditions of the contract governing the parties and thus, the award should have been interfered with under Section 34 of the Act of 1996. (3 of 11) [2026:RJ-JP:37655-DB] 6. [CMA-3299/2019] Learned counsel submits that under the terms of the contract, the price adjustment mechanism was subject to the stipulated conditions relating to advance payment and the claimant-respondent had itself communicated that it was not claiming the stipulated advance payment and, thereafter, vide communication dated 30.08.2005, the appellants specifically informed the claimant-respondent that price adjustment would be payable only on 90% of ex-works price and the claimantrespondent after accepting the said condition even proceeded ahead with the supplies to the appellants. 7. Learned counsel submits that notwithstanding the aforesaid position, the claimant-respondent subsequently raised a claim for price variation on 100% of the ex-works price, which per se was not maintainable, however, the learned Arbitral Tribunal without appreciating the effect of the communication dated 30.08.2005, erroneously proceeded to allow the claim. 8. Learned counsel submits that the aforesaid error amounted to a disregard of the contractual terms and constitutes a patent illegality warranting interference with the arbitral award. The subsequent conduct of the claimant-respondent, communication dated particularly 30.08.2005 and its acceptance continuance of of the supplies thereafter, was a material and substantial circumstance so as to decline the relief as prayed by the claimant-respondent, however, despite that the award has been passed in favour of the claimant-respondent. 9. Learned counsel submits that the learned Commercial Court, while rejecting the objections, failed to properly consider the aforesaid specific grounds raised by the appellants and hence, the order under challenge suffers from gross illegality and the jurisdiction and contours [2026:RJ-JP:37655-DB] (4 of 11) [CMA-3299/2019] as available under Section 34 of the Act of 1996 have not been judicially exercised. 10. Learned counsel further submits that the dissenting opinion of one out of three learned Arbitrators specifically records that even the procedure adopted with respect to the delivery of material was objectionable and once the claimant-respondent chose not to furnish the advance bank guarantee and receive payment of advance, the entire revised delivery schedule should have been scrapped by the appellants. 11. In support of his aforesaid submissions, learned counsel has placed reliance upon the following judgments: I. Oil and Natural Gas Corporation Ltd. Versus SAW Pipes Ltd., reported in (2003) 5 SCC 705; II. Delhi Development Authority Versus M/s. R.S. Sharma and Co., reported in (2008) 13 SCC 80; III. O.N.G.C. Ltd. Versus Garware Shipping Corporation Ltd., reported in (2007) 13 SCC 434; IV. PSA Sical Terminals Pvt. Ltd. Versus Board of Trustees of V.O. Chidambranar Port Trust Tuticorin & Ors., reported in (2023) 15 SCC 781; V. Ssangyong Engineering & Construction Co. Ltd. Versus National Highways Authority of India, reported in (2019) 15 SCC 131; and VI. Indian Oil Corporation Ltd. Versus M/s Shree Ganesh Petroleum Rajgurunagar, reported in (2022) 4 SCC 463. 12. On the aforesaid premises, learned counsel for the appellants prays that the impugned order dated 27.02.2019 be set aside and the (5 of 11) [2026:RJ-JP:37655-DB] [CMA-3299/2019] objections preferred by the appellants under Section 34 of the Act of 1996 be allowed, resulting into setting aside of the arbitral award dated 26.04.2011. SUBMISSIONS ON BEHALF OF THE RESPONDENT: 13. Au contraire, Mr. Shivangshu Naval, learned counsel appearing for the claimant-respondent opposes the present appeal and submits that no interference is warranted by this Court in exercise of the limited appellate jurisdiction available to it under Section 37 of the Act of 1996. 14. Learned counsel for the claimant-respondent submits that the learned Arbitral Tribunal had duly considered the contractual terms, the payment mechanism, the provisions relating to price adjustment, the correspondence exchanged between the parties and the subsequent conduct of the parties and only thereafter, by a majority opinion has passed the arbitral award, which has rightly not been interfered with by the learned Commercial Court. 15. Learned counsel submits that the proceedings under Section 34 and so also under Section 37 of the Act of 1996 cannot be invoked for undertaking re-appreciation of the factual aspects, more particularly in light of the specific provisions of law which provide for judicial scrutiny within a well defined and restrictive domain. 16. Learned counsel submits that merely because the appellants seek to place a different interpretation upon the contractual clauses, particularly the provisions concerning advance payment and price adjustment, or seek to attach a different consequence to the communications exchanged, more particularly the communication dated 30.08.2005 and the subsequent supplies, the same would not constitute a ground for interference under Section 37 of the Act of 1996. (6 of 11) [2026:RJ-JP:37655-DB] 17. Learned counsel for the [CMA-3299/2019] claimant-respondent while placing reliance upon the judgments of the Hon'ble Supreme Court in Hindustan Limited Construction Company Versus National Highways Authority of India, reported in (2024) 2 SCC 613, and Somdatt Builders – NCC – NEC (JV) Versus National Highways Authority of India reported in (2025) 6 SCC 757, submits that the settled jurisprudence requires the appellate Court to adopt the path of least interference while examining an arbitral award and where the Arbitral Tribunal has adopted a plausible interpretation of the contractual terms, the same cannot be substituted merely because another interpretation is possible. 18. Learned counsel submits that the challenge raised by the appellants is, in substance, an attempt to invite this Court to reconsider the contractual correspondence and the material which was already considered by the learned Arbitral Tribunal and subsequently examined by the learned Commercial Court, and such an exercise is impermissible within the limited scope of Section 37 of the Act of 1996. Thus, he prays that the present appeal be dismissed and the concurrent findings recorded in the arbitral award dated 26.04.2011 and the order dated 27.02.2019 passed by the learned Commercial Court, be affirmed. DISCUSSION AND FINDINGS: 19. We have considered the rival submissions advanced on behalf of the parties and have perused the material placed on record. 20. At the outset, it would be apposite to notice the limited jurisdiction available to this Court while exercising appellate jurisdiction under Section 37 of the Act of 1996. The legal position in this regard is more than settled that the jurisdiction exercised by this Court under Section 37 of the Act of 1996, particularly against an order passed [2026:RJ-JP:37655-DB] (7 of 11) [CMA-3299/2019] under Section 34 of the Act of 1996, is circumscribed by the statutory parameters contained in Section 34 itself. The jurisdiction cannot be equated with the ordinary appellate jurisdiction exercised by a civil court. 21. The Hon'ble Supreme Court, while considering the scope of interference under Sections 34 and 37 of the Act of 1996, in a series of judgments, has held and reiterated that the appellate jurisdiction under Section 37 of the Act of 1996 is more constrained, narrower and restrictive than the jurisdiction under Section 34 of the Act of 1996. The function of the appellate Court is essentially to examine whether the jurisdiction vested in the Court under Section 34 of the Act of 1996 has been exercised within the limits prescribed by law. 22. The principle has been succinctly illustrated by the Supreme Court in the form of a “narrowing pyramid”, observing that with each subsequent layer of appeal, the Court's approach must become increasingly hands-off so as to protect the finality of the arbitral process. The same principle assumes greater significance where the arbitral award has already been examined by the learned Commercial Court under Section 34 of the Act of 1996 and it is a concurrent finding which is under challenge. In such a situation, the jurisdiction of the Court under Section 37 of the Act of 1996 is further circumscribed and the appellate Court is not required to undertake a fresh examination of the merits of the dispute. 23. If the view adopted by the Arbitrator is a plausible one, interference is not warranted merely because another view is possible. The approach of the Court is required to give due regard to the arbitral autonomy and ensure minimum judicial deference. [2026:RJ-JP:37655-DB] 24. (8 of 11) [CMA-3299/2019] Keeping the aforesaid principles in view, the principal question which arises for consideration in the present appeal is whether the grounds raised by the appellants disclose such an infirmity in the arbitral award, or in the order passed under Section 34 of the Act of 1996, so as to warrant interference by this Court in exercise of jurisdiction under Section 37 of the Act of 1996. 25. The principal grievance of the appellants is that the learned Arbitral Tribunal failed to give effect to the contractual arrangement concerning advance payment and price adjustment and, in particular, to the communication dated 30.08.2005 whereby, according to the appellants, the claimant-respondent was informed that price adjustment would be applicable only to 90% of the ex-works price. Learned counsel for the appellants has relied upon various clauses of Special Conditions of Contract (SCC) to take home his submission that it was mandatory for the claimant-respondent to take 10% advance payment of the price of the contract and to furnish bank guarantee of an equivalent amount as security and by not claiming the advance amount it would not automatically become entitled to price adjustment on 100% of ex-works price. 26. We are unable to accept the submission in the manner in which it has been canvassed and further for the reason that the said submission has been elaborately dealt with and considered by the Arbitral Tribunal. 27. The question as to the effect of the contractual terms, the communications exchanged between the parties and the conduct of the parties in relation thereto essentially falls within the domain of the learned Arbitral Tribunal, which in a very lucid manner has duly recorded the findings to the effect that as per Clause 19.1 of the General Conditions of Contract (GCC), the contract was amenable to (9 of 11) [2026:RJ-JP:37655-DB] [CMA-3299/2019] amendments and modifications by mutual consent. The award further records that Clause 11 of SCC read with Clause 16 of GCC, duly takes care of the condition with respect to payments and price adjustments. The award further takes notice of the communications exchanged by both the parties, more particularly the communications dated 25.05.2005, 17.06.2005, 18.07.2005, 20.07.2005 and 30.08.2005, which resulted into amendment in the terms of payment and once such an exercise was done by the appellants themselves, any consequence resulting out of the same cannot be disputed by them, more so, as to challenge the award on the basis of said amendments. 28. The grievance of the appellants essentially concerns the interpretation by the learned Arbitral Tribunal of the contractual terms and the material on record. An arbitral award cannot be disturbed merely because the appellate Court considers another possible interpretation to be a preferable one. The jurisdiction under Section 37 of the Act of 1996 remains confined within the contours of Section 34 of the Act of 1996 and is exercisable essentially to ascertain whether the lower Court has acted within the jurisdiction vested in it under Section 34 of the Act of 1996. 29. Learned counsel for the appellants has, however, laid considerable emphasis upon the findings recorded in the dissenting opinion forming part of the 2:1 majority of the arbitral award and has sought to contend that the view expressed therein warrants interference with the findings returned by the learned Commercial Court. The said submission, however, cannot be countenanced. The dissenting opinion, by its very nature, does not constitute the operative determination of the Arbitral Tribunal, with the award having been rendered by the majority of the Tribunal. The mere availability of a contrary view within the arbitral [2026:RJ-JP:37655-DB] (10 of 11) [CMA-3299/2019] proceedings cannot furnish a ground for this Court, in exercise of its limited jurisdiction under Section 37 of the Act of 1996, to undertake a fresh appraisal of the contractual terms or to supplant the view of the majority with that expressed in the dissent, more so, when the majority view has already withstood scrutiny under Section 34 of the Act of 1996. Reliance in this regard is placed upon the judgment of the Hon’ble Supreme Court in the case of Hindustan Construction Co. Ltd. (supra). The jurisdiction under Section 37 of the Act of 1996 does not permit such an exercise. 30. The appellants have also alleged patent illegality and perversity. However, the mere invocation of the expressions 'patent illegality' and 'perversity' cannot enlarge the jurisdiction of the Court under Section 37 of the Act of 1996. The alleged illegality must fall within the recognised parameters of interference under Section 34 of the Act of 1996 and must be such as to justify interference with the arbitral award. Otherwise also, viewed from any angle, we find no perversity, patent illegality or other recognised ground demonstrated by the appellants so as to warrant interference with the order dated 27.02.2019 passed by the learned Commercial Court. 31. We have also gone through the judgments relied upon by learned counsel for the appellants. While, the principles laid down by the Hon’ble Supreme Court in the said judgments are not disputed, however, even therein it has been held that the construction of the terms of a contract is primarily for the Arbitral Tribunal to decide and the scope of interference in an arbitral award is limited and well defined and thus, none of the said judgments advance the case of the appellants. [2026:RJ-JP:37655-DB] 32. (11 of 11) [CMA-3299/2019] Reliance is placed upon recent pronouncement of the Hon’ble Supreme Court dated 29.05.2026 in the case of Madhya Pradesh Road Development Corporation Ltd. v. M/s Jabalpur Corridor Pvt. Ltd. (Civil Appeal No.10877 of 2018), wherein also, while upholding the arbitral award which was passed by the majority of the Arbitral Tribunal and so also the orders passed under Section 34 and under Section 37 of the Act of 1996, it was held as under: “40. From the consistent pronouncements of this Court, it is evident that the jurisdiction under Sections 34 and 37 of the 1996 Act is narrowly circumscribed and cannot be equated with ordinary appellate jurisdiction. The appellate Court under Section 37 does not sit as a court of appeal on the merits of the arbitral award; its role is confined to examining whether the Court under Section 34 has acted within the limits prescribed by law. Interference is permissible only where the Section 34 Court has exceeded its jurisdiction or failed to exercise it within the confines of Section 34, and not merely because another view of the facts or interpretation of the contract may appear preferable. Courts ordinarily must give requisite deference to finality of arbitral awards unless it is palpably clear that the award is perverse and unreasonable. The arbitral tribunal remains the final authority on appreciation of evidence, and concurrent findings under Sections 34 and 37 are entitled to great deference. The statutory scheme thus reinforces the principle of minimal judicial intervention, ensuring that arbitral awards are not disturbed save in circumstances expressly contemplated by the Act.” 33. Applying the aforesaid principles to the facts of the present case, we are unable to accept the submission of the appellants that the impugned order passed by the learned Commercial Court warrants interference in the present appeal. 34. Consequently, the present appeal stands dismissed and the arbitral award dated 26.04.2011 so also the order passed by the learned Commercial Court dated 27.02.2019 is upheld. 35. Pending application(s), if any, stands dismissed. (ANUROOP SINGHI),J Dipesh /98 (ARUN MONGA),J

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Rajasthan HC judgments →

Arbitration & Mediation advocates near the Rajasthan High Court

Dealing with a similar matter? Send a free enquiry to advocates who handle it. Fees are agreed with the advocate directly.

All Arbitration & Mediation advocates in India