The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
13. In view of the settled legal position, interference with the construction of bridge in question, which is an infrastructure project, is uncalled for by this Court, because the feasibility and viability of the bridge and connected road is to be decided by the experts involved in the project. In the instant case, as per the respondents they have not shifted the alignment of the bridge, as alleged by the petitioners, rather it is the stand of the respondents that the bridge, the petitioners are asking for is to be constructed by the Rural Development Department under a different scheme for which DPR stands already approved.
14. For all what has been said above, I find no merit in this petition, the same is, accordingly, dismissed. Interim direction shall also stand vacated. (Moksha Khajuria Kazmi) Judge Jammu.
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
h475
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
WP(C) No.2990/2025
Reserved on: 23.12.2025
Pronounced on: 26.12.2025
Uploaded on : 26.12.2025
Inhabitants of Village Kalsian, Panchayat Kalsina, through its representative
Bahadur Nath, Age 69 years Ex-Sarpanch, Panchayat Kalsian
S/o Late Sh. Paras Ram R/o Village Kalsian
Tehsil Nowshera, District Rajouri
....Petitioner(s)
Through:-Mr. Waheed Choudhary, Advocate
V/s
1.
2.
3.
4.
5.
6.
UT of Jammu and Kashmir
Through Commissioner Secretary PWD (R&B),
Department of Civil Secretariat, Jammu.
Chief Engineer, PWD (R&B), Jammu.
Superintendent Engineer PWD(R&B), Circle Rajouri.
Executive Engineer PWF(R&B), Nowshera.
Parveen Sharma, S/o Tilak Raj
R/o Village Kurlian, Tehsil Kalakote District Rajouri
Sh. Surinder Choudhary
Hon9ble Deputy CM, (Minister for PWD 9R&B)
UT of Jammu & Kashmir.
...Respondent(s)
Through:- Mr. Ravinder Gupta, AAG for R-1 to 4
Mr. Mazhar Ali Khan, Advocate for R-5
None for R-6
Coram: HON’BLE MS. JUSTICE MOKSHA KHAJURIA KAZMI, JUDGE
JUDGMENT
1.
By way of this writ petition, filed on behalf of inhabitants of village
Kalsian through Bahadur Nath, in representative capacity, the
petitioners have invoked extraordinary writ jurisdiction of this Court
vested under Article 226 of the Constitution of India, to quash allotment
order No.SER/R&B/46/4864-68, whereby work for construction of 45
meters span motorable bridge along with approach road connected to
Kalsian Satsang Ghat to Handan Tanda, has been allotted in favour of
respondent No.5, in terms of e-NIT No.12 of 2025-26 dated 03.07.2025.
A further direction is sought upon the respondents, more particularly
respondent No.5 to execute the work strictly as per the DPR prepared
and approved.
FACTUAL MATRIX
2.
The case of the petitioners, as projected in the writ petition, is that in the
year 2023, people of Kalsian and Handan Tanda Panchayat approached
the concerned MLA for completion of pending work, which involves
construction of 20 meter span of motorable bridge along with approach
road connecting Kalsian Satsang Ghar to Handan Tanda. On the
recommendations of the then MLA, DPR for construction of remaining
20 meter motorable span bridge alongwith existing approach road, was
duly prepared and forwarded to respondent Nos. 2 and 3 under
NABARD scheme.
3.
It is stated that while issuance of e-NIT was under consideration,
election in the UT of Jammu & Kashmir was announced, as such, NIT
could not be issued due to imposition of model code of conduct. The
grievance of the petitioner is that after the election was over and
government formed, respondent No.6, elected MLA from the
constituency, who happened to be the Deputy Chief Minister having
portfolio of PWD (R&B), in order to show his power in the political
corridor, managed shifting of the aforesaid work to some other place
under the same nomenclature, got the DPR approved on 08.07.2023,
and got the NIT issued for allotment of contract under new alignment,
which is about six hundred meter away from the already existing road.
The petitioner along with other members of the Panchayat stated to have
approached respondent No.6 with their grievance but of no avail,
aggrieved whereby the petitioners approached this Court by way of
present writ petition on the ground that though the e-NIT has been
issued with the same nomenclature but for totally different work, which
is contrary to the earlier DPR; once the DPR has been approved, same
cannot be shifted to other place without any justifiable reason; besides,
approach road between kalsian Satsangh Ghar to Handan Tanda, pillars
of the bridge connecting both the villages, have already been
constructed and only 20 meter motorable bridge was required to be
constructed, as such, the respondents are duty bound to complete the
execution of work in terms of the earlier DPR dated 08.07.2023;
shifting of the alignment remained unexplained by the official
respondents.
4.
Per contra, official respondents have resisted the claim of the
petitioners by filing their objections. It is stated that a Detailed Project
Report (DPR) for construction of 45 meter span motorable bridge
alongwith approach road connected to Kalsian Satsang Ghar top
Handan Tanda was prepared and sent to respondent Nos. 2 and 3 for
approval. Subsequently, respondent No.4 got the administrative
approval from respondent No.2 vide Order No.60 of 2015-26 dated
03.07.2025 at an estimated cost of Rs.321.00 lacs, for which technical
sanction also stands granted. Consequently, respondent No.3 floated the
tender for the aforesaid work vide e-NIT No.12 of 2025-26 dated
03.07.2025, which came to be allotted in favour of respondent No.5. It
is submitted that the construction work i.e foundation work at proposed
site commenced, after obtaining the mandatory technical vetting from
Dr. S.M.Gupta, Professor (Structures) Department of Civil Engineering,
National Institute of Technology, Kurukshetra, Haryana, foundation
work of the proposed site was commenced. Insofar as 20 meter span of
Motorable bridge along with approach road connecting Kalsian
Satsangh Ghar to Hanan Tanda is concerned, it is stated that the same
has actually been taken up by the Rural Development, Rajouri as per the
DPR approved by the Assistant Commissioner Development, Rajouri.
To substantiate this fact, respondents have placed on record a copy of
the certificate issued by the Block Development Officer, Nowshera vide
No.BDO/NSR/2025-26/895 dated 07.11.2025.
5.
Mr. Waheed Choudhary, learned counsel appearing for the petitioners
would argue that the proposed DPR has been made only on the
directions of the MLA concerned, who happened to be the Deputy Chief
Minister, without any justifiable reasons. He further argues that once the
DPR stands approved in the year 2023, the respondents have no
jurisdiction to change the scope of the work by changing the DPR.
6.
On the other hand, learned counsel for the official respondents submits
that the project of which the petitioners are seeking implementation is
entirely a different project undertaken by the Rural Development
Department regarding which DPR at an estimated cost of Rs.57.90 lacs
was approved by the Assistant Commissioner Development, Rajouri. He
relies upon a certified issued in this regard by the Block Development
Officer, Nowshera. He would further argue that a project of public
importance has been stalled by an interim order of this Court and if the
construction work of the project in question is not allowed, the funds
earmarked for the project during this financial year would be lapsed.
7.
Heard learned counsel for the parties and perused the material available
on record.
8.
According to the petitioner, DPR for the construction of 20 mtr span
motorable bridge along with approach road connected with Kalsian to
Satsang Ghar Road to Handan Tanda was approved in the year 2023,
however, e-NIT could not be issued, whereas, as per the stand taken by
the official respondents, abutments, approaches and filling of works
namely, construction of steel girdar motorable bridge of 23 mtr span
between Handan and Kalsian
was undertaken by the Rural
Development Department under MGNREGA and BADP as per the duly
approved DPR for <Completion of Construction of Steel Girdar
Motorable Birdge 23.00 MTS spans between Handan and Kalsian=,
reliance in this regard is placed on a certificate issued by the Block
Development Officer, Nowshera. Relevant extract of the certificate is
reproduced hereunder:<It is certified that the abutments, approaches and
filling of work namely construction of steel girder
motorable bridge 23.00 mts spans between Handan
and Kalsian were constructed by Rural Development
Department (MGNREGA and BADP).=
9.
It appears that the pillars, which according to the petitioners have been
constructed for the motorable bridge connecting Kalsian Satsangh Ghar
to Handan Tanda, have been constructed by the Rural Development
Department as per the DPR approved for 8completion of construction of
steel Girdar motorable bridge 23 Mts span between Handan and
Kalsian9, it has nothing to do with the Construction of 45 Mtr span
motorable bridge along with approach road connected to Kalsian
Satsangh Ghar to Handan Tanda, for which, after getting administrative
approval as well as technical sanction, contract stands allotted to
respondent No.5, in terms of the e-NIT No.12 of 2025-26 dated
03.07.2025.
10.
Insofar as plea of the petitioners that once the DPR stands approved for
construction of a bridge at a particular place its subsequent change by
fresh DPR is not permissible is concerned, suffice it to say that the
Courts are not at all equipped to decide upon the viability and feasibility
of a particular project and whether the particular alignment would subserve the larger public interest. The Supreme Court in the case of Union
of India v. Kushala Shetty and others, (2011) 12 SCC 69, while
dealing with the issue has observed as under:-
<Here, it will be apposite to mention that NHAI is a
professionally managed statutory body having expertise in the
field of development and maintenance of National Highways.
The projects involving construction of new highways and
widening and development of the existing highways, which
are vital for development of infrastructure in the country, are
entrusted to experts in the field of highways. It comprises of
persons having vast knowledge and expertise in the field of
highway development and maintenance. NHAI prepares and
implements projects relating to development and maintenance
of National Highways after thorough study by experts in
different fields. Detailed project reports are prepared keeping
in view the relative factors including intensity of heavy
vehicular traffic and larger public interest. The Courts are not
at all equipped to decide upon the viability and feasibility of
the particular project and whether the particular alignment
would subserve the larger public interest. In such matters, the
scope of judicial review is very limited. The Court can nullify
the acquisition of land and, in rarest of rare cases, the
particular project, if it is found to be ex-facie contrary to the
mandate of law or tainted due to mala fides.=
11.
From the afore-quoted observations of the Supreme Court, it is manifest
that while exercising writ jurisdiction, this Court cannot go into the
question of viability and feasibility of the construction of the bridge in
question and it is best left to the judgment of the experts of the
respondents.
12.
Time and again, it has been held by the Supreme Court that ordinarily
infrastructure projects should not be interfered. In M/s N.G. Projects
Ltd. v. M/s Vinod Kumar Jain, (2002) 6 SCC 127, the Supreme Court
has held that the High Court should keep in mind the intent of
legislature that infrastructure project should not be stayed. Relevant
portion of the judgment reads thus:<Since the construction of road is an infrastructure project
and keeping in view the intent of the legislature that
infrastructure projects should not be stayed, the High Court
would have been well advised to hold its hand to stay the
construction of the infrastructure project. Such provision
should be kept in view even by the Writ Court while
exercising
its
jurisdiction
under Article
226 of
the
Constitution of India.=
13.
In view of the settled legal position, interference with the construction
of bridge in question, which is an infrastructure project, is uncalled for
by this Court, because the feasibility and viability of the bridge and
connected road is to be decided by the experts involved in the project. In
the instant case, as per the respondents they have not shifted the
alignment of the bridge, as alleged by the petitioners, rather it is the
stand of the respondents that the bridge, the petitioners are asking for is
to be constructed by the Rural Development Department under a
different scheme for which DPR stands already approved.
14.
For all what has been said above, I find no merit in this petition, the
same is, accordingly, dismissed. Interim direction shall also stand
vacated.
(Moksha Khajuria Kazmi)
Judge
Jammu.
26.12.2025
Vinod.
Vinod Kumar
2025.12.23 19:15
I attest to the accuracy and
integrity of this document
Whether the order is speaking : Yes
Whether the order is reportable: No
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review