IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 06th May, 2026
Pronounced on: 17th August, 2026
#
CNR No. DLHC010392462019
+
O.M.P. (COMM) 404/2019 & I.A. No. 13516/2019
INDIA TOURISM DEVELOPMENT CORPORATION
Through:
.....Petitioner
Mr. S.D. Sanjay, Sr. Adv. with Mr.
Krishan Kumar, Mr. Seemant K. Garg,
Mr. Nitin Pal, Ms. Parthvi Ahuja, Mr.
Akanksha
Raj,
Advocates
(M:9560904323)
versus
M/S BAJAJ ELECTRICALS LTD
.....Respondent
Through: Mr. B. Devasekhar and Mr. Pawan
Kumar, Advs.
Mob: 9873276424
CORAM:
HON'BLE MS. JUSTICE MINI PUSHKARNA
JUDGMENT
MINI PUSHKARNA, J.
I.
INTRODUCTION
1.
The present petition has been filed under Section 34 of the Arbitration
and Conciliation Act, 1996 (“Arbitration Act”) for setting aside the arbitral
Award dated 30th October, 2018 (“Award”), and subsequent order for
termination of the mandate dated 01st May, 2019, passed by the Sole Arbitrator
in the arbitration proceedings titled as “Bajaj Electricals Ltd. Versus India
Tourism Development Corporation Ltd”.
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
2.
By way of the impugned Award, the Arbitral Tribunal, in sum and
substance, directed the petitioner herein, i.e., India Tourism Development
Corporation to pay to the claimant/respondent herein the principal amount of
Rs. 46,92,298.22/-, along with interest of Rs. 33,27,886/- for the period from
25th July, 2009 to 16th April, 2013 on Rs. 73,88,556.22, and interest of Rs.
31,17,742.91/-, as pendente lite interest from 17th April, 2013 till 30th October,
2018 on Rs. 46,92,298.22. The respondent herein was also awarded future
interest from the date of the Award till the date of payment.
3.
It is to be noted that vide judgment dated 13th January, 2023, this Court
decided the applications, i.e., I.A. 1351/2019 and I.A. 13519/2019 thereby,
condoning the delay in filing and in re-filing the petition, respectively.
4.
Further, by way of the order dated 08th July, 2025, this Court had
directed the petitioner to deposit the decretal amount, subject to which, there
shall be a stay on the impugned Award. However, the petitioner has failed to
deposit the said amount as directed by this Court.
5.
This Court notes that respondent herein had initially filed company
petitions, namely, CO. PET. 396/2011, CO. PET. 472/2011 and CO. PET.
473/2011, wherein, by way of the order dated 16th April, 2013, this Court has
recorded that the petitioner herein had paid an amount to the tune of Rs.
26,96,258/- to the respondent herein.
II.
BRIEF FACTS
6.
Shorn of unnecessary details, the germane facts leadings to the dispute
between the parties are as follows:
6.1.
The petitioner floated a Notice Inviting Tender (“NIT”) for the work
of Supply, Installation, Testing and Commissioning (“SITC”) of items
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
required for specialized and state of art Illumination/Lightening work at
Safdarjung Tomb Monument in New Delhi. Subsequently, the respondent,
amongst other tenderers, submitted its tender vide Letter dated 06th February,
2007.
6.2.
By way of the Letter of Intent (“LOI”) dated 04th April, 2007, the
petitioner awarded the subject works to the respondent for a total amount of
Rs. 2,08,90,095/-. After acceptance of LOI by the respondent, a detailed Work
Order dated 10th April, 2007 was issued by the petitioner to the respondent.
As per the terms and conditions, the respondent was required to submit
drawings, i.e., cable route plan, electrical load details, enclosure construction
details, etc.
6.3.
Subsequently, the parties herein signed a Contract on 22nd May, 2007,
wherein, the respondent accepted the General Conditions of Contract and
Standard Contract Forms for Engineering and Architectural Works (“GCC”).
6.4.
The GCC, which is part of the NIT and the Contract dated 22 nd May,
2007, was duly signed by the parties, including, Clause nos. 10, 11, 42, 43, 44
therein. Thus, under the Contract, the respondent was required to complete
and commission the subject work, by providing complete material and
manpower required to do so.
6.5.
During the progress of the work, news articles were published in the
newspaper on 03rd October, 2007 and 05th October, 2007, pointing out certain
damages on the Safdarjung Tomb Monument, due to the execution of work
by the respondent. Pursuant thereto, Archeological Survey of India (“ASI”)
desired to revise the fixture lay out plan, and accordingly, ASI and the
petitioner herein entered into a Memorandum of Understanding dated 31st
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
December, 2007 (“MoU”). In terms of the said MoU, a Committee was
constituted to scrutinize and finalize the drawings for light fixtures, placement
plan, fixing arrangements and cable routes.
6.6.
Thereafter, the petitioner vide letter dated 20th March, 2008 requested
the respondent to complete the work as per the revised approved drawings for
cable routes and light fitting fixtures. Further, by way of the letter dated 05th
May, 2008, the petitioner forwarded the duly approved revised drawings and
requested the respondent to restart and complete the subject work at the site.
6.7.
By way of the communication dated 23rd April, 2009, the respondent
sent requisite documents with regard to fully completed and operational
installation of the lightning system at the site. Subsequently, on 01 st June,
2009, the ASI took over the illumination work at the site.
6.8.
Consequently, the respondent submitted the final bill of Rs.
1,18,95,572/- on 08th June, 2009 out of the total value of the work, i.e., Rs.
2,39,75,000/-.
6.9.
Thereafter, the respondent on multiple occasions requested the
petitioner for payment of the outstanding amount, however, on account of
non-payment, dispute arose between the parties, leading to the filing of
Company Petition bearing CO. PET. 472/2011 before this Court. By way of
the order dated 17th April, 2013 passed in the said petition, the Court noted
the statements made by the counsels for the parties on instruction, that they
had no objection to the nomination of an Arbitrator for adjudication of
disputes between the parties. In view of the aforesaid statements, this Court
disposed of the said company petition by appointing an arbitrator for
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
adjudication of the disputes, in terms of the Arbitration Clause, i.e., Clause 48
of the GCC.
6.10. Subsequently, the Sole Arbitrator passed the impugned Award, thereby
awarding the principal amount of Rs. 46,92,298.22/-, along with interest of
Rs. 33,27,886/- for the period from 25th July, 2009 to 16th April, 2013 on Rs.
73,88,556.22, and interest of Rs. 31,17,742.91/-, as pendente lite interest from
17th April, 2013 till 30th October, 2018 on Rs. 46,92,298.22. The respondent
herein was also awarded future interest from the date of the Award till the date
of payment.
6.11. Thereafter, an application for review of the impugned Award for the
Safdurjung Tomb site was moved, however, the Arbitral Tribunal terminated
the arbitral proceedings with regard to the said application, by way of order
dated 01st May, 2019, by stating that none of the parties had deposited the
Arbitrator’s fee, as directed by the Arbitral Tribunal.
6.12. Aggrieved thereby, the petitioner has challenged the impugned Award
on the grounds of it being unreasonable, perverse, patently illegal and failure
of the Arbitrator to adopt a judicial approach in deciding the disputes between
the parties.
III.
SUBMISSIONS MADE BY THE PETITIONER
7.
The following contentions have been put forth by the petitioner for
setting aside the impugned Award:
7.1.
The Sole Arbitrator did not appreciate the provisions of the Contract
and law of contract in correct perspective while allowing the claim with
respect to materials which were neither supplied nor used by the petitioner.
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
7.2.
The Arbitrator failed to consider the deductions of Rs. 11,07,832/-
made by the petitioner towards non-execution of civil and electrical works by
the respondent, in contravention to the Book of Quantities (“BoQ”) and the
Contract dated 22nd May, 2007, as the respondent used 1100D HDPE pipe
instead of 1000D HDPE pipe, used 30W white lamp instead of 32W white
lamp, used 0.95m carbonate tube instead of 1m carbonate tube, and did not
provide MS enclosure for 12V x 50 ground burial fixtures, etc., which was
duly recorded in the Measurement Book no. 1613. Such deductions to the tune
of Rs. 11,07,832/- were then finally incorporated in the Final Measurement
Book, in accordance with the clauses of the Contract dated 22nd May, 2007.
7.3.
The Arbitrator although had noticed that the respondent never came
forward to sign the Measurement Books after 13th August, 2013, however, he
has erroneously proceeded to conclude that the total value of the work done
by the respondent, including, extra items was Rs. 1,97,04,171/-. The said
finding was arrived at by the Arbitral Tribunal on the basis of statement made
by DW-1, i.e., Mr. Dinesh Mahajan, Assistant Manager of the petitioner in his
Evidence Affidavit dated 14th October, 2014, wherein, it has been stated that
the total value of the work done is Rs. 1,95,17,988.62/- along with extra items
of Rs. 1,86,182.60/-.
7.4.
However, Arbitrator has committed perversity in ignoring the defense
of the petitioner and has considered the statements of DW-1 in piecemeal,
since paragraph 83 of Statement of Defense and paragraph 68 of the DW-1’s
evidence expressly stated and deposed, respectively, that the total value of
works done was Rs. 1,85,96,339.22/- after deductions for items of Rs.
11,07,832/-.
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
7.5.
The aforesaid deduction, as duly recorded in the Measurement Book,
were never considered nor dealt with by the Sole Arbitrator, which shows that
the Arbitrator failed to adopt a judicial approach while passing the Award and
committed perversity in not considering the facts available on record thereto.
7.6.
No payment is admissible if the same is not recorded in the
Measurement Books. There is no explanation by the respondent that such
deduction of Rs. 11,07,832/- is not as per the Contract entered into between
the parties. The measurements were never protested and in fact, despite
several requests, the respondent did not come forward to sign the Final
Measurement Book. Therefore, the Award to the extent of the principal
amount of Rs. 11,07,832/- and the accrued interest w.e.f. 25th July, 2009 till
date is liable to be set aside.
7.7.
No Challans were ever deposited by the respondent towards the deposit
of the Service Tax. Under Clause 15(a)(4) of the GCC and Clause 2 of the
Work Order, the cost of materials and works were to be inclusive of all taxes,
including Service Tax, and was to be borne by the respondent.
7.8.
The Arbitral Tribunal in paragraph 38 of the Award erroneously
awarded the withheld amount of Rs. 7,58,507/- towards Service Tax to the
respondent against the bills raised by the respondent for the subject work.
However, the aforesaid amount of Rs. 7,58,507/- was deducted by the
petitioner on account of Service Tax, since the said amount was already
deposited by the petitioner towards service tax with the concerned statutory
authority.
7.9.
Further, the Arbitral Tribunal has reached a perverse finding that during
the course of arguments in the arbitral proceedings, the respondent has
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
submitted the Challans for payment of Service Tax. However, no such
Challans evidencing the proof of deposit of Service Tax were ever submitted
by the respondent, only copies of Service Tax forms, i.e., ST-3 Forms have
been submitted.
7.10. Without prejudice, even if the deduction on account of Service Tax is
not tenable, interest could not have been granted by the Arbitral Tribunal for
the period from 25th July, 2009 till 30th October, 2018, as such Challans were
allegedly submitted by the respondent at the time of final arguments during
the arbitral proceedings.
7.11. Under Clause 4 of the of the Work Order and Clause 16.1 of the GCC,
the respondent was required to adhere to the compliances of the Employees’
State Insurance Act, 1948 (“ESI Act”) and the Employees Provident Funds
and Miscellaneous Provisions Act, 1952 (“EPF & MP Act”) wherein, the
respondent was required to deposit the statutory amounts towards ESI and
EPF to the concerned statutory authorities.
7.12. The Arbitral Tribunal in paragraph 38 of the impugned Award has
erroneously awarded the withheld amount of Rs. 14,86,312/- towards
ESI/EPF to the respondent against the bills raised by the respondent for the
work done. However, the petitioner herein has already deposited the same
amount with the concerned statutory authority.
7.13. The respondent failed to submit the Challans for the deposit of EPF and
ESI, as required under Clause 4 of the Work Order and Clause 16.1 of the
Contract, and thus, the respondent was never entitled to the amounts deducted
for non-deposit of EPF/ESI as it was the responsibility of the principal
employer, i.e., petitioner to ensure the compliances of such labour laws.
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
7.14. Further, the Arbitral Tribunal committed perversity and failed to adopt
a judicial approach, by reaching an erroneous finding that the Contract dated
22nd May, 2007 allows the release of ESI/EPF deductions to the respondent
merely upon submission of Indemnity Bonds. However, there is no such
stipulation under the said Contract.
7.15. In view of the aforesaid, the Arbitral Tribunal had no jurisdiction to
make an Award against the specific terms of the Contract. Therefore, the
Award regarding the release of ESI/EPF deduction is liable to be set aside.
7.16. Even otherwise, if the deduction on account of ESI/EPF is not tenable,
interest could not have been granted by the Arbitrator for the period from 25th
July, 2009 till 30th October, 2018, as the Indemnity Bonds were allegedly
submitted by the respondent at the time of final arguments during the
arbitration proceedings.
7.17. Under Clause 16.1 of the GCC, the respondent was required to adhere
to the compliances of all labour welfare laws, including, the Building and
Other Construction Workers Welfare Cess Act, 1996 (“Workers Welfare
Cess Act”), wherein, the respondent was required to deduct 1% towards
labour cess from the bills of the petitioner and deposit the statutory amounts
towards the concerned statutory authorities.
7.18. The Arbitral Tribunal erroneously awarded the withheld amount of Rs.
1,85,963/- towards labour cess to the respondent against the bills raised by the
respondent for the works done. The aforesaid amount had already been
deposited by the petitioner towards labour cess with the concerned statutory
authorities, and the same has not been disputed.
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
7.19. The aforesaid amount also stands reflected in the Measurement Book,
which was completely ignored by the Arbitral Tribunal. It is evident that the
Arbitrator reached an erroneous finding that the petitioner has not shown as
to why labour cess was not deducted from the Running Account bills if it was
payable and that dispute has not been raised during the proceedings about the
liability of the respondent or non-payment of labour cess by the respondent.
7.20. Thus, the petitioner was entitled to enforce recovery under Clause 47.2
from the final bill of the respondent. Therefore, the Award regarding the
release of labour cess deduction of Rs. 1,85,963/- is liable to be set aside.
7.21. The Sole Arbitrator erroneously awarded interest @ 12% per annum,
which is excessive when all the payments were already made by the petitioner
to the respondent from time to time and final payment could not be made only
on account of the fact that despite several communications, the respondent did
not come forward to sign the Measurement Book and to take the payment.
7.22. The petitioner also made a payment of Rs. 13,93,368/- to the
respondent vide Cheque no. 302416 dated 09th July, 2019, and therefore,
future interest on the same ought not to be granted.
7.23. The total value of the work done by the respondent, as accepted on 13 th
August, 2008, was Rs. 1,28,82,376.20/-. The fifth and final bill submitted by
the respondent was recorded in the Measurement Book by the Site Engineer.
Further, the total value of the work done on completion and handing over of
the site was to the tune of Rs. 1,90,45,990/-. A perusal of the Measurement
Book shows that the net payable amount comes to Rs. 57,06,432/- and
subsequent to the directions of this Court, an amount of Rs. 26,96,258/- was
paid in April, 2013 after the legitimate deductions.
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
7.24. The aforesaid deductions are legitimate deductions, including, the
statutory deductions, and thus, no amount is payable except what is
reimbursable upon satisfaction of the respondent.
7.25. Therefore, after taking into consideration all the aforesaid deductions
of Rs. 35,38,614/- and post award payment of Rs. 13,93,368/-, the petitioner
is entitled to a recovery of Rs. 2,39,629.78/- from the respondent against the
principal award amount of Rs. 46,92,298.22/-. Thus, the respondent is not
entitled to any amount towards interest.
7.26. The Sole Arbitrator failed to appreciate that for ascertaining the
intention of the parties, documents need to be read as a whole, and one has to
look at the substance of the document and not the form/nomenclature the
parties have adopted.
7.27. The respondent has failed to furnish any evidence that any work other
than the work recorded in the Measurement Book was undertaken by the
respondent. The claim of the respondent that work done on earlier occasion
was demolished has not been proved by any document on record.
7.28. Further, the contention of the respondent that the additional works were
done on the instruction of the petitioner is false and unless the same is in
writing, it cannot fasten any liability. Moreover, the bills furnished by the
respondent towards the additional works are false and fabricated. The said
additional works are for the period before 13 th August, 2008, till when the
Measurement Book was signed, and thus, no claim for any additional work
can be put forth by the respondent. Considering the same, the Measurement
Book is final and no amount can be claimed beyond the Measurement Book.
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
IV.
SUBMISSIONS MADE BY THE RESPONDENT
8.
Rebutting the contentions of the petitioner, respondent has made the
following submissions before this Court.
8.1.
The respondent herein was allotted the illumination/lighting work at
three sites, namely, Safdurjung Tomb Monument, Purana Quila Monument
and Subj Burj Monument by the petitioner. Subsequently, for the disputes with
respect to the Purana Quila Monument and Subj Burj Monument, the Arbitral
Tribunal passed the Awards dated 02nd February, 2018 and further clarificatory
order dated 30th October, 2018, whereas, the impugned Award dated 30th
October, 2018 was passed in relation to the Safdurjung Tomb Monument.
8.2.
As far as the Award passed for Purana Quila Monument and Subj Burj
Monument are concerned, the same has attained finality and are binding on
the parties in terms of Section 35 of the Arbitration Act, since no objection
has been filed against the same. The only objection filed by the petitioner in
the present petition pertains to impugned Award with respect to the
Safdurjung Tomb Monument.
8.3.
The petitioner herein alleged that the terms and conditions of the
Contract dated 22nd May, 2007, inter alia, provided that the results of the
findings of the Chief Technical Examiner shall be binding on the parties.
Since, Chief Technical Examiner inspected the work executed by the
respondent only at Purana Quila on 15th December, 2008 and 16th December,
2008 and not the Safdurjung Tomb Monument, and final findings of the Chief
Technical Examiner were yet to be received, the petitioner herein could not
release the final payment with regard to the Safdurjung Tomb Monument as
well.
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
8.4.
The Arbitral Tribunal in paragraph 53 of the impugned Award has
rightly considered the CTE’s replies dated 20th December, 2012 and 07th
January, 2013 to the Right to Information (“RTI”) applications filed by the
respondent before the CTE. In the reply dated 20th December, 2012, it has
been specifically mentioned that Chief Technical Examiner does not issue any
final report to its extensive examination reports, whereas, the reply dated 07th
January, 2013 clearly states that sites at Subj Burj and Safdurjung Tomb
Monuments were not inspected by the CTE.
8.5.
By relying upon the said replies of the CTE, the Arbitral Tribunal has
correctly come to the finding that defense of the respondent for non-payment
of outstanding dues of Safdurjung Tomb Monuments is untenable since the
Chief Technical Examiner does not submit any final report, and hence, there
was no ground for withholding the payments.
8.6.
Further, the contentions of the petitioner herein that the respondent did
not come forward to sign the Measurement Book is misplaced as the petitioner
processed the final bill only after filing of the claim petition in the year 2014,
as apparent from the statement of DW-1, i.e., Mr. Dinesh Mahajan.
8.7.
The contentions of the petitioner that there are discrepancies in the
impugned Award while calculating the amounts under different heads, such
as, for Service Tax, 1% Labour cess and ESI/EPF, are liable to be rejected.
The Arbitral Tribunal, in relation to Purana Quila Monument, has in
paragraphs 27 and 28 of the Award dated 02nd February, 2018, has given an
identical finding, and the same has not been challenged by the petitioner
herein.
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
8.8.
The Court while dealing with a petition filed under Section 34 of the
Arbitration Act can set aside an Award only on certain limited grounds and
the petitioner herein cannot come and furnish fresh evidence to improve their
case.
8.9.
The Work Order dated 10th April, 2007, issued by the petitioner, in
paragraph 4, clearly states that the petitioner shall be solely responsible for
complying with all labour related laws. The said paragraph further states that
in the event of any liability on the petitioner by virtue of it being a principal
employer, due to failure of the respondent to comply with such laws, the
respondent will be liable to indemnify and reimburse the said amount.
8.10. In terms of the aforesaid, the respondent herein has provided/submitted
the requisite Indemnity Bonds to the petitioner and the same has been rightly
recorded by the Arbitral Tribunal in paragraph 38 of the impugned Award by
stating that the respondent herein has submitted the necessary Indemnity
Bonds and therefore, the petitioner herein is not entitled to deduct any
amounts on account of ESI/EPF.
8.11. The Arbitral Tribunal in the 32nd arbitration proceeding dated 11th
August, 2017, has clearly recorded that the counsel for the respondent herein
has filed copies of the Service Tax Challans and Tax Deducted at Source
(“TDS”) Certificates. Further, the impugned Award in paragraph 38 also
records that “during the course of arguments, the Claimant submitted the
Challans for payment of ESI/EPF”. Moreover, the order passed by the
Arbitral Tribunal in 36th arbitration proceedings dated 21st December, 2017,
also records that the respondent herein has filed copies of the Indemnity
Bonds submitted with the respondent with respect to all the three cases for the
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
claims towards EPF and ESI dues. In view of the aforesaid, the respondent
has complied with the requirements mentioned in the Contract between the
parties by furnishing the Indemnity Bonds and the petitioner illegally
withheld the amount.
8.12. The argument put forth by the petitioner with regard to deduction of Rs.
11,07,832/- towards non-execution of civil and commercial electrical works,
as recorded in the Measurement Book, not being considered by the Arbitral
Tribunal is untenable, since firstly, the petitioner has failed to provide any
break-up of the said amount before the Arbitral Tribunal and secondly, the
said Measurement Book only bears the signature of the petitioner.
8.13. Though the petitioner had raised the argument that the Measurement
Book was not signed by the respondent despite various opportunities,
however, the said Measurement Book only bears the signature of the Site
Engineer of the petitioner. In contrast, the Measurement Book was required
to be signed by three persons, namely, the Contractor/respondent, Site
Engineer and the Architect Consultant.
8.14. It is pertinent to mention that the issue with respect to said deduction
of Rs. 11,07,832/- was not raised before the Arbitral Tribunal by the petitioner
and was subsequently raised by filing a review application, wherein the
petitioner failed to deposit the requisite fee for the Arbitrator, leading to the
termination of proceedings for the review. Thus, the petitioner herein cannot
raise the ground that the Arbitral Tribunal failed to consider the deductions
made by respondent, at this stage, when the petitioner itself failed to press its
claim before the Arbitral Tribunal.
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
V.
ANALYSIS AND FINDINGS
9.
I have heard learned counsels appearing for the parties and have
perused the relevant documents on record.
10.
Before dealing with the objections to the impugned Award passed by
the learned Arbitrator, it would be apposite to note the position of law with
regard Section 34 of the Arbitration Act. The law is well settled that in a
petition under Section 34 of the Arbitration Act, the Court does not sit in
appeal over the Arbitral Award.
11.
Thus, in the case of MMTC Limited Versus Vedanta Limited, (2019) 4
SCC 163, the Supreme Court held as follows:
“xxx xxx xxx
11. As far as Section 34 is concerned, the position is well-settled by
now that the Court does not sit in appeal over the arbitral award and
may interfere on merits on the limited ground provided under Section
34(2)(b)(ii) i.e. if the award is against the public policy of India. As
per the legal position clarified through decisions of this Court prior to
the amendments to the 1996 Act in 2015, a violation of Indian public
policy, in turn, includes a violation of the fundamental policy of Indian
law, a violation of the interest of India, conflict with justice or morality,
and the existence of patent illegality in the arbitral award. Additionally,
the concept of the “fundamental policy of Indian law” would cover
compliance with statutes and judicial precedents, adopting a judicial
approach, compliance with the principles of natural justice,
and Wednesbury [Associated Provincial Picture Houses v. Wednesbury
Corpn., (1948) 1 KB 223 (CA)] reasonableness. Furthermore, “patent
illegality” itself has been held to mean contravention of the substantive
law of India, contravention of the 1996 Act, and contravention of the
terms of the contract.
12. It is only if one of these conditions is met that the Court may
interfere with an arbitral award in terms of Section 34(2)(b)(ii), but
such interference does not entail a review of the merits of the dispute,
and is limited to situations where the findings of the arbitrator are
arbitrary, capricious or perverse, or when the conscience of the Court
is shocked, or when the illegality is not trivial but goes to the root of the
matter. An arbitral award may not be interfered with if the view taken
by the arbitrator is a possible view based on facts. (See Associate
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
Builders v. DDA [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015)
2 SCC (Civ) 204]. Also see ONGC Ltd. v. Saw Pipes Ltd. [ONGC
Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705]; Hindustan Zinc
Ltd. v. Friends Coal Carbonisation [Hindustan Zinc Ltd. v. Friends
Coal Carbonisation, (2006) 4 SCC 445]s; and McDermott
International Inc. v. Burn Standard Co. Ltd. [McDermott International
Inc. v. Burn Standard Co. Ltd., (2006) 11 SCC 181] )
13. It is relevant to note that after the 2015 Amendment to Section
34, the above position stands somewhat modified. Pursuant to the
insertion of Explanation 1 to Section 34(2), the scope of contravention
of Indian public policy has been modified to the extent that it now
means fraud or corruption in the making of the award, violation of
Section 75 or Section 81 of the Act, contravention of the fundamental
policy of Indian law, and conflict with the most basic notions of justice
or morality. Additionally, sub-section (2-A) has been inserted in
Section 34, which provides that in case of domestic arbitrations,
violation of Indian public policy also includes patent illegality
appearing on the face of the award. The proviso to the same states
that an award shall not be set aside merely on the ground of an
erroneous application of the law or by reappreciation of evidence.
xxx xxx xxx”
12.
(Emphasis Supplied)
Further, the Court under Section 34 of the Arbitration Act cannot re-
appreciate evidence and substitute its own conclusion to the one arrived at by
the learned Arbitrator, even though a different conclusion can be reached on
re-appreciating evidence. An Arbitral Award would not be interfered by the
Court if the view taken by the Arbitrator is a possible view based on facts of
the case.
13.
In this regard, reference is made to the decision in the case of OPG
Power Generation Private Limited Versus Enexio Power Cooling Solutions
India Private Limited and Another, (2025) 2 SCC 417, wherein, it has been
held that while exercising power under Section 34 of the Arbitration Act, the
Court does not sit in appeal over the Arbitral Award. Interference with an
Arbitral Award is only on limited grounds as set out in Section 34 of the
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
Arbitration Act. A possible view by the Arbitrator on facts is to be respected
as the Arbitrator is the ultimate master of the quantity and quality of evidence
to be relied upon. It is only when an Arbitral Award could be categorised as
perverse, that on an error of fact an Arbitral Award may be set aside. Further,
a mere erroneous application of the law or wrong appreciation of evidence by
itself is not a ground to set aside an Award.
14.
Delving on the issue of reasoning to be given in an Award, the
Supreme Court in the case of Dyna Technologies Private Limited Versus
Crompton Greaves Limited, (2019) 20 SCC 1, held that the mandate under
Section 31(3) of the Arbitration Act is to have reasoning which is intelligible
and adequate and, which can in appropriate cases be even implied by the
Courts from a fair reading of the Award and documents referred to
thereunder, if the need be. The aforesaid provision does not require an
elaborate judgment to be passed by the arbitrators having regard to the speedy
resolution of dispute.
15.
The Supreme Court in the aforesaid case held that an order should be
proper, intelligible and adequate, in order to consider the same as being
reasoned. If the challenge to an Award is based on adequacy of reasons, the
Court while exercising jurisdiction under Section 34 would adjudicate the
validity of such an Award based on the degree of particularity of reasoning
required having regard to the nature of issues falling for consideration. Even
if the Court comes to a conclusion that there were gaps in the reasoning for
the conclusions reached by the Tribunal, the Court needs to have regard to
the documents submitted by the parties and the contentions raised before the
Tribunal so that Awards with inadequate reasons are not set aside in casual
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
and cavalier manner. On the other hand, ordinarily unintelligible Awards are
to be set aside, subject to party autonomy to do away with the reasoned
Award. Therefore, the courts are required to be careful while distinguishing
between inadequacy of reasons in an Award and unintelligible Awards.
16.
Having considered the exposition of law, this Court proceeds to deal
with the objections as raised by the petitioner.
(I) Total Value Of Work, Including Extra Items:
17.
The first ground on which the petitioner has challenged the Award is
that though the Arbitrator observed that the claimant/ respondent herein never
came forward to sign the Measurement Book after 13th August, 2008, the
Arbitrator erroneously concluded that the total value of work done by the
claimant/ respondent herein, including extra items, was Rs. 1,97,04,171.22/(Rupees One Crore Ninety Seven Lacs Four Thousand One Hundred Seventy
One and twenty two paisa only). The petitioner contends that this conclusion
was drawn solely on the basis of the statement made by the petitioner’s own
witness, being DW-1, i.e., Dinesh Mahajan, whereby, in his Evidence
Affidavit, it is stated that the total value of the work done was Rs.
1,95,17,988.62/- (Rupees One Crore Ninety Five Lacs Seventeen Thousand
Nine Hundred Eighty Eight and Sixty Two paisa only) along with extra items
of Rs. 1,86,182.60/- (Rupees One Lac Eighty Six Thousand One Hundred
Eighty Two and Sixty paisa only). Petitioner has further stated that the
Arbitrator committed perversity in ignoring the defense of the petitioner and
considering the statements of DW-1 in piecemeal as the petitioner in
paragraph 83 of its Statement of Defense and DW-1 in paragraph 68 of his
Evidence Affidavit expressly stated and deposed, respectively that the total
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
value of works done was Rs. 1,85,96,339.22/- (Rupees One Crore Eighty
Five Lacs Ninety Six Thousand Three Hundred Thirty Nine and Twenty Two
paisa only) after deduction for items of Rs. 11,07,832/- (Rupees Eleven Lacs
Seven Thousand Eight Hundred Thirty Two only).
18.
In this regard, it is pertinent to note that in paragraphs 21 and 22 of the
Evidence Affidavit of DW-1, i.e., Mr. Dinesh Mahajan, following categorical
admissions have been made:
“xxx xxx xxx
xxx xxx xxx”
19.
A perusal of the above-noted submissions made by the petitioner in its
Evidence Affidavit of its witness DW-1, clearly and evidently shows that as
per the petitioner’s case itself, the total value of the work done by the
claimant/respondent herein was to the tune of Rs. 1,95,17,988.62/- and the
total amount of extra items executed by the claimant/respondent herein was
Rs. 1,86,182.60/-. Thus, it is evident that the aforesaid finding of the learned
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
Arbitrator is based upon the submissions of the petitioner itself as given in
the Evidence Affidavit of its witness. Thus, a finding by the learned
Arbitrator on the basis of submissions of the petitioner itself, cannot be
faulted with. Clearly, such finding by the learned Arbitrator is based upon the
evidence on record. This Court in the present proceedings cannot go into the
merits of the evidence or the findings of the learned Arbitrator, as the present
proceedings are not in the nature of an appeal. Once the findings of the
learned Arbitrator are found to be based on some evidence, the same cannot
be set aside by reappreciating the evidence.
20.
The contention of the petitioner that despite the amounts recorded in
the Measurement Book no. 1613, after the date of 13th August, 2008, not
being held admissible, the Arbitrator erroneously concluded that the total
value of work done by the claimant/ respondent herein, including extra items,
was Rs. 1,97,04,171/-, also fails to shock the conscience of this Court as to
warrant any interference. When the total value of work and the value of extra
items have been admitted by the petitioner, the same does not warrant any
interference under Section 34 of the Arbitration Act.
21.
The Supreme Court in the case of Ramesh Kumar Jain Versus Bharat
Aluminum Company Limited (BALCO), 2025 SCC OnLine SC 2857, held
that if there is some evidence, even a single witness’s testimony on which the
Arbitrator could rely upon and has relied upon, then the Court cannot regard
the conclusion of the Arbitrator as being patently illegal. The relevant portion
of the judgment is reproduced as under:
“xxx xxx xxx
35. Considering the aforesaid precedents, in our considered
view, the said terminology of ‘patent illegality’ indicates more
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
than one scenario such as the findings of the arbitrator must
shock the judicial conscience or the arbitrator took into account
matters he shouldn't have, or he must have failed to take into
account vital matters, leading to an unjust result; or the decision
is so irrational that no fair or sensible person would have arrived
at it given the same facts. A classic example for the same is when
an award is based on “no evidence” i.e., arbitrators cannot
conjure figures or facts out of thin air to arrive at his findings. If
a crucial finding is unsupported by any evidence or is a result of
ignoring vital evidence that was placed before the arbitrator, it
may be a ground the warrants interference. However, the said
parameter must be applied with caution by keeping in mind that
“no evidence” means truly no relevant evidence, not scant or
weak evidence. If there is some evidence, even a single witness's
testimony or a set of documents, on which the arbitrator could
rely upon or has relied upon to arrive at his conclusions, the
court cannot regard the conclusion drawn by the arbitrator as
patently illegal merely because that evidence has less probative
value. This thin line is stood crossed only when the arbitral
tribunal's conclusion cannot be reconciled with any permissible
view of the evidence.
xxx xxx xxx”
(Emphasis Supplied)
(II) Deduction Of Rs. 11,07,832/- Towards Non-Execution of Civil And
Electrical Works:
22.
According to the petitioner, the deduction of Rs. 11,07,832/- was
towards non-execution of civil and electrical works by the claimant/
respondent herein. As per the petitioner, the said non-execution by the
claimant/respondent herein was in contravention of the BoQ and the Contract,
as the claimant/ respondent herein used 1100D HDPE pipe instead of 1000D
HDPE pipe; 30W white lamp instead of 32W white lamp; 0.95m carbonate
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
tube instead of 1m carbonate tube; and did not provide MS enclosure for 12V
x 50 ground burial fixture, etc., which was duly recorded in the Measurement
Book no. 1613.
23.
Thus, as per the petitioner, such deductions were done in accordance
with the clauses of the Contract and were then recorded in the Final
Measurement Book. However, the same were never considered nor dealt with
by the learned Arbitrator.
24.
Per contra, the respondent herein has argued that the contention put
forth by the petitioner regarding the deduction of Rs. 11,07,832/- towards
non-execution of civil and commercial electrical works, as recorded in the
Measurement Book, not being considered by the Arbitral Tribunal is
untenable, since the petitioner has failed to provide any break-up of the said
amount before the Arbitral Tribunal.
25.
The respondent has further stated that the petitioner had raised the
argument that the Measurement Book was not signed by the respondent
despite various opportunities, however, the said Measurement Book only
bears the signature of the Site Engineer of the petitioner. In contrast, the
Measurement Book was required to be signed by three persons, namely, the
Contractor/respondent, Site Engineer and the Architect Consultant.
26.
On the basis of the evidence on record, the learned Arbitrator has held
that the work done till 13th August, 2013, as recorded in the Measurement
Book, would be the value of the work undertaken by the claimant/ respondent
herein, by considering that the Measurement Book was lastly signed by the
claimant/respondent on the said date. The finding of the learned Arbitrator in
this regard, is as follows:
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
“xxx xxx xxx
31. The Claimant has signed the Measurement Books up to
13.08.2013. The value of work done till this date cannot be
disputed by the Claimant. The Claimant has not filed any record
maintained by them in regular course of business to show the total
value of work done. The Respondents have filed the Measurement
Books where the work done by the Claimant has been recorded. It
is the case of the Claimant this Measurement Book was not
recorded by the Respondent in its presence. On the other hand it
is the case of the Respondent that the Claimant did not come
forward to sign the Measurement Books after 13.08.2013.
Whatever may be the case there is no other evidence to show the
total value of work done by the Claimant. I, therefore hold that the
total value of work done by the Claimant including Extra items
was Rs. 1,97,04,171.22. ---- (A)
xxx xxx xxx”
27.
This Court may note that as per the Measurement Book no. 1613, the
Measurement Book was signed up till 51 pages bearing the signatures of the
Contractor, Site Engineer, and Architect/Consultant, whereby, the last
signatures are recorded to be done on 13th August, 2008. The deduction of
Rs. 11,07,832/- is subsequently recorded at page 66 of the Measurement Book
no. 1613, whereby, the said page only bears the signature of the Site
Engineer, in the following manner:
“xxx xxx xxx
xxx xxx xxx”
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
28.
The claim raised by the petitioner herein is a question of appreciation
of evidence, specifically, pertaining to whether the deductions recorded in
one portion of the Measurement Book were duly carried forward into the final
computation of the payable amount. The learned Arbitrator has categorically
held that since the claimant/respondent herein never came forward to sign the
Measurement Book after 13th August, 2008, the amounts stipulated thereafter
would not be considered. Since the amount of Rs. 11,07,832/-, is recorded in
the Measurement Book no. 1613 after 13th August, 2008, and was not signed
by all the concerned officials, henceforth, it has been excluded by the learned
Arbitrator in the computation of the final payable amount.
29.
In this regard, this Court further notes the statements of DW-1, i.e., Mr.
Dinesh Mahajan, Assistant Manager of the petitioner, placed on record before
the Arbitrator in the Evidence Affidavit qua the SITC work of Safdarjung
Tomb. In the said affidavit, the said witness stated that the Measurement
Book has not been scrutinized/checked by the ITDC Scrutiny Cell and
Accounts Department, and thus, no amount can be determined to be payable
even if the same has been recorded in the Measurement Book. The relevant
portions of the said affidavit is extracted hereunder:
“xxx xxx xxx
…. The total value of work is based on the measurements recorded in
the measurement book but the same have not been scrutinized/checked
by ITDC Scrutiny Cell and Accounts Department as till date and in
the absence of CTE finding, no amount can be determined to be
payable even if the same has been recorded in the measurement book.
The total value of work done duly accepted by M/s Bajaj up to
13.08.2008 was of 1,28,82,376.20. The 5th and final bill submitted by
M/s Bajaj was recorded in the measurement book by the Site Engineer.
The total value of work done on completion and handing over
recorded was 1,90,45,990.00. The measurements recorded in
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
measurement book have not been scrutinized/checked by ITDC
Scrutiny Cell and Accounts Department as till date….
xxx xxx xxx”
30.
Additionally, it is pertinent to afford attention to the cross-examination
of DW-1, i.e., Mr. Dinesh Mahajan, Assistant Manager of the petitioner, who
expressly stated that he does not remember if any objection or deficiencies
were noticed at the time of handing over the project after completion.
Furthermore, he admitted that there was no enquiry by CVC, and that there
was no visit by Chief Technical Engineer of CVC for Safdurjung Tomb
Monument. He further stated that he did not remember if there was any site
order book in which the defects in this work were noted. The relevant portion
of DW-1’s cross-examination dated 20th November, 2014, reads as under:
“xxx xxx xxx
It is correct that all the lights were switched on at the time of
inauguration. Electric connection was available and the lighting was
done from that connection. I do not remember if two generator sets
were deployed on the day of inauguration by the claimant to light the
monument. I do not remember and therefore cannot deny that there
was no electricity connection available on the day of inauguration. It
is correct that Ex. CWR-17 is the first drawing. It is correct that EX.
R-45 is the second drawing. This is the approved drawing and the
work was done according to this drawing. It is correct that after
completion of the work the site was handed over to ASI. We do not
have any site order book. I do not remember if any objections or
deficiencies were noticed at the time of handing over the project after
the completion. It is correct that there was no enquiry by CVC. There
was no visit by Chief Technical Examiner Under CVC for this
monument. I do not remember if there was any site order book in
which the defects in this work were noted. It is wrong to suggest that
we have intentionally not produced the site order book because it
contained all the details of the work done.
xxx xxx xxx”
(Emphasis Supplied)
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
31.
Further, DW-1 has admitted that the work was done by the
claimant/respondent under the supervision of the petitioner’s officers. In this
regard, the relevant portion of DW-1’s cross-examination dated 24th April,
2015, reads as under:
“xxx xxx xxx
It is not in my knowledge that Site Order Book and Hindrance Register
are two different documents and are maintained separately. It is
correct that the agreement Ex. R-11 provides for maintainance of
Hindrance Register in clause 28.3 and for Site Order Book in clause
35.5. I have seen the Measurement Book No. 1613 at page No. 60. It
bears my signatures at point ‘A’ on the noting Mark-B which is my
hand. I do not remember whether the cable route drawings were
revised several times. It is wrong to suggest that the delay was due to
several revisions of cable route drawings and not on account of the
claimant. It is incorrect to suggest that ITDC officers used to
supervise the work on day to day basis however, they used to come
regularly and check the work. It is correct that the work was done by
the claimant under the supervision of ITDC officers…
xxx xxx xxx”
(Emphasis Supplied)
32.
In view of the aforesaid, it is evident that no deficiency in execution of
work has been recorded by the petitioner. This fact becomes all the more
important considering the fact that it is an admitted position that the work
was executed by the claimant/respondent herein under the supervision of the
officers of the petitioner. Furthermore, it has also come on record that no
inspection of the work at Safdarjung Tomb monument was carried out by the
Chief Technical Engineer. Therefore, there is nothing on record to justify the
deduction of Rs. 11,07,832/- towards alleged non-execution of civil and
electrical works. The findings of the learned Arbitrator are based on the
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
evidence on record. No patent illegality in the said finding has been pointed
out.
33.
This Court is of the considered opinion that the decision of the learned
Arbitrator, in not admitting the amounts recorded in the Measurement Book
no. 1613, after 13th August, 2008, let alone the amount of Rs. 11,07,832/-, is
based on appreciation of evidence on record. Therefore, the objection raised
by the petitioner does not fall within the parameters of interference by this
Court in the present proceedings.
(III) Deduction Of Rs. 14,86,312/- Towards ESI/EPF:
34.
Petitioner has stated that under Clause 4 of the Work Order dated 10th
April, 2007, and Clause 16.1 of the GCC, the respondent was required to
adhere to the compliances of labour laws including the ESI Act and the EPF
& MP Act. In view of the said compliance, the respondent was required to
deposit the statutory amounts towards ESI and EPF to the concerned statutory
authorities.
35.
Clause 4 of the Work Order dated 10th April, 2007, categorically states
that the respondent herein shall be solely responsible for complying with all
provisions related to ESI and EPF & MP Act, and in the event of any liability
on the petitioner herein by virtue of being the principal employer, the
respondent herein shall indemnify and reimburse the amount payable to the
petitioner herein. Clause 4 of the said Work Order is reproduced as
hereinunder:
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
“xxx xxx xxx
xxx xxx xxx”
36.
Clauses 16.1 and 16.2 of the GCC also require the respondent herein
to comply with the provisions of the ESI Act and the EPF & MP Act, and to
indemnify the petitioner herein against any payment made. The said Clauses
16.1 and 16.2 of the GCC read as follows:
“xxx xxx xxx
xxx xxx xxx”
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
37.
In this regard, this Court also notes Clause 16 of the Special Conditions
to Contract (“SCC”), which is reproduced as under:
“xxx xxx xxx
xxx xxx xxx”
38.
It is the case of the petitioner that the learned Arbitrator awarded the
withheld amount of Rs. 14,86,312/- towards ESI/EPF to the respondent
against the bills raised by the respondent for the works done, even though the
aforesaid amount has already been deposited by the petitioner with the
concerned statutory authority. The petitioner has further contended that the
Indemnity Bonds submitted by the respondent herein are not sufficient, as the
respondent herein was required to submit Challans.
39.
Petitioner has also stated that without prejudice to his earlier
contentions, even if the deduction on account of ESI/EPF is not tenable,
interest could not have been granted by the learned Arbitrator for the period
from 25th July, 2009, till 30th October, 2018, as such Indemnity Bond was
allegedly submitted by the respondent at the time of final arguments during
the arbitral proceedings.
40.
It is to be noted that in terms of the aforesaid contractual covenants, it
is evident that the claimant/respondent herein was required to indemnify the
petitioner herein for any payment made by the petitioner in regard to EPF and
ESI dues. The record categorically evinces that the respondent herein has
provided the requisite Indemnity Bond to the petitioner. Thus, on the said
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
basis, the learned Arbitrator has held that since the respondent herein has
submitted the necessary Indemnity Bond, and therefore, the petitioner herein
is not entitled to deduct any amounts on account of ESI/EPF dues.
41.
Moreover, the order passed by the Arbitral Tribunal in the 36 th
Arbitration Proceeding dated 21st December, 2017, also records that the
respondent herein has filed copies of the Indemnity Bonds submitted with the
respondent with respect to all the three cases for the claims towards EPF and
ESI dues. Therefore, it is to be noted that the respondent has complied with
the requirements mentioned in the Contract between the parties by furnishing
the Indemnity Bond. Therefore, on the basis of evidence and facts on record,
the learned Arbitrator has arrived at the decision that the petitioner had
illegally withheld the amount. Thus, the learned Arbitrator has held as
follows:
“xxx xxx xxx
38. The Respondent has also sought to deduct a sum of Rs. 14,86,312/+7,58,507/- = 22,44,819/- on account of Service Tax, ESI/EPL
withheld. During the course of arguments the Claimant submitted the
challans for payment of ESI/EPF. The agreement between the parties
provides that the amounts deposited by the contractor on account of
ESI/EPF have to be reimbursed on submission of Indemnity Bond. The
Claimant has now submitted the necessary Indemnity Bonds and
therefore the Respondent is not entitled to deduct any amounts on
account of ESI/EPF.
xxx xxx xxx”
42.
In the 36th Arbitration Proceeding dated 21st December, 2017, the
learned Arbitrator has made the following observations:
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
“
”
43.
The Indemnity Bond as submitted by the respondent and duly
recorded, is as follows:
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
“
”
44.
In view of the above, this Court is of the considered opinion that the
finding of the learned Arbitrator in this regard, is based upon interpretation
of the contractual terms between the parties and the evidence on record. Thus,
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
this Court finds no reason to interfere with the finding of the learned
Arbitrator.
(IV) Deduction Towards Service Tax:
45.
The petitioner has contended that the learned Arbitrator erroneously
awarded the withheld amount of Rs. 7,58,507/- towards Service Tax to the
respondent, against the bills raised by the respondent for the works done. The
aforesaid amount was already deposited by the petitioner towards Service
Tax with the concerned statutory authorities.
46.
The amount of Rs. 7,58,507/- was deducted by the petitioner on
account of Service Tax. As per the petitioner, however, the respondent till
date has not furnished the proof of deposit of such Service Tax and therefore,
the learned Arbitrator reached a perverse finding that during the course of the
arguments in the arbitral proceedings, the respondent has submitted the
Challans for payment of Service Tax.
47.
This Court takes note of the Clause 20 of the SCC, as per which the
Contractor, i.e., the respondent herein was only required to submit the proof
of Service Tax as paid against the Contract before payment of final bill.
Clause 20 of the SCC is reproduced as under:
“xxx xxx xxx
xxx xxx xxx”
48.
In this regard this Court notes the 32nd Arbitration Proceeding dated
11th August, 2017, whereby, it was expressly recorded that the claimant/
respondent herein has filed copies of the Service Tax Challans and TDS
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
Certificates. The said arbitration proceedings dated 11th August, 2017 is
reproduced as under:
“
”
49.
Therefore, having placed the requisite evidence of the Service Tax
Challans before the learned Arbitrator, the petitioner’s contention of the same
not being deposited till date, cannot be accepted by this Court. A corollary of
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
the same reflects the basis for the learned Arbitrator’s finding for disallowing
the deduction amounting to Rs. 7,58,507/- sought to be made by the
petitioner.
(IV) Labour Cess Deductible As Per The Terms Of The Contract:
50.
The petitioner has stated that as per Clause 16.1 of the GCC, the
respondent was required to adhere to the compliances of all labour welfare
laws, including, the Workers Welfare Cess Act, wherein the respondent was
required to deduct 1% of the amount towards labour cess from the bills of the
petitioner and deposit the statutory amounts towards the concerned statutory
authorities.
51.
He further contends that the learned Arbitrator has erroneously
awarded the withheld amount of Rs. 1,85,963/- towards Labour Cess to the
respondent against the bills raised by the respondent for the work done. As
per the petitioner, the aforesaid amount has already been deposited by the
petitioner with the concerned statutory authorities.
52.
In this regard, the learned Arbitrator in paragraph 37 of the impugned
Award observed as under:
“xxx xxx xxx
The Respondent has also sought to deduct a sum of Rs. 1,85,963/on account of labour cess. This amount has been calculated on the
total value of work done. The Respondent has not shown why
labour cess was not deducted from the RA bills if it was payable.
No dispute had been raised during the proceeding about the
liability of the Claimant or the non-payment of the labour cess by
the Claimant. I find that the Respondent is not entitled to recover
this amount.
xxx xxx xxx”
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
53.
Thus, the learned Arbitrator has categorically recorded that no dispute
was raised by the petitioner herein during the course of the proceedings about
the liability of the respondent towards labour cess or its non-payment.
Further, the learned Arbitrator recorded that the petitioner herein had sought
to deduct a sum on account of labour cess from the total value of the work
done, and has not deducted the same from the running account bills.
54.
In this regard, it is to be seen that deduction towards labour cess is not
specifically mentioned in the Clause 16.1 of the GCC between the parties,
except a general reference that the Contractor shall comply with provisions
of various Acts, including Labour Welfare Acts. Clause 16.1 of the GCC is
reproduced again for the ease of reference:
“xxx xxx xxx
xxx xxx xxx”
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
55.
In view of the aforesaid contractual condition, wherein, deduction of
labour cess is not specifically mentioned, the finding by the learned
Arbitrator with regard to no such submission being raised by the petitioner
qua the liability of the respondent herein towards payment of labour cess or
deduction of the said amount from the bills of the respondent, becomes
relevant.
56.
If the Contract and the liabilities therein have been interpreted by the
learned Arbitrator in a certain way, then the same would not be re-examined
by this Court, in a petition under Section 34 of the Arbitration Act.
Considering the narrow scope of judicial interference in a petition under
Section 34, this Court finds no reason to interfere with the conclusion arrived
at by the learned Arbitrator.
57.
In this regard, reference may be made to the case of Punjab State Civil
Supplies Corporation Limited and Another Versus Sanman Rice Mills and
Others, 2024 SCC OnLine SC 2632, wherein, the Supreme Court held that
the mere possibility of an alternative view on facts or interpretation of a
contract would not be enough to reverse the findings of the Arbitral Tribunal.
Merely because the view, other than the one taken by the Arbitrator, is a better
view would not suffice in rejecting the arbitral award. Thus, in the said
judgment, it was held as under:
“xxx xxx xxx
18. Recently a three-Judge Bench in Konkan Railway Corporation
Limited v. Chenab Bridge Project Undertaking [Konkan Railway
Corporation Limited v. Chenab Bridge Project Undertaking
(2023) 9 SCC 85] referring to MMTC Limited (supra) held that
the scope of jurisdiction under Section 34 and Section 37 of the
Act is not like a normal appellate jurisdiction and the courts
should not interfere with the arbitral award lightly in a casual and
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
a cavalier manner. The mere possibility of an alternative view on
facts or interpretation of the contract does not entitle the courts
to reverse the findings of the arbitral tribunal.
xxx xxx xxx
20. In view of the above position in law on the subject, the scope
of the intervention of the court in arbitral matters is virtually
prohibited, if not absolutely barred and that the interference is
confined only to the extent envisaged under Section 34 of the Act.
The appellate power of Section 37 of the Act is limited within the
domain of Section 34 of the Act. It is exercisable only to find out
if the court, exercising power under Section 34 of the Act, has
acted within its limits as prescribed thereunder or has exceeded
or failed to exercise the power so conferred. The Appellate Court
has no authority of law to consider the matter in dispute before
the arbitral tribunal on merits so as to find out as to whether the
decision of the arbitral tribunal is right or wrong upon
reappraisal of evidence as if it is sitting in an ordinary court of
appeal. It is only where the court exercising power under Section
34 has failed to exercise its jurisdiction vested in it by Section 34
or has travelled beyond its jurisdiction that the appellate court
can step in and set aside the order passed under Section 34 of the
Act. Its power is more akin to that superintendence as is vested in
civil courts while exercising revisionary powers. The arbitral
award is not liable to be interfered unless a case for interference
as set out in the earlier part of the decision, is made out. It
cannot be disturbed only for the reason that instead of the view
taken by the arbitral tribunal, the other view which is also a
possible view is a better view according to the appellate court.
xxx xxx xxx”
(Emphasis Supplied)
58.
It is well-settled that Courts ought not to interfere with the Arbitral
Award in a casual and cavalier manner. The mere possibility of an alternative
view on facts or interpretation of the contract does not entitle Courts to
reverse the findings of the Arbitral Tribunal. (See: Konkan Railway
Corporation Limited Versus Chenab Bridge Project Undertaking, (2023) 9
SCC 85)
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
59.
At this stage, this Court may also fruitfully refer to the judgment in the
case of National Highways Authority of India Versus Hindustan
Construction Company Limited, (2024) 6 SCC 809, wherein, it has been
held in clear terms that as far as the construction of the terms of a contract is
concerned, it is for the Arbitral Tribunal to adjudicate upon. If, after
considering the material on record, the Arbitral Tribunal takes a particular
view on the interpretation of the contract, the Court under Section 34 of the
Arbitration Act does not sit in appeal over the findings of the arbitrator.
60.
Considering the detailed discussion hereinabove, the view taken by the
learned Arbitrator is a plausible view, and that being the position, the same
does not warrant interference by this Court.
(V) Interest Amount:
61.
Petitioner has stated that the learned Arbitrator has erroneously
awarded interest @12% per annum, which is excessive in view of the fact
that all the payments were already made by the petitioner to the respondent
from time to time and final payment could not be made only for the reason
that despite several communications, the respondents did not come forward
to sign the Measurement Book and to take the payment.
62.
The legal framework on interest in arbitration is well settled. Section
31(7) of the Act (as amended in 2015) confers power on the Arbitral Tribunal
to award interest for the pre-reference period, the period during arbitral
proceedings, i.e., pendente lite, and the post-award period. Section 31(7) of
the Arbitration Act is reproduced as hereinunder:
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
“xxx xxx xxx
31. Form and contents of arbitral award.—
xxx xxx xxx
(7)(a) Unless otherwise agreed by the parties, where and
in so far as an arbitral award is for the payment of
money, the arbitral tribunal may include in the sum for
which the award is made interest, at such rate as it deems
reasonable, on the whole or any part of the money, for
the whole or any part of the period between the date on
which the cause of action arose and the date on which
the award is made.
[(b) A sum directed to be paid by an arbitral award shall,
unless the award otherwise directs, carry interest at the
rate of two per cent higher than the current rate of
interest prevalent on the date of award, from the date of
award to the date of payment.
Explanation.—The expression “current rate of interest”
shall have the same meaning as assigned to it under clause
(b) of Section 2 of the Interest Act, 1978 (14 of 1978).]
xxx xxx xxx”
(Emphasis Supplied)
63.
Accordingly, an Arbitral Tribunal is vested with the authority to award
interest at such rate as it deems reasonable. Determination of the appropriate
rate of interest lies primarily within the domain of the learned Arbitrator.
Reference in this regard may be made to the judgment in the case of M.A.
Zahid Versus Jindal SAW Ltd., 2025 SCC OnLine Del 5227, wherein, it has
been held as follows:
“xxx xxx xxx
16. Under the 1996 Act, power of the Arbitrator to grant interest is
governed by Section 31(7). This provision is in two parts. Under
Clause (a), in the absence of an agreement between the parties to the
contrary, an Arbitrator can award interest for the period between the
date of cause of action to the date of the award, either for the whole
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
or part of the said period. Clause (b) provides that unless the award
otherwise directs, the sum directed to be paid by the Arbitrator shall
carry interest @ 2% higher than current rate of interest from the date
of the award to the date of payment. This amendment was brought
about from 23.10.2015 by virtue of Amendment Act No. 3 of 2016. Be it
noted that this Court is not delving into the pre-reference and pendente
lite interest as the contest in the present case is only with respect to
post-award interest.
17. Read simply and as observed by the Supreme Court in Morgan
Securities and Credits Private Limited v. Videocon Industries
Limited, 2022 SCC OnLine SC 1127, both clauses (a) and (b) of
Section 31(7) are qualified. While clause (a) is qualified by the
arbitration agreement, clause (b) is qualified by the arbitration award
and placement of the phrases is crucial to their interpretation. As can
be seen from the amended Section, the phrase ‘unless otherwise
agreed by the parties', occurs at the beginning of clause (a) qualifying
the entire provision while phrase ‘unless the award otherwise directs’,
occurs after the words ‘a sum directed to be paid by an arbitral award
shall’ and before the words ‘carry interest at the rate of two per cent’,
and therefore, the phrase qualifies the rate of post-award interest. It
is settled that the Arbitrator has a wide discretion to grant: (a) prereference; (b) pendente lite; and (c) post-award interest. In North
Delhi Municipal Corporation v. S.A. Builders Ltd., 2024 SCC OnLine
SC 3768, the Supreme Court held that grant of post award interest
serves a salutary purpose and primarily acts as a disincentive to the
award-debtor not to delay payment of arbitral amount to the awardholder.
18. In Morgan Securities (supra), albeit the Supreme Court was
dealing with unamended Section 31(7)(b), it was held that Section
31(7)(a) confers a wide discretion on the Arbitrator to grant preaward interest and determine the rate of interest, the sum on which it
is to be paid and the period and when a discretion has been conferred
in regard to grant of pre-award interest, it would be against the grain
of statutory interpretation to presuppose that legislative intent was to
reduce the discretionary power of the Arbitrator for grant of postaward interest under clause (b). It was observed that clause (b) only
contemplates a situation where the arbitral award is silent on the postaward interest, in which event the award-holder is entitled to the postaward interest @ 18% stipulated in Section 31(7)(b), the unamended
provision. It was held that the Arbitrator has the discretion to grant
post-award interest and this discretion is not fettered by clause
(b) albeit it is open to the Arbitrator to decline interest in its discretion.
It was highlighted that purpose of granting post-award interest is to
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
ensure that the award-debtor does not delay the payment of the
awarded amount. With proliferation of arbitration, issues involving
both high and low financial implications are referred to arbitration and
Arbitrator takes note of various factors such as financial standing of
the award-debtor and circumstances of the parties in dispute before
awarding interest. No provision under the 1996 Act restricts the
exercise of discretion to grant post-award interest by the Arbitrator
though Arbitrator must exercise the discretion in good faith taking
into account relevant considerations and must act reasonably and
rationally. It was concluded by the Supreme Court that according to
Section 31(7)(b) only where the Arbitrator does not grant post-award
interest, provisions of second part of sub-clause (b) will come into play.
xxx xxx xxx
20. It needs no reiteration that jurisdiction of the Court under
Section 34 of the 1996 Act is extremely circumscribed and is limited
to the grounds enumerated therein. Petitioner urges that by awarding
exorbitant and dual interest, the award is vitiated by ‘patent illegality
appearing on the face of the award’. The Supreme Court and High
Courts have time and again affirmed that ‘patent illegality’ is an
illegality which goes to the root of the matter and cannot be of a trivial
nature.
[Ref.: Associate
Builders v. Delhi
Development
Authority, (2015) 3 SCC 49 and Larsen Air Conditioning and
Refrigeration Company v. Union of India, (2023) 15 SCC 472].
Proviso to Section 34(2A) itself stipulates that an award shall not be set
aside merely on erroneous application of law. Division Bench of this
Court in Aksh Optifibre Limited v. Nantong Siber Communication Co.
Ltd., 2024 SCC OnLine Del 4011, has held that it is well-settled that
fundamental policy of Indian law does not refer to violation of any
Statute but fundamental principles on which Indian law is founded. Any
difference or controversy as to rate of interest clearly falls outside the
scope of challenge on the ground of conflict with the public policy of
India unless it is evident that the rate of interest awarded is so perverse
and so unreasonable so as to shock the conscience of the
Court sans which no interference is warranted in the award, whereby
interest is awarded by the Arbitrator. Against the said judgment, the
Supreme Court dismissed the SLP (C) No. 22495/2024 on 21.10.2024.
21. On a plain reading of the impugned award in the instant case
and applying the settled law, the reasoning adopted by the learned
Arbitrator for awarding the rate of interest cannot be faulted with.
Arbitrator has considered all relevant factors such as: (a) Petitioner's
admission of his liability to pay the principal amount to the
Respondent; (b) violation of the terms of settlement in the Deed of
Settlement and related documents executed on the same day; (c)
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
financial loss caused to the Respondent; and (d) the admitted fact of
the Respondent being deprived of its right to enjoy the monies due to
it for several years, etc. Arbitrator has exercised the discretion vested
in him judiciously, taking into consideration relevant facts/factors
and eschewing irrelevant considerations.
22. It is a settled law that in the absence of an express bar in the
contract between the parties, it is the Arbitrator who enjoys absolute
discretion and has the jurisdiction to award interest including postaward interest. [Ref.: State of Rajasthan v. Ferro Concrete
Construction Private Limited, (2009) 12 SCC 1; and Indian Railway
Construction Company Limited v. National Buildings Construction
Corporation Limited, (2023) 7 SCC 390]. Clearly, the Deed of
Settlement contains no express bar regarding interest and it was thus
open to the Arbitrator to award the interest. Once interest is awarded
by the Arbitrator, Section 37(1)(b) comes into play where the
phrase ‘unless the award otherwise directs’, qualifies the rate of postaward interest, which means that once the award grants interest,
award-debtor cannot claim any other rate of interest, save and except,
where the rate of interest is so excessive or unreasonable that it shocks
the conscience of the Court, which is not the case here.
23. Counsel for the Petitioner laid much stress on the judgment of the
Supreme Court in Vedanta Limited (supra), to argue that awarding
dual interest and that too at an exorbitant rate of 15% was held to be
unjustified by the Supreme Court. In my view, this argument is
misconceived and need not detain this Court in light of the judgment of
the Supreme Court in Reliance Infrastructure Limited v. State of
Goa, 2023 SCC OnLine SC 604, as also judgments of the Bombay High
Court and this Court, to which I shall advert later. In Reliance
Infrastructure (supra), the Supreme Court was examining the legality
of the award including the issue of grant of pre-reference and postaward interest. Insofar as the post-award interest is concerned, the
High Court had reduced the rate of interest from 15 to 10% following
the decision in Vedanta Limited (supra) and principle of
proportionality. The Supreme Court observed that the reduction of
rate of interest by the High Court was unjustified. Referring to
provisions of Section 31(7)(b), more particularly, the phrase ‘unless
the award otherwise directs’, and distinguishing the decision
in Vedanta Limited (supra), the Supreme Court held that the
observation of the High Court that Court may reduce interest awarded
by the Arbitrator when such interest does not reflect the prevailing
economic condition or where it is not found reasonable or where it
promotes interest of justice, based on the decision in Vedanta
Limited (supra), was without any basis since in the case of Vedanta
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
Limited (supra), the Supreme Court was dealing with an
International Commercial Arbitration involving Rupee as well Euro
components and moreover, the rate of interest was reduced in respect
of foreign currency component to bring the interest rate in line with
international rate on the ground that rate of interest prevailing on the
rupee debt in India and on international currency in abroad were
different and international rates were lower, which was not the case
before the Supreme Court in Reliance Infrastructure (supra). It was
further held that the Arbitral Tribunal was well within its jurisdiction
under Section 31 to award interest at the rate of 15% per annum and
no justification was found to reduce the same. Significantly, it was
also observed that the High Court was not exercising any equity
jurisdiction to re-settle the rate of interest as deemed fit by it as this
was a matter relating to an award made by an Arbitral Tribunal in a
commercial dispute. Relevant passages from the judgment in Reliance
Infrastructure (supra), are as follows:—
“89. However, insofar as post-award period is concerned, the High
Court has reduced the rate of interest from 15% to 10% by following
the decision of this Court in Vedanta [Vedanta Ltd. v. Shenzhen
Shandong Nuclear Power Construction Co. Ltd., (2019) 11 SCC
465 : (2019) 4 SCC (Civ) 724]. The High Court has relied on the
principles of proportionality and has scaled down the rate of interest
to 10% p.a. while observing as under: (Reliance Infrastructure case
[State of Goa v. Reliance Infrastructure Ltd., 2021 SCC OnLine
Bom 306], SCC OnLine Bom para 175)
“175. Mr. Bhat handed in a statement indicating the interest rates
(Benchmark Prime Lending Rates) of the State Bank of India. For
the period 2017-2018, the rates indicated range around 13% to
14% p.a. This is no doubt one of the factors to be taken into
consideration for determining the prevailing economic conditions
when the impugned award was made. Again, reference is also
necessary to the principle of proportionality of the amount
awarded as an interest to the principal sums awarded. Having
cumulative regard to all the factors referred to above, we feel that
in the facts and circumstances of the present case, the award of
interest @ 15% p.a. is excessive and contrary to the principle of
proportionality and reasonableness and the same will have to be
scaled down to 10% p.a. In Vedanta [Vedanta Ltd. v. Shenzhen
Shandong Nuclear Power Construction Co. Ltd., (2019) 11 SCC
465 : (2019) 4 SCC (Civ) 724], the award was dated 9-11-2017
and the Court awarded interest @ 9% p.a. for the INR
component. The impugned award, in our case, was made on 162-2018.”
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
90. We are of the view that the aforesaid reduction of rate of
interest by the High Court is also unjustified. We have noticed the
provisions of Section 31(7)(b) that unless the award otherwise
directs, the sum payable under the arbitral award shall carry
interest @ 2% higher than the current rate of interest prevalent on
the date of the award, from the date of the award to the date of
payment. The expression “current rate of interest” has been
explained in the Explanation to the said section to have the same
meaning as assigned under Section 2(b) of the Interest Act, 1978.
The High Court has referred to the decision in Vedanta [Vedanta
Ltd. v. Shenzhen Shandong Nuclear Power Construction Co.
Ltd., (2019) 11 SCC 465 : (2019) 4 SCC (Civ) 724] to hold that a
Court may reduce interest awarded by the arbitrator when such
interest does not reflect the prevailing economic condition or
where it is not found reasonable or where it promotes interest of
justice.
91. We do not find any basis in the impugned judgment [State of
Goa v. Reliance Infrastructure Ltd., 2021 SCC OnLine Bom 306]
of the High Court for reducing the rate of interest, as in Vedanta
[Vedanta Ltd. v. Shenzhen Shandong Nuclear Power Construction
Co. Ltd., (2019) 11 SCC 465 : (2019) 4 SCC (Civ) 724], wherein this
Court was dealing with an International Commercial Arbitration
involving rupee as well as euro components. Moreover, in Vedanta
[Vedanta Ltd. v. Shenzhen Shandong Nuclear Power Construction
Co. Ltd., (2019) 11 SCC 465 : (2019) 4 SCC (Civ) 724], the rate of
interest was reduced in respect of the foreign currency component
to bring the interest rate in line with the international rate on the
ground that the rate of interest prevailing on the rupee debt in India
and on international currency abroad were different and the
international rates were lower. Such a situation is not obtaining in
the present case.
92. The High Court seems to have not considered the relevant
factual aspects. On the contrary, as has been submitted before us
as well as the High Court, the prevailing interest rate being the
prime lending rate of State Bank of India was in the range of 13%
to 14% p.a. Thus, the Arbitral Tribunal was justified in granting
interest @ 15% p.a. post-award. In our view, the Arbitral Tribunal
was well within its jurisdiction under Section 31 of the Act to award
interest @ 15% p.a. and there was no justification to reduce the
same to 10% p.a. We may observe with respect that the High Court
was not exercising any equity jurisdiction so as to resettle the rate
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
of interest as deemed fit by it. It had been a matter relating to an
award made by the Arbitral Tribunal in a commercial dispute.”
xxx xxx xxx”
(Emphasis Supplied)
64.
Accordingly, the learned Arbitrator was well within his right and
authority to grant interest @ 12% per annum. There is no material before this
Court that the award of interest or the rate of interest, suffers from any
illegality or perversity, within the contours of the jurisdiction under Section
34 of the Arbitration Act. Consequently, there is no justification to interfere
with the award of interest granted by the learned Arbitrator.
(VI) Post-Award Payment Of Rs. 13, 93,368/-:
65.
The petitioner has stated that a payment of Rs. 13,93,368/- was made to
the respondent on 09th July, 2019, vide Cheque no. 302416 dated 09th July,
2019, and therefore, the same must be subtracted from the principal amount
while calculating the future interest on the pending payable amount.
66.
This contention, as raised by the petitioner, is not a challenge to the
impugned Award per se. Rather it related to compliance with the Award and
the final amount payable. This Court would not go into the merits of this
contention since Section 34 of the Arbitration Act does not stipulate an
adjudicatory mechanism for verifying part-payments or crediting amounts said
to have been paid subsequent to, or even prior to, the passing of the Award.
The scope of a petition under Section 34 is confined to examining whether the
Award suffers from any of the grounds enumerated therein, and it does not
extend to a re-computation or reconciliation of accounts between the parties
on the basis of payments allegedly made outside the arbitral record.
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
67.
If the petitioner is of the view that a part-payment of Rs. 13,93,368/-
was in fact made on 09th July, 2019, and that the same stands unaccounted for
in the impugned Award, the appropriate remedy would be to raise this
contention at the stage of execution of the Award, where such factual disputes
regarding satisfaction or part-satisfaction of the decretal amount can be
examined and adjudicated in accordance with law, including, under Order XXI
of the Code of Civil Procedure, 1908 (“CPC”), as made applicable to
execution of Arbitral Awards. This Court, exercising jurisdiction under
Section 34 of the Arbitration Act, is neither the appropriate forum nor
possessed of the requisite mechanism to record evidence or verify such a
factual claim.
68.
Accordingly, the contention raised by the petitioner regarding
adjustment of the alleged payment of Rs. 13,93,368/- against the principal
amount for the purpose of calculating future interest is left open to be agitated
before the Executing Court, and does not warrant interference with the
impugned Award under Section 34 of the Arbitration Act.
VI.
CONCLUSION
69.
Considering the detailed discussion hereinabove, this Court finds no
grounds to interfere in the findings arrived at by the learned Arbitrator within
the scope of interference under Section 34 of the Arbitration Act. The present
petition is, accordingly, dismissed.
MINI PUSHKARNA
(JUDGE)
AUGUST 17, 2026
c
Digitally Signed
By:HARIOM SHARMA
22:01:05
O.M.P. (COMM) 404/2019
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review