ARB.P. No.1/2016
Hindustan Construction Co. Ltd. v. NEEPCO Ltd.
IN THE HIGH COURT OF MEGHALAYA AT
SHILLONG
: ORDER :
ARB.P. No.1 of 2016
Hindustan Construction Co. Ltd.
….. Petitioner
- Versus –
North Eastern Electric Power Corporation Ltd.
….. Respondent
Date of Order:
17th August, 2017
::
PRESENT
HON’BLE SHRI JUSTICE DINESH MAHESHWARI, CHIEF JUSTICE
Shri HS Thangkhiew, Sr. Adv. with Shri P. Nongbri, for the petitioner
Shri VK Jindal, Sr.Adv with Ms. MK Marak, for the respondent
BY THE COURT: (Oral)
By way of this application under Section 11 (6) of the Arbitration
and Conciliation Act, 1996 [„the Act‟], the petitioner-company has made
the request for appointment of arbitrator to adjudicate upon and decide
its dispute with the respondent-corporation, arising out of, and relating
to, the contract work of “construction of Concrete Gravity Dam,
Spillway and Appurtenant Works, Coffer Dam and Diversion Tunnel,
HRT Intake, Head Race Tunnel including Adits, Surge Shaft, Civil
Works of Pressure Shaft, Powerhouse and Tailrace of 2 X 55 MW Pare
Hydro Electric Project, Papumpare, Arunachal Pradesh”.
The petitioner has averred that in term of the procedure set out
in the contract, it had diligently mobilized its manpower, equipments
and resources in order to complete the project in time but had to incur
additional costs and expenses due to the various disruptions and
delays; and hence, claimed reimbursement of additional cost/expenses
incurred due to under utilization of resources upto 30.06.2011 by way
ARB.P. No.1/2016
Hindustan Construction Co. Ltd. v. NEEPCO Ltd.
of the letter dated 29.08.2012, addressed to the Engineer-in-Charge of
the respondent-corporation. It is submitted that the petitioner had
summarized some of the reasons for the delay and disruptions as
being due to: late issuance and frequent revision in construction
drawings; late handing over of approach roads and delayed
maintenance by the respondent-corporation; stoppage of work due to
various bandhs and local problems; additional work involved due to
extra activities as per instructions of the respondent-corporation; delay
in handing over of unencumbered quarry land; disturbances caused by
the other development works; and adverse geological conditions
leading to execution of increased quantity. The petitioner has asserted
that the additional costs and expenses incurred during the extended
period of the contract were to be reimbursed by the respondent; and
hence,
under
the
letters
dated
26.11.2012,
13.12.2012
and
11.01.2013, the principal claims were raised for such additional costs
and expenses.
It is further averred that on 08.12.2012, 14.08.2013, 23.10.2013,
08.02.2014 and 12.06.2015, the petitioner issued the notices of its
intention to commence Arbitration while invoking Clause 70(i) of the
Conditions of Contract; and despite receiving the notices, the
Engineer-in-Charge of the respondent-corporation did not convey his
decision, as required by the Conditions of Contract.
It is yet further averred that the Engineer-in-Charge having failed
to take any steps to give his decision within 60 days of such notice for
arbitration, the petitioner, by the letter dated 17.08.2015, stated its
intention to commence arbitration pursuant to Clause 70 (i) of the
Conditions of Contract; and yet, without prejudice to its rights, the
petitioner again called upon the respondent for amicable settlement of
ARB.P. No.1/2016
Hindustan Construction Co. Ltd. v. NEEPCO Ltd.
the subject dispute but the respondent failed to settle the dispute within
the stipulated period. Hence, the petitioner, by way of its letter dated
17.11.2015, took recourse as per Clause 70 (iii) of Conditions of
Contract to settle the subject dispute through arbitration; and
accordingly, made a request to the respondent-corporation to propose
a panel of names of three Arbitrators so that one could be selected as
the Sole Arbitrator to adjudicate the subject dispute.
It is pointed out that in response to the said letter dated
17.11.2015, the respondent-corporation communicated its decision that
the claim for costs incurred and/or losses suffered by the petitioner on
account of prolongation of the contract beyond the original date of
completion i.e., from 31.08.2012 till 10.04.2015 cannot be referred to
Arbitration at the given stage, because an arbitration was already going
on in relation to the petitioner‟s claim on the same cause of action.
The petitioner has further pointed out that by the letter dated
11.01.2016,
the
respondent-corporation
was
informed,
without
admitting the correctness of the respondents‟ contention, that the issue
as to whether the subject claim cannot be referred to Arbitration could
also be raised before the Arbitral Tribunal but the Engineer-in-charge
failed to take the requisite steps for reference to arbitration.
It is submitted that the inaction of the Engineer-in-charge
constitutes a refusal on the part of the respondent to comply with the
terms of the Contract with respect to the constitution of Arbitral Tribunal
and commencement of arbitration proceedings and hence, the
petitioner is approaching this Court for appropriate orders under
Section 11 of the Act.
On the other hand, it is submitted on behalf of the respondentcorporation that the petitioner has not disclosed all the facts and has
ARB.P. No.1/2016
Hindustan Construction Co. Ltd. v. NEEPCO Ltd.
deliberately concealed the facts that during the construction period,
only the work equivalent to 458 days was executed and thus, there
was a total of 637 days of delay. It is further submitted that the
petitioner sought extension of time in regard to such delay to complete
the work and provisional extension was also given without prejudice to
the respondent-corporation‟s right to claim damages. It is also pointed
out that the petitioner raised the claim due to delay and disruptions for
the extended period of contract from 31.08.2009 to 30.06.2011; and
such a claim was referred to the Sole Arbitrator Shri N.N. Singhal, who
published his award, which has been assailed under Section 34 of the
Act before the Additional Deputy Commissioner (Judicial), Shillong.
It is further submitted that the petitioner raised another claim for
the period commencing from 01.07.2011 to 30.08.2012 on account of
the same delay and disruptions during the contract period but, for the
petitioner having already raised the claim on the alleged cause of
action and the matter having already been referred to the Sole
Arbitrator, the respondent-corporation did not provide the panel of
Arbitrators but then, the petitioner approached the Hon‟ble Chief
Justice for appointment of Sole Arbitrator for resolving the disputes and
differences in respect of the claims for the period commencing from
01.07.2011 to 30.08.2012 [Arbitration Petition No.1 of 2014]; and, by
the order dated 04.11.2014, the Hon‟ble Chief Justice was pleased to
appoint Hon‟ble Shri Justice H.K. Sema, former Judge of the Supreme
Court as the Sole Arbitrator.
It is pointed out during the course of submissions today that the
said Sole Arbitrator Hon‟ble Shri Justice H.K. Sema, has now
published his award on 08.08.2017, rejecting the claim of the petitioner
as being barred by the principles of res judicata. It is submitted that the
ARB.P. No.1/2016
Hindustan Construction Co. Ltd. v. NEEPCO Ltd.
claim as suggested in the present petition for the delay is based on the
same cause of action that had already been subject of the arbitration
proceedings before the Sole Arbitrator Shri N.N. Singhal; and the other
attempt on the part of the petitioner to make further claim on the same
cause of action has failed with the second Sole Arbitrator having found
such a claim barred by the principles of res judicata.
It is, therefore, contended on behalf of the respondentcorporation that the petitioner is not entitled to split the cause of action
in this manner so as to make yet further claim by way of yet further
proceedings.
In relation to the objections raised on behalf of the respondentcorporation, it is submitted on behalf of the petitioner, inter alia, that the
facts which had led to the instant disputes are not at all of the same
cause of action on which earlier claims were made; and the petitioner
has legally and legitimately resorted to the provisions of the dispute
resolution clause of the contract.
Having heard learned counsel for the parties and having
examined the record, this Court is clearly of the view that on the limited
aspects required to be considered in this application, the submissions
regarding identity or similarity of cause of action and the objections
against the maintainability of the claim are not to be adjudicated by this
Court. So far this application is concerned, the consideration herein is
confined to the question as to whether there exists an arbitration
agreement between the parties.
In fact, the existence of arbitration agreement in this matter is not
in dispute. The arbitration Clause, being Clause 70 of the agreement,
reads as under:-
ARB.P. No.1/2016
Hindustan Construction Co. Ltd. v. NEEPCO Ltd.
“70.
Settlement of Disputes and Arbitration
i) If a dispute of any kind, whatsoever, arises between the Corporation
and the contractor in connection with, or arising out of, the Contract
Agreement or the execution of the said Contract Agreement, whether
during the execution of the work or after completion thereof, and
whether before or after repudiation or otherwise termination of the
contract, including any dispute as to any opinion, instruction,
determination, certificate or valuation of the Engineer-in-Charge, such
reference shall state that it is made pursuant to this Clause not later
than 60 (sixty) days after the day on which he receive such reference,
the Engineer-in-Charge shall give notice of his decision to the
Contractor. Such decision shall state that it is made pursuant to this
Clause.
Unless the Contract has already been repudiated or terminated, the
Contractor shall, in every case continue to proceed with the works with
all due diligence and the Contractor and the Corporation shall give
effect forthwith to every such decision of the Engineer-in-Charge,
unless and until the same shall be revised as hereinafter provided, or
by amicable settlement or through an arbitral award.
If the Contractor is not satisfied with any decision of the Engineer-inCharge, or if the Engineer-in-Charge fails to give notice of his decision
on or before the 60th(sixtieth) day after the day on which he receives
the reference, then the Contractor may, on or before the 45th(forty fifth)
day after the day on which he receives notice of such decision or on or
before the said period of 60th(sixty) days expires, as the case may be,
give notice to the Corporation of his intention to commence arbitration
as hereinafter provided, with regard to the matter in dispute. Such
notice shall establish the entitlement of the party giving the same to
commence Arbitration, with regard to such dispute which is subject to
Sub-clause 70(ii) which stipulates that no arbitration in respect thereof
may be commenced unless such notice is given.
If the Engineer-in-Charge has given notice of his decision with regard
to a matter in dispute to the Contractor and no notice of intention to
commence Arbitration with regard to such dispute has been given by
the contractor on or before the 45th (forty fifth) day after the day on
which the parties receive notice with regard to such decision from the
Engineer-in-Charge, the said decision shall become final and binding
upon the Contractor. Thereafter, such issues shall not be subjected to
Arbitration.
ii).
Amicable Settlement:
Where notice of intention to commence Arbitration as to a dispute has
been given in accordance with Sub-clause 70 (I), the parties shall
attempt to settle such dispute amicably before the commencement of
Arbitration. Provided that, unless the parties otherwise agree,
Arbitration may commence on or before the 90 th(ninetieth) day after
the day on which the notice of intention to commence Arbitration of
such dispute was given, even if no attempt at amicable settlement
thereof has been made.
iii).
Arbitration:
Any dispute in respect of which:
a. The decision, if any, of the Engineer-in-Charge has not become final
and binding pursuant of Sub-clause 7(i) and
ARB.P. No.1/2016
Hindustan Construction Co. Ltd. v. NEEPCO Ltd.
b. Amicable settlement has not been reached within the period stated in
Sub-clause 70(ii) shall be finally settled, unless otherwise specified in
the contract as below.
i.
A dispute with an Indian Contractor shall be settled by Arbitration in
accordance with the Indian Arbitration and Conciliation Act, 1996(Act
No.26 of 1996) and any rules made there under and to such other
order or orders, instructions issued by the Government of India from
time to time in this connection. The Arbitration Tribunal shall consist of
a Sale Arbitrator to be appointed by the Chairman and Managing
Director NEEPCO or by his duly authorized representative out of a
Panel of names of three Arbitrators, proposed by him and selected by
the Contractor. For the purposes of the Sub-clause, the term “Indian
Contractor” means a Contractor who is registered in India and is a
juristic person created under Indian law as well as Joint Venture
between such a Contractor and a Foreign Contractor.
ii.
The parties to the dispute, prior to referring the dispute to the
Arbitrator/or Arbitrators as the parties may mutually decide, first drawn
up the specific terms of reference/issues by way of a separate Joint
Agreement, which shall be filed before the Arbitrator or Arbitrators for
commencing the proceedings.
iii.
No dispute or difference of opinion, whatever, shall be referable to the
Arbitration after the expiry of period of 2(two) years from the date
when such dispute or difference of opinion arises.
iv.
In case of a dispute with a foreign Contractor, the dispute shall be
settled in accordance with the provision of Clause (i) above but if this
is not acceptable to the Contractor, then the dispute shall be settled in
accordance with the provision of the UNCITRAL Arbitration Rules,
which is part of the Arbitration and Conciliation Act, 1996.
v.
The reference to Arbitration may proceed notwithstanding that the
works shall not then be or be alleged to be complete, provided always
that the obligations of the Corporation and the Contractor shall not be
altered by reason of the Arbitration being conducted during the
progress of the works. The Contractor will ensure that the work under
the Contract shall continue during Arbitration proceedings and dispute
and no payment due from or payment by the Corporation shall be
withheld on account of such proceeding except to the extent that may
be in dispute.
vi.
Arbitration proceedings shall be held at Shillong/Guwahati and the
language of the Arbitration proceedings and that of all documents and
communications between the parties shall be English.
vii.
The expenses of the Arbitrators, as determined by the Arbitrators,
shall be shared equally by the Corporation and the Contractor.
However, the expenses incurred by each party in connection with the
preparation, presentation etc. of its case prior to during and after the
Arbitration proceedings shall be done by each party itself.
viii.
In event of dispute or differences arising between one Public Sector
enterprise and a Government Department or between two Public
Sector enterprises the above stipulation shall not apply and the
provisions
of
B.P.E.
office
Memorandum
No.
BPE/GI/001/76/MAN/2(110-75-BPE(GMI-1) dated 1st January, 1976 or
its amendments for arbitration shall be applicable.
ARB.P. No.1/2016
Hindustan Construction Co. Ltd. v. NEEPCO Ltd.
ix.
The Arbitrator appointed shall have no power to award interest on any
claim referred to the arbitration. No claim for interest or damages on
whatsoever count will be entertained by the corporation with respect to
any dispute, difference or misunderstanding between the corporation
and the contractor.”
From the material placed on record, it is clear that the petitioner
indeed made the requests to the respondent to proceed for arbitration
in accordance with the said arbitration agreement but, the requisite
panel was not forwarded by the respondent. In the totality of
circumstances and for the reason of failure of the procedure for
appointment of arbitrator, it is just and proper that an independent
arbitrator be appointed to adjudicate upon and decide the dispute
between the parties including their claims, counter claims and
objections.
During the course of submissions, learned senior counsel Shri
VK Jindal appearing for the respondent-corporation has submitted that
looking to the limited scope of enquiry in this application, irrespective of
other
objections, he has conferred
with Hon‟ble
Dr. Justice
Mukundakam Sarma, a former Judge of Supreme Court of India
residing at Bungalow No.105 New Motibagh, New Delhi-23, who has
agreed to take up the arbitration in this matter. Shri HS Thangkhiew,
learned senior counsel concurs with the submissions made by the
learned counsel for the respondent-corporation. In view of these
submissions ad idem, it appears just and proper to appoint Hon‟ble Dr.
Justice Mukundakam Sarma, a former Judge of Supreme Court of
India as the arbitrator in this case.
All other aspects relating to the cost of proceedings and fees are
left to be determined by the arbitrator while keeping in view the law
applicable, including the provisions contained in Fourth Schedule to the
ARB.P. No.1/2016
Hindustan Construction Co. Ltd. v. NEEPCO Ltd.
Arbitration and Conciliation Act, 1996, [as amended by the Arbitration
and Conciliation (Amendment) Act, 2015].
With
the
observations
foregoing,
Hon‟ble
Dr.
Justice
Mukundakam Sarma, a former Judge of Supreme Court of India is
appointed to act as the Sole Arbitrator to adjudicate upon and decide
all the disputes between the parties including their claims, counter
claims and objections relating to the contract in question. The
requirements of the Arbitration and Conciliation Act, 1996, [as
amended by the Arbitration and Conciliation (Amendment) Act, 2015]
shall be complied with by all the concerned.
This arbitration petition stands disposed of accordingly.
Needless to observe that all the questions arising between the
parties in this matter including the maintainability of the claim shall
remain open for determination in the arbitration proceedings.
CHIEF JUSTICE
Lam
Item No.1
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review