The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
14. In view of the foregoing settled position of law, it cannot be stated that the petitioners did not acquire perfect title to the land in question merely because their predecessor-in-interest had not sought permission of the Government before transferring his ownership rights in the land in question in favour of the petitioners. Thus, the contention of the respondents that the petitioners are not entitled to compensation for the portion of their land which has been utilized for construction of the Highway is not tenable.
15. For the foregoing reasons, the writ petition is disposed of by directing the respondent-Collector to release the compensation assessed in respect of the aforesaid land of the petitioners in their favour along with interest that may have accrued thereon. Needful be done by the Collector within a period of one month from the date, a copy of this order is served upon the respondentCollector.
16. Disposed of.
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
Sr. No. 13
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
WP(C) No. 2855/2022
CM No. 7934/2022
1. Harbans Lal S/o Sh.Kirpa Ram R/o
Marhol, Tehsil Bishnah District
Jammu
2. Raj Kumar S/o Sh. Barkat Ram R/o
Marhol Tehsil Bishnah District
Jammu.
…..Appellants
Through: Mr. Rakesh Chargotra, Advocate
Vs
1. Union Territory of Jammu and Kashmir through Commissioner/Secretary,
Revenue Department Civil Secretariat, Srinagar/Jammu
2. Deputy Commissioner, Samba
3. Sub-Divisional Magistrate, Vijaypur
4. National Highway Authority of India
Through its Project Director National Highway 1-A, 315, Sector-1 Channi
Himmat, Jammu.
.…. Respondents
Through: Ms. Chetna Manhas, Advocate vice
Mrs. Monika Kohli, Sr. AAG
Mr. Kamal Mangotra, Advocate
CORAM:
HON’BLE MR. JUSTICE SANJAY DHAR, JUDGE
ORDER
13.08.2025
1. The petitioners, through the medium of the present petition have sought a
direction upon the respondents for restraining them from constructing public
road/national highway/express road by utilizing their land measuring 04
kanals 16 marlas falling under khasra No. 113-min situated at village Bara
District Samba without adopting due course of law. Alternative prayer to the
effect that in case the said land is utilized for construction of the road, the
petitioners be paid compensation in accordance with law, has also been
made.
WP(C) No. 2855/2022
2. According to the case of the petitioners, they are owners of the aforesaid
land which they have purchased by way of registered sale deeds dated
12.04.2012 and 08.02.2012 from the erstwhile owners. It has been submitted
that Collector, Land Acquisition (Additional Deputy Commissioner), Samba
issued a notification under Section 4 (1) of the J&K Land Acquisition Act on
06.09.2012 for acquisition of the land for construction of oil depot and
approach road. The aforesaid land was also included in the said notification.
According to the petitioners, they were never served with the notice dated
06.09.2012 and the mandatory requirements regarding publication of the
notice under Section 4 (1) of the J&K Land Acquisition Act were not
adhered to by the Collector.
3. It has been submitted that on 30.10.2012, declaration under Section 6, 7 &
17 of the J&K Land Acquisition Act came to be issued by the Government
whereafter, notification under Sections 9, 9-A, 9(2) & 17-A of the Land
Acquisition Act came to be issued on 13.02.2013. The petitioners are stated
to have challenged the aforesaid notifications by way of a writ petition
bearing OWP No. 617/2013 which came to be disposed of by this Court in
terms of order dated 30.05.2013 with a direction to the respondents to
consider the objections filed by the petitioners within a period of four weeks.
4. Pursuant to the aforesaid order, the petitioners are stated to have filed their
objections to the notification under Section 4 (1) of the Land Acquisition
Act. Thereafter, the petitioners are stated to have challenged the proceedings
again by way of a writ petition bearing OWP No. 1763/2013 in which an
interim order came to be passed by this Court on 24.12.2013 whereby the
proceedings with regard to acquisition of the aforesaid land of the petitioners
WP(C) No. 2855/2022
were stayed and it was provided that the petitioners shall not be dispossessed
otherwise than in due course of law.
5. It has been submitted that in spite of the aforesaid order, the respondents
have tried to construct the road from the aforesaid land of the petitioners
without adopting due course of law which prompted the petitioners to file
another petitions bearing WP(C) No. 2711/2019. Again an interim order
came to be passed in the said writ petition on 22.07.2019 directing the
respondents not to go ahead with the construction work over the land of the
petitioners without adopting due course of law. In the meantime, respondent
No 4-National Highway Authority is stated to have tried to forcibly
construct national highway/express road on the aforesaid land of the
petitioners which was resisted by them by approaching this Court by way of
present petition. It has been contended that respondent No. 4-National
Highway Authority is obliged to pay compensation to the petitioners for
utilizing the aforesaid land and without doing so, the said respondent cannot
take possession of the land in question.
6. Respondent Nos. 1 to 3 in their reply to the writ petition have submitted that
land measuring 32 kanals 08 marlas of land situated at village Bara Tehsil
Vijaypur District Samba was notified for acquisition on 09.03.2021/
23.12.2021 by publication of notifications under Section 3 A(1) of the
National Highways Act which was duly published in newspapers namely
State Times, Amar Ujala dated 25.03.2021 and Daily Excelsior dated
26.12.2021. It has been submitted that even the objections to the said
notification were received which were duly considered. It has been further
submitted that after identification of correct area of the land, the Central
WP(C) No. 2855/2022
Government declared land measuring 32 kanals 08 marlas situated at village
Bara should be acquired in terms of Section 3-D of National Highways Act
and the said declaration was also published in the newspapers namely State
Times, Amar Ujala and Daily Excelsior. It has been contended that after
following all the provisions laid down in National Highways Act and other
rules, final award of the aforesaid land measuring 32 kanals 08 marlas was
issued by the Deputy Commissioner, Samba vide No. DCS/SM/DKE/2223/290-92 dated 22.06.2022.
7. It is the stand of the respondents that land measuring 02 kanals 10 marlas
belonging to the petitioner-Harbans Lal and land measuring 08 kanals 03
Sarsair belonging to petitioner Raj Kumar has come under the alignment of
National Highway for which compensation to the tune of Rs. 83,05,750/and Rs. 13,84,291/- respectively has been assessed. It has been submitted
that the compensation is not payable to the petitioners as the land measuring
05 kanals falling under khasra No. 113 was acquired b them from Shankar
Singh, the erstwhile owner who was conferred with ownership rights in
terms of Government Order S-432-C of 1966. It has been submitted that
because the said land could not have been alienated without prior permission
of the Government, the petitioners are not entitled to any land compensation
in respect of the aforesaid portion of the acquired land.
8. I have heard learned counsel for the parties and I have also gone through the
material on record
..
9. So far as the challenge to the acquisition proceedings is concerned, learned
counsel for the petitioners has submitted that the petitioners would be
WP(C) No. 2855/2022
satisfied if the alternative prayer made in the petition is considered by this
Court without quashing the acquisition proceedings.
10.
It is not in dispute that the land measuring 04 kanals 16 marlas falling
under khasra No. 113-min situated at village Bhara, Tehsil Vijaypur District
Samba belonging to the petitioners has been utilized by National Highway
Authority for construction of the road. It is also not in dispute that as per the
award passed by the Collector, compensation in respect of the portion of the
land belonging to the petitioners has been assessed.
11. However, contention of the respondents is that the compensation cannot
be disbursed to the petitioners because their predecessor-in-interest had
acquired the title to the said land in terms of Government Orders LB-6/C of
1958 and S-432-C of 1966. On account of this, it is being contended that
predecessor-in-interest of the petitioners could not have alienated the said
land in their favour without previous permission of the Government. It is
being contended that because the land in question has been transferred in
favour of the petitioners in violation of conditions contained in the aforesaid
two Government orders, title of the petitioners with regard to the land is
defective and illegal as such, they are not entitled to any compensation.
12. The question whether a person who has acquired proprietary rights in
respect of the land allotted in terms of Government Order No. LB-6/C of
1958 and S-432-C of 1966 is vested with power to alienate the said land is
no longer res integra. A Division Bench of this Court in the case of Kewal
Krishan Vs. State of J&K and ors; 2004 SLJ 617 has held that occupant of
a State land after being recorded as tenant-at-will in terms of Government
Order No. LB-6/C becomes entitled to ownership rights over such land in
WP(C) No. 2855/2022
terms of Government Orders No. S-432-C of 1966. The Division Bench
further held that Government Order No. LB-6/C and S-432-C are in the
nature of recognition of vested rights in favour of the person entitled to be
recorded as tenant-at-will and owner under the said Government orders. It
has been held that so long as these Government orders which confer
substantive rights upon the occupants of State lands are in force, no
restriction can be imposed upon the recognition of such rights.
13. A single Bench of this Court in the case of Mohd. Akbar Shah and ors.
Vs. State and ors.; AIR 2017 J&K 14 has more specifically dealt with the
issue relating to status of a person who has been conferred property rights
in respect of State land under Government Order No. S-432-C of 1966. The
Court has held that once the mutation pursuant to Government order No. S432-C of 1966 is attested in favour of an allottee and he is conferred with the
proprietary rights over the land, his rights are thereafter, governed by the
Transfer of Property Act, Land Alienation Act and Agrarian Reforms Act. It
has been held that the condition of seeking prior permission of Government
from alienating such land in terms of paragraph No. (4) of Government
Order No. S-432-C of 1966 has been rendered otiose and it will not affect
the right of the owner of the land to alienate the same without the previous
permission of the Government.
14. In view of the foregoing settled position of law, it cannot be stated that the
petitioners did not acquire perfect title to the land in question merely because
their predecessor-in-interest had not sought permission of the Government
before transferring his ownership rights in the land in question in favour of
the petitioners. Thus, the contention of the respondents that the petitioners
WP(C) No. 2855/2022
are not entitled to compensation for the portion of their land which has been
utilized for construction of the Highway is not tenable.
15. For the foregoing reasons, the writ petition is disposed of by directing the
respondent-Collector to release the compensation assessed in respect of the
aforesaid land of the petitioners in their favour along with interest that may
have accrued thereon. Needful be done by the Collector within a period of
one month from the date, a copy of this order is served upon the respondentCollector.
16. Disposed of.
(SANJAY DHAR)
JUDGE
JAMMU
13.08.2025
Tarun/P/S
Whether the order is speaking?
Whether the order is reportable?
Tarun Kumar Gupta
2025.09.17 22:29
I attest to the accuracy and
integrity of this document
Yes
No
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review