The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
16. In view of what has been discussed hereinabove, the writ petition is disposed of with the following directions:a) The final award dated 28.01.2023 to the extent of petitioners is set aside. b) The Collector, Land Acquisition, Banihal shall pass fresh award in respect of the petitioners only and for that purpose, he shall construe 28th January, 2023 (date of final award) as the relevant date for determination of market value. However, he shall apply the yardstick for assessment of compensation provided under the State Land Acquisition Act in respect of the acquired land of the petitioners only. c) The Collector shall also calculate other statutory benefits on such amounts including interest to be calculated and determined by taking into consideration possession. the date of taking over d) The date on which the fresh award that may be passed by the Collector in favour of the petitioners pursuant of this judgment is intimated to them shall be the date of cause of action for seeking enhancement of compensation under the State Land Acquisition Act, if the petitioners or any of them is dissatisfied with the quantum of compensation offered. e) The amount of compensation, if any, already received by the petitioners shall be taken into account while disbursing the compensation in terms of the fresh award that may be passed. f) The compensation determined in favour of the petitioners pur…
17. The writ petition is disposed of in above terms.
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
Sr. No. 32
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
WP(C) No. 2236/2024
CM No. 5446/2024
Hamid Ullah Wani and ors.
Through:
…..Appellants
Mr. Irfaan Khan, Advocate
Vs
UT of J&K and ors.
.…. Respondents
Through: Mr. Ravinder Gupta, AAG
CORAM:
HON’BLE MR. JUSTICE SANJAY DHAR, JUDGE
ORDER
10.09.2025
1.
The petitioners through the medium of present petition
have
challenged
notification
No.
SDMB/Acq/495-502
dated
04.04.2018 issued by respondent No. 1 in respect of land measuring
01 kanal 07 marlas falling in khasra No. 451 and land measuring
01 kanal 03 marlas falling in khasra No. 452 situated at village
Gund Adalkote, Tehsil Banihal, District Ramban issued under
Section 4 (1) of Jammu and Kashmir Land Acquisition, Act (Svt.)
1990 (hereinafter referred to as “Act”) for construction of road from
Kharpora Rattan Bass Road via Shabanbass Km 1-6th in village
Gund Adalkote, Tehsil Banihal District Jammu. Challenge has also
thrown to subsequent notification dated 16.10.2018 issued under
Section 6, Notification dated 14.11.2018 issued under Section 9, 9A of the State Land Acquisition Act alongwith tentative award dated
26.08.2019 and the final award dated 28.01.2023.
2.
As per case of the petitioners, their aforesaid land came
to be utilized by the official respondents for construction of the road
but the full compensation in their favour has not been released. It
WP(C) No. 2236/2024
has been submitted that only 30 to 40 percent of the compensation
assessed in favour of the petitioners in terms of the impugned
award dated 28.01.2023 has been released in favour of the
petitioners in the year, 2018.
3.
The
petitioners
have
challenged
the
acquisition
proceedings and the final award on the grounds that the same have
lapsed in view of the provisions contained in Section 11-B of the
State Land Acquisition Act. It has been contended that the
impugned award has not been passed within the stipulated period
of two years from the date of issuance of declaration under Section
6 of the State Land Acquisition Act. It has been further submitted
that the respondent-Collector has not invoked the urgency clause in
terms of Section 17 of the State Land Acquisition Act nor the 80
percent of the assessed compensation has been tendered to the
petitioners. Thus, the acquisition proceedings have lapsed and the
final award is liable to be quashed. On this basis, it has been
contended that the respondents have to initiate fresh acquisition
proceedings in terms of provisions of Right to Fair Compensation
and
Transparency
in
Land
Acquisition
Rehabilitation
and
Resettlement Act, 2013 (hereinafter referred to as “Act of 2013”).
4.
Reply on behalf of the respondent-Collector has been
filed. In the reply, it has been admitted that Notification under
Section 4 of the State Land Acquisition Act was issued on
04.04.2018 but no objections were received from any of the land
owners in respect of the said notification. It has been further
submitted that declaration under Section 6 and 7 of the State Land
Acquisition Act came to be issued by the Government on 16.10.2018
WP(C) No. 2236/2024
whereafter, Notification under Section 9, 9-A of the State Land
Acquisition Act was issued on 14.11.2018. According to the
respondent-Collector, tentative award was made on 26.08.2019
whereas, the final award was passed on 28.01.2023 thereby
acquiring the land measuring 22 kanals 02 marlas in village Gund
Adalkote and land measuring 32 kanals 14 marlas in village Nagam.
It has been contended by the respondent-Collector that the land
measuring 01 kanal 07 marlas falling in khasra No. 451 and land
measuring 01 kanal 03 marlas falling in khasra No. 452 belonging
to the petitioners situated in village Gund Adalkote Tehsil Banihal
has also been acquired for construction of the road in terms of the
aforesaid award.
5.
dated
It has been submitted that in terms of the final award
28.01.2023,
the
total
land compensation
assessed
is
Rs. 9,21,67,057/- out of which an amount of Rs. 38 lacs only has
been transferred by the intending department in the account of the
Collector in the year, 2017. It has been submitted that balance
amount of compensation has not been received from the intending
department. A number of communications were addressed by the
Collector to the intending department but till date, whole of the land
compensation amount in terms of the final award has not been
deposited with the Collector.
6.
I have heard learned counsel for the parties and perused
record of the case.
7.
As is clear from the pleadings of the parties, the facts in
this case are not in dispute. The declaration under Section 6 of the
State Land Acquisition Act has been issued on 16.10.2018 whereas,
WP(C) No. 2236/2024
the final award has been made by the Collector on 28.01.2023.
Thus, the award has been made by the respondent-Collector after
the expiry of two years from the date of publication of the
declaration.
8.
As per the provisions contained under Section 11-B of
the State Land Acquisition Act, the Collector has to make an award
within a period of two years from the date of publication of
declaration and if no award is made within the said period, the
entire proceedings for acquisition of the land stand lapsed. The
explanation to the aforesaid provision makes it clear that in
computing the period of two years, the period during which any
action or proceedings have remained stayed by an order of Court, is
to be excluded.
9.
The legal position as laid down by the Supreme Court in
the case of M/s Delhi Airtech Services Pvt. Ltd. and anr. Vs.
State of U.P and anr; 2022 INSC 1086 makes it clear that in the
event, the Collector invokes urgency clause and possession of the
acquired land is taken after tendering and paying 80 percent of the
estimated
compensation,
the
land
vests
absolutely
in
the
Government and in such a situation, the acquisition proceedings
would not lapse in spite of the fact that the award may have been
passed after expiry of two years from the date of issuance of
declaration. It has been made clear that in order to avoid the
application of Section 11-A of the Central Act of 1894 which is in
pari-materia with Section 11-B of the State Land Acquisition Act,
the conditions laid down in Sections 17-A of the State Land
Acquisition Act which corresponds to Section 17 (3A) of the Central
WP(C) No. 2236/2024
Act, have to be fulfilled inasmuch as, the land losers should have
been paid 80 percent of the compensation assessed and the
possession of the land must have been taken only thereafter. It has
also been held by the Supreme Court that if a land loser does not
challenge the acquisition proceedings on the ground that final
award has not been passed within two years of issuance of
declaration, the acquisition proceedings would not lapse and the
possession taken would not become per se illegal.
10.
With the aforesaid legal position in mind, let us now
advert to the facts of the present case. As already stated, it is not in
dispute that the award has been passed by the Collector after a
lapse of two years from the date of issuance of declaration under
Section 6 of the State Land Acquisition Act. The petitioners have
challenged the acquisition proceedings and the final award by
contending that in view of the provisions contained in Section 11-B
of the State Land Acquisition Act, the same have lapsed. It is not
case of the respondents that they have taken the possession of the
land in question after tendering 80 percent of the assessed
compensation to the petitioners. In fact, there is a categoric
admission of the respondent-Collector that only an amount of Rs.
38 lacs out of more than Rs. 9 crores of assessed compensation has
been deposited by the intending department so far. Thus, the
contention of the petitioners that they have received only 30 to 40
percent of the compensation appears to be well founded. Even
otherwise, it is not the case of respondents that urgency clause
under Section 17 of the State Land Acquisition Act has been
invoked by the Collector. Therefore, the provisions contained in
WP(C) No. 2236/2024
Section 11-B of the State Land Acquisition Act are attracted to the
facts of the present case.
11.
The question that arises for determination is as to what
should be the course of action that may be adopted in the facts and
circumstances of the present case. It is to be noted that as per the
impugned award, land measuring 22 kanals measuring 02 marlas
in village Gund Adalkote and land measuring 32 kanals 14 marlas
in village Nagam has been acquired. The said land belongs to
multiple land owners. The petitioners own only 02 kanals and 10
marlas out of the acquired land. The other land losers are not
aggrieved
of
the
acquisition
proceedings
as
they
have
not
approached this Court. Therefore, the acquisition proceedings to the
extent of other land losers cannot be set at naught. In these
circumstances, directing the respondent-Collector to initiate fresh
acquisition proceedings for only 2 kanals and 10 marlas of land
would not only be time consuming but it will also involve a lot of
effort and expenses, which would ultimately not be even in the
interest of the petitioners. Therefore, directing initiation of fresh
acquisition proceedings under the Act of 2013 in the facts and
circumstances of the case may not be appropriate.
12.
The Supreme Court in the case of M/s Delhi Airtech
Services Pvt. Ltd.’s case (supra) in similar circumstances has
moulded the relief by providing that the land losers who had
approached the court would be entitled to compensation by
determining the market value of their land with reference to the date
of issuance of final award. The relevant directions passed by the
Supreme Court in the said case are reproduced as under:-
WP(C) No. 2236/2024
“(a) The respondents shall construe 09.06.2008 as the
relevant date and determine the market value prevailing as
on that date applying the yardstick under Act, 1894 in
respect of the acquired land.
(b) To calculate the statutory benefits on such amount
including interest, the same shall be determined by taking
into consideration the date of the Section 4 notification dated
17.04.2002 since the appellant was dispossessed on
04.02.2003 pursuant to the same.
(c) The date on which the fresh award is passed pursuant to
this judgment and communicated shall be the date of cause
of action for seeking enhancement of compensation if the
appellant is dissatisfied with the quantum of compensation
offered.
(d) The compensation determined in this case shall not give
the cause of action to any other land loser whose land is
acquired under the same notification to seek redetermination
of compensation.
(e) The appellant shall be entitled to the cost incurred in these
proceedings.”
13.
Following the aforesaid guidelines, a Division Bench of
this Court in the case of Gulzar Ahmad Akhoon and ors. Vs. UT of
J&K and ors; 2023 (1) JKJ 68 adopted a similar methodology
while moulding the relief of the land losers who had succeeded in
establishing before the Court that final award had been passed
beyond the prescribed period of two years from the date of issuance
of declaration.
14.
Learned counsel for the petitioners has strenuously
argued that this Court in the case of Abdul Gani and anr. Vs. UT of
J&K and ors.; 2025 0 Supreme (J&K) 2 had, in similar
circumstances, issued directions for initiation of fresh acquisition
proceedings in terms of the Act of 2013. In this regard, it is to be
noted in Abdul Gani’s case (supra) the final award had not been
passed by the Collector even after lapse of more than two years of
issuance of notification under Section 6 & 7 of the Land Acquisition
Act. It is, in these circumstances, that this Court directed initiation
of fresh acquisition proceedings under the provisions of the Act of
WP(C) No. 2236/2024
2013. The ratio laid down in the said case is, therefore, not
applicable to the facts of the present case as, in the instant case,
the final award stands already passed by the Collector.
15.
Apart from the above, the guidelines laid down by the
Supreme Court in M/s Delhi Airtech Services Pvt. Ltd.’s case (supra)
and Division Bench of this Court in Gulzar Ahmad Akhoon’s case
(supra) have a binding force on this Court and as such, even if there
is a divergent view taken by this Court in some other case, the same
cannot be repeated and reiterated.
16.
In view of what has been discussed hereinabove, the writ
petition is disposed of with the following directions:a)
The final award dated 28.01.2023 to the
extent of petitioners is set aside.
b)
The Collector, Land Acquisition, Banihal shall
pass fresh award in respect of the petitioners only
and for that purpose, he shall construe 28th
January, 2023 (date of final award) as the relevant
date for determination of market value. However,
he shall apply the yardstick for assessment of
compensation provided under the State Land
Acquisition Act in respect of the acquired land of
the petitioners only.
c)
The
Collector
shall
also
calculate
other
statutory benefits on such amounts including
interest to be calculated and determined by taking
into
consideration
possession.
the
date
of
taking
over
d)
WP(C) No. 2236/2024
The date on which the fresh award that may
be passed by the Collector in favour of the
petitioners pursuant of this judgment is intimated
to them shall be the date of cause of action for
seeking enhancement of compensation under the
State Land Acquisition Act, if the petitioners or any
of them is dissatisfied with the quantum of
compensation offered.
e)
The amount of compensation, if any, already
received by the petitioners shall be taken into
account while disbursing the compensation in
terms of the fresh award that may be passed.
f)
The compensation determined in favour of the
petitioners pursuant to this judgment shall not
give cause of action to any other land losers whose
land has been acquired under the impugned
award.
17.
The writ petition is disposed of in above terms.
(SANJAY DHAR)
JUDGE
JAMMU
10.09.2025
Tarun/PS
Whether the order is speaking?
Whether the order is reportable?
Tarun Kumar Gupta
2025.09.17 15:37
I attest to the accuracy and
integrity of this document
Yes
Yes
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.