IN THE HIGH COURT OF DELHI AT NEW DELHI
#
+
CNR No. DLHC011092082025
ARB.P. 166/2026, I.A. 1911/2026 & I.A. 1912/2026
GPM LOOMBA SA JV
.....Petitioner
Through:
versus
UNION OF INDIA
Through:
Mr. Joydeep Mazumdar
Nishchaiy Sharma, Advs.
&
Mr.
.....Respondent
Ms. Iram Majid, CGSC with Mr.
Mohd. Suboor, Mr. Amaan & Mr.
Saad, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
ORDER
04.08.2026
%
1.
This petition is filed under Section 11(6) of the Arbitration and
Conciliation Act, 1996 (for short „the Act‟) for appointment of a sole
arbitrator.
2.
The brief facts are that the respondent invited bids on 12.03.2009 for
Detailed Engineering and Project Management Consultant (for short
„DEPMC‟) for Construction of Residential Accommodation Project at
Brichganj, Port Blair (Army), Port Blair (Navy), Port Blair (Air Force) and
Carnicobar (Air Force) and the petitioner was the successful bidder. The
contract was executed between the parties on 22.05.2009, pursuant to which
the petitioner was appointed as DEPMC. The site was handed over on
12.06.2009. On 15.10.2010, the respondent extended the time of preparation
and submission of the Detailed Project Reports and a further extension was
given on 28.10.2010.
3.
The
administrative
approval
for
construction
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 07/08/2026 at 11:21:27
of
married
accommodation at Port Blair- Army, Air Force and Navy was granted on
03.11.2010. The contractor for Port Blair (Army) was appointed on
24.12.2010. Due to the slow progress of work, the work awarded to the
contractor was cancelled on 02.11.2013 and was subsequently awarded to
another contractor on 28.10.2014. The construction at Port Blair (Army) was
completed on 15.05.2018. Dispute arose between the contractor and the
respondent qua the construction at Port Blair (Army), which culminated in
an award dated 12.06.2023.
4.
As regards Port Blair (Navy), the respondent issued a Letter of
Acceptance (for short „LOA‟) for construction on 24.12.2010. The work was
not completed within the stipulated period and was completed on
20.12.2018. In 2019, dispute arose between the respondent and the
contractor and the matter was referred to arbitration wherein the arbitral
proceedings are pending.
5.
In respect of construction at Port Blair (Air Force), the respondent
issued a LOA dated 24.12.2010. The work was delayed and was ultimately
completed on 20.02.2019. The arbitration was invoked by the contractor and
the proceedings culminated in an award dated 27.12.2023 in favour of the
contractor.
6.
As regards Car Nicobar (Air Force), the petitioner was paid for two
stages. Thereafter the project has not progressed and the respondent is yet to
float tenders for construction.
7.
The petitioner vide communication dated 01.12.2023 demanded
payment of fees towards the additional work carried out beyond the scope of
work, the costs incurred due to prolongation of the projects at Port BlairArmy, Navy and Air Force, and interest thereon.
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 07/08/2026 at 11:21:27
8.
The respondent rejected the claim on 23.02.2024 on the ground of
limitation. Vide communication dated 16.03.2024, the petitioner reiterated
the claim and informed the respondent that if the matter was not resolved
within 30 days, the dispute would be referred for arbitration under article 17
of the contract. The relevant clause is reproduced below:
“ARTICLE 17 SETTLEMENTS OF DISPUTES
All disputes, between the parties to the contract
(other than those for which the decision of the DGMAP or
any other person is by the contract expressed to be final
and binding) shall, after written notice by either party to
the Contract to the other of item, be referred to sole
arbitration of serving officer having degree in Engineering
or equivalent or having passed Final/Direct Final
Examination of Sub Division II of Institution of Surveyors
(India) recognized by the Govt. of India to be appointed by
the Engineer-in-Chief, E-in-C's Branch, Kashmir House,
New Delhi-11 or Director General of Works if specifically
delegated in writing by Engineer-in-Chief, Army
Headquarters, New Delhi whose decision shall be final,
conclusive and binding. The Arbitration shall be governed
by Arbitration and Conciliation Act, 1996.
Unless both parties agree in writing, such reference
shall not take place until after the completion or alleged
completion of the Works or termination or determination
of the Contract under conditions of this contract.
Provided that in the event of abandonment of the
works or cancellation of the Contract under conditions of
this contract, such reference shall not take place until
alternative arrangements have been finalized by the
OWNER to get the works completed by or through any
other consultant or consultants or Agency or agencies.
Provided always that commencement or continuance
of any arbitration proceeding hereunder or otherwise shall
not in any manner militate against the Owner's right of
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 07/08/2026 at 11:21:27
recovery from the consultant as provided in conditions of
this contract.
If the Arbitrator so appointed resigns his
appointment or vacates his office or is unable or unwilling
to act due to any reason whatsoever, the authority
appointing him may appoint a new Arbitrator to act in his
place.
The Arbitrator may proceed with the arbitration,
exparte, if either party, inspite of notice from the
Arbitrator, fails to take part in the proceedings.
The Arbitrator shall give his reasoned award in
writing on all matters referred to him and shall indicate his
findings, along with sums awarded, separately on each
individual item of dispute.
The venue of arbitration shall be such place or
places as may be fixed by the Arbitrator in his discretion.
The language of the arbitration proceedings and that
of all documents any communications between the parties
shall be "English".
The award of the Arbitrator shall be final and
binding on both the parties to the contract.
Notwithstanding the fact that the stations of work
are anywhere in India, only the courts at Delhi/New Delhi
shall have the jurisdiction to adjudicate and settle any
disputes between OWNER and the consultant. No other
court outside Delhi/New Delhi shall have any jurisdiction
on any matter requiring reference to Civil Court.”
9.
The arbitration was invoked under Section 21 of the Act at the
instance of the petitioner by issuing notice dated 04.11.2024. On failure to
do the needful, the present petition was filed.
10.
Learned counsel for the petitioner relies upon article 17 of the
contract to contend that the parties had agreed to resolve disputes through
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 07/08/2026 at 11:21:27
arbitration and even after issuance of a notice under Section 21 of the Act,
the respondent failed to appoint an arbitrator.
11.
Learned counsel for the respondent vehemently contends that the
claims are barred by limitation. The argument is that the construction was to
be carried out in various phases. The work was completed in 2018-19 and all
the claims cannot be raised in the year 2024. It is contended that the dispute
between the respondent and the contractor vis-à-vis the construction for Port
Blair (Navy) is pending before the arbitrator and till it is finalized, the Stage5 payment payable to the petitioner cannot be quantified.
12.
Learned counsel for the petitioner in rebuttal submits that even as per
the respondent, some of the payments were dependent upon the arbitration
proceedings pending between the respondent and the contractor which
culminated in the years 2023-24 and therefore, the claim is within limitation.
13.
The undisputed fact is that the disputes in relation to the Port Blair
(Navy) project are still pending in arbitration and that the disputes relating to
other completed projects arising from the same tender were pending in
arbitration till 2023-24. The respondent has taken the stand that the
consultancy fee of the petitioner cannot be quantified till the arbitration is
concluded. In these circumstances, prima facie it is not a case of stale claim.
14.
The law is well-settled that the scope of reference court under Section
11 of the Act is well defined. Suffice to say that at the stage of reference the
court has to satisfy regarding the existence of an arbitration clause and a
prima facie arbitrable dispute between the parties. Reliance is placed on the
decision of the Supreme Court in SBI General Insurance Co. Ltd. v. Krish
Spinning., 2024 INSC 532 and held as under:
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 07/08/2026 at 11:21:27
“114. In view of the observations made by this Court in In
Re: Interplay (supra), it is clear that the scope of enquiry at
the stage of appointment of arbitrator is limited to the
scrutiny of prima facie existence of the arbitration
agreement, and nothing else. For this reason, we find it
difficult to hold that the observations made in Vidya Drolia
(supra) and adopted in NTPC v. SPML (supra) that the
jurisdiction of the referral court when dealing with the
issue of “accord and satisfaction” under Section 11 extends
to weeding out ex-facie non-arbitrable and frivolous
disputes would continue to apply despite the subsequent
decision in In Re: Interplay (supra).”
15.
Learned counsel for the respondents on instructions has no objection
for referring the matter to arbitration.
16.
Learned counsel for the petitioner and respondents are ad idem that
Justice Mr. Rajiv Shakdher (Retd.) be appointed as the sole arbitrator.
17.
Accordingly, the petition is allowed by appointing Justice Mr. Rajiv
Shakdher (Retd.) (Mobile No.09717495004) as the sole arbitrator for
adjudication of the disputes which have arisen between the parties.
18.
Arbitral proceedings will be held under the aegis of Delhi
International Arbitration Centre (DIAC). Fee of the Arbitrator shall be fixed
as per fee schedule.
19.
Before entering upon reference, the learned Arbitrator will comply
with Section 12 of the Act.
20.
It is made clear that since this Court has not expressed any opinion on
the merits of the rival claims of the parties and has only prima facie satisfied
that the entire claim cannot be deadwood. It will be open for the parties to
file their respective claims/counter claims before the learned Arbitrator
which will be considered in accordance with law.
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 07/08/2026 at 11:21:27
21.
A copy of this order be forwarded to the learned Arbitrator for
information.
AVNEESH JHINGAN, J
AUGUST 4, 2026
Ch
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 07/08/2026 at 11:21:27
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review