The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
14. Resultantly, this Court is of the considered opinion that the project work, which was awarded in the year 2000 with a ninemonth completion timeline and had been completed in the year 2006, cannot revive a dead cause of action and also because the last payment was made on 27.12.2015. The necessary notice had to be served within a period of three years from that final payment, which the petitioner has failed to do. Filing a petition for the appointment of an arbitrator after ten years after receiving the final payment cannot revive a claim barred by limitation.
15. Resultantly, the present petition is dismissed on the grounds of delay and laches. Pending miscellaneous application(s), if any, shall also stand disposed of. (G.S. Sandhawalia) Chief Justice 30th October, 2026 (Munish Thakur)
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
( 2026:HHC:47539 )
IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
Arb. Case No.197 of 2025
Reserved on: 16.10.2026
Pronounced on: 30.10.2026
Uploaded on: 30.10.2026
Girish Gupta
.....Petitioner
Versus
HPSEBL and Others
Coram:
…..Respondents
The Hon'ble Mr. Justice G.S. Sandhawalia, Chief Justice.
Whether approved for reporting?
For the petitioner:
Mr. Rakesh Manta and Mr. Aryan Manta,
Advocates.
For the respondents:
Mr. Sourabh Chand, Advocate,
Ms. Vandana Misra, Advocate.
for
G.S. Sandhawalia, Chief Justice.
The present petition has been filed by the petitioner
under Section 11(6) of the Arbitration and Conciliation Act, 1996
(hereinafter referred to as ‘the Act’) for appointment of an Arbitrator.
The Contract in question was for the work namely, “Construction of
Type-II quarters 6 No’s set at Keleston (Bharari), Shimla-I”. The said
Contract, amounting to Rs.18,70,708/-, was awarded to the
petitioner by the Executive Engineer, Shimla (Electric), Division
No.II, HPSEBL, Kasumpti Shimla, Himachal Pradesh, vide letter
dated 23.06.2000 (Annexure P-1).
Subsequently, the parties
entered into an agreement containing the arbitration clause on the
basis of which this petition has been filed.
2.
As per the agreement (Annexure P-2), the stipulated
period for completion of the project was nine months, making the
due date 07.04.2001, however, the actual date of completion of the
project was 15.06.2006. The last payment of Rs.3,94,522/- was
received from the respondents by the petitioner on 27.12.2015.
3.
Apparently, communications were exchanged between
the parties regarding the payment of the balance amount, as
evidenced by letters dated 26.12.2017 (Annexure P-3), 27.12.2017
(Annexure P-4), and 28.12.2017 (Annexure P-5). Resultantly, the
matter was referred to the Additional Superintending Engineer,
Electrical Division No.II, HPSEBL, Shimla, by the Deputy Chief
Engineer, Operation Circle, HPSEBL, Kasumpti Shimla, vide
communications dated 05.01.2018 (Annexure P-6) and 09.01.2018
(Annexure P-7).
4.
On 05.05.2020 (Annexure P-9 colly), the price
escalation bill amounting to Rs.4,12,736/- was raised by the
petitioner and forwarded to the Additional Superintending Engineer,
Shimla (E) Division No.II, HPSEBL, Shimla. Thereafter, after a
period of almost two years, the petitioner issued a notice dated
01.07.2022 (Annexure P-10) for appointment of a sole arbitrator.
This notice informed the respondents that if they failed to appoint a
sole arbitrator in accordance with the provisions of ‘the Act’, the
petitioner would proceed in accordance with the law. The matter was
subsequently referred within the official respondents' department on
13.07.2022 (Annexure P-11), but no arbitrator was appointed,
ultimately leading to the filing of the present petition on 24.06.2025.
5.
The respondents have raised an objection as to
limitation, contending that the claim is barred by the three-year
period running from the accrual of the cause of action. While placing
reliance upon the judgments of the Apex Court in Bharat Sanchar
Nigam Limited and Another Vs. M/s. Nortel Networks India
Private Limited (2021) 5 SCC 738 and Obulapuram Mining Co.
Private Limited v. JSW Steel Limited (AIR Online 2019 BOM
2053), and following State of Himachal Pradesh & Another Vs.
M/s Himachal Techno Engineers & Another (2010) 12 SCC 210,
they have opposed the appointment of the Arbitrator.
6.
It is stated that vide letters dated 24.08.2011 and
06.09.2012, the petitioner was requested to attend the office to settle
their grievances, but failed to do so (Annexure R-A/I colly). It is
further stated that the actual work was completed by the petitioner
on 15.05.2006, which is after a lapse of five years from the original
completion period and eight months beyond the last granted
extension. Clauses 10C and 10CC of the agreement were applicable
only, if the work was executed within the stipulated period.
7.
Reliance is also placed upon the judgment of the Apex
Court in M/s Pandit Munshi Ram & Associates Vs. Delhi
Development Authority (AIR 2001 Delhi 82), wherein it has been
held that once the final bill is prepared and paid, and the contractor
accepts the same without protest, no further claim survives.
8.
The final bill and receipts of the payments were
attached as (Annexure RA-3 colly).
Because the final payment
was made on 27.12.2015, it is pleaded that stale claims could not be
entertained and the limitation period could not be extended
indefinitely. The cause of action arose way back in the year 2015,
when the payments had already been released to the petitioner.
9.
In the replication filed by the petitioner, the plea was
taken that the respondents were not bothered to make the legitimate
payments to the petitioner. Resultantly, the claim was within
limitation.
10.
A perusal of the above facts would go on to show that,
after receiving the last payment on 27.12.2015, the petitioner did
nothing except filing representations and seeking the release of final
bills and securities in the year 2017. The petitioner took no positive
steps to invoke the arbitration clause and invoke the jurisdiction of
the Court. Merely because there was some inter se correspondence
in the year 2018 does not revive the cause of action. Furthermore,
the claim was made for the first time thereafter on 05.05.2020, which
could not revive a dying right. Serving a notice under Section 21 of
the ‘the Act, 1996’ on 01.07.2022 (Annexure P-10) cannot resurrect
a dead cause of action on behalf of the petitioner. The Apex Court
has time and again held that dead causes must be weeded out, and
old, stale claims cannot be permitted or agitated merely on account
of filing representations.
11.
The said view has been consistently followed in the
judgment passed by the Apex Court in Bharat Sanchar Nigam
Limited and Another Vs. M/s. Nortel Networks India Private
Limited (supra) and also in Civil Appeal No. 4320 of 2026, titled as
State of West Bengal and Others Vs. M/s. B.B.M. Enterprises,
dated 09.04.2026, wherein the order of the High Court which had
restored a dead dispute after a period of twenty years was set aside.
12.
Reliance can also be placed upon the judgment passed
by the undersigned in Arb. Case No.167 of 2025, titled as Shashi
Sharma Vs. The State of Himachal Pradesh and Others on
03.07.2026. In that case, notice was issued five and a half years
after the cause of action arose, long after the dispute had died, as
the contractor had done nothing for eight years. It was held therein
that merely serving a notice on 22.03.2024 to claim an outstanding
amount or raise a bill would not give a fresh cause of action to the
petitioner.
13.
In Arbitration Petition (C) No.13 of 2023, titled as M/s
B and T AG Vs. Ministry of Defence, decided on 18.05.2023, a
similar issue concerning the appointment of Arbitrator arose before
the Apex Court. The encashment of the warranty bond had taken
place on 16.02.2016 and thereafter, the parties apparently remained
in discussions. The petitioner requested the respondents to review
the wrongful imposition of the 8 liquidated damages on 04.09.2019
and a notice of the arbitration was sent by the petitioner on
08.11.2021. The said notice was held to have been sent after a
period of more than five years, far beyond the limitation period of
three years. Resultantly, it was held that the ‘Breaking Point’ should
be treated as the date on which the cause of action arose for the
purpose of limitation, which was the encashment of the bank
guarantee. It was held that the entire history of the case has to be
seen and whether a party has abandoned efforts at arriving at a
settlement. It was was accordingly held that it is not open to a party
to sit tight and not file an application for settlement of a dispute within
the time prescribed by the Limitation Act and allow his right to be
extinguished by the lapse of time and thereafter to assert a cause of
action to file an application under Section 11 of the Act for
establishment of his right, which is not alive. The relevant
paragraphs of the said judgment read as under:“62. At the cost of repetition, we state that when the
bank guarantee came to be encashed in the year
2016 and the requisite amount stood transferred to
the Government account that was the end of the
matter. This "Breaking Point should be treated as the
date at which the cause of action arose for the
purpose of limitation.
63. Negotiations may continue even for a period of ten
years or twenty years after the cause of action had
arisen. Mere negotiations will not postpone the "cause
of action" for the purpose of limitation. The Legislature
has prescribed a limit of three years for the
enforcement of a claim and this statutory time period
cannot be defeated on the ground that the parties
were negotiating.”
14.
Resultantly, this Court is of the considered opinion that
the project work, which was awarded in the year 2000 with a ninemonth completion timeline and had been completed in the year
2006, cannot revive a dead cause of action and also because the
last payment was made on 27.12.2015. The necessary notice had to
be served within a period of three years from that final payment,
which the petitioner has failed to do. Filing a petition for the
appointment of an arbitrator after ten years after receiving the final
payment cannot revive a claim barred by limitation.
15.
Resultantly, the present petition is dismissed on the
grounds of delay and laches. Pending miscellaneous application(s),
if any, shall also stand disposed of.
(G.S. Sandhawalia)
Chief Justice
30th October, 2026
(Munish Thakur)
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.