IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
APPELLATE SIDE
Present:
The Hon’ble Justice Lanusungkum Jamir
And
The Hon’ble Justice Rai Chattopadhyay
MAT 1340 of 2025
Ganesh Kumbhakar & Ors.
Vs.
WB Power Development Corporation Ltd. & Ors.
For the appellants
: Mr. Amitava Mukherjee, ld. Sr. Adv.
: Ms. Arpita Saha
: Ms. Ankita Ghosh
: Ms. Antara Das
For the respondent Nos. 1 & 4
: Mr. Ranjay De, ld. Sr. Adv.
: Mr. Basabjit Banerjee
: Mr. Adityajit Abel Bose
For the State
: Mr. S. Banerjee
: Mr. Diptendu Narayan Banerjee
Heard on
: 21/01/2026
Judgment on
: 26/02/2026
Rai Chattopadhyay, J. :1.
The appellants are the sponsored candidates, appointed in a
specific project of the respondent no. 1/the West Bengal Power
Development Corporation Limited. They are aggrieved with the
judgment of the Hon’ble Single Bench, dated May 19, 2025 in WPA
No. 8847 of 2009 and file this appeal with the prayer to set aside
the said judgment and for absorption and regularization of their
service, with the respondent no. 1.
2.
The appellants intend to derive their right of absorption from a
tripartite agreement dated July 02, 2008, entered into between the
respondent no. 1 and the trade unions. According to the
appellants, the said tripartite memorandum dated July 02, 2008 is
the recognized policy decision for regularisation of workers in Unit
No. 5 and in Unit No. 6 also, during the future course. It is stated
that according to the agreed terms, unanimously entered into by
all
the
stakeholders,
the
sponsored
workers,
that
is
the
appellant/writ petitioners would be absorbed and engaged in the
operation and maintenance of Unit No. 5 immediately and in Unit
No. 6 in due course. It is stated further that by dint of the same, a
binding obligation has been created upon the respondent no. 1, to
absorb and regularise the appellants.
3.
The General Manager, Santhaldih Thermal Power Station, wrote to
the District Employment Exchange on December 17, 2004, for
sponsoring names of unskilled labourers, to be engaged in the
construction site of Unit No. 5. Hence, the names of the
appellants/petitioners were sponsored and they have been engaged
in the year 2005. The petitioners have been placed under the
contractors and this way they were continued being engaged as
unskilled labourers with the respondent no. 1.
4.
Allegedly, from mid of 2007, the authority started to terminate
those labourers, earlier sponsored by the Employment Exchange.
Consequently, labour agitation took place. Ultimately, at the
intervention of the District Magistrate, the parties have entered
into the said Memorandum dated July 02, 2008.
5.
In the writ petition as above, the appellant/petitioners have sought
for the relief that they may be directed to be absorbed and
regularised with the respondent no. 1.
6.
The Hon’ble Single Bench has held as follows:“28. It is absolutely the discretion of the respondent thermal
power plants to seek the requisite number of man power to
accomplish individual project irrespectively. The petitioners cannot
direct the respondent thermal power plants to utilize the
manpower in a specific manner, being nowhere connected with
the respondent thermal power plants either in management or in
organization. The cessation of their employment, definitely
disheartening and unfortunate, should be addressed to the
Employment Exchange for contemplating avenues for 'alternative
engagement suitably. The petitioner's deployment through
contractors does not accrue any legal right violative of the
provisions of the Constitution, since the terms and conditions of
functioning are restricted to the agreement between the
contractors and the respondent thermal power plants with
definite clause of expiration at the end of its period of validity
which cannot continue till eternity being time bound and project
specific.
29. The petitioners were not providing the job of permanent or
perennial nature. There were basically hired by the independent
contractor and were not essentially performing the work of
permanent employees to be considered for regularization or to
claim any vested right against retrenchment. The deployment of
the petitioners had been restricted to the duration of the contract
between the contractor, through whom the petitioners had been
engaged and the principal employer, being the respondent
thermal power plants. The respondent thermal power plants did
not directly employ the petitioners who are therefore debarred
from claiming any legal or vested rights against the respondent
thermal power plants for violation of constitutional provisions as
well as principles of natural justice.
30. However, the petitioners are at liberty to approach Respondent
5,6,7 to reconsider their status of retrenchment giving them an
opportunity of hearing and if legally permissible and practicable to
provide alternative engagement through contractors at different
sites if at all their work power as unskilled person is required for
the interest of public administration.”
7.
For the reasons as above, the writ petition has been dismissed,
though the appellant/writ petitioners were granted liberty to
approach
the
respondent
nos.
5,6,7,
that
is,
the
District
Magistrate/SDO/Employment Exchange Officer, for their redress.
8.
Mr. Amitava Mukherjee, learned Senior advocate on behalf of the
appellants has stated that the impugned judgment of the Single
Bench dated May 19, 2025 is absolutely misconceived and suffers
from non-application of mind and wrongful or no consideration of
what the law has provided for. The policy regarding engagement of
maintenance of unskilled labourers as determined by dint of the
said memorandum is, to engage the petitioners as unskilled
workers being sponsored by the Employment Exchange, for Unit
No. 5 and in future with unit No. 6 too. Mr. Mukherjee has
submitted that, the respondent No. 1 by writing letter to the
Employment Exchange sought for sponsorship of names of
unskilled workers for the organization. That the petitioners
reported to the respondent No. 1 and from there, they have been
channelized through the contractor, for employment. Therefore,
according to the appellant/writ petitioners the entire process of
recruitment of the appellants was at the instance of the respondent
No. 1 only. The contractor had no role to play in the same.
9.
Similarly, in day to day disposition of duty by the present
appellants and also regarding disbursement of their wages and
discipline, the only responsible authority has been the respondent
No. 1 and none else. The project in which the appellants were
engaged was directly supervised by the respondents including the
day to day work disposition of each of the appellants. Therefore,
according to them, the respondent No. 1 directly controlled and
supervised the appellants.
10. Further, it has been submitted that, the work for which the
appellants were engaged into is of perennial nature in so far as the
maintenance work of the organization is only co-extensive with the
life of the organization itself. It is submitted further that the
appellants have been consistently kept being engaged with the
respondent No. 1 though, the contractors have changed for several
times in between. Initially, the respondent No. 1 sought to engage
the appellants for three years, though continued with their service
for 5 years and more, without any break. According to the
appellants, the respondent No. 1/the principal employer should be
considered to have direct supervision and control over their work,
which is perennial in nature. Therefore, there exists employeremployee relationship between the appellants and the respondent
No. 1.
11. Further that the tripartite settlement has provided for selection of
the appellants as the sponsored candidates as regular employees of
the respondent No. 1.
12. Mr. Mukherjee has submitted that, for all the reasons, the
appellants are eligible to be absorbed and regularized with the
respondent No. 1 which the Hon’ble Single Judge has not
considered. That, the impugned judgment is passed without
considering
whether
there
existed
any
employer-employee
relationship between the appellants and the respondent No. 1 and
whether the job they were discharging was perennial in nature or
not. Also, it has not been considered that, if the appellants were
actually under direct supervision and control of the respondent No.
1. Therefore, he says that the impugned judgment is unsustainable
having not considered the legal framework for absorption of the
contract labours like the present appellants. Instead, the direction
passed by the Hon’ble Single Bench is only misconceived and
illegal. Hence, the appellants have prayed for setting aside of the
impugned judgment dated May 19, 2025 in WPA no. 8847 of 2009
and a direction upon the respondent No. 1 for their regularization.
13.
Also, according to the appellants, the instant is a case where the
employment through the contractor was sham or camouflage
arrangement, which is prima facie apparent. In that case, the law
is well-settled that the veil is to be removed to find the employeremployee relationship to be existing between the parties.
14.
The following judgments have been relied on by the appellant:i) Full Bench judgment of this Court in Awadhesh Singh
Vs. Union of India [(2013) 3 CHN Cal 407]
ii) Steel Authority of India Limited Vs. Workmen
reported in (2017) 3 CHN Cal 143.
15. The respondent No. 1 has been represented by Mr. Ranjay De,
learned senior advocate. It is submitted that, there was never any
privity of contract between the appellants and the respondent No.
1. Hence, according to the respondent, the present writ petition is
not maintainable as the appellants have no right to be enforced
under Article 226 of the Constitution of India. Mr. De has declined
to accept that the appellants have been remunerated by the
respondent No. 1 and submits that this amounts to be a disputed
question of fact which is required to be determined by a factfinding authority, upon evidence. On that score also, he challenges
the very maintainability of the writ petition.
16. According to the respondent, it is explicitly clear that the
appellants / writ petitioners were the unskilled contract labours
engaged by the contractors for the construction of unit no. 5 of
STPS. The said construction job has come to an end long back. The
appellant is of 58 years of age. That, the STPS is a highly
sophisticated power generating unit where there is no requirement
for any unskilled contract labour. That, there never subsisted any
employer-employee
relationship
between
the
respondent
Corporation and the contract labours; there is no averment in the
writ petition that the appellants / writ petitioners being the
contract labours were engaged by the respondent Corporation and
the management of the respondent was the paymaster; nor
anything could be placed on behalf of the appellants / writ
petitioners that the management of the respondent Corporation
ever exercised any supervision and control over them and, it is
settled law that no absorption can be made of the persons those
who have worked in any organization not being employed following
the prescribed Rules therefor. The respondent further says that, it
is trite law that the prayer for absorption can never be entertained
by this Hon'ble Court under Article 226 of The Constitution of
India. In other words, the prayer for absorption is unsustainable in
law as there was no privity of contract between the Corporation
and the contract labours.
17. According to the respondent, the learned Single Bench has
committed no wrong in law while dismissing the claim of the
appellants / writ petitioners for absorption in the respondent
Company and as such, the said judgment and order dated May 19,
2025, impugned herein, does not require any intervention by this
Appeal Court.
18. The following judgments have been referred to by the respondent:i) Sunil Kumar Biswas Vs. Ordnance Factory Board and
Ors. reported in [(2019) 15 SCC 617]
ii) Oshiar Prosad & Ors. Vs. The employers in relation to
management of Sudamdih Coal Washiery of M/s. BCCL,
Dhanbad, Jharkhan reported in [(2015) 4 SCC 71]
iii) A.P. SRTC & Ors. Vs. G. Srinivas Reddy & Ors.
reported in [(2006) 3 SCC 674]
iv) Secretary, State of Karnataka & Ors. Vs. Umadevi (3)
& Ors. reported in [(2006) 4 SCC 1]
v) Indian Drugs & Pharmaceuticals Ltd. Vs. Workman,
Indian Drugs & Pharmaceutical Pvt. Ltd. reported in
[(2007) 1 SCC 408]
vi) Shakti Shankar Dey & Anr. Vs. Union of India & Ors.
reported in [2005 SCC OnLine Cal 231]
vii) Awadhesh Singh & Ors. Vs. Union of India & Ors.
reported in [2013 SCC OnLine Cal 9458]
viii) General Manager (OSD), Bengal Nagpur Cotton Mills,
Rajnandgaon Vs. Bharat Lal & Ors. reported in [(2011) 1
SCC 635]
ix) Balwant Rai Saluja & Anr. Vs. AIR India & Ors.
reported in [(2014) 9 SCC 407]
x) Bharat Heavy Electricals Ltd. Vs. Mahendra Prasad
Jakhmola & Ors. reported in [(2019) 13 SCC 82]
19. It appears that, the General Manager, STPS writes to the
Employment Exchange Officer vide letter dated December 17, 2004
that, in view of the imminent construction work of one new unit at
STPS, the said respondent requires some unskilled workers (about
300 in numbers) whose service under different contractors may be
required for about three years depending on the nature of job.
Since thereafter, the names of the appellants having been
sponsored by the Employment Exchange vide letter dated January
07, 2005 they were engaged to discharge unskilled labour in the
construction site of the respondent No. 1 under different
contractors. According to the appellants, the engagement of
contractor was only a camouflage to deprive the appellants from
their lawful due upon being engaged with the respondent No. 1.
While instead, the appellants have actually worked under direct
supervision and control of the said respondent being appointed
and accountable to the respondent No. 1 only. According to them,
they have been paid by the respondent No. 1, which fact has been
disputed in this case by the said respondent. The fact of
termination of employment of the appellants has however, not
disputed by the respondent. The respondents say that, amongst
the appellants and the respondent, there is no privity of contract or
employer-employee relationship between them. Therefore, there
would not be any obligation on part of the respondent as regards
the contractual employment of the present appellants.
20. The Court notices that, the memorandum, heavily relied on by the
appellants in this case has stipulated that “the unskilled workers of
the O&M job will be engaged from the list of the candidates of
Employment Exchange, if required through selection”.
21. Considering all as above, the Court is of definite finding that, the
issues involved in the instant case relate to whether there existed
employer-employee relationship between the appellants and the
respondent No. 1 or whether the respondent No. 1 exercised direct
supervision and control on the appellants as the sponsored
unskilled labourers under contractors engaged with them; also
that, whether engagement of contractor is only a camouflage to
deprive the appellants of their lawful dues, which needs to be
wiped out. All these amount to be disputed questions of fact, which
require determination by the fact-finding authority and only upon
evidence. It is the settled law that, while exercising power of
judicial review under Article 226 of the Constitution, the High
Court would not generally consider the disputed questions of fact
and relegate the matter to the fact finding authority for decision.
22. In a petition filed under Article 226 of the Constitution, it is not for
the court to go into disputed question of fact namely, whether the
employees are under the direct supervision and control of the
employer or whether the veil of working under the contract
contractor is required to by lifted to establish the employeremployee relationship between the parties. In this context reference
may be had to the judgment of the Supreme Court in the case of
Real Estate Agencies vs. State of Goa and Others, (2012) 12
SCC 170 where the Supreme Court held as follows:
"17. However, there is no universal rule or principle of law which
debars the writ court from entertaining adjudications involving
disputed questions of fact. In fact, in the realm of legal theory, no
question or issue would be beyond the adjudicatory jurisdiction
under Article 226, even if such adjudication would require taking of
oral evidence. However, as a matter of prudence, the High Court
under Article 226 of the Constitution, normally would not entertain
a dispute which would require it to adjudicate the contested
questions and conflicting claims of the parties to determine the
correct facts for due application of the law. In ABL International Ltd.
v. Export Credit Guarantee Corpn. of India Ltd., [(2004) 3 SCC 553],
the precise position of the law in this regard has been explained in
paras 16, 17 and 19 of the judgment in the course of which the
earlier views of this Court in Gunwant Kaur v. Municipal Committee,
Bhatinda, [(1969) 3 SCC 769] and Century Spg. & Mfg. Co. Ltd. v.
Ulhasnagar Municipal Council, [(1970) 1 SCC 582] has been referred
to.
18. The aforesaid paragraphs of the judgment in ABL International
Ltd. v. Export Credit Guarantee Corpn. of India Ltd., [(2004) 3 SCC
553] may, therefore, be usefully extracted below: (SCC pp. 567-69)
"16. A perusal of this judgment though shows that a writ petition
involving serious disputed questions of facts which requires
consideration of evidence which is not on record, will not normally
be entertained by a court in the exercise of its jurisdiction under
Article 226 of the Constitution of India. This decision again, in our
opinion, does not lay down an absolute rule that in all cases
involving disputed questions of fact the parties should be relegated
to a civil suit. In this view of ours, we are supported by a judgment
of this Court in Gunwant Kaur v. Municipal Committee, Bhatinda,
[(1969) 3 SCC 769] where dealing with such a situation of disputed
questions of fact in a writ petition this Court held: (SCC p. 774, paras
14-16)
`14. The High Court observed that they will not determine disputed
question of fact in a writ petition. But what facts were in dispute
and what were admitted could only be determined after an
affidavit-in-reply was filed by the State. The High Court, however,
proceeded to dismiss the petition in limine. The High Court is not
deprived of its jurisdiction to entertain a petition under Article 226
merely because in considering the petitioner's right to relief
questions of fact may fall to be determined. In a petition under
Article 226 the High Court has jurisdiction to try issues both of fact
and law. Exercise of the jurisdiction is, it is true, discretionary, but
the discretion must be exercised on sound judicial principles. When
the petition raises questions of fact of a complex nature, which may
for their determination require oral evidence to be taken, and on
that account the High Court is of the view that the dispute may not
appropriately be tried in a writ petition, the High Court may decline
to try a petition. Rejection of a petition in limine will normally be
justified, where the High Court is of the view that the petition is
frivolous or because of the nature of the claim made dispute sought
to be agitated, or that the petition against the party against whom
relief is claimed is not maintainable or that the dispute raised
thereby is such that it would be inappropriate to try it in the writ
jurisdiction, or for analogous reasons."
23. In Sanjay Sitaram Khemka vs State of Maharashtra [(2006) 5
SCC 255] the Supreme Court has held:
“8. Having regard to the allegations and counter allegations made
by the parties before us, we are of the opinion that no relief can be
granted to the Petitioner in this petition. The writ petition has
rightly been held by the High Court to be involving disputed
questions of fact. The petitioner has several causes of action
wherefor he is required to pursue specific remedies provided
therefor in law.
9. A Writ Petition, as has rightly been pointed out by the High Court,
for grant of the said reliefs, was not the remedy. A matter involving
a great deal of disputed questions of fact cannot be dealt with by
the High Court in exercise of its power of judicial review. As the High
Court or this Court cannot, in view of the nature of the controversy
as also the disputed questions of fact, go into the merit of the
matter, evidently no relief can be granted to the Petitioner at this
stage. We are, therefore, of the opinion that the impugned
judgment of the High Court does not contain any factual or legal
error warranting interference by this Court in exercise of its
jurisdiction under Article 136 of the Constitution”.
24. Writ courts have jurisdiction over questions of fact but normally
refrain from entertaining seriously disputed or complex factual
issues requiring oral evidence or detailed investigation. Parties
must pursue specific remedies in civil courts or appropriate forums
for factual adjudication, as writ jurisdiction is extraordinary and
suited for legal errors or jurisdictional issues, not rival claims on
facts. The principle stems from prudence and judicial economy,
reinforced by Supreme Court, emphasizing that disputed facts lead
to dismissal of writ petitions.
25. It is beneficial to mention the following portion of the three-Judges
Bench decision of this Court in Awadhesh Singh’s Case (supra)
which is as follows:“15. In this context, the substance of the grievance and relief
that the party aggrieved seeks are also of some relevance.
Assuming that the claim of the contract labours succeed before
the Central Administrative Tribunal, an order would necessarily
follow directing their regularization/absorption in Railway
service. In view of the decision in L. Chandra Kumar (supra), the
High Court can be approached after the first round of litigation
is initiated before the Central Administrative Tribunal and not
directly.
16. Turning our focus to the CLRA Act, we are inclined to take
the view on examination of the provisions thereof that it is the
forum under the ID Act that ought to be ordinarily approached
for the relief that the petitioners claim. Bearing in mind the
definition of ‘contract labour’, ‘contractor’, ‘establishment’,
‘principal employer’ and ‘workman’ in the CLRA Act, the forum
that is approached for relief of regularization/absorption may
have to consider the question as to whether the contractor has
been interposed either on the ground of having undertaken to
produce a given result for the establishment or for supply of
contract labour/workmen for any work of the establishment
under a genuine contract or is a mere ruse/camouflage to
evade compliance with various beneficial provisions so as to
deprive the workmen of the benefits thereunder. Hon'ble
Supreme Court has authoritatively held in number of decisions
that where the answer is in the affirmative, the workman will
have to be treated as an employee of the principal employer
who shall be directed to regularize his service in the
establishment subject to eligibility. However, if the answer is in
the negative, the workman will be a contract labour. Reference
in this connection may be made to the case in Steel Authority of
India Ltd. v. National Union Waterfront Workers, reported in
(2001) 7 SCC 1. Answering the aforesaid question would
necessarily involve enquiry into disputed questions of fact,
which cannot conveniently be made by the High Court under
Article 226 of the Constitution, and it is the Industrial
Tribunal/Labour Court that would be the appropriate authority
to determine the issue.
17. From whichever angle the problem is viewed, it seems to be
inescapable that the contract labours must plead and prove
that the contract between the principal employer and the
contractor is a mere ruse/camouflage to deprive benefits to
them flowing from the beneficial legislations and that they are
really the employees of the principal employer. In other words,
there is relationship of employer-employee between the
principal employer and the workman and declaration ought to
be claimed for recognition of such relationship and
consequential direction for regularization/absorption. In the
absence of such a claim in the pleadings, no relief can at all be
granted and the claim is likely to fail. Once such claim is
traceable in the pleadings, the contract labours would not be
entitled to urge that notwithstanding the fact they are contract
labours they are entitled to maintain a writ petition before the
Writ Court prior to an adjudication/determination by the
Industrial Tribunal or the Central Administrative Tribunal, as
the case may be.”
26. The Court has held that, there are certain guidelines and settled
principles upon which a Court has to determine whether the
workman is an employee under the principal employer or a
contract labour but answering the said question would necessarily
involve enquiry into disputed questions of fact, which should not in
an usual and normal course, be made by the High Court under
Article 226 of the Constitution. The Court has held that, it is the
Industrial Tribunal/Labour Court that would be the appropriate
authority to determine the issue. The Court has held further that,
in case, the employees plead before the Court of a camouflage
contract to have been infused in between them and the principal
employer, the contract labours would not be entitled to urge that,
notwithstanding the fact, they are contract labours, they are
entitled to maintain a writ petition before the Writ Court, prior to
an adjudication/determination by the Industrial Tribunal.
27. Hence, therefore, there can be no doubt about the settled legal
position that, to agitate the disputes questions of fact as above, the
statutory Tribunal and not the High Court in exercise of
jurisdiction under Article 226 of the Constitution – would be the
appropriate forum. In such view of the fact, the finding of the
Hon’ble Single Judge relegating grievance of the appellants to the
District Administration appears to be de hors the law and strongly
unsustainable. The judgment as impugned in the instant case, is
thus liable to be set aside.
28. The instant writ petition faces challenge as to the maintainability
on another score. The established principle of public recruitment is
in conformity with Article 16 of the Constitution and appointment
only of the persons sponsored by the Employment Exchange,
violates the same. In Excise Superintendent, Malkapatnam v.
K.B.N. Visweshwara Rao [(1996) 6 SCC 216], the Supreme Court
held restricting recruitment only to candidates sponsored by the
Employment Exchange violates Article 16; the process must involve
wide publicity of the vacancy and ensure broader opportunity. The
Court emphasized that limiting selection only to sponsored
candidates excludes many eligible persons and is constitutionally
infirm.
29. Be that as it may, for all the reasons as discussed above, the
impugned judgment dated May 19, 2025 in WPA no. 8847 of 2009
is set aside. This Court is however, of the opinion that, there are
several disputed questions of fact which require judicial attention
of the appropriate statutory authority and the matter is to be tried
on evidence. This Court, in exercise of power under Article 226 of
the Constitution, is not to interfere into the dispute raised by
entertaining the writ petition.
30. In that view of the matter, the instant appeal is disposed of by
directing the Assistant Labour Commissioner/Conciliation Officer
under the Industrial Disputes Act, 1947 of appropriate jurisdiction,
to consider the instant writ petition as an application by the
appellant/writ petitioners presented before it, raising an industrial
dispute and consider and dispose of the same in accordance with
law.
31. The appellant/writ petitioners would be at liberty to submit a
photocopy of the writ petition before the Assistant Labour
Commissioner/Conciliation Officer under the Industrial Disputes
Act, 1947 of appropriate jurisdiction for the purpose.
32. The appeal No. MAT 1340 of 2025 is allowed and disposed of.
33. Urgent certified copies of this judgment, if applied for, be supplied
to the parties upon compliance with all requisite formalities.
(Lanusungkum Jamir, J.)
(Rai Chattopadhyay, J.)
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review