Judgments
LegalFirms.in Judgments · legalfirms.in/judgments/gajjala-venkata-subba-reddy-vs-the-union-of-india-20260902/ · Printed 27 Nov 2026
Constitutional

Gajjala Venkata Subba Reddy vs The Union of India

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Andhra Pradesh High Court
Date
2 September 2026
Case No.
WP 24974/2026
Result
Disposed
Bench
Ravi Cheemalapati
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

9. In view of the facts and circumstances of the case, taking into consideration the submissions made by the learned counsel for the parties, and since the petitioner has submitted his objections through e-mail, this Court, without going into the merits of the matter, is inclined to dispose of the Writ Petition with the following directions (i) Respondent Nos.4 to shall consider the objections/representation submitted by the petitioner through e-mail pursuant to the Publication dated 10.04.2025, along with the grievance raised by the petitioner in the affidavit filed in support of the present Writ Petition. (ii) The competent authority shall afford an opportunity of hearing to the petitioner and other concerned parties, if necessary, and thereafter pass a reasoned order on the objections raised by the petitioner, strictly in accordance with law. (iii) The aforesaid exercise shall be completed within a period of two (2) weeks from the date of receipt of a copy of this order. (iv) Till the said exercise is completed, the respondent authorities shall not proceed with the laying of the High Tension (High Voltage) Transmission lines through the petitioner's land in Survey No.175/5, to an extent of Ac.0.54 cents, situated at Kolumulapalli Village, Chinthakommadine Mandal, YSR Kadapa District.

10. Accordingly, the Writ Petition is disposed of. There shall be no order as to costs. As a sequel thereto, interlocutory applications pending, if any in the writ petition, shall also stand closed.

Filed under

Constitution of India Electricity Act, 2003 Section 164, Electricity Act, 2003

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

APHC010456992026 IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) THURSDAY, THE 3rd DAY OF SEPTEMBER 2026 PRESENT THE HONOURABLE SRI JUSTICE RAVI CHEEMALAPATI WRIT PETITION NO: 24974 OF 2026 Between: 1. GAJJALA VENKATA SUBBA REDDY, S/o. Gajjala Venkata Swamy Reddy, Aged about 75 years. Occupation Agriculture, R/o D.No.45/237, Balaji Nagar, 1st Street, Kadapa City, Y.S.R Kadapa District. ...Petitioner AND 1. THE UNION OF INDIA, Rep., by its Secretary, Ministry of Power Shram Shakti Bhawan, Rafi Marg, New Delhi Delhi-110001. 2. Transmission Corporation of Andhra Pradesh Limited APTRANSCO, Vidyut Soudha, Eluru Road, Gunadala, Vijayawada Vijayawada-520004. 3. The District Collector, YSR Kadapa District, Kadapa Kadapa-516001 516001 4. Anantapur nantapur II REZ Transmission Limited, Rep. by its Director First Floor, Urjanidhi, 1 Barakhamba Lane, Connaught Place, New Delhi Delhi-110001. 110001. 5. Anantapur II REZ Transmission Limited, Rep. by its Director DLF Cyber Park, Tower-B, B, 9th floor, Udyog vihar, Pha Phase-lll, Sector--20, Gurugram, Haryana-122016. 6. Resonia Limited, Rep. by its Chairman, Floor, RMZ Infinity, Plot No. 15, Phase IV, Sector 18 Gurugram, Shahpur, Haryana Haryana-122015. 7. Anantapur II REZ Transmission Limited Resonia Ltd, Rep. by its Director, Room No. 102, Opp Vijaya Homes Near Raja Reddy Circle, Pulivendula YSR Kadapa District-516390. ...Respondents Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue an appropriate Writ, Order or direction more particularly one in the nature of Writ of Mandamus declaring the permission granted by the respondent No.1 under Section 164 of the Electricity Act, 2003 through the Gazette Notification, dated 12.09.2025 basing on the false affidavit submitted by the respondents No.4 and 5 that no objections/ representations were received by them within two (2) months from the date of the publication notification, dated 10.04.2025 to lay High-tension (High Voltage) Transmission lines through the land in an extent of Ac.0.54 cents in Survey No. 175/5 respectively in Kolumulapalli Village Chinthakommadine Mandal, YSR Kadapa District, belong to me, despite the fact that, I submitted our objections through a written representation, dated 06.06.2025 through Registered Post and consequential actions of the respondents No.4 and 5 in proceeding further with the laying of High-tension (High Voltage) Transmission lines through the land belong to us as arbitrary, illegal, colourable exercise of power and also well-established legal principles apart from being violative of the fundamental rights and Constitutional rights guaranteed to me under Articles 14, 19, 21 and 300-A of the Constitution of India and consequently direct the respondent No.4 to consider the objections, dated 06.06.2025 submitted by me for shifting of the laying of High Tension Wires through the land in an extent of Ac.0.54 cents in Survey No.175/5 in Kolumulapalli Village, Chinthakommadine Mandal, YSR Kadapa District by setting aside the Gazette Notification, dated 12.09.2025 issued by the respondent No.1 IA NO: 1 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased to direct the respondents No.4 to 6 not to lay 765 kV Double-Circuit Transmission lines connecting Ananthapuram-ll to Kadapa in Chinthakommadine Village, C K Dinne Mandal, YSR Kadapa District, through our agricultural lands situated in an extent of Ac.0.54 cents in Survey No. Survey No. 175/5 of Liga Reddypalle Village Chinthakommadine Mandal, YSR Kadapa District, pending disposal of the above Writ Petition Counsel for the Petitioner: V R REDDY KOVVURI Counsel for the Respondents: GP FOR REVENUE Counsel for the Respondents: The Court made the following order: The grievance of the petitioner is that, despite having submitted his objections by way of a written representation dated 06.06.2025, which was sent through Registered Post, respondent No.1 granted permission under Section 164 of the Electricity Act, 2003, vide Gazette Notification dated 12.09.2025, based on the false affidavit submitted by respondent Nos.4 and 5, wherein they stated that no objections/representations were received by them within two (2) months from the date of publication of the Notification dated 10.04.2025 in respect of the proposal to lay High Tension (High Voltage) transmission lines through the petitioner's land, admeasuring Ac. 0.54 cents in Survey No. 175/5, situated at Kolumulapalli Village, Chinthakommadine Mandal, YSR Kadapa District. 2. Heard Sri V.R.Reddy Kovvuri, learned counsel for the petitioner, learned Additional Solicitor General appearing for respondent No.1, Sri V.V.Satish, learned standing counsel for APTRANSCO appearing for respondent No.2, Sri Venkata Satyanarayana, learned Assistant Government Pleader for Revenue appearing for respondent No.3 and Sri Siva Darshan, learned standing counsel for Anantapur II REZ Transmission Limited appearing for respondent Nos.4 to 7. 3. Learned counsel for the petitioner, in elaboration to what has been stated in the affidavit filed in support of the Writ Petition, contended that, pursuant to the paper Publication dated 10.04.2025, the petitioner attempted to submit his objections by Registered Post, however, the same was returned with an endorsement ‘left the office’. He further submitted that, the petitioner also sent his objections through e-mail. He further submitted that it would suffice, if a direction is issued to respondent Nos.4 to 6 to consider the objections submitted by the petitioner through e-mail and also take into consideration the grievance raised in the affidavit filed in support of the Writ Petition, and pass appropriate orders in accordance with law before proceeding with the laying of any High Tension (High Voltage) Transmission lines. 4. On the other hand, learned Standing Counsel appearing for REZ Transmission Limited, on instructions, contended that, even according to the petitioner, there is a civil dispute with certain third parties in respect of the subject property, which is pending consideration before the competent Civil Court. The petitioner cannot seek a direction to the authorities to await the outcome of the said civil proceedings. He further submitted that, though the respondents had called upon the petitioner to produce the documents evidencing his title to the subject property, the petitioner failed to produce the same. Therefore, the petitioner cannot make allegations against the officials, and the Writ Petition is liable to be dismissed at the admission stage. Hence, prayed to dismiss the Writ Petition. 5. Perused the material available on record and considered the submissions made by the learned counsel for the parties. 6. Paper Publication dated 10.04.2025 clearly called upon the general public to submit their objections/representations with regard to the proposed transmission system to the office of the concerned authority within a period of two (2) months from the date of publication of the said Notification. 7. The main grievance of the petitioner is that, pursuant to the said paper Publication, he attempted to submit his objections through Registered Post, but the same was returned with an endorsement stating ‘left the office’. It is the further case of the petitioner that, thereafter, he submitted his objections through e-mail, however, the said objections have not been considered by the authorities before proceeding further in the matter. 8. This Court is not inclined to go into the aspect as to whether the authorities have to wait for the outcome of the civil suit pending in respect of the subject property. However, since the Publication dated 10.04.2025 gave an opportunity to the general public to submit their objections/representations, the objections submitted by the petitioner pursuant to the said Publication have to be considered by the competent authorities in accordance with law. It is always open to the competent authorities to examine the objections raised by the petitioner and if the objections are found to be sustainable, the authorities shall take such further steps in accordance with law. Even if the objections are found to be untenable, the petitioner has the right to know the decision of the competent authority and the reasons for it, so that he can take any legal remedies available to him. 9. In view of the facts and circumstances of the case, taking into consideration the submissions made by the learned counsel for the parties, and since the petitioner has submitted his objections through e-mail, this Court, without going into the merits of the matter, is inclined to dispose of the Writ Petition with the following directions (i) Respondent Nos.4 to shall consider the objections/representation submitted by the petitioner through e-mail pursuant to the Publication dated 10.04.2025, along with the grievance raised by the petitioner in the affidavit filed in support of the present Writ Petition. (ii) The competent authority shall afford an opportunity of hearing to the petitioner and other concerned parties, if necessary, and thereafter pass a reasoned order on the objections raised by the petitioner, strictly in accordance with law. (iii) The aforesaid exercise shall be completed within a period of two (2) weeks from the date of receipt of a copy of this order. (iv) Till the said exercise is completed, the respondent authorities shall not proceed with the laying of the High Tension (High Voltage) Transmission lines through the petitioner's land in Survey No.175/5, to an extent of Ac.0.54 cents, situated at Kolumulapalli Village, Chinthakommadine Mandal, YSR Kadapa District. 10. Accordingly, the Writ Petition is disposed of. There shall be no order as to costs. As a sequel thereto, interlocutory applications pending, if any in the writ petition, shall also stand closed. ____________________________ JUSTICE RAVI CHEEMALAPATI 03.09.2026 MP THE HON’BLE SRI JUSTICE RAVI CHEEMALAPATI WRIT PETITION No.24974 of 2026 Dated: 03.09.2026 MP

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All AP HC judgments →