Gaggal Airport Expansion Affected Social Welfare Committee vs The Principal Secretary (Tourism and Ca) and Others

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Himachal Pradesh High Court
Date
18 November 2026
Case No.
CWP 7846/2023
Result
Disposed
Bench
Vivek Singh Thakur, Ranjan Sharma
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

193. Needless to say that respondents shall ensure all necessary clearances in terms of EIA Notification dated 14.09.2006 and also TEFR (Techno-Economic Feasibility Report) by taking appropriate step for ensuring timely completion of expansion of Kangra Airport. -113-

194. 2026:HHC:49585 The writ petition is disposed of in above terms, along with all pending applications. (Vivek Singh Thakur) Judge 18th November, 2026 (Pardeep/Susheel) (Ranjan Sharma) Judge

Filed under

Constitution of India Land Acquisition Act, 1894 Article 226, Constitution of India Article 21, Constitution of India

The sections, explained

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Supreme Court judgments it cites, on LegalFirms.in

Found by their neutral or S.C.R. citation in the text of this judgment.

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

2026:HHC:49585 IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA CWP No.7846 of 2023 Reserved on: 30.07.2026 Date of decision: 18.11.2026 Uploaded on: 19.11.2026 Gaggal Airport Expansion Affected Social Welfare Committee. ...Petitioner. Versus The Principal Secretary (Tourism & CA), Government of Himachal Pradesh & Ors. …Respondents. Coram Hon’ble Mr. Justice Vivek Singh Thakur, Judge. Hon’ble Mr. Justice Ranjan Sharma, Judge. Whether approved for reporting? Yes. For the petitioner : Ms. Ritta Goswami, Senior Advocate with Ms. Komal Chaudhary & Ms. Rekha Thakur, Advocates. For the respondent(s) : Mr. Anup Rattan, Advocate General with Mr. Ramakant Sharma, Additional Advocates General and Ms. Swati Draik, Deputy Advocate General, for respondents No.1 & 2-State as well as respondents No.3 & 4. : Mr. Balram Sharma, Deputy Solicitor General of India (Senior Advocate) with Mr. Rajeev Sharma, Advocate, for respondent No.5-UOI. : Ms. Shreya Chauhan, Advocate, for respondent No.6. Whether the reporters of the local papers may be allowed to see the Judgment? Yes -2- 2026:HHC:49585 Vivek Singh Thakur, Judge Petitioner-Gaggal Airport Expansion Affected Social Welfare Committee (hereinafter to be referred as the 'PetitionerCommittee'), through its President Rajneesh Mona, has filed this petition invoking the provisions of Article 226 of the Constitution of India, seeking the following substantial reliefs: "(1) That a writ in nature of certiorari may kindly be issued and the Notification dated 07.07.2023 may kindly be quashed in the interest of justice. (2) That the report dated 03.05.2023 prepared by SIA (Social Impact Assessment) and ditto stamped by the Expert Group vide letter dated 05.06.2023 being violative of the rules as well as the mandatory provisions of the Act ibid may kindly be rejected. (3) That if the Hon'ble court comes to the conclusion that the expansion of the Airport is for the public purpose than in that eventuality, the three alternative sites mentioned in the SIA report may kindly be considered in the interest of justice.” FACTS OF THE CASE 2. In the State of Himachal Pradesh, there are three airports, namely: Bhuntar Airport (Kullu), operational since 1956 and metalled in 1967; Shimla Airport, operational since 1987; and Kangra Airport (Gaggal Airport), operational since 1989. 3. Amongst the aforesaid airports, Kangra Airport has the largest runway length of 1372×30 meters, which is suitable for -3- 2026:HHC:49585 landing 72-seater aircraft with load penalty, and at present, ATR-42 aircraft is operating from this airport with load penalty. 4. Vide communication dated 11.07.2019, the Directorate General of Civil Aviation communicated to the Chairman, Airports Authority of India (AAI), that the Civil Aviation Department of the Government of Himachal Pradesh had no objection for night landing of Indian Air Force aircraft at Gaggal Airport in case of an actual emergency and for any future drills, as requested by AAI and the Ministry of Civil Aviation. However, during such operations, certain conditions to be complied with were also communicated. 5. On the request of the State Government of Himachal Pradesh, vide letter dated 15.11.2019 addressed to the Chairman, Airports Authority of India (AAI), regarding development/expansion of Kangra Airport, AAI officials visited the site on 21.12.2019 and 22.12.2019, and forwarded their preliminary analysis vide communication dated 03.01.2020 along with a draft Master Plan, with recommendation of runway extension of 1950 meters and to explore the feasibility for acquisition of additional land, as well as channelization of Manjhi Khad for a bridge of 380 meters width to be constructed with the approval and specifications of the Bureau of Civil Aviation Security (BCAS). -4- 6. 2026:HHC:49585 Upon receipt of the draft Master Plan, vide letter dated 29.10.2020, Government of Himachal Pradesh, Department of Tourism and Civil Aviation, conveyed that the Deputy Commissioner, Kangra at Dharamshala had identified the land for expansion of Kangra Airport. 7. Vide communications dated 11.12.2020 and 15.01.2021, the Department of Tourism and Civil Aviation requested for an Obstacle Limitation Surface (OLS) survey and a feasibility study for the land identified for the purpose of expansion of Kangra Airport. 8. An OLS survey was conducted by a team of officials of AAI, and the OLS chart and obstacle penetration data for Kangra Airport was forwarded to the Government of Himachal Pradesh on 16.04.2021 and 17.04.2021, which was confirmed by communication dated 06.05.2021. Thereafter, a feasibility study report and development plan were prepared for expansion of Kangra Airport in two phases. 9. Vide communication dated 07.10.2021, the Airports Authority of India communicated, the possibility of development of Kangra Airport (Gaggal Airport) in two phases, to the Principal Secretary (Tourism and Civil Aviation) to the Government of -5- 2026:HHC:49585 Himachal Pradesh (Annexure R-2), stating therein that Kangra Airport can be developed in two phases: Phase-I for operation of ATR-72/Q-400 type of aircraft, and Phase-II for operation of A-320 type of aircraft. 10. Vide aforesaid communication dated 07.10.2021, AAI informed the Government of Himachal Pradesh that major cutting and filling involved in the project required to be studied for diversion of streams, cutting and filling, and environmental clearances are to be obtained before taking up the work for the project, and it was decided by the State Government that land shall be acquired in only one phase for the complete expansion plan of extension of runway up to 3010 meters. 11. Vide letter dated 02.11.2021, the Airports Authority of India communicated to the Principal Secretary (Public Works, Tourism and Civil Aviation) to the Government of Himachal Pradesh that it would not be advisable to go ahead with the proposal of extension of the runway of Shimla Airport as well as Kullu (Bhuntar) Airport. 12. The Central Government, through the Ministry of Civil Aviation, constituted a Committee to carry out a study of earmarked and additional safety measures of airports in the country so that -6- 2026:HHC:49585 remedial measures can be taken. The said Committee identified nine airports in the country which require additional safety measures, and Kangra Airport (Gaggal Airport) was also one of those airports. 13. Vide communication dated 02.03.2022 (Annexure R-1), the Airports Authority of India, through its Airport Director, communicated to the Deputy Commissioner, Kangra (respondent No.3) for expansion of Gaggal Airport as Brown Field Project so that additional safety measures can be deployed to make air operations more safe, with a request to hand over land adjacent to the airport boundary near Runway End 33 up to Manjhi Khad to AAI immediately on priority, so that AAI may take up work for provision of Runway End Safety Area (RESA) as an immediate intermediate measure till the runway extension work is taken up in the future. Relevant para of the communication reads as under:“It has been suggested by the committee to explore the construction of RESA (Runway End Safety Area) at Kangra Airport. The State Govt. is already working on the land acquisition for expansion of Kangra Airport for Runway length of 3010m as per the proposed master plan. It is most humbly requested that the immediate land adjacent to airport boundary near runway end 33 upto Manjhi Khad, may please be handed over to AAI on priority, so that we may take-up the work for provision of RESA, as an immediate intermediate measure till the runway expansion work is taken up in near future.” -7- 14. 2026:HHC:49585 Vide letter dated 16.02.2023, the Government of Himachal Pradesh was requested to provide the scope of work for the techno-economic feasibility study, which was awarded to WAPCOS Ltd.. The State Government had also engaged the Central Water and Power Research Station (CWPRS) for a hydrological study of River Manjhi Khad and recommendations for construction of a bridge/box culvert on it, and WAPCOS Ltd. for a feasibility study and preparation of DPR. CWPRS has submitted its report recommending construction of a box culvert on River Manjhi underneath the proposed runway with several river training works upstream and downstream. 15. An interim report of the techno-economic feasibility study was forwarded by the Government of Himachal Pradesh vide communication dated 24.04.2023. A copy of the interim report of the techno-economic feasibility study was sent by the Principal Secretary (Tourism and Civil Aviation) vide letter dated 24.04.2023 to the Executive Director (Planning), Airports Authority of India, with a request to examine the DPR and send comments/approval for further necessary action. 16. Vide communication dated 25.08.2023, the Wing Commander, Senior Air Traffic Control Officer, communicated to the -8- 2026:HHC:49585 Airport Director, Gaggal Airport, and intimated that an Air Force exercise was planned at Gaggal Airfield on 12.09.2023, details whereof had not been finalized and would be intimated later, and requested for necessary cooperation, including providing extension of watch hours if required for the aforesaid exercise. 17. A similar letter dated 30.08.2023 (depicted to be of 12.09.2023) was sent to the Airport Director, Gaggal Airport, by the Wing Commander, Commanding Officer, who vide communication dated 08.09.2023 had informed and requested the Airport Director, Gaggal Airport, Kangra, regarding issuance of necessary clearance for conduct of exercise by the Air Force at Gaggal Airfield, Kangra, tentatively on 12.09.2023. 18. The State of Himachal Pradesh, in exercise of the powers conferred upon the Governor under Rule 4 of the Himachal Pradesh Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Social Impact Assessment and Consent) Rules, 2015 (hereinafter to be referred as ‘HP Right to Fair Compensation Rules, 2015’), has notified the constitution of the Social Impact Assessment Unit vide Notification dated 27.11.2015, to act as an independent organization for carrying out the purposes of the aforesaid Rules, comprising the Director, HP -9- 2026:HHC:49585 Institute of Public Administration (HIPA), Fairlawn, Shimla as Chairman; Incharge, State Institute of Rural Development, HIPA, Shimla as Member; Head, Department of Sociology and Social Work, HP University, Shimla, as Member; and Chief Scientific Officer, Department of Environment, Scientific & Technology, Shimla as Member. 19. On the basis of the Master Plan and Technical Feasibility Report received from the Airports Authority of India, as mentioned in the aforesaid communications, the course of action, initiated by the State Government for expansion of Kangra Airport, was undertaken, and the process for land acquisition under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 was initiated. 20. The Social Impact Assessment Unit, vide advertisement dated 11.02.2023, invited Expression of Interest (EOI) and financial bids for conducting the Social Impact Assessment study from organizations/institutions empanelled with the Social Impact Assessment Unit, notifying the last date of submission as 14.02.2023 between 10:00 AM and 5:00 PM on any working day on or before 14.02.2023. The aforesaid bids were opened on 15.02.2023 in the meeting of the Sub-Committee constituted for evaluation of the -10- 2026:HHC:49585 Expression of Interest. Three applicants, namely: (i) Ms. Taranjit Kaur, SR Asia, UP; (ii) M.R. Sharma, PRAN Foundation, Sanjouli, H.P.; and (iii) Jignesh Patel, Envision, Surat, Gujarat, submitted their bids. After evaluating the technical and financial bids, the SubCommittee recommended the name of SR Asia for having quoted the lowest rates as compared to the other participants. 21. Vide letter dated 15.02.2023, the Chairman of the Social Impact Assessment Unit submitted the case to the Principal Secretary (Tourism and Civil Aviation) to the Government of Himachal Pradesh for undertaking the Social Impact Assessment study in respect of expansion of Kangra Airport, District Kangra. 22. Vide Notification dated 28.02.2023, in exercise of powers conferred under Rule 3 of the Himachal Pradesh Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Social Impact Assessment and Consent) Rules, 2015, the Governor of Himachal Pradesh empowered the Social Impact Assessment Unit to carry out the Social Impact Assessment for the purpose of land acquisition for Kangra Airport. The Notification dated 28.02.2023 was published in two newspapers on 02.03.2023 and 03.03.2023, and was also uploaded on the official website of the State Government. -11- 23. 2026:HHC:49585 Vide communication dated 03.03.2023, the Chairman of the Social Impact Assessment Unit communicated that the Social Impact Assessment Unit had decided to award the work of the Social Impact Assessment study in respect of expansion of Kangra Airport to SR Asia, by notifying the terms of reference in the said letter, and in furtherance thereto, SR Asia was assigned the Social Impact Assessment study. 24. The Social Impact Assessment study was carried out through SR Asia. The draft Social Impact Assessment report was submitted by the agency, which was circulated as per the provisions of the Act. During the process of the Social Impact Assessment, public hearings were conducted, and objections and comments of project-affected families were recorded. The Social Impact Assessment conducting agency contacted 349 families out of 1446 project-affected families, and formal discussions were held in each Gram Panchayat. 25. The final Social Impact Assessment report was submitted vide letter dated 03.05.2023. The report was circulated to the general public through the concerned Gram Panchayats, the office of the District Collector, Sub-Divisional Magistrate, and Tehsildar, and was also uploaded on the official website of the -12- 2026:HHC:49585 Department of Tourism and Civil Aviation. The Social Impact Assessment study report was also supplied to the Pradhans of the affected Gram Panchayats of District Kangra vide communication dated 03.05.2023, with recommendations as contained at pages 234 to 236 of the record:“Chapter-10 Recommendations SIA experts had in-depth consultation with relevant stakeholders, suggestions and feedback received, discussions and FGD held with PAFs, public hearing on draft SIA reports collection of all field data, proposes the following recommendations. 10. The proposed expansion of Kangra Airport will seriously affect the large population and businesses that have been established over the years and are generally selfsustaining. It has been learned from extensive discussions with all the parties that if the proposed land is acquired, the cost of the project will be about several thousand crores and at the same time thousands of families will lose their family business, source of employment and income and social security. Will lose by making taunts. During the discussion, it has also come to be known that thousands of people working in big and small shops will also lose their livelihood due to this. As there is already a lack of opportunities for government jobs, in this situation, how will the government be able to employ thousands of people, this question is very worrying, so to deal with this situation, the affected families have sought alternative places / land and land acquisition for the project. The following suggestions have been proposed for: III. The airport should be expanded from the present runway direction of "west to north" towards Dharamshala/Sarai, this will displace the least number of families and save a lot of government money. Local peoples also are in favor of this option. -13- IV. 2026:HHC:49585 The alternative land is available at the new location which comprises of non-irrigated and government land in village Bodkwalu and Lanj in Kangra Tehsil, in which a new and big airport can be constructed easily, and at the same time the social displacement will be very low and economic burden on the government will be minimum to build the airport. As shared by project affected people cost of new airport at new suggested location will be far too low by many times than the expansion of existing Kangra Airport. 11. Before any land acquisition process starts, according to the LARR-2015, rehabilitation and resettlement plan with the cooperation of the local stakeholders is desirable. 12. The landowners are ready in the eventuality, government decides the airport at the current and proposed land provided they are made payment of four times of the market value/circle rate (as applicable) of the land in rural areas and two times the market rate of the land in urban areas as compensation for land acquisition as per schedule of the Act, 2013, which should be paid "as one project one cost" formula applicable to all PAFs. 13. Due to the expansion of the project, the problem of water logging/flood may arise in the villages and near bye areas, so an integrated water management plan should be made for the drainage and supply of water, so that the problems of flooding in the area can be minimized and prevented. 14. Those families which in the past were affected by land acquisition under any other project or by the Kangra airport construction, should be avoided displacement or in unavoidable conditions shall be given special compensation if they are being affected by the reacquisition. 15. Social Impact Management Plan (SIMP) described in this report detail out the measures to solve the village-wise problems are mentioned in Appendix-one and Jansunwai chapter number nine. Although the review of all the submitted memorandums is presented in the SIMP, the records of the memorandums received is presented in the form of Appendix-IV for appropriate actions, person-wise and pointwise. -14- 2026:HHC:49585 16. The Detailed Project Report, Feasibility Report and Rehabilitation and Resettlement Plan related to the expansion of the airport are not available, therefore the cost and benefit analysis has not been estimated under the presented Social Impact Management Plan. The cost of the project is not available hence proper cost-benefit analysis cannot be derived objectively. 17. This Kangra Airport expansion is in the public interest and serve public purpose and the construction and operation of the project will provide short term and long term benefits to all the villagers and business around it. This analysis is particularly relevant in relation to new employment opportunities, the provision of goods and services, and public investment that will result in long-term benefits to villagers, thereby helping to mitigate short and long term negative impacts. 18. Adequate data is not available on whether the potential benefits from the Gaggal Airport Expansion Project will be more or less than the cost price, so it is difficult to estimate when and how much the investment of the scheme will be profitable, although the scheme is being supported by a lot of affected families. It has been said to be expensive, the benefit of which has been said to be difficult for the government and the public to get soon. If the construction of the airport is shifted to alternative places, it will surely prove to be very beneficial for all the parties from the social and economic point of view, this conclusion has been expressed by almost all the affected families and other sections during the public hearing. SIA experts nominated by SR Asia, after assessing all the social impact impacts recommends land acquisition as per various conditions mentioned in the social impact management plan (SIMP) Annexure-I, Jansunwai Chapter Number-IX (Village and person wise objections and, and Annexure-Four (objections and suggestion in the form of memorandum).” 26. Vide Notification dated 19.04.2023, the State of Himachal Pradesh constituted a Multi-Disciplinary Expert Group under Section 7(1) of the Act, 2013, to examine the Social Impact -15- 2026:HHC:49585 Assessment report and submit its appraisal report. The MultiDisciplinary Expert Group examined the report of the Social Impact Assessment and, vide communication dated 05.06.2023, recommended the acquisition of land for the public purpose. 27. In the opinion of the Technical Expert Member of the Multi-Disciplinary Expert Group constituted for appraisal of the Social Impact Assessment of Kangra Airport, the extension of a greenfield airport at the suggested alternative sites, namely Lunj and Borkwalu, was found to be not feasible, as these sites were located quite far from the central location, and in comparison to Brown Field Airport Project, construction of a Greenfield airport involved huge cost, a long timeline, and visual requirements for No Objection Clearance from multiple agencies, which is a time-consuming exercise. The Committee also considered the location of Dharamshala, close proximity to high hills, and weather/topographical aspects, and recommended the project as not only fulfilling public interest considerations, but also having potential benefits which would outweigh the social costs and social impacts. Recommendations of the Expert Group are as under:“5. RECOMMENDATIONS OF THE EXPERT GROUP After going through the recommendations of the Social Impact Assessment Report, and taking into consideration the expert -16- 2026:HHC:49585 opinions of members, the Expert Group makes the following observations:i) Whether the project serves any public purpose? The proposed project will boost up tourism in Kangra by ensuring affordable and better aviation facilities to the tourists who intend to visit Kangra and surrounding destinations to explore RELIGIOUS, HERITAGE, ADVENTURE, SPORTS, NATURE, WILDLIFE AND HEALTH TOURISM. The promotion of Tourism will increase economic status of project affected families. It will provide affordable air services to local passengers who need to use air service in emergency to airlift their relatives to PGI Chandigarh and Delhi, benefit business persons and farmers to promote their business and farm products. The project will benefit students and job aspirants who intend to acquire high education and appear in competitive exams in metropolitan and major cities of India. Therefore, apparently the project to expand existing kangra Airport serves the public purpose. ii) Whether Potential benefits of the project outweigh the social costs and adverse social impact? The expansion of Kangra Airport is likely to displace a large number of families who are presently living in 14 muhals of Shahpur and kangra Tehsils in Kangra district and adversely affect their livelihood support and business. However, the upcoming of world class aviation infrastructure and 3010-meterlong run way with increased capacity, would accommodate Turbo Fan Aircrafts such as Airbus 320/330 etc., due to which the tourists, local passengers and students would benefit from the affordable and reasonable airfares. The increase in footfall of tourists to kangra would promote better employment avenues and better livelihood support for local people. In view of these facts, it is quite apparent that the potential benefits of the project outweigh the social costs and adverse social impact. -17- 2026:HHC:49585 iii) Whether there is other less displacing option available with effective Relief and Rehabilitation Plan? Expert Group also concluded that Project affected families’ / People’s suggestion to acquire lands at Lunj, Borkawalu to construct a green airfield was not found to be technically feasible, because both the suggested sites are quite far away from the central location / the existing Airport and also setting up a Green airfield Airport with world class aviation infrastructure there would incur huge costs and likely to take years for various clearances and non-objection certificates from multiple agencies. And, as far as proposal to expand the existing Airport from West to north side towards Dharamshala- Sarah was concerned, that patch of land being hilly was not found to be feasible and fit to expand the existing Kangra Airport. Technical Expert and member of the Expert Group constituted to evaluate the Social Impact Assessment Report for the project- expansion of Kangra Airport has shown his reservations on the Construction of a green airfield either at Lunj and Borkwalu as well as expansion of existing airport from west side to north side towards Sarah – Dharamshala and Department of Tourism and Civil Aviation to Himachal Pradesh government has found the above proposal/ suggestion of local people about constructing a green airfield at the suggested sites or expansion of the existing airport from west side to north side towards Sarah- Dharamsala, because the proposal to expand the existing airport after construction of a bridge across Manji -khad was technically approved /cleared by Airport Authority of India – the sole nodal body to clear/ approve all types of aviation infrastructures or run- way alignments. And this point was clarified by Tourism and Civil aviation to HP Government vide their no. TSM-F(6)-2015-ii-i dated 24.05.2023 (Annexure 2). So, the Expert Group noted that there was no less displacing option available with effective R&R plan which could be chosen to complete the said project. Therefore, as per the technical clearance of the proposal by Airport Authority of India to -18- 2026:HHC:49585 expand existing Kangra airport after constructing a bridge across Manjhi Khad after was the only option left. iv) Whether the extent of Land proposed to be acquired is bare minimum extent needed for the project- Expansion of Kangra Airport? The Expert Group also noted that the quantum of government and private land proposed for acquisition in 14 identified muhals, (10 and 4 muhals of Kangra tehsil and Shahpur tehsil, respectively) was bare minimum extent of land required for the project and cannot be avoided to expand existing Airport. If people would give their land for projects work, provided that they were adequately compensated for their loss. Proper Resettlement and Rehabilitation of PAFs/ PAPs be ensured as per the provisions of Right to fair compensation and Transparency in Land Acquisition Act, 2013 and HP Social Impact Assessment Rules 2015. Extent of Land proposed to be acquired for the expansion of Kangra Airport calculated to be 147-75-47 hectare is bare minimum extent required for the project. 6. CONCLUSION After making the detailed evaluation and appraisal of Social Impact Assessment Report of the project, the multi-disciplinary Expert Group concluded and recommended that the expansion of Kangra Airport would create world class aviation infrastructure and boost the Tourism sector and allied activities in a big way, thereby improving the Kangra economy and economic status of local people and thus the proposed project served the public purpose. Secondly, despite adverse social impact and adverse social costs, the potential benefits outweighed them. The Expert Group suggested that the adverse social impact and social costs arising out of project execution should be mitigated to the minimum by the measures suggested in Social Impact Management Plan and Relief and rehabilitation Plan that should -19- 2026:HHC:49585 adequately address the concerns and apprehensions of the projected affected families and project affected people for livelihoods and future. It was therefore recommended that the Relief and Rehabilitation Plan should contain the provision of highest compensation package for the project affected families / project affected people including those families who were displaced previously due to the undertaking one project or the other. In addition, Identified vulnerable persons be provided with the best support and economic assistance that could help them lead a dignified life after the displacement. Expert group also comprehensively examined the alternative sites and less displacing option with effective Relief and rehabilitation plan and concluded that construction of a green Airport at suggested sites namely Lunj and Borkwalu was not feasible in the first instance, due to legal requirement of non-objection certificates and clearances from multiple agencies, isolated location, long distance from the present airport, long time line of 10-15 years and clearance given to the proposed project to expand the existing airport after the construction of a bridge on Manji khad by Airport Authority of India -the sole and nodal agency to give technical approval to all types of Run-way alignments and Aviation infrastructure. Most importantly the expert group noted that in case a green airfield was proposed at the suggested sites, then the existing Airport situated in Gaggal would not be of any usage and public utility. The suggestion to expand the existing airport from west to north side towards Sarah- Dharamshala seemed to be non-feasible due to proximity of hills. Thus, the Expert group noted that there was no less displacing site with effective R&R plan was available; hence the only option left was to go ahead with the proposal to expand the existing airport after construction of a bridge across Manjhi Khas as finalized by Airport Authority. Expert Group was also of the opinion that total 147-75-87 hectare extent of land proposed to be acquired is the absolute bare minimum extent needed -20- 2026:HHC:49585 for the project and the expansion of Kangra Airport at the proposed land would create world class Aviation infrastructure and boost the Tourism sector and allied activities in a big way thereby improving the Kangra economy and economic status of local people. However, the opinion notes and suggestions, of panchayat - representatives, especially, setting up a satellitetown in the radius of 5 kilometres near the central point/ existing airport catering to the commercial as well as residential needs of local people might be considered by the Himachal Pradesh government.(Annexure-3) In view of the above facts, finally, the Expert Group has no hesitation in recommending the project because besides fulfilling the public interest considerations, its potential benefits would outweigh the social costs and social impacts.” 28. Thereafter, a preliminary notification under Section 11(1) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 was issued by the Government of Himachal Pradesh on 07.07.2023, inviting objections from any interested or aggrieved person within 60 days from the date of publication. For the purpose of the acquisition proceedings, the Divisional Commissioner, Kangra was appointed as Commissioner for Rehabilitation and Resettlement under Section 43, the Additional District Magistrate, Kangra at Dharamshala under Section 3(a) and 43, and the Sub-Divisional Officer (Civil), Kangra -21- 2026:HHC:49585 was appointed as Land Acquisition Collector under Section 3(g) of the Act. 29. Vide communication dated 26.09.2023, the Government of Himachal Pradesh informed that land acquisition had reached an advanced stage, 60% of land acquisition had been completed, and the State Government was in a position to transfer the same to the Airports Authority of India by November 2023. 30. Vide communication dated 20.10.2023, the draft Techno-Economic Feasibility Report prepared by WAPCOS Ltd. was forwarded to the Airports Authority of India, depicting the estimated cost of the project at approximately Rs. 10,995 crores excluding land acquisition cost, out of which the major cost component was for earth cutting and filling, soil stabilization, and bridge construction to be borne by the State Government. 31. The project cost was assessed as too high by the AAI management, and therefore it was suggested to the State Government to carry out a financial viability study in addition to a technical study, and also to take a second opinion on technical viability by taking into consideration high flooding, landsliding, etc., and also the falling of the area in Seismic Zone V, vide communication dated 09.11.2023. -22- 32. 2026:HHC:49585 In response, vide communication dated 06.12.2023, it was communicated by the respondent State that Kangra has been declared as the tourism capital of Himachal Pradesh, the State Government is committed to carry out this expansion project, and it is ready to provide land free of cost and free from all encumbrances for this project, with a request for marking and erection of 126 more boundary pillars in the field as per the Master Plan, and verification and certification by the AAI team. Vide communication dated 02.02.2024, it was also communicated that the Government is ready to bear the cost of cutting and filling apart from providing land free of cost and free from encumbrances. 33. Government of Himachal Pradesh got the TEFR report reviewed from M/s WAPCOS Ltd., wherein the project cost has been worked out to Rs. 4064.27 crores, and the modified TEFR report was submitted to AAI vide communication dated 15.03.2024. Certain comments and observations on the TEFR report were communicated by AAI vide letter dated 20.05.2024 to the State Government. The TEFR report is a prerequisite for environmental clearances. 34. In the meanwhile, after filing of present writ petition on 12.10.2023, following order was passed on 06.12.2023:- -23- 2026:HHC:49585 “Learned Deputy Solicitor General of India has placed before this Court as D.O. letter dated 09.11.2023. The said letter is taken on record. It states as under:“Reference is invited to your D.O. letter No. TSM-F(6)1/2015-IV dated 26/09/2023 and TSM-F(6)-1/2015-III dated 20th Oct. 2023 forwarding Draft Techno-Economic Feasibility Report on the subject cited above. 2. In this connection it is intimated that on the request of State Government of Himachal Pradesh (GoHP) vide letter dated 07.10.2021 AAI has prepared development plan of Kangra Airport in two PhasesPhase-I for operation of ATR-72/Q-400 type of aircraft without load penalty for VFR operations and Phase-II for operation of A-320 type of aircraft without load penalty for IFR operations. 3. It is seen from the Techno-Economic Feasibility Report of Kangra Airport prepared by WAPCOS and forwarded vide letter dated 20.10.2023 by GoHP that estimated cost of the project is approx. Rs. 10,995 Crores, excluding land acquisition cost. Out of it, cost of earth cutting & filling, soil stabilization and bridge, almost Rs.10,242 Crores, is to be borne by the State Government. Therefore, it is felt that State Government may carry out financial viability, in addition to technical viability. As far as technical viability is concerned, we would like to recommend State Government to take second opinion because proposed construction is in the area which in the recent past has witnessed heavy flooding, land sliding etc. and also comes in Seismic Zone V. IIT, Roorkee (Department of Water Resources Development and Management) can be one of the Agency which may be consulted for second opinion. In case it is found by State Government project to be technically and financially viable then AAI will take approval of the Competent Authority for extending the runway with other facilities.” -24- 2026:HHC:49585 Learned Advocate General states that reply has been filed by the State Government in the matter, but the same has not been put up. Registry to put up the reply filed by the State Government. List on 07.12.2023.” 35. On 07.12.2023, recording the assurance extended by learned Advocate General, following order was passed:“Due to paucity of time, the matter could not be taken up today. Learned Advocate General assures that till the next date of hearing, the respondents will not dispossess anybody from the land, which is forming part of notification issued under Section 11(1) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, notified for expansion of Gaggal (Kangra) Airport, and that no structure located within the land, which is subject matter of the said notification, will be demolished. The said undertaking of the State is placed on record. List on 26.12.2023.” 36. Thereafter, on 26.12.2023 the Court passed the injunction order as under:“Heard in part. Learned Advocate General shall produce Newspaper advertisement said to have been published prior to the public hearing on the draft Social Impact Assessment Report along with other connected record. -25- 2026:HHC:49585 Mr. Balram Sharma, learned Deputy Solicitor General of India shall obtain instructions from 5th respondent or file a reply in the Writ Petition by the next date of hearing. Learned counsel for the petitioner shall prepare a table of the alleged violations of the provisions of law, pleadings in the petition in that regard, and reply to those allegations in the reply filed by the respondents. List on 02.01.2024. Learned Advocate General assures that the undertaking given on the previous date of hearing will continue till the next date of hearing.” 37. On 26.12.2023 undertaking given by the learned Advocate General on previous date was assured to be continued till next date of hearing. It was continued on 02.01.2024, 04.01.2024, and on 09.01.2024, the following order was passed:“It is stated by Mr. Neeraj Gupta, learned Senior Counsel, appearing for respondents No.3 and 4 that the matter is being reexamined in light of letter dated 9.11.2023 addressed by the Airport Authority of India (5th respondent) to the 1st respondent, particularly with regard to financial viability as well as technical viability. He also placed before us Minutes of Meeting held on 02.12.2023 under the Chairpersonship of the Director Tourism recording the observation that Techno Economic Feasibility Report submitted by WAPCOS is a shoddy work and requires to be rejected. 2. Having regard to the fact that the matter is under re- consideration by the State Government, at this stage, it would not be proper to permit the respondents to proceed with the taking of possession of lands, which are notified for acquisition or demolish -26- 2026:HHC:49585 the structure thereon or to proceed with the R&R process till the next date of hearing. 3. Mr. Neeraj Gupta, learned Senior Counsel, states on instructions that some steps in the R&R process have commenced, which would not affect the rights of the persons, who are likely to be affected by the acquisition. 4. Be that as it may, since there is a possibility that the State Government may re-visit its own decision to proceed with the expansion of the Gaggal Airport after examining all aspects of the matter and in such an event, there is every possibility of the time and expenses incurred in the R&R process commenced, would go waste, till the next date of hearing, status quo in all respects with regard to the R&R process as well as taking of possession of the lands notified for acquisition or demolition of structure located in the lands notified for acquisition, shall be maintained. List on 29.02.2024.” 38. Order dated 09.01.2024 was assailed by State before the Apex Court by filing SLP(C ) No. 1676 of 2024 wherein on 22.01.2024 operation of order, passed by the Division Bench of this High Court on 09.01.2024, was stayed. 39. Civil Appeal No. 3909 of 2024 was registered, arising out of SLP(C ) No. 1676 of 2024 and it was disposed of by the Apex Court on 7th March, 2024 in the following terms:“…….. 7. During the course of the hearing Mr. Kapil Sibal, senior counsel appearing on behalf of the State of Himachal -27- 2026:HHC:49585 Pradesh has assured the Court that the statement which was made by the Advocate General before the High Court shall continue to remain in operation in the meantime, unless the Court is moved for appropriate modification in view of any change in circumstances. We take the assurance on the record. 8. In that view of the matter, we vacate the impugned order dated 9 January, 2024. The High Court would be at liberty to proceed ahead with the disposal of the writ petition on merits. In the event that there is any change in circumstances warranting an alteration of the statement by the Advocate General for the State of Himachal Pradesh, we grant liberty to the State to move the High Court in that regard…….” 40. In aforesaid background, process of acquisition of land continued during pendency of present petition. Status of Land Acquisition/Response of the State 41. During pendency of the petition, the status of land acquisition for extension of Gaggal Airport was produced on behalf of the respondent State, with the submission that after approval of the appraisal report submitted by the Multi-Disciplinary Expert Group by the Cabinet, notification under Section 11(1) of the Act was issued on 07.07.2023, which was published in the Gazette and in two daily newspapers as required under law. 42. It has been further communicated that after issuing notification dated 07.07.2023, objections under Section 15 of the -28- 2026:HHC:49585 Acquisition Act were heard from August 2023 to February 2024, and after deciding the objections, report was submitted by the Land Acquisition Collector-cum-Collector, Kangra to the Government on 15.03.2024. 43. It was further communicated that draft R&R plan was prepared by the Administrator under Section 16 of the Act, and notice to the general public for hearing was given on 20.12.2023. General public hearing was conducted from 05.02.2024 to 07.02.2024. Draft R&R scheme was reviewed by the Collector through the R&R Committee on 24.02.2024 under Section 17(1) of the Acquisition Act, and approval of the Government was conveyed on 15.03.2024. The R&R scheme was made available in the local language to the Collector, SDM Office, Tehsil, concerned Panchayats, and affected area vide letter dated 16.03.2024, and it was published on the Collector's website on 22.03.2024. 44. Declaration and notification under Section 19 of the Act was issued by the Government on 16.08.2024, which was published in the Gazette on 17.08.2024, and in newspapers on 21.08.2024. 45. Notices under Section 21 of the Acquisition Act were issued on 08.09.2024, which were published on the Collector's website and sent to the concerned Gram Panchayats, and the date -29- 2026:HHC:49585 for hearing of objections/claims was fixed on 18.10.2024 in the office of the Land Acquisition Collector, Gaggal Airport. Total 6429 notices were served under Section 21 of the Act, 158 notices stand unserved due to insufficient addresses, and a total of 44 objections were received, out of which 13 pertained to land and 31 pertained to R&R. 46. The Government has approved the R&R plan worth Rs.3349 crores. Thereafter, awards were issued under Section 23 of the Acquisition Act. As on 15.10.2024, an amount of more than Rs.460,35,82,920.33 had been disbursed in pursuance to announced R&R awards, whereas balance awards to be disbursed or announced for worth Rs.132,50,41,003/- was and is under process. SUBMISSIONS ON BEHALF OF PETITIONER 47. Assailing the impugned acquisition proceedings, it has been contended on behalf of the petitioner that the Social Impact Assessment Authority failed to take an appropriate decision on the questions and substantive objections raised by the landowners during the survey and public hearing regarding the feasibility of the project and alternative sites, and mechanically recommended acquisition without conducting a proper survey. -30- 48. 2026:HHC:49585 It has been further contended that out of 1446 affected families across the fourteen villages, the SIA team interviewed only 399 families (34.04%), on the basis of which the social, cultural, and economic status was assessed within a week without even having a Detailed Project Report (DPR) in hand. It has been contended that incorrect information was supplied in Table 48 that 52.63% of the people gave consent, whereas 100% of the land owners are unwilling to part with their fertile agricultural land. 49. It has been vehemently contended that the proposed acquisition violates Section 10(1) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, which mandates that no irrigated multicropped land shall be acquired under the Act. Referring to Tables 44 and 45 of the SIA report, it is pointed out that 69.67% of the land is fertile, 32.58% is highly fertile, and 63.91% is used for food grains, 24.56% for oilseeds, and 68.17% for commercial crops, with double cropping (wheat/mustard in Rabi, paddy/maize in Kharif, and vegetables) across 100% of the villages. It has been contended that under Section 10(2), such land can only be acquired under exceptional circumstances as a demonstrable last resort, but the SIA -31- 2026:HHC:49585 team failed to report or demonstrate that the acquisition was an unavoidable last resort. 50. Though, it has not been specifically pleaded, however, it has been contented by learned counsel for the petitioner that there is violation of mandatory provisions of Rule 3(1) of the Land Acquisition, Rehabilitation and Resettlement (Social Impact Assessment and Consent) Rules, 2014, Section 4(2) of LARR Act, 2013, Section 4(4)(a), 4(4)(e), 4(4)(f), Section 5, 7, 8 & 15(2) of LARR Act. 51. It has been submitted on behalf of the petitioner- Committee that there is violation of mandatory clearance, related to Techno-Economic Feasibility Report, Environment Clearance Report, Forest Clearance, Clearance from Bureau of Civil Aviation, DG, Civil Aviation, Central Water and Power Research Station as required before commencing the work of expansion of the airport, because as on date there is neither Technical Economic Feasibility Report, nor Environmental Impact Assessment Report or Environmental clearance has been obtained by the respondents. Further, that till date, site has not been declared suitable for runway expansion after survey feasibility study and clearance from BCAS and DGCA. -32- 52. 2026:HHC:49585 It has been contended that in SIA report, it has been incorrectly recorded that the expansion of Kangra Airport will serve the supreme interest of the State and meet the defense requirements of the Indian Air Force, whereas vide communication dated 13.04.2018 (Annexure P-4) obtained under the Right to Information Act, Air Headquarters (IAF) specifically it has been clarified that presently the IAF has no plans to expand Kangra Airport. 53. It has also been contended that a portion of the land proposed for airport expansion was already acquired by the Central Government for construction of a four-lane highway through the National Highways Authority of India (NHAI) vide notification dated 21.09.2021 (Annexure P-5), and Section 99 of the Act of 2013 specifically prohibits any change of purpose from that for which the land was originally sought to be acquired. 54. The petitioner has further raised the grievance that functional educational institutions in eight villages, Primary Schools, Colleges, ITIs, Anganwadis, Health sub-centres, and 132 KV transmission lines (with over 50 towers) will be uprooted, resulting in the destruction of one public purpose for another. 55. It has been highlighted that the bridge constructed over Manjhi Khad on NH-154 at a public cost of over Rs.9,23,26,012/- and -33- 2026:HHC:49585 completed on 25.10.2020 (Annexure P-6) will be ruined and dismantled to make way for the airstrip, causing colossal wastage of public funds. 56. It has been urged that the Panchayats had suggested three viable alternative sites, namely: (i) expansion towards the north-west (Dharamshala/Sarah); (ii) non-irrigated, less fertile land at Bodkwalu; and (iii) land in the Lanj area, which would displace far fewer families, involve barren land, and save substantial public money, but the SIA team and Expert Group arbitrarily dismissed them without conducting any technical survey. 57. It has been submitted that Kangra district falls in Seismic Zone V (98.6% seismic/sinking zone) and is an eco-sensitive area where massive construction and tree felling without prior environmental and forest clearances will trigger catastrophic ecological damage. 58. It has been further contended that the Multi-Disciplinary Expert Group failed to independently examine the severe negative impacts documented in the SIA report and merely rubber-stamped the agency's findings. -34- 59. 2026:HHC:49585 It has been further contended that the Director General of Civil Aviation, which is the final authority for airport site approval, has not granted any permission, as confirmed vide RTI communication dated 25.04.2023 (Annexure P-9). 60. It has been further urged that the impugned notification dated 07.07.2023 is an outcome of a colorable exercise of power and arbitrary exercise of administrative discretion. It has been contended that the power of eminent domain is being wielded not for a bona fide public purpose or for the benefit of the public at large, but with the sole intent of conferring undue advantage upon an elite and affluent class of persons under the guise of tourism, thereby violating the settled principles governing judicial review of administrative discretion. 61. It has been specifically contended that proceeding with the acquisition without obtaining mandatory environmental and forest clearances, and in the absence of a genuine, thorough assessment of the ecological fragility of the terrain, constitutes a flagrant infraction of the constitutional right to property guaranteed under Article 300-A of the Constitution of India, as well as the basic human rights of the affected populace, rendering the impugned reports and notification wholly arbitrary and illegal. -35- 62. 2026:HHC:49585 Learned counsel for the petitioner has further laid stress upon the plight of historically and economically vulnerable segments residing within the acquisition zone, pointing out that the proposed expansion directly displaces more than 15 families of Pong Dam oustees who have remained unrehabilitated even after a lapse of more than 47 years, as well as over 150 families who were uprooted during the 1947 Partition and have been living hand-to-mouth. It has been contended that the State has completely abdicated its duty to scrutinize its actions with heightened care, vigilance, and circumspection when dealing with marginalized citizens who are now faced with the prospect of being rendered homeless, landless, and destitute for a second time. 63. It has also been urged that the respondents acted in breach of the statutory mandate requiring the land proposed for acquisition to be the bare minimum necessary for the project. In this regard, it is contended that the SIA Authority failed to assess the catastrophic economic displacement of an established commercial hub comprising 5 Banks, 2 Petrol Pumps, and major commercial markets that provide direct employment and livelihood to upwards of 20,000 persons, which could have been entirely averted had the respondents evaluated the vacant and barren alternative sites. -36- 64. 2026:HHC:49585 To substantiate the submission that where a statute provides for a thing to be done in a particular manner, it has to be done in that manner and in no other manner, learned Senior Counsel for the petitioner has placed reliance on pronouncements of the Apex Court in Narindrajit Singh and Ranjit Singh & Ors. vs. State of U.P. & Ors., (1973) 1 SCC 157 (paragraphs 1 to 3); Chandra Kishore Jha vs. Mahavir Prasad & Ors., (1999) 8 SCC 266 (paragraph 17); Competent Authority vs. Barangore Jute Factory, (2005) 13 SCC 477 (paragraph 5); and Opto Circuit India Ltd. vs. Axis Bank & Ors., (2021) 6 SCC 707 (paragraph 14). 65. It has been submitted by the learned Senior Counsel for the petitioner that for violation of mandatory statutory provisions, the action of the State deserves to be quashed and the petition deserves to be allowed. In this regard reliance has been placed on judgments passed by the Apex Court in Competent Authority v. Barangore Jute Factory & Ors., (2005) 13 SCC 477 (paragraph 5 & 14); Women's Education Trust vs. State of Haryana & Ors., AIR 2013 SC 2488 (paragraphs 6, 7, 13, 15, and 20); Gojer Brothers Pvt. Ltd. & Anr. vs. State of West Bengal & Ors., (2013) 16 SCC 660 (paragraphs 13 to 18, 20, and 22); Ravindra Singh and Others vs. State of Haryana and Others, (2020) 17 SCC 819 (paragraph 2 to -37- 2026:HHC:49585 5); Opto Circuit India Ltd. v. Axis Bank and Others, (2021) 6 SCC 707 (paragraph 14); and Kolkata Municipal Corporation and another v. Bimal Kumar Shah and others, AIR 2024 SC 2819 (paragraphs 29, 30, and 34). 66. It has been submitted that it is case of violation of provisions of public hearing, contained in Section 15 of the LARR Act, and therefore, the proceedings are liable to be quashed and setaside. To substantiate this plea, counsel for the petitioner has placed reliance on pronouncements of Apex Court in various cases, i.e., case titled Raghbir Singh Sehrawat v. State of Haryana and Others, reported in (2012) 1 SCC 792, case titled Kamal Trading Pvt. Ltd. vs. State of West Bengal & Ors., reported in (2012) 2 SCC 25, case titled Surinder Singh Brar and Others vs. Union of India and Others, reported in (2013) 1 SCC 403, case titled Gojer Brothers Private Limited & Anr. v. State of West Bengal & Ors, reported in (2013) 16 SCC 660, (Paragraphs 17, 20, 21 and 26), case titled Woman’s Education Trust and Anr. vs. State of Haryana and Ors., reported in AIR 2013 SC 2488, (Paragraphs 6, 7 and 15).’ 67. Placing reliance on Woman’s Education Trust and Anr. vs. State of Haryana and Ors, (2013) 8 SCC 99 (paragraph -38- 2026:HHC:49585 5), it has been contended that the violation of the statutory mandate of Section 15(2) of the Land Acquisition Act is fatal to the acquisition proceedings, and thus, the petition deserves to be allowed, 68. It has been urged that in the absence of mandatory clearances and where there is a clear-cut violation of fundamental and constitutional rights, the petitioner is entitled to maintain the writ petition and the acquisition deserves to be quashed. In support of this contention, learned counsel for the petitioner has placed reliance on judgments of the Apex Court in Sachidananda Pandey and another v. State of West Bengal & Ors., reported in (1987) 2 SCC 295; Karnataka Industrial Areas Development Board v. C. Kenchappa, (2006) 6 SCC 371 (paragraphs 3, 4, 36 to 41, 66, 100, and 101); Hanuman Laxman Aroskar vs. Union of India, (2019) 15 SCC 401 (paragraphs 5, 9, 10, 11, 12, 15, 16.1, 16.2, 21.5, 31, 32, 34, 40, 42, 44, 63.1, 64, 83 to 106, and 159 to 165); Ravindra Singh and Others vs. State of Haryana and Others, (2020) 17 SCC 819 (paragraphs 3 and 4); and Project Director, Project Implementation Unit vs. P.V. Krishnamoorthy & Ors., (2021) 3 SCC 572 (paragraphs 74 and 103). Reliance has also been placed on judgment dated 16.05.2024 passed by High Court of Bombay in Vanashakti v. Union of India and others, CWP (C) No. 1394 of -39- 2026:HHC:49585 2023, decided on 16.05.2025. Judgment passed by this High Court in Dhani Ram vs. Sunder Ram, 2016 (4) Him.L.R. 2433 (paragraph 12) has also been referred. 69. It has been substantially pleaded that in the absence of a genuine public purpose, land cannot be acquired and there is no public purpose in the present case, and in this regard reliance has been placed on Sri-La-Sri Subramania Desika Gnanasambanda Pandarasannadhi v. State of Madras and Another, AIR 1965 SC 1578 (paragraph 17). 70. It has been contended on behalf of petitioner that before commencing the project, prior environmental clearance is mandatory, as provided in EIA Notification 2006, which has not been obtained so far, and until and unless there is environmental clearance in favour of respondents, these proceedings are liable to be quashed and set-aside. 71. To substantiate aforesaid plea, reliance has been placed on the judgment dated 29.07.2026 of the Constitutional Bench of the Apex Court in Writ Petition (C) No. 1394 of 2023, titled Vanashakti vs. Union of India. In this regard, reliance has also been placed on judgment dated 28.07.2025 of the Apex Court in -40- 2026:HHC:49585 SLP(C) No. 19426/2025, titled M/s Pristine Hotels and Resorts Pvt. Ltd. vs. State of Himachal Pradesh and Anr. STAND OF RESPONDENTS NO.1 TO 4 72. On first date, i.e. 17.10.2023, service on behalf of respondents No.1 to 4 was waived by learned Additional Advocate General in presence of learned Advocate General. However, on 04.01.2024, Mr. Neeraj Gupta, Senior Advocate, has also appeared on behalf of these respondents-State, but since 09.01.2024, Mr. Neeraj Gupta, had appeared only for respondents No.3 & 4, but later on he did not appear for anyone. Common and joint reply has been filed on behalf of respondents No.1 to 4. 73. It has been canvassed on behalf of respondents No. 1 to 4 that there has been a substantial increase in passenger flow at Kangra Airport over the years. In the year 2009, 10,149 passengers availed air services from Kangra Airport, which increased to 1,76,015 passengers in 2022, and during the year 2023, up to the filing of the reply in September 2023, 1,36,353 passengers had availed the service. There were 428 total scheduled flights from Kangra Airport in 2009, which increased to 3,729 in 2022, and stood at 2,452 in 2023 up to September 2023. Three airline operators, Alliance Air, SpiceJet, and IndiGo are operating from this airport, besides one -41- 2026:HHC:49585 heli-taxi service operator, namely M/s Pawan Hans Limited. However, due to load penalties and the shorter runway length, bigger charters cannot land or take off from Kangra Airport, which results in higher airfares, on account of which most local residents as well as students cannot avail of the air facility. 74. It has been submitted that Himachal Pradesh is a State with vast tourism potential for attracting tourists, and Kangra district has emerged as a hub of many tourist activities during the recent past. The famous Shaktipeeths in Kangra and adjoining districts— such as Brijeshwari temple, Chamunda Devi temple, Jwalamukhi temple, Bagalamukhi temple, Masroor Rock-Cut temple, and Chintpurni Mata temple—have made this region one of the most sought-after destinations. The State Government also intends to establish a software industry and IT Park in Dharamshala and Palampur in District Kangra. 75. It has been further averred that on account of favourable climatic conditions and the majestic view of the snow-clad Dhauladhar ranges, Dharamshala has emerged as the most preferred venue for national and international conventions, such as the G-20, the Tourism Ministers' Conference, and the Chief Secretaries' Conference in recent years. Tourist inflow in District -42- 2026:HHC:49585 Kangra has increased considerably over the years: in the year 2008, a total of 12,45,974 tourists (70,819 foreign and 12,75,155 domestic) visited District Kangra, which increased to 28,23,289 (1,38,341 foreign and 26,84,948 Indian) in the year 2017, and during the year 2022, 4,10,843 tourists (6,538 foreign and 4,04,305 Indian) visited Kangra. Hence, it has been submitted that the expansion of the Kangra Airport is the need of the hour. 76. It has been further submitted that the tourism sector in Himachal Pradesh not only creates job opportunities for youth, but also plays a pivotal role in the State Gross Domestic Product (GDP), contributing approximately 7% of the total GDP. The tourism sector has the potential to rejuvenate and mobilize the financial resources of the State, which is a major priority of the State Government. 77. It has been highlighted that the Kangra valley is famous for the scenic beauty of the Dhauladhar ranges and its landscapes, and by virtue of being the abode of His Holiness the Dalai Lama, the region commands an important presence on the world map. The valley is visited by a large number of tourists, including an appreciable number from foreign countries every year, on account of its climatic conditions, tranquil atmosphere, and historic and religious significance. Dharamshala also possesses the world's highest -43- 2026:HHC:49585 international cricket ground where national and international matches are played, while Bir-Billing is a world-famous paragliding destination where World Paragliding Championships are organized, which are contributing significantly to the region's prominence on the world tourism map. The tourist industry, which is considered of utmost importance to boost the economy of the State and uplift the social status of the people of the area, cannot flourish until the means of communication are properly developed and places of tourist interest are linked with reliable transport infrastructure. 78. It has been further submitted that Presently, limited flights of civil aviation companies like IndiGo, Air India, and SpiceJet operate on the Delhi–Kangra and Kangra–Chandigarh routes, ferrying only a limited number of tourists because big aircraft cannot land at Kangra Airport due to the small runway (1372 meters) and associated load penalties. Therefore, the expansion of Kangra Airport is a vital project capable of bringing about a paradigm shift in improving the economic status of the people through the tourism sector. 79. It has been submitted that in the aforesaid background, a Committee constituted by the Central Government through the Ministry of Civil Aviation to carry out a study to earmark additional -44- 2026:HHC:49585 safety measures for airports in the country identified nine airports requiring additional safety measures, and Kangra Airport was included in the said list. In furtherance thereto, the Airports Authority of India (AAI), vide communication dated 02.03.2022 (Annexure R1), requested the Deputy Commissioner, Kangra (respondent No. 3), to expand Gaggal Airport so that additional safety measures can be deployed to make air operations safer, recommending the provision of a Runway End Safety Area (RESA) and expanding the runway to a length of 3010 meters, requesting that land adjoining the airport boundary near Runway End 33 up to Manjhi Khad be handed over to AAI on priority. 80. It has been submitted that the process for acquisition of land for development of the airport as proposed by AAI was accordingly initiated by assigning the work of Social Impact Assessment to the Social Impact Assessment Unit already notified in the State of Himachal Pradesh under the Himachal Pradesh Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Social Impact Assessment and Consent) Rules, 2015, framed under the Land Acquisition Act, 2013 vide Notification dated 27.11.2015, because the development work is to be undertaken by AAI subject to the availability of land to be -45- 2026:HHC:49585 provided by the State Government free of cost and free of all encumbrances, including road diversions, shifting of transmission lines, river training, and removal of obstacles. 81. It has been further submitted that expansion of Gaggal Airport is beneficial not only to tourists and travellers, but also to the public at large, as enhanced connectivity will result in a proportionate increase in tourism activities, generating opportunities for selfemployment across various sectors including taxis, hotels, restaurants, and homestays. Therefore, expansion of the airport would not only serve the purpose of deploying additional safety measures to enable bigger aircraft to land and take off, but would also improve the livelihood of the people of Himachal Pradesh, particularly in District Kangra and adjoining districts. 82. vide It has been submitted that the Airports Authority of India, communication dated 07.10.2021 (Annexure R-2), recommended the expansion of Kangra Airport to a total runway length of 3010 meters, which shall be suitable for the operation of ATR-72/Q-400 and A-320 types of aircraft with an Instrument Landing System (ILS) approach on the Runway 33 side. AAI submitted the Master Plan of the project after conducting an Obstacle Limitation Surface (OLS) survey and consulting various -46- 2026:HHC:49585 airline operators, requesting the State Government to assess techno-economic feasibility and revert with a feasible way forward. 83. It has been further submitted on behalf of the respondent State that, as per the survey and study carried out by the Airports Authority of India (Annexure R-III), the expansion of the two other existing airports in Himachal Pradesh, namely Shimla and Kullu (Bhuntar), is not feasible or viable on account of constraints such as non-feasibility of instrument approach procedures, high obstacles, environmental concerns arising from river diversion, and prohibitive costs. Therefore, Kangra Airport is the only airport in the State of Himachal Pradesh that is technically feasible for expansion, capable of being developed into a high-end tourist destination for domestic and international travellers, and resulting in significant improvement in the transport sector of the State. 84. It has been stated that in the event the expansion of the airport is accomplished, significant strategic advantages shall accrue because of the expanded runway and the ability of bigger airplanes to land. The airstrip of Kangra Airport is frequently used by the Indian Air Force for mock drills and operational exercises, as evidenced by official communications placed on record (Annexure R-IV). -47- 85. 2026:HHC:49585 Regarding alternative locations for the airport, it has been submitted that the Technical Expert Member of the MultiDisciplinary Expert Group constituted for appraisal of the SIA report examined the feasibility and opined (at pages 15–16 of the appraisal report) that establishing a greenfield airport at the suggested sites, namely Lanj and Bodkwalu—was not feasible in the first instance, as those sites are situated far from the central location, and the construction of a greenfield airport would involve enormous financial expenditure, prolonged timelines, and statutory clearances from multiple agencies. It has been further clarified by Technical Expert that expansion of the existing airport from the west towards the north (towards Sarah-Dharamshala) is not feasible due to steep valleys and close proximity to high hills. The Technical Expert concluded that expansion of the existing airport after construction of a bridge across Manjhi Khad was the only viable option available, and was far more feasible than developing a greenfield airport. 86. It has been further submitted that the technical feasibility for expansion has been established by AAI, which possesses specialized technical expertise in the field and the respondent-State has taken follow up action as desired and required. -48- 87. 2026:HHC:49585 It has been submitted that in accordance with the Master Plan and technical feasibility report received from AAI (Annexure R2), the State Government initiated the requisite course of action. The task of conducting a techno-economic feasibility study and channelization of Manjhi Khad was entrusted to specialized Government of India undertakings, namely WAPCOS Ltd. and the Central Water and Power Research Station (CWPRS), Pune. 88. It has been submitted that the Airports Authority of India, while preparing the Master Plan, requisitioned the land required for the expansion of Kangra Airport, whereupon the procedure for land acquisition under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 was initiated. In compliance with the statutory provisions, the notification under Section 4 regarding the Social Impact Assessment was issued by the Governor of Himachal Pradesh on 28.02.2023, published in the Gazette on 01.03.2023, and duly published in two daily newspapers on 02.03.2023 and 03.03.2023 (Annexure R-VI), as well as uploaded on the State Government website. 89. Learned Advocate General has submitted that the SIA conducting agency consulted project-affected families in each village. Out of 1446 total project-affected families, 349 participated -49- 2026:HHC:49585 in the process. Focused group discussions were conducted in each Gram Panchayat between 27.02.2023 and 10.03.2023, and people's participation regarding agreement and disagreement for providing land was duly recorded in the SIA report dated 03.05.2023. The recommendations in Chapter 10 of the SIA report reflect the voice of the project-affected families, and the agency covered all aspects including the public interest involved in the airport expansion. The report was thereafter placed before the Multi-Disciplinary Expert Group, which vide letter dated 05.06.2023 (Annexure R-V) strongly recommended the project, recording that it had no hesitation in recommending the acquisition because, besides fulfilling public interest considerations, its potential benefits would outweigh the social costs and social impacts. 90. It has been stated that in terms of Section 7 of the Act, the Multi-Disciplinary Expert Group was constituted by the State Government vide Notification dated 19.04.2023 (Annexure R-VII), comprising of Deputy Commissioner (Relief & Rehabilitation); Joint Secretary (Revenue); Professor, Central University of Himachal Pradesh (Social Scientist); Associate Professor of Social Welfare, Central University of Himachal Pradesh (Social Scientist); Ex- -50- 2026:HHC:49585 General Manager (Architecture) (Technical Expert); Pradhan, Gram Panchayat, Gaggal; and Pradhan, Gram Panchayat, Rachhyalu. 91. It has been further submitted that the Government of Himachal Pradesh has also examined the recommendations of the Social Impact Assessment (SIA) and the Expert Group, and found that the public purpose outweighs the social impact, and accordingly decided to acquire the land in view of the facts and circumstances mentioned hereinabove. 92. It has been submitted that after undertaking aforesaid exercise, the preliminary notification under Section 11 of the Act was issued by the Government of Himachal Pradesh (Annexure P-10) in consonance with relevant provisions of the Act and Rules as applicable. The Divisional Commissioner, Kangra at Dharamshala was appointed as Commissioner under the Act, the Additional District Magistrate, Kangra at Dharamshala as Administrator under Sections 3(a) and 43, and the Sub-Divisional Officer (Civil), Kangra was appointed as Collector under Section 3(g) of the Act in view of the proposed land acquisition for expansion of Kangra Airport in both Shahpur and Kangra Sub-Divisions of District Kangra. Therefore, affected persons have filed objections before respondent No.4, most -51- 2026:HHC:49585 of which have been adjudicated in consonance with provisions of the Act, 2013, including Section 15 thereof. 93. The Multi-Disciplinary Expert Group examined the SIA report and, vide communication dated 05.06.2023 (Annexure R-5), recommended the acquisition of land for the public purpose. 94. It has been further submitted that consequent to the preliminary notification dated 07.07.2023, a total of 571 objections were received before the Land Acquisition Collector, which were categorized as under: Sr. No. Objections Related to Total Number 1. Social Impact Assessment (S.I.A.) 2. Rehabilitation & Resettlement (R&R) 3. Rehabilitation & Resettlement and Compensation 4. Compensation 5. Mutation 6. Correction of Revenue Entries 7. Missing Khasra Numbers and Left-Out Land 8. Others Total -52- 95. 2026:HHC:49585 It has been submitted that taking into consideration the total number of land parcels likely to be affected by the acquisition, the number of objections challenging the acquisition itself represents a microscopic minority (only 18 objections pertained to shifting the airport site), while the vast majority pertained to compensation, R&R, and revenue corrections, which does not reflect the general sentiment of the public. 96. On behalf of respondents No.1 to 4, it has been further submitted that the petitioner has no cause of action, as all procedures prescribed under the Act and Rules are being strictly adhered to. The writ petition is premature and not maintainable, inasmuch as the contentions raised by the petitioner are being duly considered by the Land Acquisition Collector during the hearing of objections under Section 15 of the Act and during the preparation of the Rehabilitation and Resettlement Scheme. 97. It has been contended on behalf of the respondent State that there has been no arbitrary or colourable exercise of power. There is no violation of the provisions of the 2013 Act in issuing the notification dated 07.07.2023, which was issued strictly in accordance with due process of law. The Social Impact Assessment -53- 2026:HHC:49585 study was carried out through an independent agency, M/s SR Asia, in consonance with the statutory provisions. 98. It has been further submitted that though the petitioner has challenged the SIA report submitted by SR Asia by raising technical objections with regard to the methodology and recommendation of Multi-disciplinary Expert Group by raising quantum of capability and competency, however, neither M/s SR Asia nor the Multi-Disciplinary Expert Group has been impleaded as a party respondent in the present petition. In the absence of the survey conducting agency and the Expert Group that approved the report, the allegations leveled against them cannot be adjudicated, and the petition is liable to be dismissed for non-joinder of necessary parties. 99. It has been specifically averred that the airport is not being expanded by the Indian Air Force and since it is operated as a civilian airport, the prerogative of expansion does not lie with the Armed Forces. However, expansion of the airport will provide significant strategic advantages by virtue of the extended runway and the capability to handle larger aircraft. The airstrip is frequently utilized by the Air Force for mock drills and exercises, as confirmed by communication Annexure R-IV. -54- 100. 2026:HHC:49585 With regard to the plea taken by the petitioner about the construction of a four-lane National Highway by the National Highways Authority of India (NHAI), it has been submitted that NHAI, vide letter dated 02.05.2023 (Annexure R-X), informed that earlier the project from Sihuni to Ichhi from km 51.00 to km 78.090 was being taken up together, for which notifications under Section 3A had been published on 18.08.2021 and 21.09.2021. However, due to the expansion of Gaggal Airport, the highway project is now restricted up to km 72.00 (Rajol, Kuthman, Jugehr, Bheri, Sanour, Dhugiari, Gaggal, Jhikli Ichhi, Barswalkar, Mungrehr, and Balla), and for the balance length, an alternate alignment is being finalized. Gazette notifications Nos. 3389 and 3897 dated 18.08.2021 and 21.09.2021 lapsed on 18.08.2022 and 21.09.2022, respectively, and are no more part of the alignment. In light of this communication, the question of acquisition of land for a second time does not arise at all. 101. While admitting that the acquisition of land for the expansion of Kangra Airport shall entail the acquisition of public utilities such as schools, Anganwadis, health facilities, and public infrastructure, it has been submitted that the State Government is bound by the provisions of the Third Schedule of the Act, under which the provision of all infrastructural facilities and basic minimum -55- 2026:HHC:49585 amenities shall be ensured, details whereof have been brought out and narrated in the SIA report. The shifting of transmission lines will no doubt entail financial implications, but the potential benefits of the proposed expansion of Kangra Airport are immense, and the State Government is committed to bearing such expenditure in order to allow the benefits of expansion to be reaped by its citizens. 102. It has been submitted that, as per the report of the Deputy Director of Agriculture (Annexure R-IX), out of a total 122-5242 hectares of land to be acquired, 90-04-62 hectares is cultivated and 32-04-43 hectares is uncultivated. Due to the lack of a permanent system of irrigation, agriculture work has been decreasing, and in the Rabi season, most of the area remains fallow. The State Government is bound by statutory provisions to provide compensation for land, structures, crops, and all other assets as per the Act. Similarly, as far as commercial establishments and loss of livelihood are concerned, suitable compensation shall be provided as per the Act, and the State Government is committed to including suitable provisions in the R&R scheme as well to cater to the demands and aspirations of the people of the area, details whereof have been brought out in the SIA report. -56- 103. 2026:HHC:49585 It has been submitted that any activity of Kangra Airport expansion shall be undertaken strictly as per due process of law and in tune with the seismic and ecological profile of the area. It is denied that the proposed expansion has been started with an aim to provide benefit to an eminent class of people; rather, it has been undertaken in the public interest, and the State Government is bound by the provisions of the Third Schedule of the Act to ensure the provision of all infrastructural facilities and basic minimum amenities. 104. It has been reiterated that the Airports Authority of India opined that expansion of the existing airport from the west towards the north side (towards Sarah-Dharamshala) was not feasible due to steep valleys and close proximity to high hills, and expansion of the existing airport after the construction of the bridge across Manjhi Khad was technically proposed by AAI as the only option available. Shifting the airport to alternate locations is not feasible because those sites are located far from the central location, and construction of greenfield airports involves huge cost, a long timeline, and multiagency clearance processes. The Multi-Disciplinary Expert Group, which included the Pradhans of Gram Panchayats Gaggal and Rachhyalu (where a substantial fraction of land is proposed to be acquired), evaluated the proposal neutrally and independently and -57- 2026:HHC:49585 recommended expansion of the existing airport as a last resort after exhausting all other options. The Expert Group did not rubber-stamp the SIA report, but strongly recommended that adverse social impacts and social costs must be mitigated to the minimum through the Social Impact Management Plan and Relief and Rehabilitation Plan to adequately address the livelihood concerns of projectaffected families. 105. It has been stated that the work of designing the runway bridge over Manjhi Khad has been entrusted to the Central Water and Power Research Station (CWPRS), Pune, a renowned specialized unit of the Government of India, to ensure that the project is executed in tune with the seismic and ecological profile of the area. 106. It has been submitted that the question of approval of the Directorate General of Civil Aviation does not arise at all at this stage, since the expansion plan has been submitted by the Airports Authority of India itself (Annexure R-2). Under Section 15 of the Act, affected persons have filed their objections before respondent No. 4, which are pending statutory adjudication. It has also been submitted that Hans Raj Chaudhary, Ved Prakash Chhattani, and Vijay Kumar, members of the petitioner Committee, had themselves availed of the -58- 2026:HHC:49585 statutory right of filing objections under Section 15 of the Acquisition Act. 107. In sequel to the order dated 13.11.2024 passed in the present writ petition, a Supplementary Affidavit was filed on behalf of the respondent State through the Special Secretary (Tourism & Civil Aviation) to the Government of Himachal Pradesh, placing on record a detailed chronological chart indicating the steps taken by the respondents in consonance with the provisions of the law and rules as applicable: Date Details The expansion of the Gaggal Airport in the State, whereby the respondent State has been making constant endeavors for expansion of present runway length of Gaggal Airport. 10.12.2019 The respondent State had requested to Airport Authority of India (Herein referred to as 'AAI' for short) to revisit the expansion plan for the Kangra airport and explore the possibility of runway length up to at least 3100 mtr so that wide bodied aircrafts like Airlines and Boeing 737-800 are able to operate from this Airport. -59- 2026:HHC:49585 Obstacle Limitation Surface Survey (Herein referred to as 'OLS' for short), is a pre-requisite condition for construction/ development of any airport which ensure safe aircraft operations. 03.01.2020 The respondent Airport Authority of India clearly mentioned that AAI officials had visited the site from 21.12.2019 to 22.12.2019 and had categorically observed that there is a steep valley towards Rwy15 side, hence the only possibility of runway extension is towards Rwy 33 side. Henceforth, it becomes crystal clear that all the possibilities for runway direction qua expansion of runway/ project in question have been explored and the behest of respondent AAI, which likely in all probabilities is towards Rwy 33 side. Also, the respondent AAI vide the aforesaid communication supra had enclosed a Draft Master Plan for the proposed expansion of Gaggal Airport. 04.03.2021– OLS survey was done by AAI team for the 11.03.2021 proposed runway extension of Kangra airport from 1376 Mtr. to 2150 Mtr. towards RWY-33 considering the total runway length up to 3526 Mtr. for IFR operation. 07.10.2021 The site plan for approach runway for expansion of airport was prepared by the Airport Authority of India which clearly envisages the entire details of -60- 2026:HHC:49585 the manner in which the proposed expansion has to be carried out. State Government conveyed the consent to the Draft Master Plan (for 1st Phase extension in runway from1376 to 1900 mtrs and 2nd phase from 1900 mtrs. to 3010 mtrs) received from AAI As per the above communication received from AAI, the development of airport is subject to availability of land to be provided by the State Govt. free of cost and free of all encumbrances, diversion of road, transmission lines, removal of obstacle, river training etc. 09.08.2021 The respondent AAI after carrying out OLS survey of Gaggal Airport for its expansion whereby all physical. features including essential and critical objects were collected in and around the aerodrome within a radius of around 15 km of the aerodrome covering all obstacle limitation surfaces as per DGCA CAR specifications. 07.10.2021 The respondent AAI had submitted that the master plan for the expansion of Kangra Airport in two phases up to runway length of 3010 mtr. to respondent State with a request to study techno economic feasibility and revert with feasibility way forward -61- 02.11.2021 2026:HHC:49585 That the AAI had informed that the expansion of runway at Shimla & Kullu Airports is not advisable keeping in view the constraints like non-feasibility of instrument approach procedure, high obstacles, environmental concerns arising out of diversion of river and huge cost etc. Hence, the Gaggal is the only Airport in the State where expansion is possible. 28.02.2023 SIA notification under Section 4 of the Right to Fair Compensation Rehabilitation & in Land Resettlement Acquisition, Act, (hereinafter referred as Act) was issued on 28.02.2023 which was published in newspapers on 02.03.2023 and 03.03.2023. The SR ASIA submitted SIA report which was evaluated by the independent Multi-Disciplinary Expert Group notified by the Government as per the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 which recommended the project citing that besides fulfilling the public interest considerations, its potential benefits would outweigh the social costs and social impacts. 18.03.2023 After receiving the draft SIA report, notices under Section 5 of the Act ibid were issued by the SDM Kangra and SDM Shahpur regarding public -62- 2026:HHC:49585 hearings which were received by the concerned Gram Panchayat Pradhans. 10.04.2023– Public hearings were conducted The 12.04.2023 proceedings of the public hearing are available at Chapter IX of SIA report and the videography of hearing are also posted/available on public domain i.e. You tube channel of HIPA (Pen drive available). 06.05.2023 The objections/ suggestions received from the public were incorporated in the final SIA report. The District Administration Kangra identified the land measuring 147-75-87 hectare (out of which 122-54-86 hectare land is private land) for the expansion of the Kangra Airport. 07.07.2023 The appraisal report submitted by the MultiDisciplinary Expert Group was further approved by the cabinet and thereafter the notification under section 11 of the Act was issued. The respondent State Government had engaged the services of Centre Water & Power Research Station Khadakwasla (CWPRS) Pune for Mathematical model studies to hydraulically route flood below the proposed expansion of Kangra Airport runway crossing Manjhi Khad in Shahpur, District Kangra. A draft report of CWPRS Pune was also received from CWPRS. The Special Land Acquisition Unit (SLAU) has also been set for land acquisition. The work regarding facilitation in implementation -63- 2026:HHC:49585 of land acquisition and Resettlement & Rehabilitation for expansion of Kangra airport has also been awarded to Consultant for Rural Area Development Linked Economy (CRADLE) through HPRIDCL. 20.10.2023 The task of Techno-Economic Feasibility Report (Herein referred to as 'TEFR') was assigned by the respondent State to WAPCOS Ltd. Accordingly, the draft TEFR was submitted by WAPCOS, wherein, project cost excluding the land acquisition cost was estimated to Rs. 10995.69 Cr. The draft report was then further forwarded to respondent no.5, i.e. Airport Authority of India. 09.11.2023 The respondent Authority no.5 communicated to the Applicant Department to reexamine the TEFR in view of financial viabilities and further seek technical opinion from IIT, Roorkee (Department of Water Resource Development & management. 20.11.2023 The State Government vide its notification no. TSM-F (6)-1/2015-IV-L dated 15.09.2023 constituted a Rehabilitation & Resettlement Committee at project level under Section 45 (1) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 to monitor and review the progress of implementation social audits in consultation with Gram Sabha in rural -64- 2026:HHC:49585 areas and Municipality in urban areas in r/o Expansion of Kangra Airport. 02.12.2023 A meeting under the Chairpersonship of the Director T&CA was convened and WAPCOS was directed to re-examine their draft TEFR as pointed out by respondent no.5. The Company was also directed to get the draft TEFR technically vetted from IIT Roorkee estimates for expansion of Kangra Airport and resubmit the revised TEFR. 26.02.2024 The WAPCOS Limited submitted revised TEFR stating that revised CAPEX cost is now to a tune of Rs. 3,504/- Crores plus applicable taxes (INR 4, 249 Cr. Incl. of applicable taxes.) The IRR & ERR for the project has been obtained as 2.0% and 2.90% respectively considering the rate of interest as 8%. WAPCOS Ltd. 12.03.2024 Consequently, the aforesaid R&R Committee in consultation with State Government approved the R & R scheme. Rehabilitation & Resettlement Scheme was finalized by the State Government and stands conveyed to District Administration, Kangra 15.03.2024 The State Govt. sent the revised draft TEFR to AAI on 15.03.2024 for comments/approval -65- 02.04.2024 2026:HHC:49585 WAPCOS Ltd. had sent the draft TEFR to IIT, Roorkee for vetting. 19.04.2024 As per the section 7 of the Act, Multidisciplinary Expert Group was constituted which examined the SIA report as per the mandate of the Act. The Multidisciplinary Expert Group in its appraisal report has recommended the acquisition of the land for the public purpose. Most of the objections of affected families were regarding missing Khasra numbers and R & R plan 09.05.2024 After carrying out all due processes related to fixing of boundary marks, finalization of forest Land and enumeration of trees, the case for seeking approval under the Forest Conservation Act has been uploaded on the portal by the Department of Tourism and Civil Aviation. 15.05.2024 That the respondent Department had convened a meeting with respondent no. 5, i.e. Airport Authority of India & WAPCOS Ltd. on 15th May' 2024 to discuss the submitted TEFR and the process of addressing the observations raised by respondent Airport Authority of India have been taken up with WAPCOS. It is further submitted that once observations so raised by the Airport Authority of India are attended, final vetting of -66- 2026:HHC:49585 TEFR shall be expedited by WAPCOS Ltd. from IIT, Roorkee. 24.05.2024 The respondent no. 5 AAI conveyed the: observations / comments on draft TEFR which were then again conveyed to WAPCOS Limited for necessary action. 16.08.2024 Notification under Section 19 of the Act ibid was been issued by the Government which was published in the Gazette on 17.08.2024. 21.08.2024 After attending all observations, WAPCOS has submitted draft TEFR 21.08.2024 wherein, the CAPAX has been estimated at Rs. 4064.27 Cr. (Inclusive GST). The TEFR was sent to the Govt. which has further been sent to AAI for approval. October' 2024 The Land Acquisition Collector Gaggal Airportcum-SDM Kangra issued the notices on 08.09.2024 under Section 21 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 to the families likely to be affected by the proposed expansion. Out of the total 6429 notices served u/s 21 of the Act , 158 notices stands un-served due to insufficient addresses. Total 44 objections were received out of which 13 pertains land and 31 pertains to R & R. -67- 2026:HHC:49585 October' 2024 As per the proposed timeline received from the to December' Land Acquisition Collector Gaggal airport -cum2024 SDM Kangra enquiries of objections received u/s of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 which shall be conducted. October 2024 Award shall be issued by the Collector u/s 23 of to June 2025. the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. Land Acquisition Collector Gaggal Airport-cumSDM-Kangra passed award u/s 23 of the Right to Fair Compensation in Land Acquisition, Rehabilitation & Resettlement Act, 2013 to the extent of 02-60-66 hectare land of Village Jugehar, Tehsil Shahpur, District Kangra, HP to the tune of Rs. 32, 43, 66,466.40 which has been released to DTDO Kangra by IDB, HP from the amount of Rs. 300.00 Cr. deposited with them for execution of work regarding of Kangra airport. 30.10.2024 The Land Acquisition Collector Gaggal Airportcum-SDM Kangra has also passed award for the Village Rachhiyalu, Tehsil Shahpur, District Kangra to the extent of 14-94-48 hectare to the tune of Rs. 126, 39, 53,826.67/-. -68- 06.11.2024 2026:HHC:49585 The SDM Kangra has passed the award for Villages of Dhugiari Khas, Bhadot and Bheri to the tune of Rs. 31, 49, 46,662.04/-. The approval to release the funds is under process. The awards for the villages of Kior and Sanour to the tune of Rs. 131.23 Cr. has also been issued. October' 2024 Individual award u/s 30 and R & R awards u/s 31 to July 2025. of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. October 2024 Payment of Compensation to December 2025. December' After releasing of full payment of compensation to and R& R entitlements the site shall be handed February 2026 over u/s 38 of the Act at 04 Villages of Shahpur Tehsil. 108. In sequel to the orders dated 25.11.2024, 12.12.2024, and 24.12.2024, a Status Report was placed on record on behalf of the respondent State through the Joint Secretary (Tourism & Civil Aviation) to the Government of Himachal Pradesh, stating that the respondent State is duty bound to execute the aforesaid project, for which an application has already been filed to seek forest clearance -69- 2026:HHC:49585 for diversion of 06-10-68 hectares of forest land out of the entire project area measuring 147-75-87 hectares (which comprises 12266-23 hectares of private land), which does not form even 1% of the total land in question, and the project will be executed only after securing the land with all necessary statutory compliances as and when required. 109. It has also been stated in the Status Report that the respondent State has awarded an amount of Rs. 4,89,10,01,358.47 to affected persons having private land, and compensation is being deposited in the bank accounts of only those affected persons who voluntarily agree to accept compensation upon furnishing written undertakings. 110. It has been submitted that as per the EIA Notification dated 14.09.2006 issued by the Ministry of Environment, Forest and Climate Change (MoEF), under paragraph 2, prior environmental clearance is required, wherein it has been provided as under: "...before any construction work, or preparation of land by the project management except for securing the land, is started on the project or activity..." -70- 111. 2026:HHC:49585 Referring aforesaid, it has been further submitted that securing the land is expressly permitted prior to obtaining environmental clearance, and the executing agency (AAI) would be the user agency for seeking environmental clearance once the land is secured and transferred. Furthermore, the proposal for diversion of 06-10-68 hectares of forest land under the Forest (Conservation) Act, 1980 is pending before the Technical Officer, and Section 2 of the 1980 Act applies only to land entered as 'Forest' and not to private land. The respondent State is strictly adhering to the statutory provisions of the 2013 Act and following the law laid down by the Hon'ble Supreme Court in Kolkata Municipal Corporation & Anr. v. Bimal Kumar Shah & Ors. (Civil Appeal No. 6466 of 2024, decided on 16.05.2024). 112. Learned Advocate General by referring judgment dated 10.07.2024 passed by the Apex Court in Civil Appeal No. 8048/2019, titled New Okhla Industrial Development Authority vs. Darshan Lal Bohra and Ors., reported in 2024 INSC 508, has submitted that if State Government opines that the land is needed for a larger public purpose and development projects, such land can be acquired notwithstanding the fact that it was residential and also that it is an admitted position that acquisition proceedings in instant -71- 2026:HHC:49585 case have nearly attained finality. Significant investment has been made in acquisition of land, and for accepting petitioner’s plea, claim would be required to turn back the clock, which would have adverse impact on the larger public interest. 113. Learned Advocate General to substantiate the plea that in cases of land acquisition, in larger public interest, the plea of deprivation of right to livelihood under Article 21 of the Constitution is un-sustainable, and ordinary rehabilitation should only be meant for those persons who have been rendered destitute because of loss of residence or livelihood, as a consequence of land acquisition, and on the ground of loss of residence of livelihood, an acquisition cannot be halted, has referred judgment dated 14.07.2025 passed by the Apex Court in Civil Appeal No. 7707 of 2025, titled Estate Officer, Haryana Urban Development Authority and Ors. vs. Nirmala Devi reported in 2025 INSC 843. 114. Referring judgment of Coordinate Division Bench of this High Court in case titled Vivek Sharma vs. Union of India Through Its Secretary, Ministry of Road Transport And Highways & Connected Matter, reported in 2022 (1) Him.L.R. 575, it has been submitted that Court is not at all equipped to decide upon viability or feasibility of a particular project, and it is -72- 2026:HHC:49585 only an expert body, having experience in the field of development and maintenance of airports, which can evaluate the feasibility and viability of the project, and therefore, for such plea, scope of judicial review is extremely limited. 115. Learned Advocate General to substantiate respondent- State’s plea and oppose the petitioner’s plea has also referred judgment passed by the Apex Court in Jilubhai Nanbhai Khachar and others v. State of Gujarat and another, 1995 Supp (1) SCC 596; Ramniklal N. Bhutta and another v. State of Maharashtra and others, (1997) 1 SCC 134; Sooraram Pratap Reddy and others v. District Collector, Ranga Reddy District and others, (2008) 9 SCC 552; Project Director, Project Implementation vs. P.V. Krishamoorthy & Ors., (2021) 3 SCC 572; N.G. Projects Limited v. Vinod Kumar Jain and others, (2022) 6 SCC 127; and Kolkata Municipal Corporation and another v. Bimal Kumar Shah and others, AIR 2024 SC 2819 as well as of this High Court in Vivek Sharma vs. Union of India Through Its Secretary, Ministry of Road Transport And Highways & Connected Matter, (2022) 1 HLR 575 and in M/s. Garg and Garg Co. vs. Union of India and others, AIR 2023 HP 183. -73- 2026:HHC:49585 STAND OF RESPONDENT NO.5-AIRPORTS AUTHORITY OF INDIA 116. In the reply filed on behalf of respondent No. 5, Airports Authority of India (AAI), it has been submitted that no fundamental or constitutional right whatsoever of the petitioner has been infringed, and as such the writ petition is not maintainable and the petitioner has no locus standi to file the same. At the very outset, it has been submitted that land for the expansion of Kangra Airport is required to be acquired by the State of Himachal Pradesh, and only after completion of the acquisition, the Airports Authority of India will carry out the development and expansion and seek necessary permissions from the concerned statutory authorities. It has been reiterated that AAI shall take up the expansion work after additional land is acquired by the State Government and handed over to AAI, whereas all statutory actions related to land acquisition such as Social Impact Assessment (SIA), publication of Gazette Notifications under the Land Acquisition Act, evaluation of land and property, and Rehabilitation and Resettlement are being done by the State Government. After the land is handed over by the State Government to AAI, AAI shall obtain necessary clearances and approvals from the Directorate General of Civil Aviation (DGCA) and all other -74- 2026:HHC:49585 concerned statutory authorities during execution as well as commissioning of the infrastructure. 117. Tracing the sequence of communications, it has been submitted that in reference to the letter dated 15.11.2019 addressed to the replying respondent by the State of Himachal Pradesh, the replying respondent responded on 03.01.2020 and submitted a draft plan to explore the feasibility for acquisition of additional land (Annexure R/5-A). On 03.01.2021, the State of Himachal Pradesh through its Additional Secretary wrote a letter observing that conducting of SIA and proposing realignment of the National Highway without obtaining pre-feasibility report and OLS survey report will be a futile exercise, and can be initiated only after the site is declared suitable for runway expansion by a survey feasibility study and clearance from BCAS and DGCA (Annexure R/5-B). On 17.04.2021, the OLS chart and obstacle penetration details for the Runway 33 extension at Kangra Airport were forwarded to the State of Himachal Pradesh. On 07.10.2021, the replying respondent issued a letter to the State of Himachal Pradesh mentioning therein that Kangra Airport can be developed in two phases, i.e., Phase-I for operation of ATR-72/Q-400 type of aircraft and Phase-II for operation of A-320 type of aircraft (Annexure R-5/C). On 08.11.2021, the State -75- 2026:HHC:49585 of Himachal Pradesh constituted a Committee for identification of land for development of Kangra Airport for operation of ATR-72/Q400 and A-320 type of aircraft (Annexure R-5/D). 118. It has been further submitted that on 26.09.2023, the State of Himachal Pradesh informed that the acquisition process for the expansion of Kangra Airport was in an advanced stage and requested to finalize the construction of the extended portion of the airport (Annexure R-5/E). On 20.10.2023, the State of Himachal Pradesh submitted a draft Techno-Economic Feasibility Report (TEFR) prepared by WAPCOS Ltd. for examination (Annexure R5/F). On 09.11.2023, the replying respondent wrote a letter to the State advising it to carry out a study on financial viability in addition to technical viability (Annexure R-5/G). In a review meeting convened on 02.12.2023, it was observed that the TEFR submitted was shoddy and not made in a professional way, reflecting a lackadaisical approach by WAPCOS, and it was conveyed that the points and observations raised were only indicative and the onus lay on WAPCOS to expedite revision of its report, address all shortcomings, and make the report in sync with reality based on facts and figures (Annexure R-5/H). On 06.12.2023, the State of Himachal Pradesh issued directions to carry out necessary verification and -76- 2026:HHC:49585 certification of boundary pillars in consonance with the approved Master Plan, explore alternate locations for DVOR, and plan the creation of new infrastructure (Annexure R-5/J & K), and on 01.01.2024, WAPCOS Ltd. informed the State Government that its team would visit the site in the second week of January, 2024 (Annexure R-5/L). 119. It has been further submitted by respondent No. 5 that in various meetings, it was suggested and opined that possibilities may be explored for extension of the runway for operation of bigger aircraft and making the airport operations from Visual Flight Rules (VFR) to Instrument Flight Rules (IFR) to reduce flight cancellations, load penalties, and airfares. Accordingly, based on the OLS survey report, the Airports Authority of India prepared a Master Plan for expansion of Kangra Airport for extension of the existing runway length from 1376 meters to 3010 meters suitable for operation of AB320 type of aircraft, while catering to other requirements like Runway End Safety Area (RESA) and land for approach lighting on the same alignment. The Master Plan has been shared with the State Government, which involves an additional land requirement of 369.82 acres for the proposed expansion. AAI has reiterated that it shall take up the expansion work after additional land is acquired by -77- 2026:HHC:49585 the State Government, all statutory actions relating to land acquisition, notifications, valuation, and Rehabilitation and Resettlement are completed, and possession is handed over to AAI, whereafter AAI shall obtain necessary clearances and approvals from DGCA and other concerned statutory authorities during execution as well as commissioning of the infrastructure. 120. Subsequently, in compliance with the order dated 08.01.2025 passed by this Court in the present writ petition— whereby the replying respondent was directed to file a status report regarding the TEFR submitted by the State of Himachal Pradesh and apprise whether it is technically viable that the expansion can be carried out on the airport to the extent proposed by the State Government for Phase-I for operation of ATR-72/Q-400 type of aircraft without load penalty for VFR operations and Phase-II for operation of A-320 type of aircraft without load penalty for IFR operations—an affidavit dated 03.03.2025 was placed on record on behalf of respondent No. 5 through Shri Dhirendra Singh, Airport Director, Kangra Airport. 121. In the aforesaid response and affidavit, it has been stated regarding the latest status on the TEFR for expansion of Kangra Airport that in October 2024, a revised report was submitted -78- 2026:HHC:49585 to AAI by the State Government in which the proposal for expansion of Kangra Airport, including extension of runway for IFR operations for A-320 type of aircraft along with construction of new terminal building, ATC tower, fire station, and associated facilities in a single phase was given, and the capital expenditure cost was revised to Rs. 4,064 crores. Comments on the same were conveyed to the State Government by AAI in December 2024, advising it to incorporate the same and re-submit a revised TEFR. The revised TEFR is awaited from the State Government, and upon its submission, it will be analyzed by AAI. If the project is found to be technically and financially viable and the State Government is willing to bear the cost of cutting and filling, soil stabilization, and construction of the bridge over Manjhi Khad, then AAI can take up the work for extension of the runway and other facilities subject to approval of the Competent Authority. Regarding whether it is technically viable that the expansion can be done on the airport to the extent proposed by the State Government for Phase-I and Phase-II, it has been stated that since the revised TEFR is currently pending from the State Government, AAI will conduct a thorough analysis of its technical feasibility once it is submitted, and only after such evaluation will the replying respondent be able to provide any comments. -79- 122. 2026:HHC:49585 With regard to proposed expansion and alternatives sites suggested in SIA Report as well as proposed by the petitioner, including alternative depicted in Annexure P-7 appended with the petition, the AAI has responded as under:"i. The Kangra Airport is under operational and the expansion proposed is extension of Runway and that shall not hinder the ongoing operations. ii. The proposal suggested is re-orienting the Runway and that needs study of feasibility with respect to Wind directions, Obstacles, Hazards and Dangerous zones etc and the financial viability. iii. This needs the whole procedures of Feasibility study, OLS study and the Tecno- Economic feasibility study to be once again carried out as carried out earlier by GoHP in coordination with AAI for the earlier expansion proposed which leads time overrun & cost overrun and fresh pocket of land to be identified for the feasibility study. iv. The present proposal of Expansion of Runway is on same alignment which require the least span of the bridge over Manjhi Khad. The re-orientation suggested in Annexure P7, is crossing through two branches of rivers Sarah and Manjhi Khad, required to construct larger span of bridge which may not structurally suitable to construct runway over it. v. The re-orientation suggested such that even if the study on the alternative proposal turns out to be financially viable for GoHP, technically it may not be possible to carry out on an operational Airport. Also, the the cost co incurred to shift all -80- 2026:HHC:49585 the existing infra structures to be ascertained the same to be borned by whom? vi. Further, to go with re-orientation of expansion, the operations of the Airport had to be closed for the reorientation process, it is to bring in here that there are only two airports Kullu and Kangra Airports in this valley. Shimla is situated in the down southern part of Himachal Pradesh. vii. Therefore, in this case, operation of Kangra Airport may hinder and it may impact to potential efficiency as well as effectiveness of AAI at Kangra." 123. Learned Deputy Solicitor General of India has also questioned locus of the petitioner and submitted that present petition is not maintainable, as it has not been filed by an aggrieved person, and petitioner-Committee is not legal entity to be an aggrieved person. According to him, three persons, namely, (1) directly aggrieved, (2) person authorized by aggrieved person or, (3) person having no personal interest, but public interest at large is involved, can only file writ petition of present nature. He has submitted that petitioner-Committee is not a directly aggrieved person, though it is claiming authorization by the Panchayat, but authorization is in favour of persons, but not in favour of petitioner-Committee. It has been further submitted that present case has not been filed as a Public Interest Litigation, as mandatory requirements for filing Public Interest Litigation have not been followed. -81- 124. 2026:HHC:49585 It has been further submitted by learned Deputy Solicitor General that resolution passed by Gram Panchayat, Nandehar, is in favour of persons named in the resolution, but writ petition has been filed in the name of Committee, whereas there is no authorization in favour of the Committee either by the Gram Panchayat, Nandehar or anyone else to agitate their cause in present matter. Therefore, it has been contended that petition deserves to be dismissed on this sole ground. 125. Learned Deputy Solicitor General has also submitted that no locus lies in favour of petitioner or anyone else. It has been submitted that petitioner-Committee has misled the Court by concealing necessary facts and thus, petition deserves to be dismissed. 126. To substantiate his plea, learned Deputy Solicitor General has referred pronouncements of Apex Court in various cases, i.e., in case titled Ayaaubkhan Noorkhan Pathan vs. State of Maharashtra and Others, reported in (2013) 4 SCC 465, case titled Ghulam Qadir vs. Special Tribunal and Others, reported in (2002) 1 SCC 33, case titled Vinoy Kumar vs. State of U.P. & Ors, reported in AIR 2001 SC 1739, case titled State of Bihar and Another vs. P.P. Sharma, IAS and Another reported in (1992) -82- 2026:HHC:49585 Supp 1 SCC 222 and case titled Dr. J.N. Banavalikar vs Municipal Corporation Of Delhi And Anr., reported in AIR 1996 SC 326. 127. Learned Deputy Solicitor General has submitted that SIA and Expert Committee are not party, who have prepared and affirmed the report and the nature of pleadings are clear that there are no mala fide allegations against SIA and Expert Committee. 128. According to learned Deputy Solicitor General, as there is defect in pleadings, the writ petition deserves to be dismissed, as held by the Apex Court in various pronouncements referred hereinafter, i.e., case titled Udit Narain Singh Malpaharia vs. Additional Member, Board of Revenue, Bihar and Anr., reported in AIR 1963 SC 786, case titled Prabodh Verma and Others etc. etc. v. State of Uttar Pradesh and Others, reported in AIR 1985 SC 167, case titled Public Service Commission, Uttaranchal vs. Mamta Bisht and Others, reported in (2010) 12 SCC 204, and in CWP No. 6652 of 2022, titled Bishamber Singh vs. State of H.P. & others, decided on 27.04.2023. 129. Learned Deputy Solicitor General has further submitted that though Order 1 Rule 10 CPC is not strictly applicable to the writ proceedings, however, principles of CPC are always applicable, and there is complete non-compliance of Order 1 Rule 10 CPC, and -83- 2026:HHC:49585 therefore, for non-compliance thereof, petition deserves to be dismissed. 130. To substantiate aforesaid plea, learned Deputy Solicitor General has referred to pronouncements of Apex Court, i.e., case titled The Chairman, Tamil Nadu Housing Board, Madras vs. T.N. Ganapathy, reported in AIR 1990 SC 642, case titled Ramchander Sunda and Another v. Union of India and Others, reported in (1999) 9 SCC 105, case titled V. Chandrasekaran and Another v. Administrative Officer and Others, reported in (2012) 12 SCC 133, case titled Ayaaubkhan Noorkhan Pathan v. State of Maharashtra & Ors., reported in (2013) 4 SCC 465 and case titled Narmada Bachao Andolan v. Union of India and Others, reported in (2000) 10 SCC 664. STAND OF RESPONDENT NO.6 131. On behalf of respondent No. 6, National Highways Authority of India (NHAI), it has been submitted that the replying respondent is an autonomous agency of the Government of India and a nodal agency of the Ministry of Road Transport and Highways, responsible for the development and management of highway networks in the country. The Government of India, vide Gazette Notification dated 15.09.2016, upgraded NH-20 (Himachal -84- 2026:HHC:49585 Pradesh/Punjab Border to Mandi, km 11.000 to km 208.000) from two lanes to four lanes, and the alignment of the proposed NH-154 was finalized on 10.01.2018. The highway project was divided into five packages, and the stretch involved in the present petition falls in Package-II (Sihuni to Parour) from chainage 51+000 to 100+840, having a length of 49.840 km. Package-II is further sub-divided into three sub-packages, namely Package-IIA (Sihuni to Rajol) which is under construction, Package-IIB (Rajol to Thanpuri) which is under Detailed Project Report (DPR) preparation due to the expansion of Gaggal Airport, and Package-IIC (Thanpuri to Parour) which has already been awarded. 132. It has been further submitted that respondent No. 2, vide letter dated 27.08.2020, conveyed information regarding the proposal for expansion of the existing Gaggal Airport from 1376 meters of landing strip to 3187 meters of landing strip as per the drawing provided by respondent No. 5, which intersects with the proposed National Highway. In a meeting held on 02.09.2020, the Project Director, NHAI Palampur, was directed to prepare and submit a revised alignment of Package-IIB (Rajol to Thanpuri) and provide three alternative options in consultation with the Joint Committee comprising the Deputy Director (Tourism & Civil -85- 2026:HHC:49585 Aviation), SDM Kangra, SDM Shahpur, revenue officials, and the Airport Director. The DPR consultant explored the feasibility of alternate alignments and submitted a draft comparative report, and based on suggestions from the Deputy Commissioner, Kangra, proposed alternate Option-III was prepared and submitted to NHAI Headquarters for approval, where it is under active consideration. 133. It has been submitted that Gazette Notifications under Section 3A of the National Highways Act, 1956 were published on 18.08.2021 and 21.09.2021 (Annexure P-5) for the project Sihuni to Ichhi from km 51.00 to km 78.090. However, due to the expansion of Gaggal Airport, the highway project was restricted up to km 72.00, and for the balance length, an alternate alignment was to be finalized. Consequently, declarations under Section 3D of the National Highways Act, 1956 were not issued within the statutory period of one year as provided under Section 3D(3) of the Act, and the notifications issued under Section 3A lapsed on 18.08.2022 and 21.09.2022, respectively, which was duly communicated to respondent No. 2 vide letter dated 01.08.2023 (Annexure R-6/1). In light of this, the highway alignment does not pass through the proposed airport land, and the plea of the petitioner regarding dual acquisition of the same land for a second time does not arise at all. -86- 134. 2026:HHC:49585 Respondent No.6 has further raised a preliminary objection that the petitioner Committee is an unregistered society and an association of persons, which is not conferred with the status of a legal entity under any statute. Not being a juristic person, an unregistered society cannot sue or maintain a writ petition in its own name, rendering the present petition bad in law and liable to be dismissed on this ground alone. 135. It has been averred that there is no violation of any statutory, legal, or vested right of the petitioner, no injustice has been caused, and the petitioner has no cause of action. The impugned preliminary notification dated 07.07.2023 has not been issued by respondent No. 6, and no relief has been claimed against the replying respondent, whereby the petition is frivolous, baseless, and deserves to be dismissed. REBUTTAL SUBMISSIONS ON BEHALF OF PETITIONER 136. Learned Senior Counsel for the petitioner has submitted that the rejoinder forms an integral part of the pleadings, and to substantiate this submission, reliance has been placed on Vivek Sharma vs. Union of India Through Its Secretary, Ministry of Road Transport And Highways & Connected Matter, (2022) 1 HLR 575 (paragraph 11). -87- 137. 2026:HHC:49585 In the rejoinder filed on behalf of the petitioner, it has been reiterated that the State and its instrumentalities have resorted to massive acquisition of agricultural land without complying with the statutory mandate. It has been pleaded that when the land of uneducated agriculturists is acquired, who are not empowered to adopt alternative livelihoods, not only the present but future generations are ruined, which is one of the reasons why farmers who are deprived of their landholdings are driven to suicide. It has been urged that the authorities are unmindful of the plight of those sections of society who are deprived of their only assets, like agriculture, small houses, and small industrial units, and before acquiring private land, the State should, as far as possible, utilize land belonging to the State for specified public purposes; if acquisition of private land becomes absolutely necessary, land that is barren, unfertile, and involves zero displacement should be preferred, in strict compliance with relevant statutory provisions and the rules of natural justice. 138. It is the case of the petitioner that the Social Impact Assessment team visited the villages in an arbitrary manner, without giving any prior information regarding their visit to the Gram Panchayats and without publishing public notice of the substance of the notification at convenient places in the locality through the -88- 2026:HHC:49585 Collector, and the rights of the people are being taken away in utter disregard of the provisions of law and statutory mandate. 139. Further, it has been submitted that the Rehabilitation and Resettlement plan was not available with the SIA team, and therefore, the SIA report is not based on complete facts, and thus could not be relied upon to carry on the project of expansion of the airport as proposed. 140. It has been highlighted in the rejoinder that due to the peculiar topography of the State of Himachal Pradesh, the Gaggal Airport expansion project involves the construction of a bridge of 380 meters width over the Manjhi River, which would form part of the expanded runway and would entail massive river training and diversion works, as well as realignment of the National Highway. In its letter dated 09.11.2023, the Airports Authority of India had recommended that the State Government take a second opinion from the Department of Water Resources Development and Management, IIT Roorkee, because the proposed construction is to be carried out in an area that has in the recent past witnessed heavy flooding, landslides, etc., and falls in Seismic Zone V. This recommendation was made by AAI on the basis of the draft TechnoEconomic Feasibility Report issued by WAPCOS Ltd., a Public -89- 2026:HHC:49585 Sector Enterprise under the Ministry of Jal Shakti, Government of India. Even in its communication dated 07.10.2021, AAI had categorically opined that techno-economic feasibility and environmental clearance need to be obtained prior to the expansion work. 141. Learned counsel for the petitioner has further submitted that the State of Himachal Pradesh witnessed the wrath of nature in the form of incessant rains, cloudbursts, flash floods, and landslides during the monsoon season of 2023. The Manjhi River is prone to floods every rainy season, and the proposed construction of a 380meter-wide bridge over the river to form part of the extended runway, apart from requiring clearances from the Bureau of Civil Aviation Security, would entail extensive river training and diversion. The expansion work, if carried out at this natal stage without an approved, vetted techno-economic study, would entail serious environmental hazards, and the hapless public at large would suffer the brunt of such an injudicious exercise carried out in a haphazard manner. 142. It has been contended that the Multi-Disciplinary Expert Group constituted under Section 7 of the Act cannot be termed an independent group, since it is chaired by the Deputy Commissioner (Relief & Rehabilitation), who cannot be stated to be an independent -90- 2026:HHC:49585 person for the purpose of the evaluation to be carried out by the Expert Group. Because of an inherent element of institutional prejudice, the Expert Group failed to appreciate that the social costs and adverse social impacts of the project outweigh the potential benefits. Moreover, the Expert Group brushed aside the alternative sites suggested in the Social Impact Assessment study by a sidewind without examining their technical and financial aspects, whereas considering those alternative sites would be financially and economically viable and would prevent mass displacement. CONSIDERATION AND ANALYSIS A. 143. Competence and Status of the Petitioner Committee Before adverting to consideration on merits with regard to plea of the petitioner and response thereto, we are of the opinion that in given facts and circumstances it would also be necessary to consider competence and status of the petitioner-Committee to file present petition as constituted and preferred, and accordingly, the same has been considered hereinafter. 144. The petitioner is stated to be a committee constituted for representing the grievances of local residents of the villages whose land was and is proposed to be acquired by the respondents for -91- 2026:HHC:49585 expansion of Gaggal Airport, as averred in paragraph 1 of the writ petition. 145. There is nothing on record regarding the constitution of the Committee and registration thereof. It is also not clear whether the Committee is registered or unregistered. The aims and objects of the Committee, as well as its Memorandum of Association, have also not been placed on record. 146. There is no resolution of the Committee on record authorizing the filing of the present petition, nor is there anything on record to indicate the competence of the President of this so-called Committee to file the petition on behalf of the Committee. Who are the members of the Committee is also not traceable from the material placed on record. 147. It has been claimed in paragraph 1 of the petition that the Gram Panchayats of the villages referred in this para had passed resolutions and authorized the President and other members of the Committee to pursue the matter on their behalf. However, there is no resolution on record except one purported to have been passed by Gram Panchayat, Nandehar. -92- 148. 2026:HHC:49585 This resolution is also defective. In this resolution, it has been resolved to oppose the expansion of Kangra Airport on the ground that most of the villagers depend for their livelihood on agriculture, and their agricultural lands, residential houses, shops, and commercial establishments are coming within the acquisition for expansion of the airport, and for contesting the legal battle on behalf of the Panchayat, Rajneesh Saini (President), Hans Raj Chaudhery (General Secretary), Ved Chattani (Senior Vice President), and Vijay Kumar (Member) are authorized. 149. It is worth noticing that in the memo of parties of the writ petition, the President of the petitioner Committee has been described as Rajneesh Mona, whereas in the resolution, he has been named as Rajneesh Saini. 150. Further, the resolution has been passed in favour of and authorizing the office bearers of "Gaggal Hawai Adda Vistar Prabhavit Kalyan Committee", whereas the petitioner before this Court is "Gaggal Airport Expansion Affected Social Welfare Committee". 151. The name of the Committee in either language should be one and the same. It cannot be that the name in Hindi is different and in English it is different. If such a practice were to be permissible, -93- 2026:HHC:49585 then a person named "Lal Chand" in Hindi would have to be named as "Red Moon" or “Son of Moon” in English. 152. It is further noticeable that the authorization by the Gram Panchayat was to contest the legal battle on behalf of the Panchayat, but the present petition has not been filed on behalf of Gram Panchayat, Nandehar, but on behalf of the Gaggal Airport Expansion Affected Social Welfare Committee. It is not a petition by Gram Panchayat through Committee or by Committee on behalf of Gram Panchayat. 153. Further that there is no resolution on record to file a petition by the Committee on behalf of the Gram Panchayat. In fact, while the office bearers were authorized to contest on behalf of Gram Panchayat, Nandehar, the petition has been filed by the Committee, and not by the office bearers on behalf of the Gram Panchayat. The petitioner-Committee has filed this petition independent of the resolution passed by the Gram Panchayat. 154. Moreover, the resolution placed on record is only of one Gram Panchayat, and there is nothing on record regarding the resolutions of the other Gram Panchayats as claimed in paragraph 1 of the petition. -94- 155. 2026:HHC:49585 It is also a matter of fact that most of the residents and land owners of the villages comprising Gram Panchayat, Nandehar have already accepted the amount of compensation. 156. In absence of any material on record regarding registration of the petitioner-Committee with competent authority, which has also not been placed on record despite objection taken by the respondents with regard to maintainability and locus of the petitioner-Committee to file the writ petition, the only inference which can be drawn is that either Committee is not in existence or it is an unregistered Committee. 157. Authorization by aggrieved person or Gram Panchayat can be given to a natural person or at least a juristic person (which includes natural person also), but an unregistered Committee is neither a natural person nor a juristic person, and thus, even if resolution passed by Gram Panchayat, Nandehar is taken as resolution in favour of Committee, the Committee being a non-juristic person is not competent to prefer the present writ petition. 158. Resolution of Gram Panchayat Nandehar, also appears to be in favour of persons whose names are mentioned in the resolution, though against their names, their status as office bearers of the Committee has also been indicated, and in any case this -95- 2026:HHC:49585 resolution is not in favour of the Committee, but in favour of members authorized by Gram Panchayat, Nandehar for legal battle in the matter. But petition has been filed by the Committee, and admittedly Committee has no proprietary right in the land proposed to be acquired or being acquired and, therefore, there is no threat of legal injury likely to be caused to the petitioner-Committee, creating a remedial right in favour of Committee, as available to an injured person and being a non-affected entity, Committee has no right to file present writ petition, as rights under Article 226 of the Constitution of India can be enforced only by aggrieved person, except in writ petitions, falling in the category of Habeas Corpus or Quo Warranto or writ petition is filed in public interest. Present writ petition, has not been stated to have been filed as a Public Interest Litigation, and thus, it has been registered as ordinary petition, which was never objected or got rectified by the petitioner, if the petitioner was pursuing the matter in public interest. It appears that Committee is a self-styled Committee of four persons only, who have their personal interest in the matter and, thus, petition appears to have been preferred to agitate the matter for personal reasons only. 159. We acknowledge that even petition under Article 226 of the Constitution can be invoked even by unregistered Cooperative -96- 2026:HHC:49585 Body, but in such case, aggrieved person or class of person must be incapable, suppressed or without means to approach the Court, whereas in present case, nothing material is available on record, so as to construe that the petitioner-Committee is preferring this petition on behalf of distressed, weaker, suppressed persons/class, who are not able and/or afford the litigation. 160. In view of above referred facts, circumstances and discussion, we are of the considered opinion that petitionerCommittee is not competent to file and maintain present writ petition, and for absence of locus of the petitioner-Committee, the petition is liable to be dismissed, being not filed by competent/aggrieved person. B. 161. Consideration and analysis on merit. Though we are of the opinion that petitioner-Committee is neither competent nor has locus to file and maintain present writ petition, however, we have also dealt with the objections/plea taken by the petitioner-Committee with regard to the acquisition process initiated by the respondent-State for providing land to the Airports Authority of India for expansion of Kangra Airport, and on merits also, for discussion here-in-after, we find that no ground for interference is made out at this stage. -97- 162. 2026:HHC:49585 We have gone through the pleadings and documents placed on record by the parties and have also considered the submissions of respective counsels for the petitioner-Committee, learned Advocate General, learned Deputy Solicitor General of India as well as counsel for respondent No. 6 and judgments cited by them in support of their respective contentions. 163. With regard to violation of Rule 3(1) of Land Acquisition, Rehabilitation and Resettlement (Social Impact Assessment and Consent) Rules, 2014 as well as Section 4(2) and 5 of LARR Act, 2013, it has been submitted that Notification for conducting Social Impact Assessment for the proposed expansion of Kangra Airport was issued on 28.02.2023. However, SIA team visited the spot on 27.02.2023 and 28.02.2023, i.e., prior to issuance of Notification and Publication of the same. 164. From the material on record, it is evident that possibility of development of Kangra Airport by its expansion was being considered since 2019, and vide Communication dated 07.10.2021, it was formally communicated by the Airports Authority of India to Principal Secretary (Civil Aviation) to Government of Himachal Pradesh. Thereafter, Airports Authority of India had requested Deputy Commissioner, Kangra, by Communication dated -98- 2026:HHC:49585 02.03.2022, to hand over the land adjacent to airport boundary, so that expansion work is taken up in future, and in continuation thereof, vide Advertisement dated 11.02.2023, limited to empanelled Social Impact Assessment partners/institutions, Expression of Interest (EOI) and financial bids for conducting Social Impact Assessment study were invited with last date of submission as 14.02.2023 and bids were opened on 15.02.2023, wherein SR Asia was recommended as an agency to be hired for Social Impact Assessment. On the same day, that is on 15.02.2023, request was submitted by Social Impact Assessment Unit to Principal Secretary (Civil Aviation) to Government of Himachal Pradesh for undertaking of Social Impact Assessment study in respect of expansion of Kangra Airport at Gaggal. Therefore, though formally work was awarded to SR Asia vide Communication dated 03.03.2023, however, it was well within knowledge of SR Asia and all concerned that it was the institution recommended by the Social Impact Assessment Unit to be hired for Social Impact Assessment. It is true that Notification for conducting Social Impact Assessment was issued on 28.02.2023, but it was finalized on 27.02.2023. In aforesaid facts and circumstances, there is every possibility that officials from SR Asia were in touch with the concerned authorities with regard to progress in the work, including issuance of Notification -99- 2026:HHC:49585 dated 28.02.2023 as well as recommendation and award of work to it, and in such situation, visiting by SIA team on the spot on 27.02.2023 and 28.02.2023 is by no means indicate any violation of law as alleged. It is also apt to record that there is no material on record to establish that SIA team visited the spot on 27.02.2023 or 28.02.2023. Further, except visiting the spot/village, no other activity undertaken by SR Asia has been alleged. 165. The petitioner has also failed to establish any prejudice caused to the Committee or public at large because of the spot visit by the team of SIA on 27.02.2023 and 28.02.2023. No report has been submitted on the basis of such visit, but the impact assessment survey has been completed by SR Asia by conducting public hearing after public notices. 166. It is also a matter of record that for commenting upon, either accepting or rebutting, the plea of the petitioner with respect to the methodology adopted and conduct of SR Asia and grounds of appraisal by the Multi-Disciplinary Expert Group as well as competency and expertise of its Technical Members, the appropriate person/entity would have been SR Asia and the MultiDisciplinary Expert Group, but they have not been arrayed as parties to the writ petition. Otherwise also, from material on record, -100- 2026:HHC:49585 including the response of the respondents, it is evident that no fault can be found in SR Asia's impact assessment report, which has been considered and deliberated by the Multi-Disciplinary Expert Group before recommending the expansion of the airport in its appraisal report. 167. Referring Section 4(4)(e) of LARR Act, it has been alleged that three alternative site locations were available for constructing new airport, which would displace the least number of families. Firstly, the Airports Authority of India was and is seeking land adjacent to existing airport for expansion of airport. It is not a project of new airport. Expansion of existing airports, have been considered by the Committee constituted by the Central Government, Civil Aviation Ministry, for additional safety measures by expanding existing airport, wherein Kangra Airport has also been included. Therefore, suggestion to shift the entire airport or to construct a new airport in alternative site, clearly depicts nonapplication of mind. Plea taken by the petitioner-Committee by referring Para No. 18 of Chapter 10 of SIA report regarding alternative sites is also misconceived, as in Para 1.5 of Chapter-1 of its report, SIA team has suggested to select suitable alternative site for project, but only after suggestions for technical team for site -101- 2026:HHC:49585 selection, and thereafter, report was considered by Multi-Disciplinary Expert Group, and appraisal report of the Expert Group was submitted to Government, wherein all issues, including public purpose, potential benefits of project, vis-a-vis social costs and adverse social impact, alternative sites, have been duly considered by the Expert Group. Expert Group has concluded and recommended that apparently the project to expand existing Kangra Airport serves the public purpose; the potential benefits of the project outweigh the social costs and adverse social impact; there was no less displacing option available with effective R&R plan, which could be chosen to complete the said project. therefore, as per the technical clearance of the proposal by Airport Authority of India to expand existing Kangra airport after constructing a bridge across Manjhi Khad was the only option left; Extent of Land proposed to be acquired for the expansion of Kangra Airport calculated to be 14775-47 hectare is bare minimum extent required for the project; and thus, the proposed project served the public purpose. Secondly, despite adverse social impact and adverse social costs, the potential benefits outweighed them; and the Expert Group has no hesitation in recommending the project because besides fulfilling the public interest considerations, its potential benefits would outweigh the social costs and social impacts. -102- 168. 2026:HHC:49585 In its response, AAI has also rejected alternative proposed sites with submission that the present proposal of Expansion of Runway is on same alignment which require the least span of the bridge over Manjhi Khad. The re-orientation suggested in Annexure P-7, is crossing through two branches of rivers Sarah and Manjhi Khad, required to construct larger span of bridge which may not structurally suitable to construct runway over it. The reorientation suggested such that even if the study on the alternative proposal turns out to be financially viable for GoHP, technically it may not be possible to carry out on an operational Airport. 169. In view of above material on record, it is apparent that alternative sites being suggested by the petitioner-Committee are not viable for expansion of airport. Two sites are far away and not adjacent to existing airport, and definitely selection of those sites, even if found suitable, would not have yield any result because project of the Central Government is expansion of existing airport. In case of shifting the airport to alternative sites, would have amounted to shift the airport from present place to another place, situated at a distance, which will be a project of construction of New Airport, for which no proposal has yet been received either from Central Government or Airports Authority of India. -103- 170. 2026:HHC:49585 Third proposal has also not been found suitable by the Multi-Disciplinary Committee as well as AAI on account of topographical condition and situation on that site. This Court cannot replace its opinion or petitioner’s opinion to the opinion of expert body involved in task of expansion of airport, including Airports Authority of India. Therefore, plea of petitioner to shift airport to alternative site or realign/reorient the expansion, is not sustainable. 171. Alternative sites have been considered by the Social Impact Assessment report as well as the appraisal thereof, and reasons for rejection of such proposal have also been given in the response filed by the AAI, but the same is not under challenge. 172. With respect to plea of alternative sites, it is also relevant to consider that it is not a case of construction or establishment of a new airport, but the fact remains that there is an existing airport and the Central Government has considered it fit for expansion, and it has been included in the nine airports recommended by the Committee constituted by the Central Government. Therefore, suggestions of alternative sites, which would be amounting to the construction of a new airport, are not acceptable, because in such an eventuality Kangra Airport will be out of the list of the airports -104- 2026:HHC:49585 selected for expansion, and for establishment of a new airport there is no sanction of the concerned authority, and shifting of the airport to another place would not be possible in the near future. 173. Multi-Disciplinary Expert Committee has considered the purpose going to be served by expansion of airport in detail and the material and information placed on record by respondents is also sufficient to hold that expansion of airport is definitely in the larger interest of public, and plea, that cost of expansion has not been compared or estimated with the benefit to be achieved and loss to be caused in monetary terms as well as social impact on account of displacement, is not relevant, as everything cannot be calculated in terms of money. 174. Plea of petitioner-Committee that expansion of airport is being done for benefiting the elite or high profile class of society is also misconceived, because as on date, maximum number of air travellers in India are from middle class or lower middle class and even the labour class is also travelling by air to reach their destination at the earliest and it is possible only because of affordable air fare due to frequency of air flights. It is apparent that in case airport is expanded, bigger planes would be able to land and take off, and definitely higher the number of passengers, lower the -105- 2026:HHC:49585 cost of traveling, which would be definitely beneficial to all classes of society and, thus, the plea taken by petitioner-Committee is not only unsustainable, but absurd. 175. Plea with regard to violation of mandate of Section 10(1) and 10(2), providing that no irrigated multi-cropped land shall be acquired under the Act, and such multi-crop irrigated land may be acquired under exceptional circumstances as a demonstrable last resort, is also not sustainable because from the material on record, as discussed supra, it is evident that the expansion of airport is in a larger interest of public, and expansion cannot be shifted to a land not adjacent to the airport, and therefore, there is no other option except to utilize the land adjacent to the airport irrespective of its category or classification for expansion of the airport in the larger public interest. 176. To substantiate the plea that no defence purpose is going to be served by expansion of Kangra Airport, petitionerCommittee has relied upon Communication dated 13.04.2018 issued by Wing Commander, J.D. Operations (ATS), whereby it has been informed that Indian Air Force (IAF) has no plans to expand Kangra Airport. Response of the respondent-State demolishes this plea, as it has been clarified in the reply that Kangra Airport is maintained by -106- 2026:HHC:49585 Airports Authority of India, but not by the Indian Air Force, and therefore, there is no question of any plan with the Indian Air Force for expansion of Kangra Airport. 177. No one can dispute that Kangra Airport is nearer to the international border, and in an emergency it can be used for Air Force operations at the time of war. From record it is evident that it is being used by Indian Air Force for mock drill as well as military exercises. Therefore, this airport has also military strategic importance. 178. With regard to aforesaid plea, it is also apt to record that letter relied upon by the petitioner-Committee was issued on 13.04.2018, whereas proposal of expansion of Kangra Airport has been initiated by Civil Aviation Ministry in the year 2019. Respondent-State has also placed on record Communications dated 11.07.2019, indicating that in the year 2019, Kangra Airport was being used for Indian Air Force drill. 179. Respondent-State has also placed on record Letter dated 25.08.2023 and 30.08.2023 received from Wing Commander, Senior Air Traffic Control Officer, addressed to Airport Director, Gaggal Airport, whereby it has been intimated that Air Force exercise -107- 2026:HHC:49585 was planned at Gaggal airfield on 12.09.2023, depicting that Kangra Airport is being used for operations of Indian Air Force aircraft. 180. With material on record, including aforesaid Communications, clearly depicts the importance of Kangra Airport to be used by the Defence Forces, including the Indian Air Force, and expansion of which will definitely enhance the possibilities of landing and taking off of the modern fighting aircraft as well as transport aircrafts of the Indian Air Force. Therefore, on this count also, plea of the petitioner-Committee is not acceptable. 181. Plea with regard to violation of Section 7 in constituting Multi-Disciplinary Expert Group on the ground the members of Expert Group were and are already part and parcel of acquisition proceedings, and thus, the group is not an independent agency, is also not sustainable because the land is not being acquired by the State for itself or by the persons involved in acquisition for their personal gain or their personal department. In both capacities, they are performing their official function, which are independent of each other. Unless any mala fide or personal interest in the expansion of airport of the members of the Expert Group is brought on record, it cannot be said that merely for the members were and are already -108- 2026:HHC:49585 involved in official capacity for acquisition of the land, the Expert Group loses its identity of independent agency. 182. Opposition of expansion of airport on the ground that Kangra District is located in seismic zone and sinking zone, is also not sustainable, as it is not a case of construction of new airport. The airport is already existing, and the project of expansion of the existing airport is being undertaken, and when airport is already functioning, there cannot be any reason of preventing its expansion on the ground that the area is situated in seismic zone. Otherwise also, it has been submitted on behalf of respondents that at the time of raising construction for expansion of airport, every care shall be taken with regard to the location of the area in seismic zone and sinking zone. It would also be apt to record here that District Bhuj in Gujarat is also highly sensitive seismic zone/sinking zone, but the airport has been constructed there, which is functioning in perfect working condition. Thus, this plea of the petitioner-Committee is also not sustainable. 183. In view of above discussion, plea with regard to violation of Section 15(2) of the LARR Act is also not sustainable. 184. Plea with regard to violation of Fundamental Rights guaranteed under Articles 14 and 21 of the Constitution, is also not -109- 2026:HHC:49585 sustainable in the given facts and circumstances, as held by the Apex Court in case Estate Officer, Haryana Urban Development Authority and Ors. vs. Nirmala Devi, referred supra. 185. Right of residence and livelihood envisaged under Article 21 of the Constitution of India, cannot be a ground in cases of land acquisition where land acquisition is inevitable in larger interest of public. In present case, as evident from the material on record, the expansion of Airport is in public interest, and acquisition for that purpose is inevitable, and thus, opposition of expansion of airport on this ground is not sustainable. 186. Objection with regard to the approval of Director General of Civil Aviation is not relevant, as the expansion plan has been submitted by Airports Authority of India only, and the process has been initiated on the basis of recommendations of Committee constituted by Civil Aviation Ministry of Central Government, and such proposal has been made by identification of Kangra Airport, suitable and necessary for expansion, as it has also come on record that the Airports Authority of India has categorically stated that in Himachal Pradesh, only Kangra Airport is suitable for expansion, but not Kullu or Shimla Airport. -110- 187. 2026:HHC:49585 With regard to clearance in terms of EIA Notification 2006 issued by Ministry of Environment and Forests, plea of the petitioner-Committee is not sustainable for the reason that in paragraph 2 of the said Notification, it has been provided that prior environmental clearance shall be necessary for starting the project or activity except for securing the land. Acquisition process is an act for securing the land, and therefore, in view of the exception carved out in the EIA Notification dated 14.09.2006 itself, plea of petitionerCommittee regarding violation of relevant provision in this regard of EIA Notification 2006, is not sustainable. 188. In case rejection of objections by the Land Acquisition Collector was illegal, the aggrieved persons were having the right to assail the same as provided in the scheme of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, and in case there was no remedy provided under the Act, such decision could have been assailed by invoking the power of judicial review under Article 226 of the Constitution of India, but from the material placed on record, no such challenge appears to have been laid by the any person, if someone was aggrieved. -111- 189. 2026:HHC:49585 The total land proposed to be acquired for extension of Kangra Airport is 147-75-87 hectares, out of which 122-66-23 hectares is private land, and 06-10-68 hectares is forest land. There is very less forest land involved in the project, whereas rest of the land is owned and possessed by private owners. 190. Existence of schools, hospitals, and commercial establishments has already been considered. Once the public purpose for the project stands established and that the project is required to be implemented in the larger interest of the public, the other smaller interests have to give way for the larger public interest. 191. Before parting, we would like to observe that though the EIA Notification of 2006 permits that land can be acquired for any project before environmental clearances, however, it has to be considered by the respondent State that thousands of crores of public money is likely to be spent for extension of the airport, and out of that, more than Rs. 460 crores have been disbursed in sequel to acquisition awards passed by the Land Acquisition Collector. But in case of non-acceptance of the techno-economic feasibility report, the entire public money shall be wasted. Therefore, irrespective of the fact that the EIA Notification of 2006 provides a window for -112- 2026:HHC:49585 acquisition of land for any project before environmental clearances, however, there is a difference between public entities and private entrepreneurs. A private entrepreneur may acquire or arrange land for the project before environmental clearances and the TEFR report, and on failure of getting environmental clearances, the private entrepreneur can utilize the land for any other purpose, but it will not be possible where the project proponent is a public authority spending huge public money for the project. 192. Therefore, we would like to suggest, request, and direct the respondent State to ensure completion of the TEFR report at the earliest, and take appropriate steps for environmental clearances in terms of the EIA Notification of 2006 immediately without waiting for completion of the acquisition process, because otherwise also the commencement of project work can be initiated only after having environmental clearances, for which the TEFR report is a prerequisite. 193. Needless to say that respondents shall ensure all necessary clearances in terms of EIA Notification dated 14.09.2006 and also TEFR (Techno-Economic Feasibility Report) by taking appropriate step for ensuring timely completion of expansion of Kangra Airport. -113- 194. 2026:HHC:49585 The writ petition is disposed of in above terms, along with all pending applications. (Vivek Singh Thakur) Judge 18th November, 2026 (Pardeep/Susheel) (Ranjan Sharma) Judge

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All HP HC judgments →

Real Estate advocates near the Himachal Pradesh High Court

Dealing with a similar matter? Send a free enquiry to advocates who handle it. Fees are agreed with the advocate directly.

All Real Estate advocates in India