16. Thus the writ petition is dismissed. However, the dismissal of the writ petition will not prevent the petitioner to take appropriate steps before the appropriate forum for his claim.
17. WPA 20466 of 2025 is dismissed.
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
S/L 9
13.02.2026
Court. No. 25
Suvayan/
Sourav
WPA 20466 of 2025
Dilip Kumar Konar
Vs.
The State of West Bengal & Ors.
Mr. Sourav Prasanna Mukherjee
Mr. Arka Mondal
…for the Petitioner.
Mr. Amal Kr. Sen, ld. AAG
Mr. Lal Mohan Basu
…for the State.
1.
The petitioner has filed the present writ application
praying for a direction upon the respondent authorities
for release of the outstanding due amount of Rs.
75,54,161/-. The petitioner submits that the respondent
authorities have issued four work orders for the four
schemes and as per the work order issued by the
respondent authorities, the petitioner has completed the
work and submit the bill for a total amount of Rs.
75,54,161/- but the same has not paid.
2. Learned counsel for the petitioner submits that by an
order dated September 4, 2025 when the writ petition is
moved before this Court the respondent authorities have
admitted an amount of Rs. 36 lakhs and in terms of the
order passed by this Court, the respondent authorities
have paid an amount of Rs. 31,80,753/- after deducting
the all tax and remaining amount has not been paid. In
compliance of the order dated September 4, 2025 the
respondent authorities have filed the report but the
report is contrary to the document which the petitioner
has disclosed and the documents relied by the
respondents is created after the order passed by this
Court.
3. The petitioner has relied upon the judgment in the case
of ABL International Ltd. & Anr. vs. Export
Credit Guarantee Corporation reported in AIR
Online 2003 SC 700 and submits that in an
appropriate case a writ petition as against State or an
instrumentality of a State arising out of a contractual
obligation is maintainable. He further submits that the
Hon’ble Supreme Court has also held that because of
some disputed questions of facts arise for consideration,
same cannot be a ground to refuse to entertain a writ
petition in all cases as the matter of rule. He further
submits that the Hon’ble Supreme Court has further held
that the writ petition involving the consequential relief of
monetary claim is also maintainable.
4. Learned counsel for the State submits that this prior to
filing of the writ application the petitioner has filed
previous writ application being WPA 12712 of 2025 and
the said writ petition was disposed of by this Court by an
order dated June 20,2025 wherein this Court directed
the petitioner to visit the office of the Block Development
Officer for putting the signature in the measurement
book. This Court also directed the petitioner to produce
the copy of the bills raised for receiving payment and this
Court directed the Block Development Officer to ensure
that payment is released in favour of the petitioner
within six weeks from the date of completion of the work.
Learned counsel for the State submits that the petitioner
has not challenged the said order.
5. Learned counsel for the respondents submits that in
spite of request made to the petitioner, the petitioner has
not come forward to sign measure book in spite he has
submitted the representation.
6. The learned counsel for the State submits that the
respondent authorities have issued four work orders
under four schemes.
As per the measurement book
available with the authorities though the petitioner has
not come forward to sign the measurement book, the
authorities have calculated the amount and released the
amount of Rs. 31,80,753/- after deducting the total tax.
The
petitioner
is
disputing
with
regard
to
the
measurement of the work and thus this Court in the writ
jurisdiction cannot decide the disputed question of fact
in the writ petition.
7.
In support of his submission, the learned counsel for the
respondents has relied upon the judgment in the case of
Union of India & Ors. vs. Puna Hinda reported in
(2021) 10 SCC 690 and submits that in the said case
the Hon’ble Supreme Court has categorically held that
the disputed could not be raised by way of a writ petition
on the disputed questions of fact. He prays for dismissal
of the writ application.
8. Heard the learned counsel for the respective parties
perused the materials on record and the documents
relied by the parties.
9. This is a second round of litigation.
On the earlier
occasion the similar prayer was made by the petitioner
for release of the amount. This Court by an order dated
June 20, 2025 has disposed of the writ application by
passing the following order:
“4. Upon hearing the parties and on perusal of
the documents placed before this Court it appears
that till the technical part is complied with, it
may not be possible for the Block Development
Officer to release payment. The signature of the
petitioner would be required in the measurement
book.
5. The petitioner is directed to visit the office of
the Block Development Officer for putting his
signature
in
the
measurement
book.
The
petitioner shall produce the copy of the bills
raised for receiving payment.
6. The Block Development Officer is directed to
ensure that payment is released in favour of the
petitioner within six weeks from the date of
completion of all necessary formalities.
7. The petitioner is directed to cooperate with the
Block Development Officer and the Block Medical
Officer of Health for the purpose of releasing the
final bill”
10. In terms of the order passed by this Court dated June 20,
2025, the Block Development Officer has requested the
petitioner to visit the engineering section of the Block
and to execute the measurement book and to resubmit
the bill in conformity with the record measurement in
consultation with the assigned engineer to facilitate the
release of the payment without any further delay.
11. The petitioner instead of appearing before the authorities
have submitted his representation and refused the sign
the measurement.
As the petitioner has not come
forward to sign the measurement book and finding no
other alternative, the measurement book available with
the respondent authorities, the authorities have verified
the bill submitted by the petitioner and finds that the
petitioner is entitled to get the total amount of Rs.
36,98,553/- and out of the said amount, an amount of
Rs. 5,17,800/- has been deducted being the tax payable
to the Government and the remaining amount of Rs.
31,80,753/- has been paid to the petitioner and there is
no amount due and pending against the petitioner.
12. The petitioner in his reply to the report filed by the
authorities, stated that if the measurement book
available with the petitioner is compared with the
measurement book of the respondents, the respondents
have reduced the quantity of work executed by the
petitioner and calculated less quantity of work than the
work executed by the petitioner.
13. The judgment relied by the petitioner in the case of ABL
International Ltd. & Anr. (supra), the Hon’ble
Supreme Court held that in an appropriate case the writ
petition against the state or instrumentalities of the State
arising out of the contract is maintainable but in the
present case, this Court finds that the petitioner is not
visiting the office of the respondent authorities to sign
the measurement book. Finding no other alternative, the
measurement book which was available with the
authorities, the authorities have calculated the amount
and came to the conclusion that the petitioner is entitled
to get an amount of Rs. 36,98,553/-.
14. Now the petitioner is relying upon his own measurement
book and submits that the measurement book relied by
the respondents is not tallying with the measurement
book available with the petitioner. The said disputed
question cannot go into by this Court in the writ
jurisdiction. In the case of Puna Hinda (supra) the
Hon’ble Supreme Court categorically held that:
“24. Therefore, the dispute could not be raised by
way of a writ petition on the disputed questions
of fact. Though, the jurisdiction of the High Court
is wide but in respect of pure contractual matters
in the field of private law, having no statutory
flavour, are better adjudicated upon by the forum
agreed to by the parties. The dispute as to
whether the amount is payable or not and/or
how much amount is payable are disputed
questions of facts. There is no admission on the
part of the appellants to infer that the amount
stands crystallised. Therefore, in the absence of
any acceptance of joint survey report by the
competent authority, no right would accrue to the
writ petitioner only because measurements
cannot be undertaken after passage of time.
Maybe, the resurvey cannot take place but the
measurement books of the work executed from
time to time would form a reasonable basis for
assessing the amount due and payable to the writ
petitioner, but such process could be undertaken
only by the agreed forum i.e. arbitration and not
by the writ court as it does not have the expertise
in respect of measurements or construction of
roads”
15. In the present case also the respondents are relying upon
the measurement book on the basis of which on
verification of the said measurement book has come to
the conclusion that the petitioner is entitled to get an
amount of Rs. 36,98,553/- and the respondents after
deducting the relevant tax release the said amount of Rs.
31,80,753/-. As regard the balance amount which the
petitioner is claiming in terms of the measurement book
with the petitioner, this Court cannot go into the said
disputed question of fact whether the petitioner has
actually executed the work which the petitioner is relying
upon or the measurement book which the respondents
are relied upon is not correct.
16. Thus the writ petition is dismissed.
However, the
dismissal of the writ petition will not prevent the
petitioner
to
take
appropriate
steps
before
the
appropriate forum for his claim.
17. WPA 20466 of 2025 is dismissed.
18. Urgent Xerox certified copy of this order, if applied for,
be given to the parties upon compliance of all necessary
formalities.
(Krishna Rao, J.)
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review