The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
14. 03.2023 has been received by the Chief Engineer on 05.04.2023 and the cover letter together with the endorsement (acknowledgment) has been placed before the Section 34 Court but the Section 34 Court has disbelieved this on the basis of the contents of the State counsel’s cover letter. The Section 34 Court has proceeded on the basis that learned State Counsel in the cover letter has held that the limitation is 3 months and condonation is permissible only for 30 days thereafter, in other words, 3 months limitation period which is the prescribed period and 30 days cap which is the condonable period have been set out by the learned State counsel in the cover letter itself. The Section 34 Court took the view that a learned State counsel who is responsible and who has taken pains to make it clear that said award has to be challenged within 3 months and that the condonable period is only 30 days, would not have slept over it till 05.04.2023. [19] It is in the aforesaid backdrop that the matter has come to this Court under Section 37. As already adverted to supra, the appeal fits into Section 37(1)(c) slot in the light of Chintels India Limited Vs. Bhayana Builders Private Limited reported in 2021 (4) SCC 602 which reiterates Essar Constructions Vs. NP. Rama Krishna Reddy reported in (2000) 6 SCC 94. Essar principle reiterated in Chintels is to the effect that refusal of a Section 34 C…
05. 04.2023 being the appropriate date in the case on hand. To be noted, this Court has arrived at 05.04.2023 as the reckoning date by applying Tecco Trichy as reiterated in Motilal more particularly paragraph 21 thereat which has been extracted and reproduced supra. This Section 37 Court deems it appropriate to add that Section 34 Court disbelieving 05.04.2023 acknowledgment solely by making an inference on the basis of contents of State counsel’s letter is in the realm of surmises and conjectures. [22] If 05.04.2023 is taken as the reckoning date, the period of delay to be condoned is 11 days according to the State, we find that this computation also may not be correct and it is 12 days. [23] As the Section 34 Court has proceeded on the basis that the delay sought to be condoned is beyond the cap of 30 days and on that basis rejected the CoD application, the reasons for delay from 05.04.2023 to 17.07.2023 has not been gone into. Ideally, under such circumstances, a remand would have been a good option but considering the length of time that has been spent on a CoD application, we deem it appropriate to consider the reason given by State. [24] As would be evident from the pleadings before us, the Chief Engineer of PWD, on receipt on 05.04.2023, has sent a communication on the same day to the Commissioner as regards challenge to the said award. Thereafter, the Section 34 petition h…
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
KABORAMBAM KABORAMBAM
SANDEEP SINGH
SANDEEP SINGH Date: 2025.10.14
18:33:58 +05'30'
(Supple 2) Sl. No. 3-7
IN THE HIGH COURT OF MANIPUR
AT IMPHAL
Arb. A. No. 1 of 2025
The Chief Engineer, Public Works Department (including NH &
NEC) Imphal
Vs.
M/S Keystone Infra Private Limited
Clubbed with
MC (Arb. A.) No. 5 of 2025
MC (Arb. A.) No. 6 of 2025 with
MC (Arb. A.) No. 7 of 2025 with
MC (Arb. A.) No. 2 of 2025
Appellant
Respondent
BEFORE
HON’BLE THE CHIEF JUSTICE MR. M. SUNDAR
HON'BLE MR. JUSTICE A. GUNESHWAR SHARMA
(ORDER)
(Order of the Court was made by M. Sundar, CJ)
08.10.2025
[1]
Heard Mr. M. Rarry, learned senior counsel instructed by Ms. M.
Nikita, learned counsel for appellant and Mr. HS Paonam, learned senior counsel
instructed by Mr. Purvesh Buttan and Ms. Th. Lekhakumari, learned counsel for
respondent.
[2]
Captioned statutory appeal was last listed on 06.10.2025 and the
following proceedings were made:
‘06.10.2025.
[1]
Captioned appeal is a statutory appeal under Section 37 of the
‘Arbitration & Conciliation Act, 1996’(hereinafter ‘A&C Act’ for the sake of
clarity and brevity).
[2]
An ‘Arbitral Award dated 20.02.2023’ (‘said award’ for the sake of
brevity) made by a ‘Arbitral Tribunal’(AT for brevity and to be noted AT
has been constituted by a sole Arbitrator) was assailed by the State
respondents in the 34 court with a ‘Condonation of Delay’(‘CoD’ for
brevity) application.
[3]
Delay sought to be condoned was 11 days. The CoD application
was dismissed by the 34 court in and by ‘an order dated
04.07.2025’(impugned order).
[4]
Assailing the impugned order of the 34 court, captioned statutory
appeal under section 37 has been filed by State.
[5]
As regards the appeal, learned senior counsel, Mr. M. Rarry,
appearing on behalf of learned counsel on record for the State submits
that it is under 37(1)(c) of A&C Act in the light of Chintels reported in
(2021) 4 SCC 602.
Crucial Dates and Events set out in a tabulation is as follows:
Sl.
Date
Events
Remarks
20.02.2023
said Award made by AT
--
14.03.2023
Cover letter of State counsel(under
covered of this letter said award is
said to have been sent to State)
--
05.04.2023
Afore-referred cover letter is said to This
was
have been received by the State.
disbelieved by
section
court
04.07.2025
34 courts dismissed the CoD Impugned
application vide impugned order.
order is under
challenge in
captioned
appeal
[6]
In the afore-referred tabulation, one date is the bone of contention
and that date is 05.04.2023. Section 34 court disbelieved the State
version, held the date of receipt to be 14.03.2023 and dismissed the CoD
application on the ground that it is beyond 30 days cap. To be noted,
CoD application was resisted by the claimant before the AT.
[7]
Claimant seeks time to get instruction on the date of receipt of said
Award by the claimant.
[8]
[3]
At request of claimant, list on 08.10.2025.’
The afore-referred proceedings dated 06.10.2025 shall now be read
as an integral part and parcel of this order. This means that short forms,
abbreviations and short references used in the earlier proceedings dated
06.10.2025 shall continue to be used in the instant order also.
[4]
Learned senior counsel on both sides submitted without any
disputation that facts and dates have been correctly captured in 06.10.2025
proceedings.
[5]
As would be evident from the earlier proceedings, an Arbitral Award
made more than two and half years ago, to be precise, on 20.02.2023, i.e., ‘said
award’ has not been tested by the Section 34 Court, as the Section 34 petition
filed on 17.07.2023 has seen tributaries and orders owing to the same having
been filed with a CoD prayer qua 11 days delay.
[6]
The bone of contention is, while State contends that said award
was received only on 05.04.2023 (under cover of State counsel’s letter dated
14.03.2023), claimant contends to the contrary, i.e., that soft copies of the award
was e-mailed to both the claimant and the State by the Hon’ble AT on
20.02.2023, the same was received instantaneously and therefore, 20.02.2023
should be the reckoning date.
[7]
Before we proceed further, we deem it appropriate to write that we
would be referring to the ‘appellant’ before us as ‘State’ and the ‘respondent’
before us as ‘contractor’ for the sake of convenience and clarity.
[8]
A contract dated 12.06.2014 for improvement of road between
Bishnupur and Nungba from km 0.000 to km 89.520 is the nucleus of the entire
matter. This contract shall be referred to as ‘said contract’ for the sake of
convenience and clarity. This work shall be referred to as ‘said work’ also for the
sake of convenience and clarity.
[9]
There is no disputation or disagreement between State and
Contractor that there is an arbitration clause in the Special Conditions of Contract
(SCC) as between the parties. To be noted, SCC forms part of said contract. The
said work has been completed but there is allegation of delay. To be noted, time
frame for completing said work is 36 months (3 years). It is also to be noted that
the value of the contract is a little over 92.25 crores INR (Rs. 92,25,04,156.23/to be precise).
[10]
On arbitrable disputes having erupted between the contractor and
the State, arbitration clause was triggered. A Sole arbitrator constituted the
Arbitral Tribunal (AT) and AT after full contest, made an award in favour of the
claimant to the tune of a little over Rupees 96.16 crores (Rs. 96,16,28,522/- to
be precise). The counter claim of the State was negatived wholly by the AT.
[11]
State filed a petition under Section 34 (as alluded to supra) and this
Section 34 petition was filed with a delay which is 11 days according to State,
11 days has been computed by State by taking 05.04.2023 as the date of receipt
of award for the purposes of 34(3) of A&C Act. As already alluded to supra,
contractor contends that date of receipt of award should be 20.02.2023, i.e., the
date on which soft copies were e-mailed to both contractor and State by the
Hon’ble AT.
[12]
Multiple pleadings of different hues and shades have been made
before the Section 34 Court. The reason is, both parties sought amendments of
pleadings in CoD application. The crux and gravamen of the matter is while State
originally pleaded that the date of receipt of said award is 14.03.2023 and
computed 120 days therefrom, it subsequently changed its stand and took the
plea that the said award was received by the Chief Engineer of the Public Works
Department (PWD) only on 05.04.2023 under cover of State counsel’s letter
dated 14.03.2023. In this regard, this Court is acutely conscious that ‘120 days’
is plainly incorrect as it is ‘3 months and 30 days’ but it is not necessary to dilate
on this.
[13]
The details of the pleadings before the Section 34 Court can be put
in a nutshell. State sought amendment of its pleading in the aforesaid manner
vide an amendment application dated 21.08.2023 and it also sought amendment
of the rejoinder vide another amendment application dated 27.10.2023. Both
these amendment applications were allowed by the Section 34 Court by an order
dated 08.01.2024 on terms, i.e., on terms of Rs. 10,000/- (Rupees Ten
Thousand), the same has been paid by State, accepted by contractor and the
matter has been given legal quietus. To put it differently, contractor has not
chosen to assail the orders allowing amendment applications.
Be that as it may, the Contractor also chose to amend the pleadings
which according to the contractor is consequential qua amendments by State,
the same was also allowed but State assailed the amendment order of the Section
34 Court of the contractor. This was assailed by the State vide CRP (C.R.P. Art.
227) No. 36 of 2024 and the same came to be dismissed by a Hon’ble Single
Judge of this Court in and by a detailed order dated 16.01.2025. It may really
not be necessary to dilate further on these aspects of the matter as the pleadings
stood frozen post amendments and the matter was heard out by the Section 34
Court on the basis of the amended pleadings.
[14]
At the outset, it is necessary to write that the Section 34 Court did
not accept the contractor’s plea that 20.02.2023 is the date of receipt of award.
The reason as can be culled out from the impugned order of the Section 34 Court
is, the contents of the cover e-mail under which the soft copies of the said award
were sent to the contractor and the State. The Section 34 Court has construed
the contents of the e-mail as a disclaimer, as it makes it clear that the e-mail is
only for the purposes of information and that a signed hard copy is being
couriered to both parties. This part of the order means that e-mail is no
compliance with Section 31(5) of A&C Act but the same has not been assailed by
the contractor. To be noted, law is now settled that Section 31(5) requirement is
not merely procedural but a matter of substance.
[15]
The above leads us to the question as to whether the date of receipt
is 17.03.2023 as originally contended or it is 05.04.2023 as contended post
amendment of pleadings. Once pleadings are amended, the original pleadings
stand effaced. The pleading as amended to which quietus has been given will
govern the parties.
[16]
In the case on hand, as would be evident form the allusion supra,
the amendments were given quietus and therefore the parties stood governed
by the amended pleadings.
[17]
Learned senior counsel for the contractor contended that the
pleadings have not been amended in its entirety and only sub-clauses (a) and
(b) of para 1.7 of the original pleadings stood amended, whereas sub paragraph
(c) and (d) were not amended. We carefully considered this arguments. This
point turns on a very simple issue is our considered view. The issue is in cases
of Government, the award should be received by a person who is in full control
of the arbitration proceedings and who is in a position to take a decision about
assailing the award under Section 34 of A & C Act. This principle was laid down
by Hon’ble Supreme Court in M/S. Motilal Agarwala Vs. State Of West
Bengal & Anr. reported in Neutral Citation of Hon’ble Supreme Court being
2025 INSC 1062. In Motilal, a similar issue arose and after considering all the
facts and circumstances of the case, Hon’ble Supreme Court made it clear that
the term ‘party’ occurring in Section 34(3) is ‘party’ within the meaning of Section
2(1)(h) of A & C Act. It was further elucidated that parties within the meaning of
Section 2(1)(h) in the context of Government should be understood as a person
who has knowledge and is in the best person to understand and appreciate an
award and more particularly to take a decision for its challenge. In this regard,
Hon’ble Supreme Court reiterated the principle laid down in Union of India Vs.
Tecco Trichy Engineers & Contractors reported in (2005) 4 SCC 239. In
Tecco Trichy, the arbitral award was served on 12.03.2001, but the service on
the person having control over the arbitral proceedings was on 19.03.2001 and
19.03.2001 was taken as the relevant reckoning date. The judgement of Hon’ble
Supreme Court in Motilal which reiterates Tecco Trichy is very instructive and
we respectfully follow the same and for the sake of convenience, we deem it
appropriate to extract and reproduce paragraph 21 of Motilal, which reads as
follows:
‘21. What exactly constitutes a “party”, in the context of Government, has
been interpreted by this Court in Union of India vs. Tecco Trichy Engineers &
Contractors, reported in (2005) 4 SCC 239. In the said decision, this Court
held that in order to constitute an effective service, a copy of an award, where
such party is the Ministry of a particular Department, is to be delivered to a
person who has the knowledge and is the best person to understand and
appreciate an award and more particularly, to take decision for its challenge.
We are of the view that the authorised representative of the State could not
have taken the final decision to challenge the award. It is only the Secretary
of the concerned Department or the Executive Engineer, who could be said to
be the competent authority to take a decision as to whether the award could
be challenged or not.’
[18]
This Court also deems it appropriate to refer to an earlier judgment
of the Hon’ble Supreme Court rendered in Benarsi Krishna Committee and
others Vs. Karmyogi Shelters Private Limited reported in (2012) 9 SCC
496. In Karmyogi, Hon’ble Supreme Court made it clear that term ‘party’
occurring in Section 34(3) is ‘party’ within the meaning of Section 2(1)(h). As
already alluded to supra, party within the meaning of Section 2(1)(h) with regard
to Government has been explained in Motilal to be a person who has control
over the arbitral proceedings and who is in a position to appreciate the award
and also take a decision with regard to challenge to the award under Section 34.
In the case on hand, ‘party’ is Chief Engineer of PWD and this is clear as day light
from proceedings of AT and said award. The cover letter of State counsel dated
14.03.2023 has been received by the Chief Engineer on 05.04.2023 and the cover
letter together with the endorsement (acknowledgment) has been placed before
the Section 34 Court but the Section 34 Court has disbelieved this on the basis
of the contents of the State counsel’s cover letter. The Section 34 Court has
proceeded on the basis that learned State Counsel in the cover letter has held
that the limitation is 3 months and condonation is permissible only for 30 days
thereafter, in other words, 3 months limitation period which is the prescribed
period and 30 days cap which is the condonable period have been set out by the
learned State counsel in the cover letter itself. The Section 34 Court took the
view that a learned State counsel who is responsible and who has taken pains to
make it clear that said award has to be challenged within 3 months and that the
condonable period is only 30 days, would not have slept over it till 05.04.2023.
[19]
It is in the aforesaid backdrop that the matter has come to this
Court under Section 37. As already adverted to supra, the appeal fits into Section
37(1)(c) slot in the light of Chintels India Limited Vs. Bhayana Builders
Private Limited reported in 2021 (4) SCC 602 which reiterates Essar
Constructions Vs. NP. Rama Krishna Reddy reported in (2000) 6 SCC 94.
Essar principle reiterated in Chintels is to the effect that refusal of a Section 34
Court to condone delay in filing a Section 34 petition will tantamount to refusal
to set aside an award and therefore, the same can be challenged vide a statutory
appeal under Section 37 and therefore it snugly fits into 37(1)(c). It is in this
scenario and setting that we heard out the captioned matter which is a statutory
appeal.
[20]
This Court also notices that the Section 34 Court has made it clear
that 3 months occurring in 34(3) should not be construed as 90 days. This aspect
of the matter is correct and we deem it appropriate to make it clear that periods
can be expressed in different units, it can either be months or days. As regards
the manner for computing the periods when expressed in different units, when
the period is expressed in terms of months, the same date in the next English
calendar month will be one month and likewise it would be for two months or
three months. Therefore, one month may or may not be 30 days depending on
the calendar months over which the two months spread. This is regarding period
as defined in the Limitation Act, 1963 (Act No. 36 of 1963) vide 2(j). To be noted
2(j) defines ‘period of limitation’ as well as ‘prescribed period’. As regards the
condonable period, which occurs vide proviso to 34(3), the same has been
expressed in terms of another unit, namely, days. In terms of condonable period,
it is 30 days. Therefore, computation of condonable period will be in terms of
number of days and not in terms of one month. It has become necessary to make
this clarification so that there is absolute specificity and clarity with regard to
matters arising under Section 34.
[21]
It was also argued that even 1 day delay beyond the condonable
period of 30 days is not permissible and there can be no disputation or quarrel
on this proposition. In this view of the matter, if 14.03.2023 is taken as the
reckoning date, the condonation will be beyond the tolerance period or beyond
the cap but if it is 05.04.2023, it is well within the tolerance period, i.e., cap of
30 days. This Court has already set out this dispositive reasoning with regard to
05.04.2023 being the appropriate date in the case on hand. To be noted, this
Court has arrived at 05.04.2023 as the reckoning date by applying Tecco Trichy
as reiterated in Motilal more particularly paragraph 21 thereat which has been
extracted and reproduced supra. This Section 37 Court deems it appropriate to
add that Section 34 Court disbelieving 05.04.2023 acknowledgment solely by
making an inference on the basis of contents of State counsel’s letter is in the
realm of surmises and conjectures.
[22]
If 05.04.2023 is taken as the reckoning date, the period of delay to
be condoned is 11 days according to the State, we find that this computation
also may not be correct and it is 12 days.
[23]
As the Section 34 Court has proceeded on the basis that the delay
sought to be condoned is beyond the cap of 30 days and on that basis rejected
the CoD application, the reasons for delay from 05.04.2023 to 17.07.2023 has
not been gone into. Ideally, under such circumstances, a remand would have
been a good option but considering the length of time that has been spent on a
CoD application, we deem it appropriate to consider the reason given by State.
[24]
As would be evident from the pleadings before us, the Chief
Engineer of PWD, on receipt on 05.04.2023, has sent a communication on the
same day to the Commissioner as regards challenge to the said award.
Thereafter, the Section 34 petition has been finalized and the same has been
filed. In this view of the matter, the 12 days delay explained as time consumed
in preparing, finalizing and filing the Section 34 petition is clearly condonable.
Therefore, we have no difficulty in holding that the order of the Section 34 Court
rejecting the CoD application deserves to be interfered with.
[25]
We make the following order:
(i)
The impugned order of the Section 34 Court dated 04.07.2025
made in Judl. Misc. Case No. 37 of 2023 is set aside;
(ii)
The delay of 12 days in filing the Section 34 petition by the State
is condoned;
(iii)
The Section 34 Court is requested to take up the Section 34
petition of the State, consider the same on its own merits in
accordance with law and render a verdict as expeditiously as the
business of the Court would permit;
(iv)
With regard to the above, we deemed it appropriate to write that
the statute itself prescribes a period for disposal of 34 petition and
that is contained in Sub-section (6) of Section 34;
(v)
Sub-section (6) of Section 34 talks about 1 year from the date on
which Sub-section (5) notice is served, but Sub-section (5) notice
has been held to be not mandatory in State of Bihar Vs. Bihar
Rajya Bhumi Vikas Bank Samiti reported in (2018) 9 SCC
472;
(vi)
As Sub-section (5) notice has been held to be not mandatory, now
the 1 year reckoning date will be from the date of filing of the
petition;
(vii)
The Section 34 Court would do well to dispose of the Section 34
petition on its own merits and in accordance with law as
expeditiously as its business would permit as directed supra
keeping in mind Sub-sections (5), (6) of Section 34 in the light of
ratio of Hon’ble Supreme Court in Bhumi Vikas were expeditious
disposal of Section 34 petition has also been emphasized;
(viii)
Captioned appeal is allowed with aforementioned observations.
Consequently, captioned miscellaneous cases are also disposed of
as closed. There shall be no order as to costs.
Sandeep
JUDGE
CHIEF JUSTICE
This page is for informational and research purposes only and does not constitute legal advice.