$~4 & 5
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
+
CS(OS) 231/2017 & I.A. 6377/2017, I.A. 12078/2017, I.A. 4629/2021
CENTRAL ELECTRONICS LIMITED & ANOTHER .....Plaintiffs
Through:
Appearance not given
versus
LIVE MEDIA & PUBLISHERS PVT. LTD. & OTHERS
.....Defendants
Through: Mr. Pranav Sachdeva, Mr.Sanyam
Jain, Ms.Khushboo Singhal, Mr.
P.Rohit Ram, Advocates
+
CS(OS) 31/2018 & I.A. 1157/2018, I.A. 3602/2018, I.A. 4627/2021,
I.A. 2190/2023, I.A. 16934/2025
CENTRAL ELECTRONICS LIMITED & ANOTHER
.....Plaintiff
Through:
Appearance not given
versus
LIVE MEDIA & PUBLISHERS PVT. LTD. & OTHERS
.....Defendant
Through: Mr. Pranav Sachdeva, Mr.Sanyam
Jain, Ms.Khushboo Singhal, Mr.
P.Rohit Ram, Advocates
CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
%
CS(OS) 231/2017 etc.
ORDER
27.01.2026
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 03/02/2026 at 12:33:01
1.
The present Suits are for damages for causing defamation.
2.
During the pendency of the present Suits, the parties have entered into
a settlement before the Delhi High Court Mediation and Conciliation Centre
vide a Settlement Agreement dated 05.12.2025. The Settlement Agreement
is being reproduced in its entirety and the same reads as under:
“
SETTLEMENT AGREEMENT
This Settlement Agreement is entered on 05.12.2025.
BETWEEN
CENTRAL ELECTRONICS LIMITED (CEL), REGD.
OFFICE AT 8th FLOOR, 823, ANSAL VIKAS DEEP
BUILDING, PLOT NO. 18, DISTRICT CENTRE,
LAXMI NAGAR, DELHI-110092 & ALSO AT SITE-IV,
INDUSTRIAL
AREA,
SAHIBABAD,
UTTAR
PRADESH (201010) THROUGH ITS AUTHORISED
REPRESENTATIVE SH. RAJAT GARG, GENERAL
MANAGER (HRD) AUTHORISED VIDE AUTHORITY
LETTER DATED 05.12.2025. THE COPY OF SAID
AUTHORITY LETTER IS ANNEXED HEREWITH AS
ANNEXURE-A.
(HEREINAFTER REFERRED TO AS FIRST PARTY)
(WHICH EXPRESSION SHALL MEAN AND
INCLUDE
ITS,
SUCCESSORS,
LEGAL
REPRESENTATIVES,
ADMINISTRATORS,
EXECUTORS, AND ASSIGNEE ETC.)
AND
1. LIVE MEDIA AND PUBLISHERS PRIVATE
LIMITED, REGD. OFFICE AT: 1004, NEW DELHI
HOUSE, 27 BARAKHAMBA ROAD, NEW DELHI110001,
THROUGH
ITS
AUTHORISED
REPRESENTATIVE
MR.
ANIL
KUMAR
CS(OS) 231/2017 etc.
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 03/02/2026 at 12:33:01
AUTHORISED VIDE AUTHORISATION LETTER
DATED 24.02.2025. THE COPY OF SAID
AUTHORISATION
LETTER
IS
ANNEXED
HEREWITH AS ANNEXURE-B.
2.
SH. ANIL KUMAR, EDITOR-IN-CHIEF OF
LIVE MEDIA AND PUBLISHERS HAVING REGD.
OFFICE AT: 1004, NEW DELHI HOUSE, 27,
BARAKHAMBA ROAD, NEW DELHI-110001.
3.
DR. RASHMI SINGH, EDITOR OF TELECOM
LIVE, LIVE MEDIA AND PUBLISHERS PVT. LTD.,
HAVING REGD. OFFICE AT: 1004, NEW DELHI
HOUSE, 27, BARAKHAMBA ROAD, NEW DELHI110001
THROUGH
HER
AUTHORIZED
REPRESENTATIVE
MR.
ANIL
KUMAR
AUTHORIZED VIDE AUTHORITY LETTER DATED
05.12.2025. COPY OF THE SAME IS ANNEXED
HEREWITH AS ANNEXURE-C.
(HEREINAFTER COLLECTIVELY REFERRED TO
AS THE “SECOND PARTY”) (WHICH EXPRESSION
SHALL
MEAN
AND
INCLUDE
THEIR
SUCCESSORS,
LEGAL
REPRESENTATIVES,
ADMINISTRATORS, EXECUTORS AND ASSIGNS
ETC.)
[The First Party and the Second Party shall be
collectively referred to as the
“Parties” and individually as “Party”]
WHEREAS the First Party was established in 1974,
with the objective of commercially exploiting
indigenous technologies developed by National
Laboratories and R&D Institutions in the country. The
First Party has developed a number of products for the
first time in the country through its own R&D efforts
and in close association with the premier National &
CS(OS) 231/2017 etc.
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 03/02/2026 at 12:33:01
International
Laboratories
including
Defense
Laboratories. The First Party is a Company engaged
in the field of production of solar photo voltaic panels,
high efficiency solar cells and establishment of solar
power plants and service centres.
AND WHEREAS the Second Party is a Private Limited
Company engaged in the business of publishing
magazines and online news on the telecom, IT and
infrastructure sectors.
AND WHEREAS in February of 2017, the Second
Party received certain internal information belonging
to the First Party from an erstwhile employee of the
First Party and subsequently published articles in the
magazine, “TelecomLive” about the First Party as
well as its erstwhile Chairman & Managing Director
Dr. Nalin Singhal.
AND WHEREAS according to the First Party, it was
not been given sufficient time to respond to the
allegations levelled against it prior to its publication
and the article/material was published. The said
published material was found objectionable by the
First Party and therefore the First Party alongwith
said Dr. Nalin Singhal (erstwhile Chairman &
Managing Director) filed a civil suit before the
Hon’ble High Court of Delhi, being CS (OS) 231 of
2017, titled as Central Electronics Ltd. & Anr. Vs. Live
Media Publishers Pvt. Ltd. & Ors.
AND WHEREAS the said civil suit was first listed on
23.05.2017, on which date the Hon’ble Court was
pleased to restrain the Second Party from further
publishing, circulating or propagating either
physically or digitally the article that was published at
page 41 in their February 2017 magazine. AND
WHEREAS the First Party filed a complaint case being
CS(OS) 231/2017 etc.
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 03/02/2026 at 12:33:01
Ct. Cases 13433/2017 (CNR-DLND020090012017)
against the Second Party, which is pending before
Judicial Magistrate First Class-05, Patiala House
Courts, New Delhi.
AND WHEREAS the Second Party again received
certain internal and confidential information,
belonging to the First Party, from an erstwhile
employee of the First Party and subsequently published
another article in the magazine, “TelecomLive” in the
month of January, 2018, which contained certain
allegations against the First Party and its erstwhile
Chairman & Managing Director Dr. Nalin Singhal.
AND WHEREAS aggrieved by the said article
published in the magazine, “TelecomLive” in January,
2018, the First Party, alongwith said Dr. Nalin Singhal
(erstwhile Chairman & Managing Director) preferred
another civil suit before the Hon’ble High Court of
Delhi, being CS (OS) 31 of 2018, titled as Central
Electronics Ltd. Vs Live Media Publishers & Ors. The
Hon’ble Court, vide order dated 24.01.2018 granted
an ex-parte injunction order thereby restraining the
Second Party from further publishing, circulating or
propagating either physically or digitally the said
article published in January, 2018.
AND WHEREAS the First Party also filed a case in
Ghaziabad District Court against the Second Party,
being Complaint Case No. 625 of 2018 (CNRUPGZ040145522018), which is pending before Addl.
Chief Judicial Magistrate, Ghaziabad.
AND
WHEREAS during the pendency of the aforesaid two
suits i.e. CS (OS) 231 of 2017 and CS (OS) 31 of 2018,
said Dr. Nalin Singhal, the erstwhile Chairman &
Managing Director of the First Party (Plaintiff No.2 in
both the said suits) entered into a compromise with the
Second Party vide settlement Deed dated 21.02.2025
CS(OS) 231/2017 etc.
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 03/02/2026 at 12:33:01
whereby he agreed to withdraw all the suits and
complaints filed by him against the Second Party.
AND WHEREAS as per the First Party, no major
disputes now survive between the First Party and the
Second Party in light of the said compromise between
Dr. Nalin Singhal and the Second Party, as the said
articles were primarily targeted towards Dr. Nalin
Singhal with minimal allegations against the First
Party.
AND WHEREAS CS (OS) 231/2017 & CS (OS)
31/2018 was referred to Samadhan, Delhi High Court
Mediation and Conciliation Centre by Hon’ble Delhi
High Court vide order dated 25.02.2025 for resolving
the disputes between the Parties.
AND WHEREAS Ms. Isha Khanna, Advocate was
assigned the matter to act as a Mediator to facilitate
the Parties in resolving their disputes for mediation by
SAMADHAN.
TERMS AND CONDITIONS
I. The Second Party unconditionally withdraws all the
allegations made against the First Party and tenders
unconditional apology for harm caused to the First
Party. It is agreed by the Parties that this shall be
without prejudice to the rights and contentions of both
the Parties in the pending court cases against the third
parties and shall not be taken as any comment on the
stand of either of the Parties with respect to each other
in the said pending cases.
II. The Second Party agrees to immediately
withdraw/delete the aforesaid two articles and/or any
other article(s) that may have a mention of the First
Party, whether published in print, online or any other
CS(OS) 231/2017 etc.
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 03/02/2026 at 12:33:01
medium and to take all necessary steps to ensure their
removal from public access.
III. The Second Party further agrees that neither of its
constituents i.e. Live Media Publishers Private
Limited, Mr. Anil Kumar, Dr. Rashmi Singh, or their
successor companies/entities/individual, while being a
part of Second Party or while working in any other
company/organisation or in any other capacity, shall
or shall cause to publish, distribute, or disseminate any
articles, reports, or content of any kind concerning the
First Party, or allude to it, in the future, whether
directly or indirectly, without the express written
consent of the First Party.
IV. The First Party further agrees and undertakes to
withdraw the following Criminal Cases filed against
the Second Party within 30 days of signing of the
present Settlement Agreement: i. CT CASE 13433/2017
pending before Judicial Magistrate First Class-05,
Patiala House Court, New Delhi and the next date of
hearing is 09-01-2026. ii. CC NO. 625/2018 pending
before Additional Chief Judicial Magistrate,
Ghaziabad, Uttar Pradesh and the next date of hearing
is 09.12.2025.
V. The Hon’ble Court may consider refund of the court
fees to the First Party in terms of Section 16 of the
Court Fees Act, 1870 read with Section 89 of the Code
of Civil Procedure. It is further agreed by the Second
Party that if the amount of court fees ordered to be
refunded is less than the court fees paid alongwith the
aforesaid suits, then it will pay the said differential
amount to the First Party so as to make it equivalent to
the court fee paid by the First Party in the aforesaid
two suits.
VI. The Second Party further agrees to pay Rs. 50,000
CS(OS) 231/2017 etc.
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 03/02/2026 at 12:33:01
(Rupees Fifty Thousand only) received from the First
Party towards the costs imposed on the First Party by
the Hon’ble High Court of Delhi in pursuance to its
order dated 20.05.2024.
VII. The Parties further agree that the instant
settlement agreement shall not impact the rights of the
First Party to take any action against any person found
to have provided the aforementioned internal and
confidential information to the Second Party and that
this agreement shall not be construed to have absolved
such person of any wrongdoing.
VIII. The Parties further agree that the instant
agreement is confidential and that the Second Party
shall not disclose the settlement agreement or the terms
thereof to any third party unless legally bound to do so.
IX. The Parties undertake to present themselves before
the Hon’ble Court confirming the terms of the present
Settlement Agreement and to make a joint request to
the Hon’ble High Court to decree the Suit being CS
(OS) 231/2017 & CS (OS) 31/2018 in view of the
present Settlement Agreement.
X. The Parties agree that neither of the Parties shall be
left with any claim against each other regarding the
subject matter of the present dispute and shall not raise
any claim against each other in future qua the same.
XI. Both the Parties confirm that no other case has
been filed by them against the other with respect to the
subject matter of the present case and in an event, it is
found that any judicial, quasi-judicial or
administrative proceeding has got initiated which is
not stated herein, then the said Party, on whose
instance the proceedings got initiated, shall withdraw
the same promptly in terms of the present Settlement
CS(OS) 231/2017 etc.
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 03/02/2026 at 12:33:01
Agreement.
XII. The Parties further agree that the present
Settlement Agreement has been read over by them and
they have agreed to the present terms after thoroughly
reading and understanding the same by their mutual
irrevocable voluntary consent without any force,
coercion, misrepresentation, undue influence, pressure
from any corner and will not retract such consent at
any stage in any manner whatsoever.”
3.
It is stated by the learned Counsel for the Plaintiff that the Plaintiff
has received a cheque bearing No.823767, dated 27.01.2026, from the
Defendants for Rs.50,000/-.
4.
This Court has gone through the Settlement Agreement which is legal
and lawful.
5.
In view of the fact that settlement has been arrived at between the
Parties, the Suits are disposed of in terms of Order XXIII Rule 3 of CPC and
the Settlement Agreement entered into between the Parties.
6.
Pending applications, if any, also stand disposed of.
7.
Let the Decree Sheets be prepared accordingly.
8.
The Parties shall be bound by the terms of the Settlement Agreement.
9.
The Court Fee be refunded in accordance with Section 16 of the Court
Fees Act, 1870.
SUBRAMONIUM PRASAD, J
JANUARY 27, 2026
Rahul
CS(OS) 231/2017 etc.
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 03/02/2026 at 12:33:01
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review