Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
23.11.2026
Court No. 12
Item No.01
Cp/Sandip
MAT 1959 of 2026
With
CAN 1 of 2026
Carbon Resources Private Limited & Anr.
Vs.
Steel Authority of India Limited & Ors.
Mr. Jishnu Chowdhury, Sr. Advocate
Mr. Ankit Kanodia
Mr. Risabh Karnani
Mr. Deep Basak
Mr. Shovan Ojha
Ms. Tulika Roy
Ms. Megha Agarwal
…… for the Appellants.
Mr. Kishore Datta, Sr. Advocate
Mr. Lakshmi Kanta Pal
Ms. Sumita Shaw
……. for the Durgapur Steel Plant.
Ms. Mary Datta
……for the Union of India.
1. It is submitted that the defect has been cured.
2. This is an appeal against the order dated November
19, 2026, passed in WPA 32253 of 2026. By the
order impugned dated November 19, 2026, the
learned Single Judge dismissed the writ petition.
The appellants/writ petitioners (hereinafter referred
to as ‘the appellants’), filed the writ petition
challenging a decision of the Steel Authority of India
Limited (hereinafter referred to as ‘SAIL’), rejecting
the technical bid of the appellants.
3. The Durgapur Steel Plant, (SAIL) published a tender
notice through Government – e-marketplace (GeM)
for supply of Petroleum Coke (V2). The appellant
participated
in
the
said
tender
process
and
submitted its bid. Along with its technical bid, the
appellant also submitted a bank guarantee on
October 8, 2026. The address mentioned in the
bank
guarantee
was
incorrect.
The
following
address was incorporated instead of the correct
address:
“TO
M/S STEEL AUTHORITY OF INDIA LTD.
SAIL-DAP
CHANDRAPUR FERRO ALLOY PLANT
CHANDA-MUL-ROAD
CHANDRAPUR-442401 (MAHARASTRA)”
4. The IFSC Code of the beneficiary’s bank was also
wrongly mentioned as SBIN0000346.
5. The technical bid was opened on October 23, 2026
and the aforesaid defect contained in the bank
guarantee
was
detected.
It
appears
that
the
appellant obtained the said bank guarantee on
October 8, 2026 and uploaded it in the portal of
GeM on October 15, 2026. The evaluation of the
technical bid was completed on November 10, 2026.
6. On October 28, 2026, the amended bank guarantee
was
furnished.
On
November
12,
2026,
the
technical bid of the appellant was rejected by SAIL
with the following comment.
“For EMD, the party has uploaded BG dt
08.10.2026 of Rs.70.15 lacs submitted in
favour of SAIL-CFAP in GeM and original hard
copy of the same BG received in DSP. Later an
original hard copy of same BG with amendment
dt 28.10.2026 in favour of SAIL-DSP received in
DSP on 28.10.2026. As original BG dt
08.10.2026 Is not in favour of SAIL-DSP and
amended BG issued on 28.10.2026 which is
after ToD and also not uploaded on GeM on or
before ToD, techno-commercial offer submitted
by the party has not been considered for
evaluation and their offer/bid has been rejected
because of non-submission of requisite EMD on
or before ToD.”
7. It appears from the record that Yes Bank Limited,
by a letter dated November 13, 2026 informed SAIL
that the beneficiary of the bank guarantee was
SAIL-DSP, and the bank guarantee furnished by the
appellants bearing No. 190BG09262810001 was
100% genuine, valid and legally binding from its
original issuance date. The bank further informed
SAIL-DSP, that in the bank guarantee furnished by
the appellants, there was a clerical error in the
beneficiary’s address. However, the bank clarified
that such clerical error would not affect SAIL-DSP’s
unconditional legal right to invoke a claim the
guaranteed amount.
8. In spite of letter dated November 13, 2026 issued
by the Yes Bank Limited, SAIL chose not to
consider the technical bid of the appellants as a
valid one. Challenging such decision of SAIL, the
appellants filed the writ petition.
9. The learned single Judge, upon considering the
rival submissions of the parties, inter alia, held as
follows :“21. Considering as above, this Court finds that
in the present case, the beneficiary of the Bank
Guarantee was AGM, Durgapur Steel Plant
(SAIL),
Durgapur
713203,
West
Bengal
(Durgapur Steel Plant, Sail). But admittedly, the
Bank Guarantee was in the name of M/S Steel
Authority
of
India
Limited,
SAIL-DSP,
Chandrapur Ferro Alloy Plant, Chanda-MulRoad, Chandrapur – 442 401 (Maharashtra). The
beneficiary of the Bank Guarantee dated 8th
October, 2026 submitted by the petitioner on
18th October, 2026 is different than the
beneficiary mentioned in the Tender document.
The terms and conditions of the Tender
document also provides that if the if EMD or
Exemption documents etc. submitted by vendor
are not found in order, the offer shall not be
considered.
22. Considering the above, this Court finds that
there is no illegality by rejecting the Technical
Bid of the petitioner as the petitioner has not
submitted the EMD by way of BG in the proper
name of the beneficiary.”
10. Mr. Jishnu Chowdhury, learned senior Advocate
appearing for the appellants submits that in the
bank guarantee which was initially submitted by
his client, there was a clerical mistake on the part
of the Yes Bank Limited. As soon as such clerical
mistake was detected, the same was rectified and
the amended bank guarantee was submitted. Mr.
Chowdhury further submits that his client is ready
to match the price of the L1. According to Mr.
Chowdhury, no prejudice would be caused to the
tendering authority if the reverse auction in redone. The tendering authority had received the
amended bank guarantee much before the rejection
of the technical bid. As such, the amended bank
guarantee should have been accepted by SAIL on
October 28, 2026. At the relevant point of time the
evaluation of the technical bid was going on.
11. Per contra, Mr. Datta, learned senior counsel for
SAIL-DSP, submits that the technical bid of the
appellants was rejected in conformity with the
terms and conditions of the notice inviting tender.
The mistake in the bank guarantee was apparent
on the face of the record and the appellant could
not claim any equity before a writ Court. The writ
court did not enjoy any authority to restrain SAIL
from invoking the tender conditions.
12. Heard the parties.
13. The scope of judicial review in respect of matters
relating to tenders is microscopic. In Tata Celular
Vs. Union of India, reported in (1994) 6 SCC 651,
the Hon’ble Apex Court held as follows :“77. The duty of the court is to confine itself to
the question of legality. Its concern should be:
1. Whether a decision-making authority
exceeded its powers?
2. Committed an error of law,
3. committed a breach of the rules of natural
justice,
4. reached a decision which no reasonable
tribunal would have reached or,
5. abused its powers.
Therefore, it is not for the court to determine
whether a particular policy or particular decision
taken in the fulfilment of that policy is fair. It is
only concerned with the manner in which those
decisions have been taken. The extent of the
duty to act fairly will vary from case to case.
Shortly put, the grounds upon which an
administrative action is subject to control by
judicial review can be classified as under:
(i) Illegality : This means the decision-maker
must understand correctly the law that regulates
his decision-making power and must give effect
to it.
(ii)
Irrationality,
namely,
Wednesbury
unreasonableness.
(iii) Procedural impropriety.
The above are only the broad grounds but it does
not rule out addition of further grounds in
course of time. As a matter of fact, in R. v.
Secretary of State for the Home Department, ex
Brind [(1991) 1 AC 696] , Lord Diplock refers
specifically to one development, namely, the
possible recognition of the principle of
proportionality. In all these cases the test to be
adopted is that the court should, “consider
whether something has gone wrong of a nature
and degree which requires its intervention”.
14. Therefore, a writ Court can interfere with the
decision of the tendering authority under limited
circumstances:(1) If the decision is arbitrary.
(2) If the decision violates the rules of natural
justice.
(3) If the tender inviting authority violates any
statutory provision.
(4) If the decision adopted by the decision
making authority is such that, no reasonable
person shall have come to such a decision.
(5) If it is found that the contract is tailor
made, in order to favour a particular person
or class of person.
(6) If the decision is against public interest.
15. The Bid document dated September 30, 2026
provided as follows :“(a) The bidder seeking EMD exemption, must
submit the valid supporting document for the
relevant category as per GeM GTC with the bid.
Under MIS category, only manufactures for
goods and service Providers for Services are
eligible for exemption from EMD. Traders are
excluded from the purview of this Policy.
(b) The EMD Amount will be applicable for each
schedule/group selected during Bid creation.
(c) EMD & Performance security should be in
favour of Beneficiary, wherever it is applicable.
(d) Earnest Money Deposit (EMD) shall also be
accepted by the buyer in the form of a surety
bond.
Beneficiary :
AGM
Durgapur Steel Plant (SAIL), Durgapur-713203,
West Bengal
(Durgapur Steel Plant, Sail)”
16. The date for opening the technical bid was fixed on
October 23, 2026. As on that date, the bank
guarantee was not in proper form. It did not
conform to the terms and conditions of the bid
document. The tender document further provided
under Clause 4 (a) that, if the EMD or Exemption
documents etc., that were submitted by the vendor
were not found to be in order, the offer shall not be
considered. Clause 5(a) of the bid document is
quoted below : -
“5.
Earnest
Money
Deposit
(EMD)/Bid
Security:a.
Tenderer
participating
in
multiple
Markets/Schedules need to submit EMD/Bid
Security for respective Markets/Schedules.
EMD/Bid
Security
favouring
“STEEL
AUTHORITY OF INDIA LIMITED, DURGAPUR
STEEL PLANT” and payable at Durgapur may
be submitted in the form of online transfer,
Demand
Draft,
Banker’s
Cheque,
Bank
Guarantee (BG) or Fixed Deposit Receipt (FDR)
from any Scheduled Commercial Bank except
Co-operative and Gramin Bank but shall not
be accepted in cash. The bank account details
of DURGAPUR STEEL PLANT is BANKER
NAME: STATE BANK OF INDIA, ACCOUNT
NAME: SAIL A/C DURGAPUR STEEL PLANT,
ACCOUNT
NO:
10894391546,
IFSC:
SBIN0000074.”
17. The bank details of the beneficiary bears IFSC Code
SBIN 0000074, whereas, from the communication
of the bank we find that the IFSC Code of the
beneficiary on the initial bank guarantee was
mentioned as IFSC SBIN 0000346. Thus, not only
was the address of the beneficiary incorrect and
contrary to the tender document, the IFSC Code of
the bank was also incorrect. In view of the mistake
in the IFSC Code (account details), invocation of the
bank guarantee would not be possible. Clause 5 (b)
provides as follows :“b.
Tenderers
Security
on
shall
GeM
submit
Portal
EMD/Bid
as
per
GeM
procedures & upload scanned copy of
EMD/Bid Security & EMD/Bid Security
Receipt with their Techno-commercial offer
on GeM portal and submit hard copy of the
same
in
sealed
envelope
directly
to
SAIL/DSP within 5 working days of Tender
opening Date, failing which the bid may be
treated as incomplete & may lead to
rejection of the bid without making any
reference to the bidder [GeM provision].”
18. In this case, the physical copy contained the wrong
address. Clause 5(c) provides as follows :“c.
Tenderers
are
required
to
submit
Physical copy of EMD/Bid Security in a
sealed cover clearly super scribing GeM Bid
Number, Earnest Money Deposit (EMD), due
date of Submission, due date of opening and
the Name & Address of the bidder.
Address for submission of EMD:
Md. Asif Khan
AGM (MM-Purchase)
Room No. 310, Purchase Department,
Third Floor, Ispat Bhavan,
Durgapur Steel Plant,
Durgapur, West Bengal-713203, India.”
21. From the said document that was submitted, it
was clear that the beneficiary’s address had been
incorrectly incorporated in the bank guarantee.
Under
such
circumstances,
the
tender
issuing
authority reserved the absolute right and freedom to
reject the bid. Exercise of such right can neither be
questioned before a writ court nor can the same be
set aside by way of judicial review. In view of the
deviation from the bid document, the authority
rightly rejected the technical bid. Even though an
amendment was made later on, the authority was not
bound to accept the same. Whether the error cropped
up at the instance of the bank or at the instance of
the appellants, was not available on record.
22. However, in the event the appellants are aggrieved
by the alleged action of the bank, the appellants are
at liberty to proceed against the bank in accordance
with law.
23. We do not find any reason to interfere with the
order impugned. The same does not suffer from
perversity. His Lordship has applied the principles of
law and rightly expressed His Lordship’s inability to
review the decision of the tendering authority in the
matter of rejection of a technical bid on the ground
that the bank guarantee was not in proper form.
24. In the matter of Maa Binda Express Carrier
and Anr. vs Northeast Frontier railway and Ors.
reported in AIR 2014 SC 390, the Hon’ble Apex
Court held as follows:-
“8. The scope of judicial review in matters
relating to award of contracts by the State and
its instrumentalities is settled by a long line of
decisions of this Court. While these decisions
clearly recognise that power exercised by the
Government and its instrumentalities in regard
to allotment of contract is subject to judicial
review at the instance of an aggrieved party,
submission of a tender in response to a notice
inviting such tenders is no more than making an
offer which the State or its agencies are under
no obligation to accept. The bidders participating
in the tender process cannot, therefore, insist
that their tenders should be accepted simply
because a given tender is the highest or lowest
depending upon whether the contract is for sale
of public property or for execution of works on
behalf of the Government. All that participating
bidders are entitled to is a fair, equal and nondiscriminatory treatment in the matter of
evaluation of their tenders. It is also fairly well
settled that award of a contract is essentially a
commercial
transaction
which
must
be
determined on the basis of consideration that
are relevant to such commercial decision. This
implies that terms subject to which tenders are
invited are not open to the judicial scrutiny
unless it is found that the same have been
tailor-made to benefit any particular tenderer or
class of tenderers. So also, the authority inviting
tenders can enter into negotiations or grant
relaxation for bona fide and cogent reasons
provided such relaxation is permissible under
the terms governing the tender process.
9. Suffice it to say that in the matter of award of
contracts the Government and its agencies have
to act reasonably and fairly at all points of time.
To that extent the tenderer has an enforceable
right in the court which is competent to examine
whether the aggrieved party has been treated
unfairly or discriminated against to the
detriment of public interest. (See Meerut
Development Authority v. Assn. of Management
Studies [(2009) 6 SCC 171 : (2009) 2 SCC (Civ)
803] and Air India Ltd. v. Cochin International
Airport Ltd. [(2000) 2 SCC 617 : (2000) 1 SCR
505] )
10. The scope of judicial review in contractual
matters was further examined by this Court
in Tata Cellular v. Union of India [(1994) 6 SCC
651] , Raunaq International Ltd. case [Raunaq
International Ltd. v. I.V.R. Construction Ltd.,
(1999)
SCC
492]
and
in Jagdish
Mandal v. State of Orissa [(2007) 14 SCC 517]
besides several other decisions to which we need
not refer.
11. In Michigan Rubber (India) Ltd. v. State of
Karnataka [(2012) 8 SCC 216] the legal position
on the subject was summed up after a
comprehensive review and principles of law
applicable to the process for judicial review
identified in the following words: (SCC p. 229,
paras 23-24)
“23. From the above decisions, the following
principles emerge:
(a) the basic requirement of Article 14 is fairness
in action by the State, and non-arbitrariness in
essence and substance is the heartbeat of fair
play. These actions are amenable to the judicial
review only to the extent that the State must act
validly for a discernible reason and not
whimsically for any ulterior purpose. If the State
acts within the bounds of reasonableness, it
would be legitimate to take into consideration
the national priorities;
(b) fixation of a value of the tender is entirely
within the purview of the executive and courts
hardly have any role to play in this process
except for striking down such action of the
executive as is proved to be arbitrary or
unreasonable. If the Government acts in
conformity with certain healthy standards and
norms such as awarding of contracts by inviting
tenders, in those circumstances, the interference
by courts is very limited;
(c) in the matter of formulating conditions of a
tender document and awarding a contract,
greater latitude is required to be conceded to the
State authorities unless the action of the
tendering authority is found to be malicious and
a misuse of its statutory powers, interference by
courts is not warranted;
(d) certain preconditions or qualifications for
tenders have to be laid down to ensure that the
contractor has the capacity and the resources to
successfully execute the work; and
(e) if the State or its instrumentalities act
reasonably, fairly and in public interest in
awarding contract, here again, interference by
court is very restrictive since no person can claim
a fundamental right to carry on business with the
Government.
20. Therefore, a court before interfering in tender
or contractual matters, in exercise of power of
judicial review, should pose to itself the following
questions:
(i) Whether the process adopted or decision made
by the authority is mala fide or intended to favour
someone; or whether the process adopted or
decision made is so arbitrary and irrational that
the court can say: ‘the decision is such that no
responsible authority acting reasonably and in
accordance with relevant law could have
reached’? and
(ii) Whether the public interest is affected?
If the answers to the above questions are in the
negative, then there should be no interference
under Article 226.”
(e
mphasis supplied)
12. As pointed out in the earlier part of this
order, the decision to cancel the tender process
was in no way discriminatory or mala fide. On
the contrary, if a contract had been awarded
despite the deficiencies in the tender process
serious questions touching the legality and
propriety affecting the validity of the tender
process would have arisen. Inasmuch as the
competent authority decided to cancel the tender
process, it did not violate any fundamental right
of the appellant nor could the action of the
respondent be termed unreasonable so as to
warrant any interference from this Court. The
Division Bench of the High Court was, in that
view, perfectly justified in setting aside the order
[Maa Binda Express Carrier v. Union of India, WP
(C) No. 4668 of 2011, order dated 4-2-2012
(Gau)] passed by the Single Judge and
dismissing the writ petition.”
25. In the matter of Balaji Ventures Pvt. Ltd. vs
Maharashtra State Power Generation Company
Ltd. & Anr. decided in Special Leave to Appeal
(C) No(s). 1616 & 1673 /2022, the Hon’ble Apex
Court held as follows:“5.1 Now so far as the impugned Judgment and
order passed by the High Court dismissing the
writ petitions is concerned, what was challenged
before the High Court was one of the tender
conditions/clauses. The High Court has
specifically observed and noted the justification
for providing clause 1.12(V). The said clause was
to be applied to all the tenderers/bidders. It
cannot be said that such clause was a tailor
made to suit a particular bidder. It was
applicable to all. Owner should always have the
freedom to provide the eligibility criteria and/or
the terms and conditions of the bid unless it is
found to be arbitrary, mala fide and/or tailor
made. The bidder/tenderer cannot be permitted
to challenge the bid condition/clause which
might not suit him and/or convenient to him. As
per the settled proposition of law as such it is an
offer to the prospective bidder/tenderer to
compete and submit the tender considering the
terms and conditions mentioned in the tender
document.”
26.
In
the
case
of
Silppi
Constructions
Contractors vs. Union of India, (2020) 16 SCC
489, it is observed in para 20 as under:
“20. The essence of the law laid down in the
judgments referred to above is the exercise of
restraint and caution; the need for overwhelming
public interest to justify judicial intervention in
matters of contract involving the State
instrumentalities; the courts should give way to
the opinion of the experts unless the decision is
totally arbitrary or unreasonable; the court does
not sit like a court of appeal over the appropriate
authority; the court must realise that the
authority floating the tender is the best judge of
its requirements and, therefore, the court's
interference should be minimal. The authority
which floats the contract or tender, and has
authored the tender documents is the best judge
as to how the documents have to be interpreted.
If two interpretations are possible then the
interpretation of the author must be accepted.
The courts will only interfere to prevent
arbitrariness, irrationality, bias, mala fides or
perversity. With this approach in mind we shall
deal with the present case.”
27. In Jagdish Mandal v. State of Orissa and
Ors. WITH Laxman Sharma Vs. State of Orissa
and Ors. reported in (2007) 14 SCC 517 it was
held as hereunder: “22. Judicial review of administrative action is
intended to prevent arbitrariness, irrationality,
unreasonableness, bias and mala fides. Its
purpose is to check whether choice or decision
is made “lawfully” and not to check whether
choice or decision is “sound”. When the power
of judicial review is invoked in matters relating
to tenders or award of contracts, certain special
features should be borne in mind. A contract is
a commercial transaction. Evaluating tenders
and awarding contracts are essentially
commercial functions. Principles of equity and
natural justice stay at a distance. If the
decision relating to award of contract is bona
fide and is in public interest, courts will not, in
exercise of power of judicial review, interfere
even if a procedural aberration or error in
assessment or prejudice to a tenderer, is made
out. The power of judicial review will not be
permitted to be invoked to protect private
interest at the cost of public interest, or to
decide contractual disputes. The tenderer or
contractor with a grievance can always seek
damages in a civil court. Attempts by
unsuccessful
tenderers
with
imaginary
grievances, wounded pride and business
rivalry, to make mountains out of molehills of
some technical/procedural violation or some
prejudice to self, and persuade courts to
interfere by exercising power of judicial review,
should be resisted. Such interferences, either
interim or final, may hold up public works for
years, or delay relief and succour to thousands
and millions and may increase the project cost
manifold. Therefore, a court before interfering
in tender or contractual matters in exercise of
power of judicial review, should pose to itself
the following questions:
(i) Whether the process adopted or decision
made by the authority is mala fide or intended
to favour someone;
OR
Whether the process adopted or decision made
is so arbitrary and irrational that the court can
say: “the decision is such that no responsible
authority acting reasonably and in accordance
with relevant law could have reached”;
(ii) Whether public interest is affected.
If the answers are in the negative, there should
be no interference under Article 226. Cases
involving blacklisting or imposition of penal
consequences on a tenderer/contractor or
distribution of State largesse (allotment of
sites/shops, grant of licences, dealerships and
franchises) stand on a different footing as they
may require a higher degree of fairness in
action.”
28. Accordingly, the appeal and the connected
application are dismissed.
(Shampa Sarkar, J.)
(Arjun Ray Mukherjee, J.)
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review