Bdcc Bank Employees Co Operative Society Ltd vs The Bengaluru Development Authority

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Karnataka High Court
Date
14 October 2026
Case No.
WP 29756/2024
Result
Allowed
Bench
R. Nataraj
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

8. As rightly contended by the learned Senior counsel for the petitioner, the petitioner having paid a sum of Rs.51,27,500/- in the year 2000, is entitled to legitimately expect that the respondent No.1 would fulfill its promise by concluding the transaction. It is this legitimate expectation that compelled the petitioner to defend several litigation - 30 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 initiated by the erstwhile landowners in respect of the land bearing Sy.No.78 of Nagarabhavi. As rightly contended by the learned Senior counsel for the petitioner, the respondent No.1 must have rescinded the resolution dated 31.12.1997 within a reasonable time and it cannot sleep over it, even when all the material documents were available to it to take action. It may be that the petitioner was not a housing society as on the date, the application was filed seeking bulk allotment. This Court, however cannot lose sight of the fact that the members of the petitioner would have parted with large sums of money in the fond hope of getting a site. The respondent No.1 therefore, is estopped by conduct from now taking a contrary view to contend that the petitioner was not entitled for allotment of land in bulk under Section 38B of the BDA Act, 1976. As rightly contended by the learned Senior counsel for the petitioner soon after an amendment to the objectives of the pe…

9. Consequently, the following order is passed : (i) The writ petition is allowed. (ii) The impugned show-cause No.¨ÉAC¥Áæ/DAiÀÄÄPÀÛgÀÄ/2488/2016-2017, notice bearing ¨ÉAUÀ¼ÀÆgÀÄ dated

27. 07.2016 and the consequent order bearing No.©rJ/DAiÀÄÄPÀÛgÀÄ/GPÁ-1/954/2024-25 dated 26.09.2024 passed by the respondent No.1, are quashed. (iii) The respondent No.1 is directed to convey 5 acres of land in Sy.No.78 of Nagarabhavi village, Yeshwanthpura Hobli, Bengaluru North Taluk, to the petitioner within one month from the date of receipt of copy of this order by executing necessary deeds of conveyance. If the area available in Sy.No.78 is less than 5 acres, the respondent No.1 shall convey - 33 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 the extent available and refund the proportionate consideration along with interest at the rate of 12% per annum from the date of deposit till the date of refund. (iv) On such conveyance, the petitioner shall obtain necessary plan for forming a layout from the respondent No.1 and execute relinquishment deed/s in respect of roads/drains/parks and open spaces in favour of the respondent No.1, who shall maintain same. (v) Copy of this order shall be circulated by the petitioner to all its members. (vi) The petitioner shall also file list of members based on seniority i.e., based on dates when they deposited sital value seeking allotment of sites in Sy.No.78 of Nagarabhavi. Allotment of sites shall only be in accordance with such list. - 34 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 (vii) List …

Filed under

Constitution of India

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

-1HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 14TH DAY OF OCTOBER, 2026 BEFORE THE HON'BLE MR. JUSTICE R. NATARAJ WRIT PETITION NO. 29756 OF 2024 (BDA) BETWEEN: BDCC BANK EMPLOYEES' CO-OPERATIVE SOCIETY LTD., A CO-OPERATIVE SOCIETY REGISTERED UNDER THE KARNATAKA CO-OPERATIVE SOCIETIES ACT, 1969 HAVING ITS REGISTERED OFFICE AT NO.6, "LAKSHMI SADAN", 5TH MAIN ROAD, CHAMARAJAPET, BENGALURU-560018 REPRESENTED BY ITS DIRECTOR, SRI. N.S. BETTASWAMY GOWDA …PETITIONER (BY SRI. S.S. NAGANANDA, SENIOR ADVOCATE FOR SMT. SUMANA NAGANAND, ADVOCATE) AND: Digitally signed by HEMALATHA J Location: HIGH COURT OF KARNATAKA 1. THE BENGALURU DEVELOPMENT AUTHORITY KUMARA PARK WEST, T.CHOWDAIAH ROAD, BENGALURU - 560020 REPRESENTED BY ITS COMMISSIONER 2. STATE OF KARNATAKA DEPARTMENT OF HOUSING VIKASA SOUDHA, BENGALURU-560001 REPRESENTED BY ITS PRINCIPAL SECRETARY 3. STATE OF KARNATAKA DEPARTMENT OF URBAN DEVELOPMENT VIKASA SOUDHA, BENGALURU - 560001 REPRESENTED BY ITS SECRETARY …RESPONDENTS -2HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 (BY SRI. G.S.KANNUR, SENIOR ADVOCATE FOR SRI. AJAYKUMAR M., ADVOCATE FOR RESPONDENT NO.1; SMT. POOJA M. KOORSE, HIGH COURT GOVERNMENT PLEADER FOR RESPONDENT NOS.2 AND 3) THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE IMPUGNED SHOW CAUSE NOTICE DATED 27.07.2016 BEARING NO.BEM AA PA/AAYAKTHARU/2488/2016-17 ISSUED BY RESPONDENT NO.1 (ANNEXURE-S) AND ETC. THIS PETITION, COMING ON FOR ORDERS, THIS DAY, ORDER WAS MADE THEREIN AS UNDER: CORAM: HON'BLE MR. JUSTICE R. NATARAJ ORAL ORDER The petitioner has called in question a show-cause notice bearing No.¨ÉAC¥Áæ/DAiÀÄÄPÀÛgÀÄ/2488/2016-2017, ¨ÉAUÀ¼ÀÆgÀÄ dated 27.07.2016 issued by the respondent No.1 and the consequent order bearing No.©rJ/DAiÀÄÄPÀÛgÀÄ/GPÁ-1/954/2024-25 dated 26.09.2024 passed by the respondent No.1, by which the request of the petitioner for conclusion of the bulk allotment made in its favour was rejected. The petitioner has also sought for a direction to the respondent No.1 to execute a deed of conveyance in its favour to conclude the bulk allotment pursuant to the letter dated 08.09.2000. -3HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 2. (i) The petitioner claims to be a Co-operative Society established with an objective to acquire land and provide housing to its members. It claims that in furtherance of its objective, it entered into an agreement of sale dated 26.08.1981 to purchase 10 acres 20 guntas of land in Sy.No.78 of Nagarbhavi village, Yeshwanthpura Hobli, Bengaluru North Taluk, at a sum of Rs.1,90,000/- per acre. This agreement was later confirmed by the family members of the vendor in terms of supplementary agreements of sale dated 12.09.1984 and 21.10.1991. The petitioner claims that the respondent No.1 proposed to acquire the land in Sy.No.78 in terms of a preliminary notification dated 15.07.1982 followed by a final notification dated 16.08.1985 and an award dated 12.05.1988 was passed. The petitioner claimed that it made requests before the respondent No.1, consequent to which the respondent No.1 informed it vide letter dated 11.04.1988 to apply against any bulk allotment that may be notified by the respondent No.1. It was further stated that the land in Sy.No.78 of Nagarbhavi would be included in the said notification to enable the petitioner to apply. The petitioner -4HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 claims that aggrieved W.P.No.12119/1988 by the challenging said letter, it filed the acquisition and alternatively sought bulk allotment of the land in Sy.No.78. The said writ petition and the consequent writ appeal filed in W.A.No.1696/1988 were dismissed. A Special Leave Petition was filed in a Civil Appeal No.17/1991. In the interregnum, the Bangalore Development Authority Act, (henceforth referred to as 'BDA Act, 1976') was amended retrospectively with effect from 20.12.1975 and Section 38 of the BDA Act, 1976 was amended to provide for bulk allotments. The petitioner claimed that as a result, the Hon'ble Supreme Court dismissed Civil Appeal No.17/1991 as infructuous vide order dated 18.09.1995 and directed the petitioner to approach the respondent No.1 directly for bulk allotment of the said land or any other land notified for acquisition by the respondent No.1. (ii) The respondent No.1 thereafter issued a notification on 06.05.1998 for bulk allotment of the land in Sy.No.78 of Nagarbhavi in respect of an area measuring 5 acres. The petitioner also applied for the same. The respondent No.1 vide resolution dated 31.12.1997 on Subject No.335/1997 accorded -5HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 approval for bulk allotment, which was approved by the Department of Housing and Urban Development vide order dated 06.01.1999. Following this, the Department of Housing and Urban Development vide its letter dated 23.05.2000 fixed the price at a sum of Rs.10,25,000/- per acre. A demand letter dated 08.09.2000 was also issued by respondent No.1 calling upon the petitioner to pay a sum of Rs.51,27,500/- towards the value of 5 acres of land to be allotted in bulk. Accordingly, the petitioner deposited a sum of Rs.51,27,500/- in terms of a Demand Draft dated 17.10.2000. the (iii) Petitioner contends that after nearly 15 years from date of representatives issuing the final notification, of the erstwhile the legal landowner filed W.P.No.27671/2000 challenging the preliminary notification dated 15.07.1982, final notification dated 16.08.1985 and the award dated 12.05.1988. The said writ petition was dismissed in terms of an order dated 16.01.2004. W.A.No.2945/2004 was also dismissed on 15.09.2004 following which Special Leave Petition in Civil Appeal No.175/2009 was also dismissed on 14.01.2009. Review Petition (Civil) No.420/2009 was also -6HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 dismissed on 14.01.2009. Petitioner contends that the erstwhile land owners then filed O.S.No.911/2009 against the respondent No.1 for perpetual injunction. Though the Civil Court initially granted an interim order, thereafter the same was vacated and the suit also came to be dismissed on 04.02.2010 as not pressed. Petitioner contends that the erstwhile landowners thereafter submitted representations to the respondent No.2 for de-notification of the land bearing Sy.No.78 of Nagarbhavi under Section 48A of the Land Acquisition Act, 1894. A writ petition in W.P.No.4243/2009 was also filed on 13.02.2009 by the erstwhile landlowners for a direction to the authorities to consider and decide their applications for de-notification. In the said writ petition, it was held that the erstwhile landowners had lost possession and therefore, their prayer for de-notification cannot be considered. Consequently, the writ petition was dismissed. Later, W.A.Nos.1642-1646/2009 were filed by them which too was dismissed vide order dated 26.05.2009. SLP (Civil) Nos.14930-14934/2009 filed thereagainst was also dismissed in terms of an order dated 17.08.2009. -7HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 (iv) Petitioner contends that it came to know that the Chief Minister of Karnataka had ordered de-notification of the land in Sy.No.78 of Nagarbhavi, measuring 5 acres 13 guntas at the request of the petitioners vide his order dated 16.10.2009. On 18.11.2009, the erstwhile landowners filed W.P.Nos.34023-27/2009 seeking a direction against the State to notify the order passed by the Chief Minister of Karnataka on 16.10.2009 in the Official Gazette. The said writ petitions were thereafter withdrawn by the 05.03.2010. The erstwhile erstwhile landowners on landowners again filed W.P.No.5779/2010 challenging the communications issued by the respondent No.1, whereby the bulk allotment was made in favour of the petitioner was approved. The said writ petition was dismissed as not maintainable vide order dated 09.03.2010. W.A.No.1666/2010 preferred by the erstwhile landowners was also dismissed as withdrawn. (v) of Pursuant to the order passed by the Chief Minister Karnataka, referred supra, a notification bearing No.UDD/426/MNX/2007 dated 02.06.2010 was issued under Section 48(1) of the Land Acquisition Act, 1894 withdrawing -8HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 the acquisition proceedings. The petitioner challenged the same in W.P.No.21349/2010. This Court vide order dated 10.11.2010 held that the matter required further examination as it had a public flavour and referred the matter to the Division Bench. Therefore, a withdrawing notification the earlier dated 19.10.2010 notification dated was issued 02.06.2010. Therefore, the writ petition filed by the petitioner was dismissed as the same was rendered infructuous in view of withdrawal of the order of de-notification. (vi) When things stood thus, the erstwhile landowners filed W.P.No.37111/2010 challenging the notification dated 19.10.2010. The said writ petition was dismissed vide order dated 29.03.2012 on the ground that the erstwhile landowners did not have any locus standi. Special Leave Petitions preferred against the said order in SLP (Civil) Nos.27537-38/2012 were dismissed vide order dated 06.05.2016. Review petitions were thereafter filed by the erstwhile landowners in R.P.Nos.28932894/2016 26.07.2016. which too Thereafter, were dismissed vide order dated the erstwhile landowners filed W.P.No.5201/2017 challenging the acquisition proceedings on -9HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 the ground that it had lapsed under Section 24 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation Resettlement Act, 2013. The said writ petition was dismissed in terms of an order dated 21.08.2024. It is contended that W.A.No.1471/2024 is filed which too was dismissed on 10.11.2025. (vii) Petitioner contends that it was requesting the respondent No.1 time and again to execute a deed of conveyance in its favour and since none of them found favour, it filed W.P.No.36340/2009 seeking for a direction to execute a deed of conveyance. The respondent No.1 filed its statement of objections in the said writ petition contending that it would provide alternate land instead of the land in Sy.No.78 as it was required for its use. It is contended that the respondent No.1 never took a stand that the petitioner was not eligible for allotment of land in bulk under Section 38B of the BDA Act, 1976. During the pendency of W.P.No.36340/2009, the respondent No.1 issued an order dated 27.07.2016 unilaterally withdrawing the bulk allotment issued in favour of the petitioner and also forfeited a sum of Rs.51,27,500/-. Aggrieved - 10 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 thereby, the petitioner filed W.P.No.47525/2016. In view of the withdrawal of the order of bulk allotment, W.P.No.36340/2009 was disposed off on 28.03.2019 reserving liberty to the petitioner to revive the proceeding for execution of the deed of conveyance in the event the petitioner succeeds in (viii) During the pendency of W.P.No.47525/2016, the W.P.No.47525/2016. petitioner amended its objectives and incorporated objects enabling it to acquire lands for the purpose of constructing houses for its members. The petitioner issued a notice dated 25.08.2023 to all its members for conducting the General Body meeting. Thereafter, at the meeting held on 10.09.2023, it was unanimously resolved to pass an amendment to amend the objectives of the petitioner to incorporate the aforesaid objects. Thereafter, the petitioner submitted a representation dated 25.09.2023 and enclosed its proposal for amendment of its objects under Section 12(2) of the Karnataka Co-operative Societies Act, 1959. Since the said representation was not considered, the petitioner claims that it was deemed to be registered under Section 12(2A) of the Karnataka Co-operative - 11 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 Societies Act, 1959. Petitioner claims that pursuant to the General Body meeting, it has amended its objectives and byelaws and the said change is reported to the Registrar of Cooperative Societies on 25.09.2024. Petitioner contends that the amendment of the bye-laws was brought to the notice of this Court in W.P.No.47525/2016 and this Court held that the order dated 27.07.2016 was passed by the respondent No.1 without providing an opportunity to the petitioner of being heard. Hence, the said order dated 27.07.2016 was treated as a showcause notice and the petitioner was permitted to reply to the said notice within a period of two weeks. The parties were directed to maintain status quo as regards the subject land. (ix) Pursuant to the order passed in WP No.47525/2016, the petitioner issued a reply on 02.09.2024 highlighting that it had complied with all the requirements of the demand letter issued by the respondent No.1 and that it had promptly paid the amount. It further stated that a perusal of the show-cause notice indicated that it was issued at the instance of the erstwhile landowners. It claimed that the amendments to the bye-laws of the society allowed it to acquire land for housing - 12 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 which was also brought to the notice of the respondent No.1. However, the respondent No.1 passed the impugned order dated 26.09.2024 rejecting the claim of the petitioner and affirming the show-cause notice dated 27.07.2016. (x) Being aggrieved by the said order, the petitioner is before this Court. 3. (i) A statement of objections is filed by the respondent No.1 wherein it has admitted the fact of the petitioner making a request for allotment of land in Sy.No.78 of Nagarbhavi in bulk. It has also admitted that the application was placed before the Bulk Allotment Committee which passed a resolution on Subject No.335/1997 on 31.12.1997 and resolved to allot up to 5 acres of land to the petitioner under bulk allotment. The State Government vide order bearing No.UDD/322/BDA/98 dated 06.01.1999 granted approval for the resolution of the Committee. The respondent No.1 on 19.02.1999 called upon the petitioner to deposit a sum of Rs.5,26,48,879/- towards cost of 5 acres of land. The petitioner then made a request before the State Government for - 13 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 reduction of the cost of the land, consequent to which the State Government by its letter dated 23.05.2000 granted approval for allotment of 5 acres of land in Sy.No.78 of Nagarbhavi at a cost of Rs.10,25,000/- per acre. Accordingly, a sum of Rs.51,27,500/- was deposited by the petitioner on 20.10.2000. (ii) It is contended that the respondent No.1 had already formed a layout in Sy.No.78 of Nagarbhavi village. In view of the formation of the layout and considering the fact that as per the zonal regulation, the society could form sites only in 50% of the area and the remaining 50% had to be reserved for park, playground, civic amenities and roads, the respondent No.1 by its letter dated 22.04.2002 informed the petitioner that it had at a meeting held on 07.02.2002 resolved on Subject No.83/2001 to allot 1 acre 36 guntas to the society in bulk. The said letter was received by the petitioner - society on 24.04.2002. The petitioner filed W.P.No.28141/2002 for a direction to the respondent No.1 to allot 5 acres of land. The said writ petition was disposed off directing the petitioner to appear before the respondent No.1 and furnish documents to show its entitlement for 5 acres of land and the respondent - 14 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 No.1 was directed to consider the claim of the petitioner and hand over possession of 1 acre 36 guntas of land only and not 5 acres as claimed. The respondent No.1 identified 1 acre 36 guntas of land in Sy.No.36 of Malagala Village. But in view of a litigation, the possession of the said site could not be handed over to the petitioner. Later, respondent No.1 identified 1 acre 36 guntas of land in Sy.Nos.55/1 and 2 of Malagala village. However, the erstwhile landowner had filed W.P.No.8340/2003 which was dismissed on 24.07.2007 and W.A.No.1979/2007 was also dismissed on 25.05.2009. (iii) Meanwhile, the area was developed for commercial purposes and large number of unauthorised construction came up in the unallotted sites in Sy.No.78. Therefore, the respondent No.1 at a meeting held on 12.01.2010 on Subject No.14/2010, resolved to auction the unallotted sites formed in Sy.No.78 of Nagarbhavi and also to remove the unauthorised construction and to recall its earlier resolution on Subject No.106/2000 dated 19.08.2000, whereby it had resolved to allot 5 acres of land in Sy.No.78 of Nagarbhavi village to this petitioner. It was also resolved to allot 5 acres of land in some - 15 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 other layout to be formed by the respondent No.1 to the petitioner and to send the proposal to the State Government with request to recall its earlier order dated 23.05.2000 and to approve the above proposal. The proposal was sent to the State Government on 26.08.2010. The respondent No.1 claims that the petitioner filed W.P.No.36340/2009 seeking for a direction to execute a conveyance deed in respect of 5 acres of land allotted to it in bulk and also to quash the resolution dated 12.01.2010 passed by the respondent No.1 on Subject No.14/2010. The respondent No.1 considered the eligibility conditions prescribed under Section 38B of the BDA Act, 1976 and noticed that the petitioner though was a Co-operative Society but its objectives did not permit acquisition of land, formation of layouts and allotment to its members. It was not a housing society, but was a society which was permitted to attract capital and grant loan to its members for construction or purchasing sites and dwelling houses etc. The respondent No.1 learnt that the petitioner had sought for amendment of its byelaws and inserted a provision to enable it to purchase land, form sites and allot to its members, which was however - 16 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 rejected by the Joint Registrar of Co-operative Societies in terms of an order dated 01.02.2001. Therefore, it contended that the object of the society was not to form layouts and allot site to its members and therefore, the petitioner was not entitled for allotment of land in bulk. Therefore, the respondent No.1 claimed that it had rightly rejected the request of the petitioner for bulk W.P.No.36340/2009 allotment. was The disposed writ off petition vide filed order in dated 28.03.2019 by which time the respondent No.1 had already passed an order rejecting the prayer for bulk allotment. This was then challenged in W.P.No.47525/2016, which was allowed and the respondent No.1 was directed to treat the order dated 27.07.2016 as a show-cause notice. The petitioner then filed its reply. (iv) During the pendency of W.P.No.47525/2016, the petitioner once again sought for amendment of its bye-laws in 2023 which was purportedly accepted by the Registrar of Cooperative Societies on 04.11.2024. It contended that though the petitioner is now eligible for allotment of land in bulk but as on the date of the previous order of bulk allotment, it was - 17 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 ineligible for allotment. It thus contended that the petitioner was not a Housing Society as on the date of the application for allotment in bulk and as on the date when the respondent No.1 cancelled the order of bulk allotment on 27.07.2016. Therefore, it is contended that the petitioner cannot allege that the respondent No.1 is bound by the principle of promissory estoppel and that the petitioner is entitled to legitimately expect the conclusion of the bulk allotment. (v) With these and similar contentions, it contended that the petitioner is not entitled to any relief. Furthermore, it contended that Section 38B of the BDA Act, 1976 does not create any mandatory obligation to allot land but is only an enabling provision empowering the authority to consider applications for bulk allotment to eligible societies. 4. (i) The learned Senior Counsel for the petitioner submitted that the ground on which the respondent No.1 has alleged that the petitioner is not eligible under Section 38B of the BDA Act, 1976 for bulk allotment is that the petitioner is not a Housing Co-operative Society. It is contended that the petitioner had amended its objectives and filed its proposal for - 18 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 amendment dated 25.09.2023 before the Registrar of Cooperative Societies and since the same was not considered within three months, under Section 12(2-A) of the Act, 1959, there is a deemed approval of the said proposal from 26.12.2023. Hence, as on the date of the passing of the impugned order dated 26.09.2024, the bye-laws of the petitioner society permitted it to engage in housing activities. He contends that the respondent No.1 disregarded this aspect and has held that no documents were placed to show the change of bye-laws of the petitioner - society. He contends that when the petitioner applied for bulk allotment, on 06.05.1998 the respondent No.1 had categorically endorsed that the petitioner may apply for bulk allotment in future and that Sy.No.78 was also included in the bulk allotment notification to enable the petitioner to apply. He contends that the State Government has also granted approval on 06.01.1999 and 23.05.2000 and thereafter, the respondent No.1 had issued a demand dated 08.09.2000 demanding a sum of Rs.51,27,500/which was accordingly paid. Therefore, he contends that the respondent No.1 cannot blow hot and cold by contending that - 19 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 the petitioner is now not eligible for bulk allotment. He therefore contends that the respondent No.1 is barred from contending that the petitioner is not eligible for allotment of a bulk allotment and that the respondent No.1 is estopped by the principles of promissory estoppel. He also contends that the petitioner is entitled to legitimately expect that the bulk allotment order passed in its favour would culminate in a conveyance. (ii) He contends that after the State Government and the respondent No.1 passed an order directing the petitioner to pay sum of Rs.51,27,500/-, the same was deposited vide a demand draft which is encashed by the respondent No.1. He contends that when a person alters his position based on a promise made by an instrumentality of the State, principles of promissory estoppel would apply. In support of this contention, he relied upon the judgment of this Court in K.S. Prakash vs Bangalore Development Authority [ILR 1990 KAR 3599]. He also contended that apart from depositing a sum of Rs.51,27,500/-, the petitioner has also incurred significant expenditure in contesting various litigations against the - 20 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 landowners solely on the basis that it is an allottee of the land in question and in all these proceedings, the respondent No.1 never took a contention that the petitioner was ineligible for allotment and that the allotment in favour of the petitioner was erroneous. He therefore, contended that petitioner is legitimately entitled to expect that the respondent No.1 would ensure that the land is conveyed to it. He further contended that the very same ground was urged by the erstwhile landowners in W.P.No.5779/2010 which was resisted by the respondent No.1. However, it did not raise any contention that the allotment in favour of the petitioner was invalid. When the petitioner filed W.P.No.36340/2009 seeking conveyance of the land allotted to it in bulk, the respondent No.1 filed objections offering alternate land and never raised a ground that the petitioner was not eligible for bulk allotment. Therefore, he contended that the respondent No.1 is estopped by record and conduct from taking any contrary stand in the present proceedings by passing the impugned order. He also contends that the principles of constructive res judicata is applicable as the respondent No.1 never raised such a ground in an earlier - 21 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 proceeding between the petitioner and the respondent No.1. He contends that the respondent No.1 has claimed in its objections that no unequivocal promise was made by it that the land would be allotted in bulk to the petitioner and therefore, no binding expectation of allotment could be stated to have been made. He contends that this is contrary to numerous decisions of this Court including the judgment in S. Lalithamma vs State of Karnataka and another [2018 SCC OnLine KAR 4767], where it was categorically held that, "an allotment letter calling for payment is an 'offer' and the due payment of the demanded amount would amount to acceptance, meaning thereby that an accomplished transaction in the nature of a contract comes into existence. As such, the action of the BDA in seeking to resile from the said obligation would be wholly arbitrary and contrary to law." (iii) He contends that the impugned show-cause notice dated 27.07.2016 reveals that the same was issued at the instance of the erstwhile landowners whose right, title and interest in the property stood wholly extinguished. Therefore, it is clear that the entire proceeding is an attempt on the part of - 22 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 the erstwhile landowners to regain the land in question. He contends that the respondent No.1 has not only withdrawn/cancelled the order of bulk allotment but also forfeited a sum of Rs.51,27,500/- paid in the year 2000 and no reasons are mentioned justifying the forfeiture and hence, the same is arbitrary and also violates Article 300A of the Constitution of India. He also contends that the impugned notice relies on a Circular dated 12.08.2014 which is wholly inapplicable to the petitioner as it applies to societies registered in the Karnataka Souharda Sahakari Act, 1997 and not to societies registered under the Karnataka Co-operative Societies Act, 1959. He therefore, contends that the reliance placed on the Circular to withdraw the bulk allotment made in favour of the petitioner is extraneous and hence, the impugned order is arbitrary. He contends that the respondent No.1 has stated in the statement of objections that various plots of various sizes have been formed and buildings have been constructed over the property. However, the said statement is wholly contrary to the interim orders passed by this Court across various writ petitions from the year 2005. He contends that from the year - 23 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 2005, the property has been the subject matter of litigation and interim orders are passed. He has invited the attention of the Court to the interim order passed in SLP (Civil) No.2173/2005 which was in force till 14.01.2009, interim order dated 12.01.2010 passed in W.P.No.36340/2009 which was in force till 28.03.2019 and interim order dated 01.12.2010 in W.P.No.37111/2010 which was in force till 29.03.2012, an interim order dated 06.09.2016 in W.P.No.47525/2016 which was in force till 21.08.2024 and the interim order dated 14.02.2017 in W.P.No.5201/2017 which was in force till 21.08.2024. He contends that the inability of the respondent No.1 to form layout due to interim orders is also borne from the record. He contends in a counter affidavit filed by the respondent No.1 in SLP (Civil) No.2173/2005 (C.A.No.174/2009), it had admitted that no layout was formed in the light of the interim orders of the Court regarding the land in Sy.No.78. (iv) petitioner He further contends that a memo is filed by the dated 12.08.2025 wherein it has enclosed a communication dated 18.09.2007 addressed by the respondent - 24 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 No.1 wherein it is admitted that no layout is formed in Sy.No.78 due to pendency of litigation. He contends that the non-development of the layout in Sy.No.78 is also recorded by this Court in para 11 of the order dated 26.05.2009 in W.A.No.1642/2009. Likewise, in the statement of objections dated 11.01.2010 in W.P.No.36040/2009, the respondent No.1 has admitted that the formation of layout in Sy.No.78 could not be completed due to several litigations. He therefore, contends that no layout is formed and assuming such a layout is formed, the same would be contrary to the orders of the Court and would hence be non-est in the eyes of law. He contends that the impugned order is wholly without jurisdiction as it has withdrawn the bulk allotment made after 16 years. He contends that such revisionary power cannot be exercised after inordinate delay and must be exercised within a reasonable time. In support of this contention, he relied upon the judgment of the Hon'ble Supreme Court in the case of Joint Collector and another vs. D. Narsingha Rao and others [2015 (3) SCC 695]. He also relied upon the judgment passed in Kalabharati Advertising vs. Hemant Vimalnath - 25 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 Narichania and others [(2010) 9 SCC 437]. He contends that the allotment made in favour of the petitioner was done upon the approval accorded by the Department of Housing and Urban Development on 06.01.1999 and the letter dated 23.06.2000. Therefore, the permission once having been granted by the Department of Urban Development, the action of the respondent No.1 unilaterally withdrawing the bulk allotment would be non-est and contrary to Government orders. He contends that the conduct of the respondent No.1 is unbecoming. (v) He contends that Article 14 of the Constitution of India mandates that all statutory bodies must act in a fair and transparent manner. In the instant case, the respondent No.1 having demanded and collected a sum of Rs.51,27,500/-, without any reasons, to compound the misery of the petitioner has passed the impugned order not only cancelling the bulk allotment but also forfeiting the consideration paid by the petitioner. He contends that the respondent No.1 represented that the petitioner is a bulk allottee before various Courts in various rounds of litigation and when the petitioner sought - 26 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 conveyance of the subject land, it took a volte face to contend that the allotment was never made and that it was only an offer made by it to the petitioner. He also contends that the respondent No.1 did not even comply with the direction issued in W.P.No.28141/2022 whereby respondent No.1 was directed to handover possession of 1 acre 36 guntas of land in Sy.No.78. He therefore, contends that the action of the respondent No.1 in cancelling the allotment made to the petitioner in bulk after so many years is arbitrary and is liable to be interfered with. 5. Learned Senior counsel for respondent No.1 submitted that the petitioner was admittedly not a Housing Cooperative Society but more in the nature of Credit Co-operative Society. He contends that under Section 38B of the BDA Act, 1976, the petitioner was not entitled for allotment of land in bulk. He contends that the petitioner had represented that it was a Housing Co-operative Society and based upon such a representation, the land in Sy.No.78 of Nagarbhavi was allotted to it. He contends that the objectives of the petitioner was amended from November, 2024 and therefore, till November, - 27 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 2024, the petitioner was not a Housing Co-operative Society and therefore, the respondent No.1 was justified in rejecting the request of the petitioner for conclusion of the allotment. He contends that the amendment of the bye-laws of the society would come into effect from the date, the Registrar registered the amendments. In the instant case, the Registrar initially rejected it and thereafter, had registered it in November, 2024. Thus, he contends that the petitioner is not entitled for allotment of land in bulk since as on the date of the application, the petitioner was not a Housing Society. In support of this contention, he relied upon the judgment of the Co-ordinate bench of this Court in Mallappa vs. The Joint Registrar of Co-operative Societies and another [ILR 1980 Karnataka 1234]. He also referred to the judgments of the Hon'ble Supreme Court in M/s. Jit Ram Shiv Kumar and others vs. State of Haryana and others [(1981) 1 SCC 11] and Shree Sidhbali Steels Limited and others vs State of Uttar Pradesh and others [(2011) 3 SCC 193]. - 28 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 6. I have considered the submissions of the learned Senior counsel for the petitioner and the learned Senior counsel for the respondent No.1. 7. The fact that 5 acres of land in Sy.No.78 of Nagarbhavi was notified by inviting applications from eligible entities for bulk allotment, is not in dispute. It is also not in dispute that the respondent No.1 passed a resolution accepting the request of the petitioner and the same was reserved for the orders of the State Government, who approved it. The State Government thereafter reduced the value of bulk allotment and a demand raised by the respondent No.1 for a sum of Rs.10,25,000/- per acre was also fulfilled by the petitioner. Later, the erstwhile owners of the land in Sy.No.78 challenged the acquisition of the land in W.P.No.27671/2000. The petitioner herein was arrayed as respondent in the said writ petition and it was contended in the said writ petition that the land was proposed to be allotted to the petitioner. Therefore, from the year 2000, the respondent No.1 had an opportunity to recall its resolution and revoke the order of allotment. However, the respondent No.1 did not take any action from the - 29 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 year 2000 till the year 2016 by which time, various writ petitions and other proceedings were initiated before this Court and the Hon'ble Supreme Court, which was defended effectively by the respondent No.1 and the petitioner. In all these proceedings, the respondent No.1 did not think it fit to revisit the order allotting land in bulk to the petitioner. Even in W.P.No.36340/2009, the respondent No.1 offered to allot suitable alternate land to the petitioner but did not chose to cancel the allotment. As a matter of fact, a Co-ordinate Bench of this Court in W.P.No.47525/2016 had reserved liberty to the respondent No.1 to go into the validity or otherwise of the allotment made in favour of the petitioner. However, the respondent No.1 did not take advantage of the said observation and cancel the allotment. 8. As rightly contended by the learned Senior counsel for the petitioner, the petitioner having paid a sum of Rs.51,27,500/- in the year 2000, is entitled to legitimately expect that the respondent No.1 would fulfill its promise by concluding the transaction. It is this legitimate expectation that compelled the petitioner to defend several litigation - 30 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 initiated by the erstwhile landowners in respect of the land bearing Sy.No.78 of Nagarabhavi. As rightly contended by the learned Senior counsel for the petitioner, the respondent No.1 must have rescinded the resolution dated 31.12.1997 within a reasonable time and it cannot sleep over it, even when all the material documents were available to it to take action. It may be that the petitioner was not a housing society as on the date, the application was filed seeking bulk allotment. This Court, however cannot lose sight of the fact that the members of the petitioner would have parted with large sums of money in the fond hope of getting a site. The respondent No.1 therefore, is estopped by conduct from now taking a contrary view to contend that the petitioner was not entitled for allotment of land in bulk under Section 38B of the BDA Act, 1976. As rightly contended by the learned Senior counsel for the petitioner soon after an amendment to the objectives of the petitioner, the same was filed before the Registrar. However, the Registrar did not take a decision in the matter within the time stipulated and consequently, the amendment sought for was deemed to have been registered in view of Section 12(2A) of the Karnataka - 31 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 Cooperative Societies Act, 1959. It may be that the Registrar later rejected the application but the fact remains that prior to the impugned order being passed, there was already an amendment to the objectives of the petitioner society. It is no doubt true that the amendment would come into effect from the date of its registration and in the instant case, the amendment was registered with effect from 04.11.2024 by which time, the impugned order was passed on 26.09.2024. However, as stated above, respondent No.1 having allowed the petitioner to defend various litigation before the various Courts on the premise that it was an allottee of a land in bulk, it cannot now upset the applecart by contending that the petitioner was not entitled to be registered as an applicant for bulk allotment. The respondent No.1 being an instrumentality of the State and a statutory body is bound to stick to its promise and is bound to honour its commitment. The way in which the respondent No.1 has conducted itself over the years and the way in which it has belatedly cancelled the allotment of land in bulk and also forfeit the sum of Rs.51,27,500/-, shows the arbitrary way in which the respondent No.1 has conducted - 32 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 itself. Therefore, this Court has no hesitation that the impugned show-cause notice and the order passed by the respondent No.1 is liable to be interfered with. 9. Consequently, the following order is passed : ORDER (i) The writ petition is allowed. (ii) The impugned show-cause No.¨ÉAC¥Áæ/DAiÀÄÄPÀÛgÀÄ/2488/2016-2017, notice bearing ¨ÉAUÀ¼ÀÆgÀÄ dated 27.07.2016 and the consequent order bearing No.©rJ/DAiÀÄÄPÀÛgÀÄ/GPÁ-1/954/2024-25 dated 26.09.2024 passed by the respondent No.1, are quashed. (iii) The respondent No.1 is directed to convey 5 acres of land in Sy.No.78 of Nagarabhavi village, Yeshwanthpura Hobli, Bengaluru North Taluk, to the petitioner within one month from the date of receipt of copy of this order by executing necessary deeds of conveyance. If the area available in Sy.No.78 is less than 5 acres, the respondent No.1 shall convey - 33 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 the extent available and refund the proportionate consideration along with interest at the rate of 12% per annum from the date of deposit till the date of refund. (iv) On such conveyance, the petitioner shall obtain necessary plan for forming a layout from the respondent No.1 and execute relinquishment deed/s in respect of roads/drains/parks and open spaces in favour of the respondent No.1, who shall maintain same. (v) Copy of this order shall be circulated by the petitioner to all its members. (vi) The petitioner shall also file list of members based on seniority i.e., based on dates when they deposited sital value seeking allotment of sites in Sy.No.78 of Nagarabhavi. Allotment of sites shall only be in accordance with such list. - 34 HC-KAR NC: 2026:KHC:58169 WP No. 29756 of 2024 CNR: KAHC010631292024 (vii) List of seniority shall be filed before this Court within a month from the date of receipt of copy of this Order. List this petition on 20.11.2026 for compliance. In view of disposal of the petitions, pending I.As., if any, do not survive for consideration and the same stand disposed off. Sd/(R. NATARAJ) JUDGE PMR List No.: 1 Sl No.: 44

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Karnataka HC judgments →