IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 27.03.2026
+
ARB.P. 1858/2025
ASHWANI GARG
Through:
.....Petitioner
Mr. Avinash Trivedi & Mr.
Rahul Aggarwal, Advs.
versus
DELHI TOURISM AND TRANSPORTATION
DEVELOPMENT CORPORATION LTD .....Respondent
Through: Mr. Gyanendra Kumar, Adv.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
AVNEESH JHINGAN, J. (ORAL)
1.
The present petition is filed under Section 11(6) of the
Arbitration and Conciliation Act, 1996 (for short „the Act‟) for
appointment of an arbitrator.
2.
The brief facts are that the petitioner was awarded a works
contract for upgradation and face-lifting work of a government school
at Dr. Ambedkar Nagar, Sector-5, New Delhi vide Letter of
Acceptance (for short „LoA‟) dated 03.02.2016. The project was to be
completed within 240 days but was actually completed on 20.06.2018.
Time was extended by the respondent on 12.03.2019 without levying
liquidated damages. The final bill was paid on 30.08.2019. On
31.08.2019, the petitioner addressed a communication to the
Executive Engineer (SP) stating that claims inter alia for escalation in
Signed By:HONEY ARB. P. 1858/2025
ARORA
14:53:43
prices under clauses 10C and 10CA of the contract were pending.
2.1
On 05.12.2023, the petitioner approached the Executive
Engineer (SP) in terms of clause 25 of the General Conditions of
Contract (for short „GCC‟) however, no response was received. On
19.02.2024, the petitioner addressed a letter to the Chief Project
Manager regarding the pending disputes and sought reconciliation. On
04.05.2024, a request was made by the petitioner for formation of a
Dispute Redressal Committee (for short „DRC‟) as provided under
clause 25 of the GCC. Thereafter, a notice under Section 21 of the Act
was issued on 15.07.2024 and hence, the present petition.
3.
Before proceeding further, it would be relevant to reproduce the
clause 25 of the GCC providing for settlement of dispute through
arbitration.
“25. Settlement of Dispute & Arbitration
Except where otherwise provided in the Contract all
questions and disputes relating to the meaning of the
specifications, design, drawings and instructions herein
before mentioned and as to the quality of workmanship or
materials used on the work or as to any other question,
claim, right, matter or thing whatsoever in any way arising
out of or relating to the Contract, designs, drawings,
specifications, estimates, instructions, orders or these
conditions or otherwise concerning the works or the
execution or failure to execute the same whether arising
during the progress of the work or after the cancellation,
termination, completion or abandonment thereof shall be
dealt with as mentioned hereinafter:
1)
If the Contractor considers any work demanded of
him to be outside the requirements of the Contract, or
Signed By:HONEY ARB. P. 1858/2025
ARORA
14:53:43
disputes and drawings, record or decision given in writing
by the Engineer on any matter in connection with or
arising out of the Contract or carrying out of the work, to
be unacceptable, he shall promptly within 15 days request
the superintending engineer shall give his written
instructions or decision within a period of one month from
the receipt of the Contractor‟s letter.
If the superintending engineer fails to give his
instructions or decision in writing within the aforesaid
period or if the Contractor is dissatisfied with the
instructions or decision of the superintending engineer, the
Contractor may, within 15 days of the receipt of the
superintending engineer decision, appeal to the chief
engineer who shall afford an opportunity to the Contractor
to be heard, if the latter so desires, and to offer evidence in
support of his appeal. The Chief Engineer shall give his
decision within 30 days of receipt of contractor‟s appeal.
If the Contractor is dissatisfied with this decision of the
Chief Engineer, the contractor may within 30 days from
the receipt of the Chief Engineer decision, appeal before
the Dispute Redressal Committee (DEC) along with a list
of disputes with amounts claimed in respect of each such
dispute and giving reference to the rejection of his disputes
by the Chief Engineer. The Dispute Redressal Committee
(DRC) shall give his decision within a period of 90 days
from the receipt of Contractor‟s appeal. The constitution of
Dispute Redressal Committee (DRC) shall be as indicated
in Schedule „F‟. If the Dispute Redressal Committee
(DRC) fails to give his decision within the aforesaid period
or any party is dissatisfied with the decision of Dispute
Redressal Committee (DRC), then either party may within
a period of 30 days from the receipt of the decision of
Dispute Redressal Committee (DRC), give notice to the
Chief Engineer for appointment of arbitrator on prescribed
proforma as per appendix XV, failing which the said
decision shall be final binding and conclusive and not
referable to adjudication by the arbitrator.
Signed By:HONEY ARB. P. 1858/2025
ARORA
14:53:43
It is the term of contract that each party invoking
arbitration must exhaust the aforesaid mechanism of
settlement of claims/disputes prior to invoking arbitration.
2)
Except where the decision has become final, binding
and conclusive in terms of Sub Para (1) above, disputes or
difference shall be referred for adjudication through
arbitrator by a sole arbitrator appointed by the chief
engineer, CPWD, in charge of the work there be no chief
engineer, the additional director general, the director
general of the concerned regional work CPWD or if there
be no additional director general, the director of general of
work, CPWD, if the arbitrator so appointed is unable or
unwilling to act or resigns his appointment vacates his
office due to any reason whatsoever, another sole arbitrator
shall be appoint in the manner aforesaid. Such person shall
be entitled to proceed with the reference from the stage at
which it was left by his predecessor.
It is a term of this Contract that the party invoking
arbitration shall give a list of disputes with amount claimed
in respect of each such dispute along with the notice for
appointment of arbitrator and giving reference to the
rejection by the chief engineer of the appeal.
It is also a term of this Contract that no person other
than a person appointed by such Accepting Authority as
aforesaid should act as arbitrator and if for any reason that
is not possible, the matter shall not be referred to
arbitration at all.
It is also a term of this Contract that if the
Contractor does not make any demand for appointment of
arbitrator in respect of any claims in writing as aforesaid
within 120 days of receiving the intimation from the
Engineer-in-Charge that the final bill is ready for payment,
the claim of the Contractor shall be deemed to have been
waived and absolutely barred and the Employer shall be
discharged and released of all liabilities under the Contract
in respect of these claims.
Signed By:HONEY ARB. P. 1858/2025
ARORA
14:53:43
The arbitration shall be conducted in accordance
with the provisions of the Arbitration and Conciliation Act,
1996 (26 of 1996) or any statutory modifications or
reenactment thereof and the rules made there under and for
the time being in force shall apply to the arbitration
proceeding under this clause, except for cases falling under
para 2(i) or (ii).
It is also a term of this Contract that the arbitrator
shall adjudicate on only such disputes as are referred to
him by the appointing authority and give separate award
against each dispute and claim referred to him and in all
cases where the total amount of the claims by any party
exceeds Rs. 1,00,000/- the arbitrator shall give reasons for
the award.
It is also a term of the Contract that if any fees are
payable to the arbitrator, these shall be paid equally by
both the parties.
It is also a term of the Contract that the arbitrator
shall be deemed to have entered on the reference on the
date he issues notice to both the parties calling them to
submit their statement of claims and counter statement of
claims. The venue of the arbitration shall be such place as
may be fixed by the arbitrator in his sole discretion. The
fees, if any, of the arbitrator shall, if required to be paid
before the award is made and published, be paid half and
half by each of the parties. The cost of the reference and of
the award (including the fees, if any, of the arbitrator) shall
be in the discretion of the arbitrator who may direct to any
by whom and in what manner, such costs or any part
thereof shall be paid and fix or settle the amount of costs to
be so paid.”
4.
Learned counsel for the respondent raises an issue that the claim
is time-barred. The contract was completed in 2018 and invocation of
arbitration proceedings was on 15.07.2024. The contention is that the
escalation claim could have been made during the contract period and
Signed By:HONEY ARB. P. 1858/2025
ARORA
14:53:43
not thereafter.
5.
Learned counsel for the petitioner submits that the petitioner
availed the remedies provided under clause 25 of the GCC before
invoking arbitration. It is emphasized that the Supreme Court in the
case of In Re: Congnizance for Extension of Limitation, Suo Motu
Writ Petition (C) No. 3/2020, held that for the purpose of counting
the period of limitation, due to the covid-19 pandemic the period from
15.03.2020 to 28.02.2022 is to be excluded.
6.
The contention that this six-year gap between completion of the
contract and invocation of arbitration renders the claim time-barred is
prima facie ill-founded.
7.
It is undisputed that the final bill was paid on 30.08.2019. At
that time it transpired that the claim of the petitioner for escalation in
prices had not been considered while clearing the final bill. On the
very next day i.e. 31.08.2019, the petitioner apprised the Executive
Engineer (SP) that the claims inter alia under clauses 10C and 10CA
were pending. Clause 25 provides the procedure to be adopted before
invoking arbitration. It is further stipulated that each party before
invoking arbitration must exhaust the mechanism for settlement of
claims. The petitioner approached the respondent on 05.12.2023,
19.02.2024 and 04.05.2024. On failure of the respondent to respond to
the mechanism for settlement of claims, the notice dated 15.07.2024
was issued invoking arbitration.
8.
The only issue that remains is the time period between the
Signed By:HONEY ARB. P. 1858/2025
ARORA
14:53:43
payment of the final bill on 30.08.2019 and the first communication
for pre-arbitration mechanism on 05.12.2023. The Supreme Court in
In Re: Congnizance for Extension of Limitation (supra) considering
the pandemic directed exclusion of the period from 15.03.2020 to
28.02.2022 for computing limitation. With the exclusion of this period
the notice dated 15.07.2024 shall be within three years from the date
of final payment.
9.
At the referral stage, the court cannot go into the merits of the
case and hence the objection of the learned counsel for the respondent
that the claim made by the petitioner has no merits as it was made
after the contract concluded is not dilated upon. There is an arbitration
clause agreed between the parties. The respondent failed to respond to
the notice issued under Section 21of the Act.
10.
The petition is allowed by appointing Mr. Kanwal Jeet Arora,
District and Sessions Judge (Retd.) (Mobile No. 9910384733), as the
sole arbitrator for adjudication of the disputes which have arisen
between the parties.
11.
It is clarified that the observations made hereinabove are only
for the purpose of deciding the petition under Section 11(6) of the Act.
The arbitrator shall proceed with the claims and counter-claims
without being influenced by the observations of this Court.
12.
Arbitral proceedings will be held under the aegis of Delhi
International Arbitration Centre (DIAC). Fee of the Arbitrator shall be
fixed as per fee schedule.
Signed By:HONEY ARB. P. 1858/2025
ARORA
14:53:43
13.
Before entering upon reference, the learned Arbitrator will
comply with Section 12 of the Act.
14.
It is made clear that since this Court has not expressed any
opinion on the merits of the rival claims of the parties and it will be
open for the parties to file their respective claims/counter claims
before the learned Arbitrator which will be considered in accordance
with law.
15.
A copy of this order be forwarded to the learned Arbitrator for
information.
AVNEESH JHINGAN, J
MARCH 25, 2026
Ch
Reportable:- Yes
Signed By:HONEY ARB. P. 1858/2025
ARORA
14:53:43
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review