Sr. No.-
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
Reserved on:20.02.2025.
Pronounced on: 27.02.2025
Arb P No. 69/2023
Ashok Kumar Padha, Age 58 years
S/O Sh. Prabh Dayal,
R/O Ward No.9, adjoining Girls City Middle
School, Lambi Gali, Udhampur.
Through:
…Petitioner(s)
Mr. Anil Khajuria, Advocate.
Vs.
1.
The General Officer Commanding,
71 Sub Area, Patron APS, Dhar Road,
Udhampur,
C/O 56 APO.
2.
The Chairman,
611(I) AD Brigade,
C/O 56 APO
3.
The Vice Chairman,
104 AD Regt.
C/o 56 APO.
4.
The Principal,
Army Public School,
Dhar Road, Udhampur.
Through:
...Respondent(s)
Mr. Vishal Sharma, DSGI.
Arb P No. 70/2023
Ashok Kumar Padha, Age 58 years
S/O Sh. Prabh Dayal,
R/O Ward No.9, adjoining Girls City Middle
School, Lambi Gali, Udhampur.
Through:
…Petitioner(s)
Mr. Anil Khajuria, Advocate.
Vs.
1.
The General Officer Commanding,
71 Sub Area, Patron APS, Dhar Road,
Udhampur,
C/O 56 APO.
...Respondent(s)
Arb P Nos.69&70/2023
2.
The Chairman,
611(I) AD Brigade,
C/O 56 APO
3.
The Vice Chairman,
104 AD Regt.
C/o 56 APO.
4.
The Principal,
Army Public School,
Dhar Road, Udhampur.
Through:
Mr. Vishal Sharma, DSGI.
CORAM:
HON’BLE THE CHIEF JUSTICE
ORDER
1.
As both the two petitions are heard analogously, this court proposes
to dispose of these two petitions by a common order.
2.
Heard Mr. Anil Khajuria, learned counsel for the petitioner and Mr.
Vishal Sharma, learned DSGI for the respondents at length and perused the
record in both the petitions.
3.
These two petitions have been filed by the petitioner seeking
appointment of an independent Arbitrator in both the petitions filed under
Section 11(6) of the J&K Arbitration and Conciliation Act, 1996, to resolve
the dispute that has arisen between the parties.
4.
Brief facts, which lead to the filing of the present petitions, are that
in Arb P No. 69/2023, pursuant to the Request for Proposal initiated by the
respondent by inviting bids for construction of three class rooms on first
floor in existing building with roof trusses on iron colour coated sheets at
Army Public School, Dhar Road, Udhampur for the year 2019-20, the
respondents invited bids in sealed covers for supply of items listed in part-II
of the RFP. The petitioner participated in the bidding process initiated
Arb P Nos.69&70/2023
pursuant to RFP and the bids offered by the petitioner was accepted by the
respondents after negotiations and due deliberations. The contract was
awarded to the petitioner and the same was executed by the petitioner. In the
meantime, the respondents pressurized the petitioner to execute the
additional work over the above the work which formed part of the contract.
Since the petitioner was made to execute the additional work by the
respondents, which did not form part of the tender and in the process the
petitioner had to spend extra amount for the execution of the contract. The
respondents despite receipt of several communications from the petitioner
have failed to make payment to the petitioner to the tune of Rs. 7,48,796/for additional work executed by the petitioner. Consequently, the petitioner
was constrained to issue a communication to the respondents dated
28.03.2023 seeking amicable settlement as well as the release of amount of
Rs. 7.50 lacs towards the payment on account of additional works executed
by the petitioner. It was further requested to the respondents that in case the
amount above referred is not paid, the same communication be treated as a
notice for appointment of arbitrator and the Arbitration Clause in Para 3 of
Part-III (Standard Conditions of RFP) shall stand invoked. The respondents
vide communication dated 25.04.2023 conveyed the petitioner that they have
discharged their contractual obligation. In the aforesaid backdrop, the
petitioner has filed Arb P No. 69/2023 for appointment of sole arbitrator.
5.
Facts which lead to filing of Arb P No. 70/2023 are pursuant to the
Request for Proposal initiated by the respondents by inviting bids for
construction of four class rooms (double storey) and separate washroom for
boys and girls at Army Public School, Dhar Road, Udhampur for the year
Arb P Nos.69&70/2023
2019-20, the respondents invited bids in sealed covers for supply of items
listed in part-II of the RFP. The petitioner participated in the bidding process
initiated pursuant to RFP and the bids offered by the petitioner was accepted
by the respondents after negotiations and due deliberations. The contract was
awarded to the petitioner and the same was executed by the petitioner. In the
meantime, the respondents pressurized the petitioner to execute the
additional work over the above the work which formed part of the contract.
Since the petitioner was made to execute the additional work by the
respondents, which did not form part of the tender and in the process the
petitioner had to spend extra amount for the execution of the contract. The
respondents despite receipt of several communications from the petitioner
have failed to make payment to the petitioner to the tune of Rs2,85,000/payable towards Seismic provisions and have illegally and wrongfully
deducted the said amount from the total payment to be made to the
petitioner. In essence the respondents have in fact deducted an amount of
Rs. 5.70 lacs payable to the petitioner. That in addition to the payment of
RS. 5.70 lacs, the respondents are also liable to pay for an additional amount
of Rs. 14.00 lacs. Despite the receipt of several representations, the
respondents have neither issued completion certificate in favour of petitioner
nor have settled the outstanding amount payable to the petitioner on account
of Seismic provisions and as well as for additional work executed and also
towards the illegally deduced amount of Rs. 2.85 lacs.
6.
Consequently,
the
petitioner
was
constrained
to
issue
a
communication to the respondents dated 29.03.2023 (Annexure-III) seeking
the release of amount of Rs. 9.54 lacs in favour of the petitioner. It was
Arb P Nos.69&70/2023
further requested to the respondents in the said communication that in case
the amount above referred is not paid, the same communication be treated as
a notice for appointment of arbitrator and the Arbitration Clause in Para 3 of
Part-III (Standard Conditions of RFP) shall stand invoked. In view of no
response from the respondents, the petitioner has approached this court by
way of filing this petition for appointment of sole arbitrator.
7.
It is submitted by the learned counsel for the petitioner that a Clause
3 of Part-III- Standard Conditions of RRP talks of referring the disputes,
which cannot be amicably settled, to arbitration. The said clause is
reproduced as below:
3... Arbitration. All disputes or differences arising out of or in
connection with the contract shall be settled by bilateral
discussions. Any dispute, disagreement or question arising out of
or relating to the contract or relating to construction or
performance, which cannot be settled amicably, may be resolved
through arbitration. The standard clause of arbitration is as per
Forms DPM-7, DPM-8 and DPM-9 (The same can be
downloaded from MoD website).
8.
It is stated in the petition that before taking recourse to the
appointment of arbitrator, the petitioner had already sought the settlement
of the issues inter se parties. But the reluctance of the respondents had
constrained the petitioner to issue a notice for appointment of arbitrator and
thus after the expiry of 30 days from the date of receipt of the notice, the
respondents have not taken any step further to resolve the dispute. Hence
the present petitions.
9.
It is submitted that an independent arbitrator is required to be
appointed in this case as no serving officer of the department is eligible to be
Arb P Nos.69&70/2023
so appointed in view of the prohibition contained in Section 12(5) of
Arbitration and Conciliation Act, 1996 read with Schedule 7 thereof.
10.
In the above backdrop, the petitioner approached this court under
Section 11(6) of the Arbitration and Conciliation Act, 1996 for reference of
disputes/claims to an independent arbitrator.
11.
Mr. Vishal Sharma, learned DSGI appearing for the respondents has
filed detailed objections and vehemently resisted the two petitions for
appointment of arbitrator.
12.
The fact that the petitioner has raised certain claims which,
according to the petitioner, have not been addressed by the respondents, this
Court is of the view that a dispute exists between the parties, which would
require resolution in accordance with the aforementioned Clause 3 of
Part-III of Standard Conditions of RFP and this court is of the view that the
dispute has to be ultimately decided by an Arbitrator.
13.
In view of what has been observed hereinabove, I appoint Mr.
Suneet Gupta, retired District & Sessions Judge to act as the sole
Arbitrator in both the petitions, who shall adjudicate the disputes between
the parties and make an award in accordance with law after hearing the
parties and charging the prescribed fee along with incidental expenses to be
shared by the parties.
14.
Parties may raise their claims and counter claims before the learned
Arbitrator. Additionally, all legal contentions, including objections, if any,
available to the respondents, are kept open to be taken up before the learned
Arbitrator.
15.
Registry to inform the Ld. Arbitrator accordingly.
16.
Arb P Nos.69&70/2023
With the above observation and direction, the petitions stand
disposed of.
(TASHI RABSTAN)
CHIEF JUSTICE
JAMMU
27.02.2025
Raj Kumar
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review