IN THE HIGH COURT OF DELHI AT NEW DELHI
+
W.P.(C) 15305/2022
ASHISH KAPOOR & ORS.
.....Petitioners
Through: Mr. Ajay Vikram Singh Ms. Priyanka
Singh Mr. M Aamir Faiyaz, Advs.
versus
DELHI DEVELOPMENT AUTHORITY
.....Respondent
Through: Ms.Vrinda Kapoor, Ms. Saumya
Soni,Mr. Vishal Vaid, Ms. Muskan Narang,
Advocatesfor R1
%
1.
CORAM:
HON'BLE MR. JUSTICE JASMEET SINGH
ORDER
18.02.2026
This is a writ petition filed under Article 226 of the Constitution of
India seeking the following prayer(s):“a. Issue a Writ of Certiorarified Mandamus or any other
Writ, Order or Direction calling upon the Respondent (Delhi
Development Authority) to refund the amount of Rs.
1,25,75,927/- along with 18% interest from the date of
deposited of the said amount by the Petitioners under protest
in view of the illegal demand raised by the Respondent as
composition charges.”
2.
The brief facts are that one plot bearing No. C-336 in Government
School Teachers CHBS Ltd. in Saraswati Vihar, Delhi (“said
property”) was sub-leased by the respondent i.e., Delhi Development
Authority (“DDA”) to one Ms. Pushpa Kapoor, daughter of Sh. Rai
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 25/02/2026 at 15:48:19
Sahib Nar Singh Dass, vide a sub-lease deed executed on 19.10.1975.
3.
Ms. Pushpa Kapoor passed away intestate in the year 1977, without any
Class-I legal heirs. Thereafter, in 1978, Sh. Harish Kapur, real brother
and Class-II Legal heir of deceased Ms. Pushpa Kapoor, filed a Probate
Case being PC No. 384 1994. Later, the Court vide order dated
30.07.2008 in M.C.P. No. 07/2007 ordered to issue Letter of
Administration in favour of Ashish Kapoor i.e., the petitioner No.1 and
Amulya Kapoor, Pratima Kapoor.
4.
In the Probate Case, Letter of Administration was granted on
27.01.2011, on the basis of a compromise arrived at between the
contesting parties. Subsequently, on 30.08.2011, the petitioners moved
an application for mutation of the said property in their name. On
08.02.2012, the petitioners again filed a reminder for mutation.
5.
However, the mutation was not affected in their favor by the
respondent.
6.
The Government School Teachers CHBS Ltd. Saraswati Vihar, Delhi
Society intimated the respondent that the Conveyance Deed in favour
of one Mr. Jagdish Mittal in the said property has been obtained on
fictitious papers.
7.
Consequently, the Class-II legal heirs of the deceased Ms. Pushpa
Kapoor filed a writ petition being W.P.(C) No. 4561 of 2012 for
direction to the respondent to mutate the said property in their name,
which was disposed of vide order dated 17.09.2013 with direction to
petitioners to file fresh application for mutation and to respondent to
process expeditiously.
8.
The petitioners filed fresh application for mutation on 27.12.2013 and
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 25/02/2026 at 15:48:19
filed reminder on 19.05.2014.
9.
Later, a Relinquishment Deed was executed on 13.07.2017, wherein
Pratima Kapoor and Amulya Kapoor relinquished their share in the said
Property to Sh. Ashish Kapoor, Smt. Jyoti Nayar and Smt. Asha Trehan
i.e., the petitioners.
10. Finally, the mutation of the said property was completed by the
respondent in name of the petitioner on 24.12.2018. Thereafter, the
petitioners requested for extension of time for construction and waiver
of compensation on the said land vide letter dated 11.01.2019, which
was accepted by the respondent but on depositing composition fee of
Rs. 1,25,75,927/-.
11. The petitioners duly deposited Rs. 1,25,75,927 under protest.
12. The Conveyance Deed was executed on 22.12.2020 in favour of the
petitioners.
13. The Petitioners on 12.02.2021 moved an application for refund of the
composition amount of Rs. 1,25,75,927/- as the delay in construction
was in view of the pending suit for grant of letter of administration and
conveyance deed.
14. However,the respondent did not refund the composition amount.
Hence, the present petition.
15. Mr. Singh, learned counsel for the petitioners, states that in the present
case, the petitioners were not at fault. From the year 1978 till 2011, the
title of the petitioners was pending adjudication before competent
Courts of law. Thereafter, the respondent had wrongly mutated the
property in some other person’s name and the same was rectified in the
year 2018 only. The petitioners sought extension of time only once
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 25/02/2026 at 15:48:19
thereafter and is not responsible for the delay of about 40 years in
construction.
16. Ms. Kapoor, learned counsel for the respondent, opposes the petition
and states that the delay in construction was on account of inter se
disputes and the respondent is not a party to the same. Additionally, the
petitioners have already deposited the entire composition fee and it is
only thereafter the extension was granted.
17. She relies upon office order dated 09.09.2019 and more particularly
paragraph No. 5 which reads as under:“5.Delegation of powers for permitting EOT is as below:(i) On payment of composition fees as per the above
chart in para 3, Dy. Director of the concerned land
branch is authorized to issue EOT.
(ii) In cases where EOT is granted on old/existing
composition fee rates, the Director of the concerned
land division is authorized to issue EOT.
(iii) Cases where allottee claim relaxation/waiver of
composition fees for compelling reasons (such as stay
of construction by orders of a statutory authority) will
be put up to the Lessor i.e. the Hon’ble LG of Delhi.
(iv) Cases of Government departments/organizations
seeking waiver of composition fees will be decided
by,VC, DDA.”
18. I have heard learned counsels for the parties.
19. Reliance is correctly placed on Vijaya C. Gursahaney v. Delhi
Development Authority, 2013 SCC OnLine Del 913, wherein a
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 25/02/2026 at 15:48:19
Coordinate Bench of this Court held as under:“10. In view of the aforesaid law laid down by this Court,
indubitably the Vice-Chairman has the power to condone the
delay without composition where there are internecine
disputes amongst the legal heirs of the original allottee and to
direct the DDA to take account of the period spent in
litigation. The logic behind this is simple. It is only when
mutation is effected by the DDA after resolution of the pending
litigation that it would be possible for the legal heirs to pursue
their application for extension of time to carry out the
construction. The present case, in my considered opinion,
stands on an even better footing, in that the litigation was
pending between the DDA and the Petitioner in respect of a
demand raised by the DDA for mutating the plot in the name
of the Petitioner. There is no gainsaying that till the mutation
was effected, the Petitioner could not have pursued his
application for extension of time for construction.”
(Emphasis added)
20. Additionally, a legal opinion was drawn by the Law Department, DDA
with respect to issue of waiver of composition fee and the legal opinion
reads as under:“There is no reason as to why the above observation made by
the Hon’ble Court should not apply to the facts of the present
case. It is not possible for the applicants to pursue their
application for extension of time or for construction of
building till mutation is allowed in their favour. They came
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 25/02/2026 at 15:48:19
into picture only when their right to mutation was established
and mutation has been allowed. Therefore, the composition fee
ought not to be levied/charged in the peculiar facts and
circumstances of the case.”
21. I am of the view that in the present case, the delay is not attributable to
the petitioners. The petitioners could have only commenced
construction once the petitioners had clear title to the property (which
was in the year 2011) and thereafter, mutation was carried out in their
favour (which was in the year 2018).
22. The judgment of Vijaya C. Gursahaney (supra), supports the said
view. The legal opinion, as reproduced above, also is on the same lines.
23. For the said reasons, the petition is allowed and the respondent shall
return the composition fee to the petitioners expeditiously and not later
than 6 weeks from today.
24. Mr. Singh, learned counsel for the petitioners, states that the petitioners
are not seeking any interest.
25. In case the amount is not paid within 6 weeks from today, the same
shall carry interest at the rate of 9% per annum.
26. The petition is disposed of in the aforesaid terms.
JASMEET SINGH, J
FEBRUARY 18, 2026 / (MS)
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
The Order is downloaded from the DHC Server on 25/02/2026 at 15:48:19
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review