APHC010448792025
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3331]
TUESDAY, THE SEVENTEENTH DAY OF MARCH
TWO THOUSAND AND TWENTY SIX
PRESENT
THE HONOURABLE SRI JUSTICE SUBBA REDDY SATTI
WRIT PETITION NO: 23957/2025
Between:
1. ARIKATLA KOTI LINGAIAH, S/O. VENKATA RAMNAIAH, AGED
ABOUT 65 YEARS, OCCNOMINEE WORKS COMMITTEE, R/O. 1263A, SIVALAYAM, KONDAPI VILLAGE, AND MANDAL, PRAKASAM
DISTRICT.
...PETITIONER
AND
1. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL
SECRETARY,
PANCHAYAT RAJ
RURAL DEPARTMENT,
SECRETARIAT, VELAGAPUDI, AMARAVATI, GUNTUR DISTRICT. 2.
2. THE STATE OF ANDHRA PRADESH, REP. ITS PRINCIPAL
SECRETARY, FINANCEPLANNING DEPARTMENT, SECRETARIAT
,VELAGAPUDI,AMARAVATI,GUNTUR DISTRICT. 3.
3. THE DISTRICT COLLECTOR PANCHAYAT RAJ WING, ONGOLE,
PRAKASAM DISTRICT. 4
4. THE EXECUTIVE ENGINEER, PRI DIVISION, KANDUKUR, SPSR
NELLORE DISTRICT.
5. THE DEPUTY EXECUTIVE ENGINEER,
KONDAPI, PRAKSAM DISTRICT 6.
PRI
SUB-DIVISION,
6. HE ASSISTANT EXECUTIVE ENGINEER,
KONDAPI, PRAKSAM DISTRICT 7.
PRI
SUB-DIVISION,
7. THE MANDAL PARISHAD DEVELOPMENT OFFICER, MANDAL
PRAJA PARISHAD OFFICER, KONDAPI ONGOLE, PRAKASAM
DISTRICT. 8
8. THE KONDAPI GRAM PANCHAYATHY, REP. BY IT'S PANCHAYAT
SECRETARY,
DISTRICT.
KONDAPI VILLAGE AND MANDAL, PRAKASAM
...RESPONDENT(S):
Petition under Article 226 of the Constitution of India praying that in the
circumstances stated in the affidavit filed therewith, the High Court may be
pleased to issue an appropriate Writ, Order or direction more particularly one
in the nature of Writ of Mandamus declaring action of the Respondents in
withholding the payments of 4 Works (1) Rs. 2,97,575/- (Rupees Two Lakhs
Ninety Seven Thousand Five Hundred and Seventy Five Only) For execution
of Work Improment to the Road From SC Colony to Mupparajupalem Reach
03 in Kondapi GP of Kondapi Mandal with MB.No.09/A/MPP/22, (2)
Rs.2,98,870/-(Rupees Two Lakhs Ninety Eight Thousand Eight Hundred and
Seventy Only) For execution of Work Improment to the Road From SC
Colony to Mupparajupalem Reach 04 in Kondapi GP of Kondapi Mandal with
MB.No.lO/A/MPP/22, (3) Rs.2,97,974/-(Rupees Two Lakhs Ninety Seven
Thousand Nine Hundred and Seventy four Only) For execution of Work
Improment to the Road From SC Colony to Mupparajupalem Reach 05 in
Kondapi GP of Kondapi Mandal with MB.No.10/C/MPP/22 and (4) Rs.Tl,489/(Rupees Eleven Thousand Four Hundred and Eighty Nine Only) For
execution of Work
Improment to the Road From SC Colony to
Mupparajupalem Reach 06 in Kondapi GP of Kondapi Mandalwith
MB.NO.05/C/MPP/22 total amount of Rs. 9,05,908/- (Rupees Nine Lakhs
Five Thousand Nine hundred and Eight Rupees only) under the M.P. General
Fund Grant-2022-23 duly approved by the respondents as bad. illegal,
arbitrary, improper, unjust and against the Article 21 of Constitution of India
and consequently to direct the respondents to release the amounts worth of
Rs.9,05,908/- (Rupees Nine Lakhs Five Thousand Nine hundred and Eight
Rupees only) with interest per annum for the delayed amount till date of
realization for the works executed Improment to the Road From SC Colony to
Mupparajupalem Reach 01,02,03,04,05 and 06 in Kondapi GP of Kondapi
Mandal by the petitioner and to pass
IA NO: 1 OF 2025
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased to
direct the respondents to release the amounts worth of Rs.9,05,908/(Rupees Nine Lakhs Five Thousand Nine hundred and Eight Rupees only)
with interest per annum for the delayed amount till date of realization for the
works executed "Improment to the Road From SC Colony to Mupparajupalem
Reach 01,02,03,04,05 and 06 in Kondapi GP of Kondapi Mandal" by the
petitioner forthwith pending disposal of the above writ petition and to pass
Counsel for the Petitioner:
1. SHAIK MEERAVALI
Counsel for the Respondent(S):
1. GP FOR PANCHAYAT RAJ RURAL DEV
2. GP FOR FINANCE PLANNING
The Court made the following order:
Heard Sri Shaik Meeravali, learned counsel for the petitioner, Sri P.
Rajesh Kumar, learned Assistant Government Pleader for Panchayat Raj and
Rural Development & Finance and Planning Department, for the respondents
1 to 6, and Ms. Kavitha, learned counsel representing Sri M.Sudhir, learned
Standing counsel for the respondents 7 and 8.
2.
The above writ petition was filed to declare the action of the
respondents in not releasing the amount of Rs.9,05,908/- payable to the
petitioner in relation to the works executed by it i.e., 1) Improment to the Road
from SC Colony to Mupparajupalem Reach 03 in Kondapi Gram Panchayat,
Kondapi Mandal, 2) Improment to the Road from SC Colony to
Mupparajupalem Reach 04 in Kondapi Gram Panchayat, Kondapi Mandal, 3)
Improment to the Road from SC Colony to Mupparajupalem Reach 05 in
Kondapi Gram Pancahayat, Kondapi Mandal, and 4) Improment to the Road
from SC Colony to MUpparajupalem Reach 06 in Kondapi Gram Panchayat,
Kondapi Mandal, as illegal and arbitrary.
3.
Today, when the matter is taken up for consideration, Ms.Kavitha,
learned counsel representing Sri M.Sudhir, learned Standing counsel for the
respondents 7 and 8, submitted instructions of the Mandal Parishad
Development Officer, Mandal Praja Parishad, Kondapi – 7th respondent,
dated 04.03.2026. Wherein it is stated as follows:
“I submit that Administration sanction was accorded in respect of 4
works i.e., 1. Providing – M.P. General Fund grant, 2022-23 for
improvement to the Road from S.C colony to Mupparajupalem Reach03, Reach-04, Reach-05 and Reach-06 vide Administration sanction
Rc.No.B/304/2022 dated 19.01.2023 etc., of the M.P.D.O, Kondapi.
Technical Sanction was also accorded to the above works by the
Executive Engineer, PRI Division, Kandukur.
Sri Arikatla Kotilingaiah, nominee works Committee of Kondapi GP
approached the MPDO, Kondapi to conclude the agreement within
week days to complete the works in stipulated time duly following the
guidelines norks under M.P. General Fund and the Assistant Executive
Engineer, Kondapi was accordingly directed to complete the work
under his supervision following the norms imposed by the State
Government, payment will be made from MP General Funds basing on
availability of Funds.
It is submitted that the above works were executed by the Writ
Petitioner i.e., Arikatla Kotilingaiah and requested the MPDO for
payment of the amount due for execution of works. Since there was no
GST number assigned, the writ petitioner was directed to obtain GST
number and then to approach the MPDO. The Writ Petitioner has
obtained GST number belatedly i.e., just one week back and sought for
payment of the amounts due to him. But by that time, there was no
amount available in General funds for making payment to him and the
MPDO assured him payment of one lakh rupees within following week
days and promised him payment of the balance amount within next six
months installment wise as and when the General funds are available
with MPDO.”
4.
Thus, as seen from the instructions, there is no dispute regarding the
execution of work and the petitioner’s entitlement for Rs.9,05,908/-. Since the
amount payable is admitted and undisputed, the writ petition is maintainable.
5.
The Hon’ble Apex Court in Surya Constructions v. State of Uttar
Pradesh and Others1, in Para Nos.3 & 4, has observed as follows:
“3. It is clear, therefore, from the aforesaid order dated 22-3-2014
that there is no dispute as to the amount that has to be paid to the
appellant. Despite this, when the appellant knocked at the doors of
the High Court in a writ petition being Writ Civil No. 25216 of 2014,
the impugned judgment dated 2-5-2014 [Surya Construction v.
State of U.P., 2014 SCC OnLine All 6071] dismissed the writ
petition stating that disputed questions of fact arise and that the
(2019) 16 SCC 794
amount due arises out of a contract. We are afraid the High Court
was wholly incorrect inasmuch as there was no disputed question
of fact. On the contrary, the amount payable to the appellant is
wholly undisputed. Equally, it is well settled that where the State
behaves arbitrarily, even in the realm of contract, the High Court
could interfere under Article 226 of the Constitution of India (ABL
International Ltd. v. Export Credit Guarantee Corpn. of India Ltd.
[ABL International Ltd. v. Export Credit Guarantee Corpn. of India
Ltd., (2004) 3 SCC 553] ).
6.
In M/s Utkal Highways Engineers and Contractors v. Chief General
Manager & Ors2, it was held at Para No.8 as under:
“Be that as it may, the High court has not dealt with the merits of the
writ petition. Moreover, it is not an inviolable rule that no money claim
can be adjudicated upon in exercise of writ jurisdiction. Non-payment
of admitted dues, inter alia, may be considered an arbitrary action on
the part of respondents and for claiming the same, a writ petition may
lie.Further, throwing a writ petition on ground of availability of
alternative remedy after 10 years, particularly, when parties have
exchanged their affidavits, is not the correct course unless there are
disputed questions of fact which by their very nature cannot be
adjudicated upon without recording formal evidence.”.
7.
However, the amount was not paid as per the instructions, due to paucity
of funds. After works were executed, the amount cannot be stopped due to
paucity of funds.
8.
In Mr. S.C. Meena, EE (Project Narela) v. Amit Tanwar3, the Hon’ble
High Court of Delhi, held in Para No.48, which is usefully extracted hereunder:
“48. It is equally strange that the Corporation seeks to justify the
non-payment on the ground of non-availability of funds for
medicines or hospital items or pensions or salaries of the
Corporation. Running the Corporation is not the business of the
Contractor. It is for the Corporation to manage its affairs as per the
funds available with it and it cannot be a defense that the
Contractor should bear the brunt of non-payment for years, of
works executed by him.”
2025 SCC online SC 1400
2018 SCC OnLine Del 8035
9.
In Kashmir Wood Products v. Verinag Development Authority and
Others4, the Hon’ble High Court of Jammu & Kashmir, held in Para No.8,
which is usefully extracted hereunder:
“8. It is astonishing to note that despite there being no dispute as
regards the claim of the petitioners, the respondents have sit over
the matter for the last more than six years and they have not
released the payment in favour of the petitioner. If the requisite
funds were not available with the respondents, they had no
business to allot the work to 4 the petitioner and if in spite of
financial constraints, the respondents have made the petitioner to
execute the work out of his own funds, it is their bounden duty to
reimburse the petitioner at the earliest, that too with interest.”
10.
Given the discussions supra, coupled with the instructions furnished by
the Mandal Parishad Development Officer, Mandal Praja Parishad, Kondapi –
7th respondent, the Writ Petition is disposed of directing the respondents to
release the amount of Rs.9,05,908/- (Rupees Nine Lakhs Five Thousand Nine
Hundred and Eight only) payable to the petitioner regarding execution of
aforementioned work, within three (03) months from the date of receipt of the
copy of this order. No order as to costs.
As a sequel, pending miscellaneous petitions, if any, shall stand closed.
___________________________
JUSTICE SUBBA REDDY SATTI
Date: 17.03.2026
SNI
2021 SCC OnLine J&K 814
THE HONOURABLE SRI JUSTICE SUBBA REDDY SATTI
WRIT PETITION NO: 23957 of 2025
Date: 17.03.2026
SNI
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review