The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
9. Having regard to the submissions made by the learned counsel for both the parties and on perusal of the written instructions placed on record and the order dated 22.07.2026 passed by this Court in W.P.No.19965 of 2026, as contended by the learned counsel for the petitioner, this Court deems it appropriate to extend the similar relief to the petitioner herein also. For better understanding, the operative portion of the order dated 22.07.2026 passed by this Court in W.P.No.19965 of 2026 is extracted hereunder: Having regard to the submissions made by both the counsel, this Court deems it appropriate to dispose of the writ petition, with the following directions: i) The impugned assessment notice dated 14.05.2026 is hereby set aside; ii) Further, the matter is hereby remanded to the respondent No.2 for fresh consideration. iii) The respondents are directed to remove the seals affixed upon the petitioner’s roof top solar power plant, pending such fresh consideration.”
10. In view of the foregoing discussion, the present Writ Petition is disposed of, with the following directions: i) The impugned assessment notice dated 21.07.2026 is hereby set aside; ii) Further, the matter is hereby remanded to the respondent No.2 for fresh consideration and the 2nd respondent is directed to pass a detailed speaking order after affording an opportunity of hearing to the petitioner, if necessary, in accordance with law, at the earliest. There shall be no order as to costs. As a sequel, miscellaneous petitions, if any, pending shall stand closed.
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
APHC010495302026
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
MONDAY, THE 21st DAY OF SEPTEMBER 2026
PRESENT
THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
WRIT PETITION NO: 26958 OF 2026
Between:
1. APITORIA PHARMA PRIVATE LIMITED, Having its Regd. office at Galaxy,
Floors 22-24, Plot No.1 Survey No.83/1, Hyderabad Knowledge City Raidurg
Panmaktha, Ranga Reddy District Hyderabad - 500 032, Having its Unit at
Pydibheemavaram Village, Ranasthalam Mandal, Srikakulam District - 532
409 Bearing HT SC No.SKL-139. Represented by its Authorized Signatory
Ms. M.Vanita D/o. Late Maruti Rao Devatraj R/o. Hyderabad, Telangana
...Petitioner
AND
1. THE STATE OF ANDHRA PRADESH, Rep. by its Principal Secretary
Energy Department, Secretariat
Velagapudi, Amaravati, Guntur District-
522238.
2. Eastern Power Distribution Company of Andhra Pradesh Limited
APEPDCL, Rep. by its Chairman and Managing Director Corporate Office, P
and T Colony Seethammadhara, Visakhapatnam - 530 013.
3. The Superintending Engineer, Operation Circle, APEPDCL Srikakulam 532 001.
4. The Assistant Divisional Engineer, Provisional Assessment Officer,
Operation
409.
Ranasthalam Sub-Division, APEPDCL
Srikakulam District-532
5. The Executive Engineer HT/DPE, APEPDCL, Srikakulam-532001.
6. The Senior Accounts Officer SAO, Operation Circle, APEPDCL
Srikakulam-532 001.
7. The Deputy Executive Engineer, Operation, Ranasthalam, APEPDCL
Srikakulam District-532 409.
...Respondents
Petition under Article 226 of the Constitution of India praying that in the
circumstances stated in the affidavit filed therewith, the High Court may be
pleased to issue a writ direction or order, more particularly one in the nature
of Writ of Mandamus, declaring that the action of the Respondent No.4 in
issuing Assessment Notice for Short Billing vide Lr. No. Dy. EE/
0/
RANASTHALAM/
No
F.
No.
MATS/
D.No.383
Case
HT/DE/DPE/SKL/075092/2026 dated 21.07.2026 levying Grid
Support
ChargesGSC on the Petitioners 10 MW captive co generation Steam Turbine
Generators STGs for the period
from 01.04.2022 to 10.07.2026 and
consequential action of the 6th respondent in issuing C.C bill for the month of
August, 2026 dated.05.09.2026 including a sum of Rs. 1,28,23,580/- Rupees
One Crore Twenty Eight Lakhs Twenty Three Thousand Five Hundred and
Eighty only under the head MATS CASE HT/ DE/ DPE/ SKL/ 075092 /2026,
without considering the Petitioners Reply dt.23.07.2026, without affording any
opportunity of hearing
as wholly illegal, highhanded, arbitrary, irrational,
without jurisdiction, contrary to the provisions of Electricity Act, 2003 and the
Retail Supply Tariff Orders of the Honble APERC, besides being contrary to
the principles of Natural Justice, besides being violative of the Petitioners
fundamental rights guaranteed under Articles 14, 19(1)g and 300-A of the
Constitution of India and consequently set aside the impugned Assessment
Notice for
Short Billing vide Lr. No. Dy. EE/ 0/ RANASTHALAM/ F. No.
MATS/ D.No.383 Case No HT /DE/DPE/SKL/075092/2026 dated 21.07.2026
and direct the Respondent Nos.2 to 7 herein to
forthwith withdraw the
demand of GSC amounting to Rs. 1,28,23,580/- Rupees One Crore Twenty
Eight Lakhs Twenty Three Thousand Five Hundred and Eighty only from the
Petitioners CC bill by declaring that the Petitioner is not liable to pay Grid
Support Charges GSC so long as Petitioners co
generation STGs are
operated in isolation from the Grid and Pass
IA NO: 1 OF 2026
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased
stay all further proceedings pursuant to the impugned Assessment Notice for
Short Billing vide Lr. No. Dy. EE/ 0/ RANASTHALAM/ F. No.MATS/D.No.383
(Case No: HT/DE/DPE/SKL/075092/2026) dated 21.07.2026 issued by the
4„^ Respondent, including the recovery of the sum of Rs. 1,28,23,580/- or any
part thereof included as “MATS CASE HT/ DE/ DPE/ SKL/ 075092/2026” in
the Petitioner‟s CC bill for the month of August, 2026 dated.05.09.2026, and
direct the Respondents not to take any coercive action against the Petitioner
including disconnection of power supply to HT SC No. SKL-139 and pass
IA NO: 2 OF 2026
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased
direct the Respondent Nos.2 to 7 herein not to levy Grid Support Charges
(GSC) in the subsequent monthly C.C bills of the Petitioner‟s HT SC No. SKL139
Counsel for the Petitioner: CKR ASSOCIATES
Counsel for the Respondents: GP FOR ENERGY Counsel for the
Respondents:V V SATISH (SC for APEPDCL)
The Court made the following order:
THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
WRIT PETITION NO: 26958 OF 2026
ORDER:
The present Writ Petition is filed under Article 226 of the Constitution of
India seeking following relief:
“to issue a writ, direction or order, more particularly one in
the nature of Writ of Mandamus, declaring that the action of the
Respondent No.4 in issuing Assessment Notice for Short Billing
vide Lr. No. Dy. EE/ O/ RANASTHALAM/ F. No. MATS/ D.No.383
(Case
No.HT/DE/DPE/SKL/075092/2026)
dated
21.07.2026
levying Grid Support Charges (GSC) on the Petitioner’s 10 MW
captive co- generation Steam Turbine Generators STGs for the
period from 01.04.2022 to 10.07.2026 and consequential action
of the 6th respondent in issuing C.C bill for the month of August,
dated.05.09.2026 including a sum of Rs.1,28,23,580/-
Rupees One Crore Twenty Eight Lakhs Twenty Three Thousand
Five Hundred and Eighty only under the head MATS CASE HT/
DE/DPE/SKL/075092/2026, without considering the Petitioners
Reply dt.23.07.2026, without affording any opportunity of hearing
as wholly illegal, highhanded, arbitrary, irrational, without
jurisdiction, contrary to the provisions of Electricity Act, 2003 and
the Retail Supply Tariff Orders of the Honble APERC, besides
being contrary to the principles of Natural Justice, besides being
violative of the Petitioners fundamental rights guaranteed under
Articles 14, 19(1)g and 300-A of the Constitution of India and
consequently set aside the impugned Assessment Notice for
Short Billing vide Lr.No.Dy.EE/0/RANASTHALAM/F.No.MATS/
D.No.383
(Case
No.HT/DE/DPE/SKL/075092/2026)
dated
21.07.2026 and direct the Respondent Nos.2 to 7 herein to
forthwith withdraw the demand of GSC amounting to Rs.
1,28,23,580/- Rupees One Crore Twenty Eight Lakhs Twenty
Three Thousand Five Hundred and Eighty only from the
Petitioners CC bill by declaring that the Petitioner is not liable to
pay Grid Support Charges GSC so long as Petitioners co
generation STGs are operated in isolation from the Grid and
pass such other order or orders…”
2.
Heard learned counsel for the petitioner and learned Standing Counsel
for the respondents.
3.
Learned counsel for the petitioner submits that petitioner is a
Pharmaceutical company incorporated under the provisions of the Companies
Act, 1956 and it has a manufacturing unit, which requires continuous and
uninterrupted electricity supply for its operations, for which, the petitioner has
accordingly entered into an HT agreement with APEPDCL bearing Service
Connection No.SKL-139, under HT Category IIIA (Industry-General), with
power supply at 132 KV and with a Contracted Maximum Demand of
23,000/KVA, subject to the terms and conditions as contemplated therein and
in accordance with law. The petitioner herein to secure an additional, reliable
and continuous relaying of power in a critical, uninterrupted manufacturing
process and to reduce its energy costs, the petitioner installed a captive Cogeneration plants within the very same premises of Service Connection
No.SKL-139, captive Co-Generation Steam Turbine Generators (STG‟s) of an
aggregate installed capacity of 10 MW, namely STG-1 of 3.0 MW, STG-2 of
2.5 MW and STG-3 of 4.5 MW.
The steam generated in the petitioner‟s
boilers is passed through the said turbines and is thereafter used as process
steam, and thus steam/thermal energy and electricity energy are generated
simultaneously. Since the petitioner‟s plant produces two different forms of
energy simultaneously, then it qualifies as a captive Co-Generation plant. The
entire power so generated is utilized in isolated manner exclusively to meet a
part of the petitioner‟s own internal captive load, correspondingly reducing the
petitioner‟s drawal of power and consumption billed by, the Respondent
DISCOM. The petitioner had duly obtained the statutory approval from the
Director of Electrical Safety and Chief Electrical Inspector to Government of
Andhra Pradesh (CEIG) under Section 54 of the Electricity Act, 2003 read with
Regulation 43 (4) of the Central Electricity Authority (Measures relating to
Safety and Electric Supply) Regulations, 2010. The said CEIG approval is the
only required sufficient statutory clearance as contemplated by law for the
installation and energisation of a captive co-generation plant, and the same
has been obtained by this petitioner without any deviation whatsoever.
4.
Learned counsel for the petitioner further submits that while things
stood thus, on 10.07.2026, respondent No.5 conducted a periodical inspection
of the petitioner‟s premises without issuing any prior notice to the petitioner
and surprisingly, the respondent No.4 issued an assessment notice dated
21.07.2026 purportedly on the alleged ground of defective meter under Clause
7.5.1 of the General Terms and Conditions of Supply categorized as
unauthorized usage of Electricity and demanding the petitioner to pay an
amount of Rs.1,28,23,580/- towards grid supporting charges for the period
from 01.04.2022 to 10.07.2026. It is further stated that if the petitioner is
aggrieved by the said assessment notice, the petitioner can submit an
appropriate representation to the respondent No.3 within a period of 15 days
from the date of receipt of notice and the same will be disposed of after giving
opportunity to the petitioner. If no representation was submitted within 15
days, the charges will be included as arrears in the subsequent bills.
5.
Learned counsel for the petitioner further submits that immediately upon
receipt of the impugned assessment notice, the petitioner addressed
a
detailed representation on 23.07.2026 to the respondent No.3 stating that the
petitioner‟s Co-Gen STGs of 10 MW are operated in isolation mode and as
long as the petitioner‟s plant operates in isolation from the grid, GSC (Grid
Supporting Charges) is not applicable to the petitioner‟s plant. He further
submits that since the petitioner is utilizing the electricity supply for its own
operations, the respondent/DISCOM has no authority over the said power
procured by it. However, the respondents are making the petitioner liable to
pay the grid supporting charges for the period from 01.04.2022 to 10.07.2026,
which is contrary to the facts and law, hence, illegal and arbitrary.
6.
In support of his contention, learned counsel for the petitioner has
drawn the attention of this Court to the order dated 22.07.2026 passed by this
court in W.P.No.19965 of 2026 in similar circumstances and hence, prayed to
extend the same relief to the petitioner herein also.
7.
On the other hand, learned Standing Counsel for the respondents
furnished written instructions issued by the respondents, wherein, it is stated
as follows:
“a) As per the Retail supply Tariff order, the Grid support
charges came into effect from April 2022 and are to be applied
on all the generators that operate either by directly connecting
with Grid or connecting through their loads, shall have to pay
grid support charges unless they operate in complete isolation,
b) As per the CEIG-approved single-line drawing and
observations of the MRT Vigilance wing inspection dated
23.05.2024, the co-generating thermal plants were connected
to the APTRANSCO grid through their connected loads.
c) Hence, the Grid Supporting Charges are to be imposed on
the three co-generating thermal plants from the date of their
applicability.
d) The Grid support charges are to be applied on the total
installed capacity l.e., 10 MW @ Rs.25/-per KW per month for
the co-generation plants connected to the Grid.
e) Further, if the consumer desires to operate their Thermal based Co-Generating plants In continuous isolation mode, it is
required to provide a proper sealing arrangement at the point.
of inter connection of the co-generation thermal plants with the
grid. The continuous isolation mode of operation of the Cogeneration plants is to be declared by the competent authority.
duly ensuring their isolation from the grid till the last load point.
M/S. APITORIA PHARMA PRIVATE LIMITED has no
synchronization approvals for 10 MW (3MW +2.5MW+4.5MW)
Thermal-based Co-Generating captive Power plant.
8.
Learned Standing Counsel for the respondents further submits that the
demand has been raised strictly in accordance with the applicable statutory
provisions and the governing regulations.
9.
Having regard to the submissions made by the learned counsel for both
the parties and on perusal of the written instructions placed on record and the
order dated 22.07.2026 passed by this Court in W.P.No.19965 of 2026, as
contended by the learned counsel for the petitioner, this Court deems it
appropriate to extend the similar relief to the petitioner herein also. For better
understanding, the operative portion of the order dated 22.07.2026 passed by
this Court in W.P.No.19965 of 2026 is extracted hereunder:
Having regard to the submissions made by both the counsel,
this Court deems it appropriate to dispose of the writ petition, with
the following directions:
i)
The impugned assessment notice dated 14.05.2026 is hereby set
aside;
ii)
Further, the matter is hereby remanded to the respondent No.2 for
fresh consideration.
iii)
The respondents are directed to remove the seals affixed upon the
petitioner’s roof top solar power plant, pending such fresh
consideration.”
10.
In view of the foregoing discussion, the present Writ Petition is disposed
of, with the following directions:
i)
The impugned assessment notice dated 21.07.2026 is
hereby set aside;
ii)
Further, the matter is hereby remanded to the
respondent No.2 for fresh consideration and the 2nd
respondent is directed to pass a detailed speaking order
after affording an opportunity of hearing to the petitioner,
if necessary, in accordance with law, at the earliest.
There shall be no order as to costs.
As a sequel, miscellaneous petitions, if any, pending shall stand closed.
__________________________________
VENKATESWARLU NIMMAGADDA, J
21.09.2026
BSP
HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
WRIT PETITION NO: 26958 OF 2026
21.09.2026
BSP
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review