Judgments
LegalFirms.in Judgments · legalfirms.in/judgments/apitoria-pharma-private-limited-vs-the-state-of-andhra-pradesh-20260920/ · Printed 27 Nov 2026
Constitutional

Apitoria Pharma Private Limited vs The State of Andhra Pradesh

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Andhra Pradesh High Court
Date
20 September 2026
Case No.
WP 26958/2026
Result
Disposed
Bench
Venkateswarlu Nimmagadda
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

9. Having regard to the submissions made by the learned counsel for both the parties and on perusal of the written instructions placed on record and the order dated 22.07.2026 passed by this Court in W.P.No.19965 of 2026, as contended by the learned counsel for the petitioner, this Court deems it appropriate to extend the similar relief to the petitioner herein also. For better understanding, the operative portion of the order dated 22.07.2026 passed by this Court in W.P.No.19965 of 2026 is extracted hereunder: Having regard to the submissions made by both the counsel, this Court deems it appropriate to dispose of the writ petition, with the following directions: i) The impugned assessment notice dated 14.05.2026 is hereby set aside; ii) Further, the matter is hereby remanded to the respondent No.2 for fresh consideration. iii) The respondents are directed to remove the seals affixed upon the petitioner’s roof top solar power plant, pending such fresh consideration.”

10. In view of the foregoing discussion, the present Writ Petition is disposed of, with the following directions: i) The impugned assessment notice dated 21.07.2026 is hereby set aside; ii) Further, the matter is hereby remanded to the respondent No.2 for fresh consideration and the 2nd respondent is directed to pass a detailed speaking order after affording an opportunity of hearing to the petitioner, if necessary, in accordance with law, at the earliest. There shall be no order as to costs. As a sequel, miscellaneous petitions, if any, pending shall stand closed.

Filed under

Constitution of India Code of Civil Procedure, 1908 Electricity Act, 2003 Article 226, Constitution of India Section 151, Code of Civil Procedure, 1908

The sections, explained

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

APHC010495302026 IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) MONDAY, THE 21st DAY OF SEPTEMBER 2026 PRESENT THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 26958 OF 2026 Between: 1. APITORIA PHARMA PRIVATE LIMITED, Having its Regd. office at Galaxy, Floors 22-24, Plot No.1 Survey No.83/1, Hyderabad Knowledge City Raidurg Panmaktha, Ranga Reddy District Hyderabad - 500 032, Having its Unit at Pydibheemavaram Village, Ranasthalam Mandal, Srikakulam District - 532 409 Bearing HT SC No.SKL-139. Represented by its Authorized Signatory Ms. M.Vanita D/o. Late Maruti Rao Devatraj R/o. Hyderabad, Telangana ...Petitioner AND 1. THE STATE OF ANDHRA PRADESH, Rep. by its Principal Secretary Energy Department, Secretariat Velagapudi, Amaravati, Guntur District- 522238. 2. Eastern Power Distribution Company of Andhra Pradesh Limited APEPDCL, Rep. by its Chairman and Managing Director Corporate Office, P and T Colony Seethammadhara, Visakhapatnam - 530 013. 3. The Superintending Engineer, Operation Circle, APEPDCL Srikakulam 532 001. 4. The Assistant Divisional Engineer, Provisional Assessment Officer, Operation 409. Ranasthalam Sub-Division, APEPDCL Srikakulam District-532 5. The Executive Engineer HT/DPE, APEPDCL, Srikakulam-532001. 6. The Senior Accounts Officer SAO, Operation Circle, APEPDCL Srikakulam-532 001. 7. The Deputy Executive Engineer, Operation, Ranasthalam, APEPDCL Srikakulam District-532 409. ...Respondents Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue a writ direction or order, more particularly one in the nature of Writ of Mandamus, declaring that the action of the Respondent No.4 in issuing Assessment Notice for Short Billing vide Lr. No. Dy. EE/ 0/ RANASTHALAM/ No F. No. MATS/ D.No.383 Case HT/DE/DPE/SKL/075092/2026 dated 21.07.2026 levying Grid Support ChargesGSC on the Petitioners 10 MW captive co generation Steam Turbine Generators STGs for the period from 01.04.2022 to 10.07.2026 and consequential action of the 6th respondent in issuing C.C bill for the month of August, 2026 dated.05.09.2026 including a sum of Rs. 1,28,23,580/- Rupees One Crore Twenty Eight Lakhs Twenty Three Thousand Five Hundred and Eighty only under the head MATS CASE HT/ DE/ DPE/ SKL/ 075092 /2026, without considering the Petitioners Reply dt.23.07.2026, without affording any opportunity of hearing as wholly illegal, highhanded, arbitrary, irrational, without jurisdiction, contrary to the provisions of Electricity Act, 2003 and the Retail Supply Tariff Orders of the Honble APERC, besides being contrary to the principles of Natural Justice, besides being violative of the Petitioners fundamental rights guaranteed under Articles 14, 19(1)g and 300-A of the Constitution of India and consequently set aside the impugned Assessment Notice for Short Billing vide Lr. No. Dy. EE/ 0/ RANASTHALAM/ F. No. MATS/ D.No.383 Case No HT /DE/DPE/SKL/075092/2026 dated 21.07.2026 and direct the Respondent Nos.2 to 7 herein to forthwith withdraw the demand of GSC amounting to Rs. 1,28,23,580/- Rupees One Crore Twenty Eight Lakhs Twenty Three Thousand Five Hundred and Eighty only from the Petitioners CC bill by declaring that the Petitioner is not liable to pay Grid Support Charges GSC so long as Petitioners co generation STGs are operated in isolation from the Grid and Pass IA NO: 1 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased stay all further proceedings pursuant to the impugned Assessment Notice for Short Billing vide Lr. No. Dy. EE/ 0/ RANASTHALAM/ F. No.MATS/D.No.383 (Case No: HT/DE/DPE/SKL/075092/2026) dated 21.07.2026 issued by the 4„^ Respondent, including the recovery of the sum of Rs. 1,28,23,580/- or any part thereof included as “MATS CASE HT/ DE/ DPE/ SKL/ 075092/2026” in the Petitioner‟s CC bill for the month of August, 2026 dated.05.09.2026, and direct the Respondents not to take any coercive action against the Petitioner including disconnection of power supply to HT SC No. SKL-139 and pass IA NO: 2 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased direct the Respondent Nos.2 to 7 herein not to levy Grid Support Charges (GSC) in the subsequent monthly C.C bills of the Petitioner‟s HT SC No. SKL139 Counsel for the Petitioner: CKR ASSOCIATES Counsel for the Respondents: GP FOR ENERGY Counsel for the Respondents:V V SATISH (SC for APEPDCL) The Court made the following order: THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 26958 OF 2026 ORDER: The present Writ Petition is filed under Article 226 of the Constitution of India seeking following relief: “to issue a writ, direction or order, more particularly one in the nature of Writ of Mandamus, declaring that the action of the Respondent No.4 in issuing Assessment Notice for Short Billing vide Lr. No. Dy. EE/ O/ RANASTHALAM/ F. No. MATS/ D.No.383 (Case No.HT/DE/DPE/SKL/075092/2026) dated 21.07.2026 levying Grid Support Charges (GSC) on the Petitioner’s 10 MW captive co- generation Steam Turbine Generators STGs for the period from 01.04.2022 to 10.07.2026 and consequential action of the 6th respondent in issuing C.C bill for the month of August, dated.05.09.2026 including a sum of Rs.1,28,23,580/- Rupees One Crore Twenty Eight Lakhs Twenty Three Thousand Five Hundred and Eighty only under the head MATS CASE HT/ DE/DPE/SKL/075092/2026, without considering the Petitioners Reply dt.23.07.2026, without affording any opportunity of hearing as wholly illegal, highhanded, arbitrary, irrational, without jurisdiction, contrary to the provisions of Electricity Act, 2003 and the Retail Supply Tariff Orders of the Honble APERC, besides being contrary to the principles of Natural Justice, besides being violative of the Petitioners fundamental rights guaranteed under Articles 14, 19(1)g and 300-A of the Constitution of India and consequently set aside the impugned Assessment Notice for Short Billing vide Lr.No.Dy.EE/0/RANASTHALAM/F.No.MATS/ D.No.383 (Case No.HT/DE/DPE/SKL/075092/2026) dated 21.07.2026 and direct the Respondent Nos.2 to 7 herein to forthwith withdraw the demand of GSC amounting to Rs. 1,28,23,580/- Rupees One Crore Twenty Eight Lakhs Twenty Three Thousand Five Hundred and Eighty only from the Petitioners CC bill by declaring that the Petitioner is not liable to pay Grid Support Charges GSC so long as Petitioners co generation STGs are operated in isolation from the Grid and pass such other order or orders…” 2. Heard learned counsel for the petitioner and learned Standing Counsel for the respondents. 3. Learned counsel for the petitioner submits that petitioner is a Pharmaceutical company incorporated under the provisions of the Companies Act, 1956 and it has a manufacturing unit, which requires continuous and uninterrupted electricity supply for its operations, for which, the petitioner has accordingly entered into an HT agreement with APEPDCL bearing Service Connection No.SKL-139, under HT Category IIIA (Industry-General), with power supply at 132 KV and with a Contracted Maximum Demand of 23,000/KVA, subject to the terms and conditions as contemplated therein and in accordance with law. The petitioner herein to secure an additional, reliable and continuous relaying of power in a critical, uninterrupted manufacturing process and to reduce its energy costs, the petitioner installed a captive Cogeneration plants within the very same premises of Service Connection No.SKL-139, captive Co-Generation Steam Turbine Generators (STG‟s) of an aggregate installed capacity of 10 MW, namely STG-1 of 3.0 MW, STG-2 of 2.5 MW and STG-3 of 4.5 MW. The steam generated in the petitioner‟s boilers is passed through the said turbines and is thereafter used as process steam, and thus steam/thermal energy and electricity energy are generated simultaneously. Since the petitioner‟s plant produces two different forms of energy simultaneously, then it qualifies as a captive Co-Generation plant. The entire power so generated is utilized in isolated manner exclusively to meet a part of the petitioner‟s own internal captive load, correspondingly reducing the petitioner‟s drawal of power and consumption billed by, the Respondent DISCOM. The petitioner had duly obtained the statutory approval from the Director of Electrical Safety and Chief Electrical Inspector to Government of Andhra Pradesh (CEIG) under Section 54 of the Electricity Act, 2003 read with Regulation 43 (4) of the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2010. The said CEIG approval is the only required sufficient statutory clearance as contemplated by law for the installation and energisation of a captive co-generation plant, and the same has been obtained by this petitioner without any deviation whatsoever. 4. Learned counsel for the petitioner further submits that while things stood thus, on 10.07.2026, respondent No.5 conducted a periodical inspection of the petitioner‟s premises without issuing any prior notice to the petitioner and surprisingly, the respondent No.4 issued an assessment notice dated 21.07.2026 purportedly on the alleged ground of defective meter under Clause 7.5.1 of the General Terms and Conditions of Supply categorized as unauthorized usage of Electricity and demanding the petitioner to pay an amount of Rs.1,28,23,580/- towards grid supporting charges for the period from 01.04.2022 to 10.07.2026. It is further stated that if the petitioner is aggrieved by the said assessment notice, the petitioner can submit an appropriate representation to the respondent No.3 within a period of 15 days from the date of receipt of notice and the same will be disposed of after giving opportunity to the petitioner. If no representation was submitted within 15 days, the charges will be included as arrears in the subsequent bills. 5. Learned counsel for the petitioner further submits that immediately upon receipt of the impugned assessment notice, the petitioner addressed a detailed representation on 23.07.2026 to the respondent No.3 stating that the petitioner‟s Co-Gen STGs of 10 MW are operated in isolation mode and as long as the petitioner‟s plant operates in isolation from the grid, GSC (Grid Supporting Charges) is not applicable to the petitioner‟s plant. He further submits that since the petitioner is utilizing the electricity supply for its own operations, the respondent/DISCOM has no authority over the said power procured by it. However, the respondents are making the petitioner liable to pay the grid supporting charges for the period from 01.04.2022 to 10.07.2026, which is contrary to the facts and law, hence, illegal and arbitrary. 6. In support of his contention, learned counsel for the petitioner has drawn the attention of this Court to the order dated 22.07.2026 passed by this court in W.P.No.19965 of 2026 in similar circumstances and hence, prayed to extend the same relief to the petitioner herein also. 7. On the other hand, learned Standing Counsel for the respondents furnished written instructions issued by the respondents, wherein, it is stated as follows: “a) As per the Retail supply Tariff order, the Grid support charges came into effect from April 2022 and are to be applied on all the generators that operate either by directly connecting with Grid or connecting through their loads, shall have to pay grid support charges unless they operate in complete isolation, b) As per the CEIG-approved single-line drawing and observations of the MRT Vigilance wing inspection dated 23.05.2024, the co-generating thermal plants were connected to the APTRANSCO grid through their connected loads. c) Hence, the Grid Supporting Charges are to be imposed on the three co-generating thermal plants from the date of their applicability. d) The Grid support charges are to be applied on the total installed capacity l.e., 10 MW @ Rs.25/-per KW per month for the co-generation plants connected to the Grid. e) Further, if the consumer desires to operate their Thermal based Co-Generating plants In continuous isolation mode, it is required to provide a proper sealing arrangement at the point. of inter connection of the co-generation thermal plants with the grid. The continuous isolation mode of operation of the Cogeneration plants is to be declared by the competent authority. duly ensuring their isolation from the grid till the last load point. M/S. APITORIA PHARMA PRIVATE LIMITED has no synchronization approvals for 10 MW (3MW +2.5MW+4.5MW) Thermal-based Co-Generating captive Power plant. 8. Learned Standing Counsel for the respondents further submits that the demand has been raised strictly in accordance with the applicable statutory provisions and the governing regulations. 9. Having regard to the submissions made by the learned counsel for both the parties and on perusal of the written instructions placed on record and the order dated 22.07.2026 passed by this Court in W.P.No.19965 of 2026, as contended by the learned counsel for the petitioner, this Court deems it appropriate to extend the similar relief to the petitioner herein also. For better understanding, the operative portion of the order dated 22.07.2026 passed by this Court in W.P.No.19965 of 2026 is extracted hereunder: Having regard to the submissions made by both the counsel, this Court deems it appropriate to dispose of the writ petition, with the following directions: i) The impugned assessment notice dated 14.05.2026 is hereby set aside; ii) Further, the matter is hereby remanded to the respondent No.2 for fresh consideration. iii) The respondents are directed to remove the seals affixed upon the petitioner’s roof top solar power plant, pending such fresh consideration.” 10. In view of the foregoing discussion, the present Writ Petition is disposed of, with the following directions: i) The impugned assessment notice dated 21.07.2026 is hereby set aside; ii) Further, the matter is hereby remanded to the respondent No.2 for fresh consideration and the 2nd respondent is directed to pass a detailed speaking order after affording an opportunity of hearing to the petitioner, if necessary, in accordance with law, at the earliest. There shall be no order as to costs. As a sequel, miscellaneous petitions, if any, pending shall stand closed. __________________________________ VENKATESWARLU NIMMAGADDA, J 21.09.2026 BSP HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 26958 OF 2026 21.09.2026 BSP

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All AP HC judgments →