Page No.# 1/18
GAHC010070822024
2026:GAU-AS:623
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WP(C)/2123/2024
ANUP TRADE AND TRANSPORT PVT LTD
A COMPANY REGD. UNDER THE COMPANIES ACT, 1956 HAVING ITS REGD
OFFICE AT H.NO-51, SUNDARPUR MAIN LANE, JAPORIGOG, GUWAHATI05, KAMRUP (M),
RE. BY THE DIRECTOR, ANUP KUMAR JASRASARIA
VERSUS
FOOD CORPORATION OF INDIA AND 3 ORS
REP. BY ITS CHAIRMAN CUM MANAGING DIRECTOR, HEADQUARTERS,
16-20, BARAKHAMBA ROAD, NEW DELHI-06, ASSAM
2:EXECUTIVE DIRECTOR (NE)
FOOD CORPORATION OF INDIA
ASSAM
GS ROAD
PALTAN BAZAR
G
3:GENERAL MANAGER
FOOD CORPORATION OF INDIA
ASSAM REGIONAL OFFICE
ASSAM REGION
G.S ROAD
PALTAN BAZAR
4:ASSISTANT GENERAL MANAGER (CONTRACT)
FOOD CORPORATION OF INDIA
ASSAM REGIONAL OFFICE
ASSAM REGION
G.S ROAD
Page No.# 2/18
PALTAN BAZA
BEFORE
HON’BLE MR. JUSTICE DEVASHIS BARUAH
Advocates for the petitioner(s)
:
Mr. B Chakraborty
Advocates for the respondent(s)
:
Mr. PK Roy
Senior Advocate
Mr. SK Chakraborty
Date on which Judgment is reserved
:
Date of Pronouncement of Judgment
: 20.01.2026
Whether the Pronouncement is of the
Operative Part of the Judgment
: NA
Whether the Full Judgment has been
Pronounced
: Yes
NA
JUDGMENT & ORDER (ORAL)
Heard Mr. B Chakraborty, the learned counsel appearing on
behalf of the petitioner. I have also heard Mr. PK Roy, the learned
Senior Counsel assisted by Mr. SK Chakraborty, who appears on behalf
of the Food Corporation of India (for short, the FCI).
2.
The present petition has been filed by the petitioner for setting
aside and quashing the orders dated 20.05.2023 and 05.12.2023 and
the petitioner further has sought for a direction for refund of the
deducted amount of Rs.45,99,718/- from the petitioner with interest
@ 12% per annum.
Page No.# 3/18
3.
The brief facts of the case are that a Notice Inviting Tender was
issued on 04.10.2019 by the FCI for appointment on regular basis for
a period of 2(two) years in respect of Transport Contract Ex Rly.
Siding/FSD
weighbridge.
North
Lakhimpur
to
FSD
The
estimated
value
Ziro
of
(Dolopoliong)
the
contract
via
was
Rs.4,88,00,000/-. The petitioner participated in the said tender
process and an acceptance letter dated 17.12.2019 was issued which
the petitioner duly accepted by the communication dated 03.01.2020.
4.
Pursuant thereto, the petitioner was appointed as a Transport
Contractor Ex Rly. Siding/FSD North Lakhimpur to FSD Ziro
(Dolopoliong) via weighbridge on regular basis for a period of two
years. It is very relevant to take note of that in the appointment letter,
there was no mention as regards the quantity of goods the petitioner
had to transport. But what was mentioned was that the petitioner was
appointed as a Transport Contractor Ex Rly. Siding/FSD North
Lakhimpur to FSD Ziro (Dolopoliong) via weighbridge on regular basis
for a period of two years with immediate effect i.e 26.02.2020 at a
quoted rate of Rs.2288/- per MT for the entire distance for
transportation. It was also mentioned in the said appointment letter
that in the event of failure, the Assistant General Manager (Cont) for
General Manager (R) /and or Divisional Manager FCI, North
Page No.# 4/18
Lakhimpur reserved the right to get the work done at the petitioner's
risk and cost to maintain Public Distribution System intact and on such
event, the extra cost and expenditure that shall incur in the process
will straightway be recovered from any of the petitioner’s dues on any
account in terms of the tender agreement either during the currency
of the contract or thereafter.
5.
The petitioner upon receipt of the said appointment letter dated
26.02.2020 duly accepted the terms vide the communication dated
07.03.2020.
6.
The record reveals that the petitioner during the entire period
from April 2020 to May 2021 could transport only 1371.123 MT
against the allocated quantity of 33,950 MT resulting in a substantial
shortfall of 32578.877 MT.
7.
It is the further case of the petitioner that the respondent
authorities thereupon initiated process for engaging other contractors
on adhoc basis for the transportation work from RH/FSD North
Lakhimpur via FSD Ziro by issuance of adhoc tender on spot basis
dated 22.07.2020. The said aspect was also informed to the petitioner
by communication dated 23.07.2020.
8.
The record further reveals that a contractor was appointed vide
Page No.# 5/18
the communication dated 27.07.2020 at a quoted rate of Rs.3990/per MT for the entire distance. The said contractor namely, Dipen
Saikia could supply only 117 MT and, as such, on account of the
additional amount, an amount of Rs.2.3 Lacs was recovered from the
petitioner.
9.
It is the further case of the petitioner that the FCI issued another
Notice Inviting Tender dated 24.04.2021 and the contract was
awarded to one M/s. Atu Apa, Developers (Proprietor Sanngha Tagik)
at a rate of Rs.2333.33 per MT from 27.08 2021 to 25.02.2022. It is
the case of the petitioner that since the rate of the petitioner i.e
Rs.2228/- per MT became Rs.2333.41/-, taking into account the diesel
price hike vis-à-vis, the adhoc rate of Rs.2333.33 per MT, there was
no loss/recovery from the petitioner.
10.
It is the further case of the petitioner that on account of the
failure on the part of the petitioner to transport the allocated quantity
the respondents have also imposed damages by applying Clause X(b)
of the Model Tender Form and an amount of Rs.10,50,000/- had been
imposed upon the petitioner.
11.
Mr. B. Chakraborty, the learned counsel appearing on behalf of
the petitioner submitted that the petitioner does not have any
Page No.# 6/18
grievance as regards the imposition of Rs.10,50,000/- as well as
Rs.2,30,000/- made by the FCI. The grievance of a petitioner is that
vide an order dated 20.05.2023, the respondent authorities have
imposed a fine of Rs.45,99,718/-. It is the case of a petitioner that the
said aspect has been decided only on the basis of a CAG report and
contrary to the terms and conditions of the contract.
12.
The petitioner upon being issued the order on 20.05.2023,
sought for a clarification from the respondent FCI vide the
communication dated 20.07.2023. On 30.08.2023, a communication
was issued by the FCI giving clarification as to how the amount of
Rs.45,99,718/- was arrived at and why recovery is sought to be made
from the petitioner.
13.
Being aggrieved, the petitioner submitted an application on
23.08.2023 before the Grievance Redressal Committee (GRC) for
redressal of his grievance against the order dated 20.05.2023. The
application submitted by the petitioner before the GRC was, however,
rejected, as was intimated to the petitioner by the respondent No.2
vide the communication dated 01.01.2024. It is under such
circumstances, the petitioner has assailed the order dated 20.05.2023
as well as the order dated 05.12.2023 and sought for refund of the
entire amounts which have been recovered from the petitioner in the
Page No.# 7/18
meantime.
14. The instant writ petition was filed on 02.04.2024. This Court vide
an order dated 20.04.2024 issued notice and further observed that
the pendency of the writ petition shall not be a bar for the respondent
authorities to examine the claim of the petitioner for reversal of the
deduction.
15. The record reveals that an affidavit-in-opposition was filed by the
respondents on 28.08.2025. In the said affidavit-in-opposition, it was
categorically mentioned that the petitioner failed to perform the
contractual duties as mandated in the contract. Details were given as
regards the trucks required and the trucks supplied by the petitioner
at paragraph No.3 of the said affidavit-in-opposition. It was further
mentioned that the pleas which have been taken by the petitioner
were non-acceptable pleas. It was also stated that in the appointment
letter, it was categorically mentioned that in the event of failure, the
FCI authorities reserved the right to get the work done at the
petitioner's risk and cost to maintain the public distribution system
intact and in such circumstances, the extra cost and expenditure that
shall be incurred in the process would be straightway recovered from
any of the dues of the petitioner in any account in terms of the tender
agreement either during the currency of the contract or thereafter. It
Page No.# 8/18
was mentioned that the petitioner duly accepted the said term and
submitted the joining report on 07.03.2020.
16.
At paragraph 7 of the said affidavit, it was also mentioned that
the petitioner cannot take the plea as regards the area where the
supply was required to be made inasmuch as, the tenderers were
required to get themselves fully acquainted with the size and location
of the Godown vis-à-vis, the loading or the unloading points before
submission of the tender.
17. At paragraph No.9 of the affidavit-in-opposition all the allegations
which have been made by the petitioner were rebutted. It was
mentioned that the representations which were made by the
petitioner were duly considered and thereupon rejected.
18. At paragraph number 9(g), it was mentioned that the deduction
of Rs.45,99,718/- was done for the additional stock of 15447.294 MT
moved through the alternative route Ex-FSD Bandarduwa to route
amounting to incur additional expenditure by FCI i.e. Rs.15447.294 x
Rs.252= Rs.38,00,000/- and the short deduction of Liquidation
Damage as found by the CAG was Rs.7.07 Lacs and, therefore, the
competent authority imposed a total recovery of Rs.45,99,718/-. It
Page No.# 9/18
was also mentioned that the petitioner’s application dated 23.08.2023
was duly considered as per the established procedure and by giving
the petitioner sufficient opportunity to present his case.
19.
At paragraph No.9(m), the details were given as to how the
amount of Rs.45,99,718/- was in accordance with the terms and
conditions of the contract.
20.
To the said affidavit-in-opposition, an affidavit-in-reply was filed
reiterating the statements which have been made in the writ petition.
At paragraph No.14 of the affidavit-in-reply, the petitioner alleged that
recovery of Rs.38,92,718.08 was illegal and not permissible on the
ground that the contract with M/s.TT Enterprise was a separate
contract from different destination i.e. Bandarduwa/Harmutty to Ziro,
which was awarded much prior to the contract awarded to the
petitioner. It was, therefore, alleged that it cannot be contended by
the FCI that the TT Enterprise was appointed when the petitioner had
defaulted. It was, therefore, contended that the procedure adopted by
the CAG to work out the loss of Rs.252 per MT with reference to that
contract was illegal.
It was also mentioned that a contract VOC with TT Enterprise
was Rs.6,58,00,000 @ Rs.2540/- per MT, and, therefore, the minimum
Page No.# 10/18
estimated transportation of that contract was 25,905.51 MT. It was
further mentioned that the excess transportation of Rs.5400.185 MT
by CAG from May 2020 to July 2020 which was calculated was not
intimated. The petitioner further questioned as to how excess
transportation by M/s.TT Enterprise of 15447.294 MT was calculated
by the FCI is not known and, therefore, the recovery was arbitrary on
that ground also.
21.
In the backdrop of above pleadings, this Court had also heard
the learned counsels appearing on behalf of the parties.
22.
Mr. B. Chakraborty, the learned counsel appearing on behalf of
the petitioner submitted that the imposition of risk and cost upon the
petitioner @ Rs.252 per MT for supply of 15447.294 per MT was
contrary to the terms and conditions of the contract, inasmuch as, as
per the terms and conditions of the contract, the imposition of risk
and cost can only be made when there was a failure on the part of
the petitioner. Referring to the appointment order of M/s. TT
Enterprise, the learned counsel submitted that the appointment order
of M/s.TT Enterprise was dated 23.09.2019, which was much prior to
the alleged default committed by the petitioner. Therefore, the
imposition of the amount of Rs.38,00,000/- is illegal and completely
unjustified.
Page No.# 11/18
23. The learned counsel appearing on behalf of the petitioner further
submitted that there is also no material on record to show that the
respondent FCI had transported 15447.294 MT which was allocated to
the petitioner through M/s. TT Enterprise. Merely on the basis of the
CAG objection, the respondent authorities cannot be permitted to
recover from the petitioner, if the respondents have not in fact
transported such food grains which were allocated to the petitioner.
24. Per contra Mr. P K Roy, the learned Senior Counsel appearing on
behalf of the respondents submitted that the petitioner herein had not
assailed the communication dated 03.08.2023, whereby the petitioner
was duly intimated as to how the amount of Rs.45,99,718/- had been
imposed upon the petitioner. The learned Senior Counsel for the
respondents further submitted that the petitioner had also not
assailed the communication dated 01.01.2024. On these grounds
alone, the instant writ petition cannot succeed. The learned Senior
Counsel by referring to the affidavit-in-opposition submitted that the
petitioner
was appointed
for
a period
of
2(two)
years
for
transportation of the food grains from RH/FSD North Lakhimpur to
FSD Ziro and despite multiple notices from the FCI, the petitioner
performance was inadequate with delayed and incomplete service
deliveries thereby jeopardizing the food security under the PDS. The
Page No.# 12/18
learned Senior Counsel further submitted that though the petitioner
had blamed the external factors, but other contractors successfully
managed under similar conditions.
25.
The learned Senior Counsel for the respondents further
submitted that from the month of April 2020 to May 2021 against the
allocated quantity of 33,950 MT, the petitioner transported only
1371.123 MT resulting in a substantial shortfall of 32578.877 MT. The
FCI was compelled to engage alternative contractors under the risk
and cost clause as per clauses X and XI of the Model Tender Form
ensuring uninterrupted food supply. The learned Senior Counsel
submitted that M/s. TT Enterprise and Mr. Dipen Saikia had to be
engaged at higher rates to compensate for the non-performance of
the petitioner so as to fulfill PDS requirement. The FCI had no other
option rather than allowing another tender of higher rate for
dispatching the stocks and this loss was suffered by FCI due to the
negligence on the part of the petitioner. It is under such
circumstances, the respondents FCI had deducted the loss suffered by
the Corporation as per Clause X(a).
26.
The alternative contractors were appointed keeping in view the
interest of the Corporation. Further parallel contractor such as Mr.
Dipen Saikia was appointed for the same reason and recovery was
Page No.# 13/18
made in terms of Clause XI(c). The differential cost incurred due to
this arrangement amounting to Rs.13.60 Lacs which was recoverable
from the petitioner. Further to that as per the contract provisions
Liquidated Damages of Rs.10.85 Lacs was levied, but only 3.79 Lacs
was recovered leading to a short recovery of 7.07 Lacs. It was further
mentioned that 15447.294 MT was supplied through alternative route
Ex-FSD Bandarduwa to FSD Ziro, that too, at the request of the
petitioner which had resulted in incurring additional expenditure of
Rs.38 Lacs.
27. The learned Senior Counsel further referred to the representation
submitted by the petitioner dated 30.04.2021 before the Grievance
Redressal Committee (GRC), and further referred to paragraph No.69,
whereby the petitioner itself suggested that the FCI may approach the
parallel contractor, i.e. Ex. Railhead Harmutty for this tender to fulfill
the remaining tenure of the tender and the petitioner was ready to
pay the difference of the amount to the parallel contractor only
because the petitioner had tried every possible means to complete the
tender peacefully.
28. The learned Senior Counsel, therefore, submitted that taking into
account the very stand of the petitioner as contained in paragraph
No.69 of the representation dated 30.04.2021, the instant writ
Page No.# 14/18
petition is totally misconceived.
29.
I have heard the learned counsels appearing on behalf of the
parties and have perused the materials on record.
30.
A perusal of the Notice Inviting Tender dated 04.10.2019
stipulates that the estimated value of the contract in question was
Rs.4,88,00,000/-. The petitioner has submitted his offer and a letter
of acceptance was issued on 17.12.2019. The petitioner thereupon
was issued the appointment letter on 26.02.2020, wherein the rate
was quoted at Rs.2228/- per MT for the entire distance for
transportation. The petitioner accepted the said appointment letter.
One of the conditions so mentioned in the appointment letter having
relevance is reproduced hereinunder:
“…In the event of failure, the undersigned/ and or Divisional Manager, FCI, North
Lakhimpur reserves the right to get the work done at your Risk and Cost to maintain
Public Distribution System intact, and on such even the extra cost and expenditure that
shall incur in the process, will be straightway recovered from any of your dues on any
account in terms of the tender agreement either during the currency of the contract or
thereafter.”
31.
The above-quoted stipulation in the appointment letter
empowered the General Manager (R) /and or Divisional Manager FCI,
North Lakhimpur to get the work done at the petitioner's risk and cost
Page No.# 15/18
to maintain the Public Distribution System intact, if there was a failure
on the part of the petitioner and such extra cost and expenditure
would be straightway recovered from any of the petitioner’s dues on
any account in terms of the tender agreement either during the
currency of the contract or thereafter.
32. The petitioner with open eyes accepted the said terms vide the
communication dated 07.03.2020. The fact that the petitioner failed to
supply is not in dispute. The further fact that the petitioner
transported only 1371.123 MT for the period from April 2020 to May
2021 is also not in dispute. The respondent FCI have categorically
stated that the petitioner was allocated a total quantity of 33,950 MT
and there was a substantial short fall of 32578.877 MT.
33. As per the submissions made by Mr. B Chakraborty, the learned
counsel appearing on behalf of the petitioner, the imposition in terms
with Clause X(a), as well as the imposition of an amount of Rs.2.3
Lacs on the basis of risk and cost is not what the petitioner is
aggrieved. The grievance of the petitioner as submitted by the
learned counsel was that without carrying out the process of any risk
and cost endeavour, an amount of Rs.38,00,000/- was imposed upon
the petitioner for non-supply of the additional stock of 15447.294 MT
through an alternative route Ex-FSD Banderdewa to FSD Ziro which
Page No.# 16/18
was not as per the terms and conditions of the contract, inasmuch as,
the additional amount of Rs.252 per MT was recovered on the basis of
certain CAG objection. But a question arises as to whether the
petitioner can raise such issues in the present facts and circumstances
of the case, more particularly, in a writ proceedings. In this regard,
this Court finds it very pertinent to take note of the representation so
submitted by the petitioner before the Grievance Redressal Committee
dated 30.04.2021 and, more particularly, to the contents of paragraph
69 wherein the petitioner referred to an application dated 08.03.2021
thereby suggesting that the FCI may approach the parallel contractor
i.e. Ex. Railhead Harmutty to fulfill the remaining tenure of the tender
and the petitioner was ready to pay the difference of the amount to
the parallel contractor. Paragraph 69 of the said representation dated
30.04.2021 being relevant is reproduced hereinunder:
“69.
Faced with such impediments and unrealistic demands/indented quantity, we
preferred an application dated 08.03.2021 before the Grievance Redressal Committee,
wherein we, without prejudice, suggested that FCI may approach the Parallel contractor
i.e. Ex. Railhead Harmutty for this tender to fulfil the remaining tenure of the tender and
we were ready to pay the difference of amount to the parallel contractor only because
we have tried every possible means to complete this tender peacefully but the
concerned authorities are never satisfied and making unrealistic demands. The content
of our letter dated 08.03.2021 may be deemed and treated as part and parcel of the
instant application and contents thereof are not reiterated herein for sake of brevity.”
Page No.# 17/18
34. The petitioner has raised issues in the affidavit-in-reply as to the
authenticity of the claim of the FCI that 15447.294 MT was
transported by M/s. TT Enterprise which was originally allocated to the
petitioner. In the opinion of this Court, this aspect as to whether
15447.294 MT were at all supplied by M/s. TT Enterprise which was
originally allocated to the petitioner is an issue which would require an
elaborate adjudication on the basis of evidence. Be that as it may,
taking into account the stand taken at paragraph 69 of the
representation dated 30.04.2021, one aspect is clear that the
petitioner had no objection in paying the difference of the amount, if
the allocated quantity which the petitioner could not supply was
transported through a parallel contractor i.e Ex. Railhead Harmutty.
35. Considering the above, it is the opinion of this Court that this
Court in exercise of the writ jurisdiction would not be the appropriate
Court for deciding as to whether the FCI transported 15447.294 MT
from the allocated quantity of the petitioner through M/s. TT
Enterprise. It is also the opinion of this Court that this factual
adjudication would impact on the legality and validity of the impugned
demand and recovery made by the FCI. Accordingly, the instant writ
petition, therefore, stands disposed of with the following observations
and directions:
(i). In view of what has been discussed hereinabove, this
Court is not inclined to decide the legality and validity of the
Page No.# 18/18
impugned orders dated 20.05.2023 and 05.12.2023. The
reason being that it would require an in-depth analysis of the
evidence which a competent Court of Civil Jurisdiction can
adjudicate.
(ii). This Court grants liberty to the petitioner to approach
the competent Civil Court challenging the orders dated
20.05.2023 as well as 05.12.2023 as well as the recovery of
Rs.45,99,718/- from the petitioner and seek realization, if so
advised.
(iii). This Court further is of the opinion that the petitioner
having bona fidely litigated before this Court is entitled to the
benefit of Section 14 of the Limitation Act, 1963 and
accordingly the period from 02.04.2024 till date be excluded
while computing the period of limitation.
(iv). The observations made in the present judgment shall
not prejudice either of the parties in any such proceedings
initiated before a competent court of writ jurisdiction.
36. There shall be no order as to costs.
JUDGE
Shivani
Gautam
Shivani Gautam
Date: 2026.01.28
17:39:25 +05'30'
Comparing Assistant
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review