10. Accordingly, without expressing any opinion on the merits of the rival claims, this Writ Petition is disposed of with the following directions: (i) Respondent No.5, the Central Electricity Regulatory Commission, shall take up the interlocutory application filed by the petitioner RC,J W.P.No.29862 of 2026 along with its petition dated 09.10.2026, afford an opportunity of hearing to the concerned parties, and pass an appropriate reasoned order, in accordance with law, as expeditiously as possible, preferably within two weeks from the date of receipt of a copy of this order. (ii) Until respondent No.5 passes orders on the said interlocutory application, respondent No.2 shall not allocate, reallocate, or otherwise grant the disputed 100 MW connectivity, revoked by proceedings dated 01.10.2026, in favour of any third party. (iii) There shall be no order as to costs. As a sequel, pending miscellaneous applications, if any, shall stand closed. 12TH October, 2026
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
RC,J
W.P.No.29862 of 2026
APHC010548402026
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3332]
MONDAY, THE 12th DAY OF OCTOBER 2026
PRESENT
THE HONOURABLE SRI JUSTICE RAVI CHEEMALAPATI
WRIT PETITION NO: 29862/2026
Between:
1. ANDHRA PRADESH SOLAR POWER CORPORATION PVT. LTD.,
THROUGH
ITS
AUTHORIZED
SIGNATORY,
VENKATA
SATYANARAYANA JAYAVARAPU, REGISTERED OFFICE AT 3RD
FLOOR, VIDYUT SOUDHA, GUNADALA, VIJAYAWADA
VIJAYAWADA-520 004,
NTR DISTRICT, ADMINISTRATIVE OFFICE AT FLAT NO.401 AND
402,
GARUDA
ENCLAVE,
EN
TADEPALLI522
501,
GUNTURDISTRICT,A.P.
...PETITIONER
AND
1. UNION OF INDIA, UNION OF INDIA, MINISTRY OF NEW AND
RENEWABLE ENERGY (MNRE) REP. BY ITS SECRETARY, NEW
DELHI.
2. CENTRAL TRANSMISSION UTILITY OF INDIA, REP. BY ITS CHIEF
OPERATING OFFICER, 5TH AND 10TH FLOOR, TOWER-1,
TOWER 1, IRCON
INTERNATIONAL TOWER, FLAT NO.16, SECTOR
SECTOR- 32, GURUGRAM,
HARYANA.
3. GRID CONTROL OF INDIA, SOUTHERN REGIONAL LOAN
DISPATCH CENTRE,
THROUGH EXECUTIVE DIRECTOR
DIRECTOR-29
CROSS ROAD, BENGALURU, KARNATAKA STATE.
4. M/S HPCL RENEWABLE GREEN ENERGY LIMITED, REP. BY ITS
CHAIRMAN AND MANAGING DIRECTOR,
5TH
FLOOR,
RC,J
W.P.No.29862 of 2026
PETROLEUM HOUSE, JAMSHEDGI TATA ROAD CHURCH GATE,
MUMBAI, MAHARASHTRA STATE.
5. CENTRAL ELECTRICITY REGULATORY COMMISSION, REP. BY ITS
CHAIR PERSON 6, 7 AND 8TH FLOOR, TOWER B, OLDRATE
CENTER, NOWROAGE NAGAR, NEW DELHI.
...RESPONDENT(S):
Petition under Article 226 of the Constitution of India praying that in the
circumstances stated in the affidavit filed therewith, the High Court may be
pleased topleased to issue any writ, order or direction more particularly one in
the nature of Writ of Mandamus declaring the action of the respondent No.2
in allocating 100 MW connectivity to third parties in pursuance of orders dated
01-10-2026 in Ref No. C/CTU-PLG/CON/S/ 2015/NP Kunta- PR issued by
the 2nd respondent is illegal, arbitrary and violation of Article 14 of the
Constitution of India and to consequently direct the respondents not to provide
connectivity through any third party at N.P Kunta 400/220 kv substation
connecting point during the pendency of petition Dairy No.776/2026 before
the 5th respondent and to pass
IA NO: 1 OF 2026
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased
pleased to direct the 2nd respondent not to allocatelOO MW connectivity to
third parties at N.P Kunta 400/220 kv sub station in pursuance of orders
dated 01-10-2026 in Ref No. C/CTU PLG/CON/S/ 2015/NP- Kunta- PR
issued by the 2"^ respondent pending disposal of the writ petition and to
pass
Counsel for the Petitioner:
1. V V SATISH
Counsel for the Respondent(S):
1.
The Court made the following:
RC,J
W.P.No.29862 of 2026
ORDER
This Writ Petition is filed questioning the action of respondent no.2 in
allocating 100 MW connectivity to third parties in pursuance of orders dated
01.10.2026 in Ref.No.C/CTU-PLG/CON/S/2015/NP-Kunta-PR.
2. The contents of the petition, in brief, are that the petitioner is a
company incorporated under the provisions of Companies Act with an object
to plan, develop and operate solar parks in the State of Andhra Pradesh under
Ministry of New and Renewable Energy Scheme (MNRE) for development of
solar parks and Ultra Mega Solar Power Projects in the State of Andhra
Pradesh. That respondent no.1 had approved setting up of 2500 MW solar
parks in the State of Andhra Pradesh and out of it, solar parks with 1500 MW
capacity has been approved in respect of sites at N.P.Kunta Mandal, Satya Sai
District and Galivedu Mandal, Annamayya District in an extent of Ac.5500 and
Ac.3,300 respectively. The respondent no.1 appointed the petitioner as Solar
Park developer and an applicant for connectivity and long term access in
Interstate Transmission System and directed the petitioner to undertake
infrastructure activities for N.P.Kunta Solar park with capacity of 1500 MW
and to undertake arrangement of connectivity on behalf of Solar Power
Generation in the above stated parks. In pursuance thereafter the petitioner
undertaken the land acquisition and developed basic infrastructure. That out
RC,J
W.P.No.29862 of 2026
of the total 1500 MW, a quantity of 1400 MW has been successfully
commissioned, pooling stations were constructed for them and connected to
the grid. It is the further case of the petitioner that as the petitioner could not
complete and develop 100 MW as per the terms of the contract, a notice
came to be issued by respondent no.2 calling the petitioner to submit the
schedule commercial operation date (SCOD) and revised SCOD in respect of
the petitioner’s generating stations along with the supporting document. For
which the petitioner submitted letter dated 25.09.2026 informing the details
of entire project including the reasons for non-commission of 100 MW and
requested time till 20.12.2026, requesting to grant an extension of timeline,
with exemption from the applicable Milestone Extension Charges (MEC), as a
special case, in accordance with the commissioning schedule furnished by
M/s. HPRGE for the balance 100 MW Solar Project of Ananthapuramu Ultra
Mega Solar Park (1500 MW) considering the circumstances beyond the control
of APSPCL and the continuous efforts being made to obtain the requisite
approvals and complete the commissioning process. But the respondent no.2
sent a letter dated 25.09.2026 rejecting the request of the petitioner stating
that there is no provision in CERC regulations to grant exemption in respect of
extension of commissioning timeline and on 01.10.2026, the respondent no.2
RC,J
W.P.No.29862 of 2026
issued proceedings revoking grant of connectivity for 100 MW out of 1500 MW
that was issued in favour of the petitioner.
It is the further case of the petitioner assailing the orders dated
01.10.2026 of respondent no.2, the petitioner preferred a petition before the
respondent no.5-Central Electricity Regulatory Commission, under section
79(1)(c) and section 79(1)(k) of Electricity Act, 2003, read with Regulations
41 and 42 of General Network Access Regulations, 2022 on 09.10.2026 along
with interlocutory Application to stay the operation of orders dated
01.10.2026 issued by respondent no.2. As the said Interlocutory Application
filed for stay of the operation has not been taken up for consideration, the
present writ petition came to be filed.
3. Heard Sri Dammalapati Srinivas, learned Advocate General, assisted
by Sri V.V.Satish, learned Standing counsel for petitioner and Sri Y.V.Anil
Kumar, learned Central Government Counsel.
4. Sri Dammalapati Srinivas, learned Advocate General, while reiterating
the contents of the writ affidavit would contend that since commissioning of
the remaining 100 MW power out of 1500 MW was beyond the control of the
petitioner, it entered into an agreement with respondent no.4-M/s.HPCL
Renewable Green Energy Limited, for commissioning and development of the
RC,J
W.P.No.29862 of 2026
said 100 MW. The learned Advocate General would further contend that the
said fact has duly been brought to the notice of respondent no.2 in the
explanation submitted by the petitioner. The learned Advocate General would
further contend that in fact the petitioner had also informed the respondent
no.2 in his explanation dated 25.09.2026 that the trial run for a capacity of
52.8 MW AC/ 70 MW DC is scheduled to be successfully completed by
09.10.2026, followed by commencement of commercial operations by
15.10.2026 and the balance capacity of 47.2 MW is expected to be
commissioned by 20.12.2026, despite the same the respondent no.2 without
application of mind rejected the request of the petitioner. The learned
Advocate General would further contend that the Interlocutory Application
(IA) filed along with the petition assailing the rejection orders, has not been
considered by respondent no.5-Central Electricity Regulatory Commission,
despite request made and in the meantime if respondent no.2 enter into any
agreement with any third party regarding the remaining 100 MW by revoking
the bank guarantees, the petitioner as well as respondent no.4, with whom
the petitioner entered into agreement for commissioning and development of
remaining 100 MW, would be put to irreparable loss and hardship. Further, in
such an eventuality the respondent no.4 may proceed and take steps against
the petitioner. The learned Advocate General, at this juncture, submitted that
RC,J
W.P.No.29862 of 2026
the relief sought in this writ petition is being restricted for issuance of a
direction to respondent no.5 to take up the Interlocutory Application filed for
stay of operation of the order dated 01.10.2026 and accordingly prayed to
pass appropriate orders.
5. On the other hand, Sri Y.V.Anil Kumar, learned Central Government
Counsel, submitted that respondent no.1 is only a pro forma party to the writ
petition and the rejection order was passed by respondent no.2 and the
petition preferred against such rejection was pending before respondent no.5.
6. Perused the material available on record and considered the
submissions made by learned counsel for the parties.
7. It is not in dispute that connectivity for 1500 MW was originally
granted in relation to the solar park, that 1400 MW has been commissioned,
and that the controversy concerns the balance 100 MW. The petitioner states
that it furnished a revised commissioning schedule by its communication
dated 25.09.2026 and sought extension up to 20.12.2026. Respondent No.2,
however, rejected the request and revoked connectivity to the extent of 100
MW by proceedings dated 01.10.2026.
8. The petitioner has already approached respondent No.5, the Central
Electricity Regulatory Commission, by filing a petition on 09.10.2026 under
RC,J
W.P.No.29862 of 2026
Section 79(1)(c) and (k) of the Electricity Act, 2003 read with Regulations 41
and 42 of the General Network Access Regulations, 2022, together with an
interlocutory application seeking stay of the proceedings dated 01.10.2026. At
the hearing, learned Advocate General confined the relief pressed in this writ
petition to an expeditious consideration of that application. In these
circumstances, this Court considers it appropriate to leave all questions
touching the merits of the revocation to respondent No.5.
9. The apprehension expressed by the petitioner that the disputed 100
MW connectivity may be allocated to third parties before its application is
considered cannot be ignored. If such allocation is made in the meantime,
third-party interests may intervene and the request for interim protection
pending before respondent No.5 may be rendered substantially ineffective.
The balance of convenience, for this limited purpose, therefore favours
preservation of the disputed capacity until respondent No.5 has an
opportunity to decide the interlocutory application after hearing the concerned
parties.
10. Accordingly, without expressing any opinion on the merits of the
rival claims, this Writ Petition is disposed of with the following directions:
(i)
Respondent No.5, the Central Electricity Regulatory Commission,
shall take up the interlocutory application filed by the petitioner
RC,J
W.P.No.29862 of 2026
along with its petition dated 09.10.2026, afford an opportunity
of hearing to the concerned parties, and pass an appropriate
reasoned order, in accordance with law, as expeditiously as
possible, preferably within two weeks from the date of receipt of
a copy of this order.
(ii) Until respondent No.5 passes orders on the said interlocutory
application, respondent No.2 shall not allocate, reallocate, or
otherwise grant the disputed 100 MW connectivity, revoked by
proceedings dated 01.10.2026, in favour of any third party.
(iii) There shall be no order as to costs.
As a sequel, pending miscellaneous applications, if any, shall stand
closed.
12TH October, 2026
________________________
JUSTICE RAVI CHEEMALAPATI
RR
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review