10. Therefore, I find that the Annexure-9 i.e., the letter address to the petitioner dated 14th August, 2017 has no stand in the eye of law. Accordingly, I set aside the said order.
11. With this observation and direction, the petition is allowed and stands disposed of. Misc. case also stands disposed of. (S.R.Sen) Meghalaya
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
Serial No. 17
Regular List
HIGH COURT OF MEGHALAYA
AT SHILLONG
Date of Decision : 19.02.2019
WP(C). No.238 of 2017
___________________________________________________________
Smti. Amelia Sohliya
Coram:
Vs.
State of Meghalaya & Ors.
Hon’ble Mr. Justice S.R.Sen, Judge (Oral)
Appearance:
For the Petitioner/Appellant(s) : Mr. S.C.Chakrawarty, Sr. Adv. with
Ms. R.Sumer, Adv.
For the Respondent(s)
: Mr. H. Abraham, GA for R 1-4.
Mr. K.Paul, Adv. for R 5.
___________________________________________________________
1. Heard Mr. S.C.Chakrawarty, learned Sr. counsel assisted by Ms.
R.Sumer, learned counsel on behalf of the petitioner as well as Mr.
H.Abraham, learned GA on behalf of the respondents No. 1-4 and
Mr. K.Paul, learned counsel on behalf of the respondent No. 5.
The petitioner’s case in a nutshell is that:
“The petitioner is a citizen of India
belonging to the Khasi Tribe of Meghalaya who
usually and habitually resides at the
aforestated address. There was a dispute
between the petitioner and her neighbor Smti.
Twes Nongsiej regarding a portion of the
petitioner’s land which had been permitted to
be used for ingress and egress into the
neighbour’s property, the same led to the
institution of the Revenue Case No.
L.14/3(6)/2012 between the petitioner and the
petitioner’s said neighbor which was finally
decided by the final order of the Additional
Deputy Commissioner (Revenue) at Shillong,
conveyed by his Letter No. L.14/3(6)2012/18
dated 04.06.2013 to the parties to that dispute.
From the said final order in the said Revenue
Case it is seen that the Additional Deputy
Commissioner had taken note of the fact that
the records produced by the Executive
Engineer, Public Works Department, Shillong
Central Division, Shillong, showed that the
disputed portion of the petitioner’s land
included a portion of the road constructed by
the Public Works Department during 20072008 and a map was also available with regard
thereto but there was no observation or finding
to the effect that the Public Works Department
had any records to show that that portion of the
road was owned by the Public works
Department or that the Public Works
Department ever made any claim of such
ownership. As such the only finding given by
the
Honourable
Additional
Deputy
Commissioner (Revenue) was that if the entire
disputed portion of that road was allowed to be
fenced by a boundary wall by the petitioner
then the ingress and egress to the said
neighbour’s property would become restricted
whereupon a direction was given to maintain
status quo. The said final order of the
Additional Deputy Commissioner (Revenue)
amply clarifies that the records of Public Works
Department merely indicate that the said
disputed portion of the road was constructed
only once by the Public Works Department
during the year 2007-2008, that the Public
Works Department had no records to show that
they were the owners of the said disputed
portion of the road and that actually the Public
Works Department never even made a claim
that they were owners of that road.
Subsequently the matter went on an
appeal before the Meghalaya Board of Revenue
where a compromise was arrived at in a Lok
Adalat which accordingly gave the award as
recorded by the order dated 11.12.2014, of the
Chairman of the Board.
However, the petitioner’s said neighbor
assailed the said award of the Lok Adalat and
the order of the Meghalaya Board of Revenue
before Honourable The High Court of
Meghalaya by filing the Writ Petition(Civil) No.
1 of 2015 which was finally disposed off by the
judgement and order dated 17.03.2017 without
interfering with the impugned award and order
and the Writ Appeal No. 4 of 2017 assailing
that order dated 17.03.2017 was also disposed
off by the order dated 18.04.2017 upholding the
said order in the writ petition.
After
Honourable The High Court of Meghalaya
gave the said judgements and orders dated
17.03.2017 and 18.04.2017, the petitioner
wrote her letter dated 28.04.2017 to the Deputy
Commissioner at Shillong on the subject of
fencing her said land and property at Dunoon
Compound, Kench’s Trace, Shillong informing
him about the said award of the Lok Adalat,
order of the Board of Revenue and the orders of
the Honourable High Court and requested him
to allow her to build the fencing wall as per
that award and the said orders and also to
provide her with security as she would be
building the said wall on 01.05.2017 onwards.
Only after the sequence of events described
hereinabove, did the petitioner construct the
compound wall of her said compound and the
construction of the same was completed quite
sometime ago and the completion report duly
intimated to the Deputy Commissioner.
By the said impugned letters dated
31.07.2017 and 14.08.2017, it has been alleged
that the petitioner has encroached upon a
Public Works Department Road by constructing
a compound wall which has been revealed from
the official records available with the
respondent No. 4 but the exact nature of such
records has not been disclosed for reasons
which appear to be best known to the
respondent no. 4. After receiving the said
impugned letters dated 31.07.2017 and
14.08.2017 the petitioner had duly represented
the respondents by her letter dated 18.08.2017
addressed to the respondent No. 4 with a copy
to the respondent No. 3 but till date there has
been no response to the same.
The Petitioner had sought for justice but
the same has been denied to her and now,
having no other equally efficacious remedy
available she is filing this instant writ petition.”
2. Learned Sr. Counsel for the petitioner, Mr. S.C Chakrawarty
submits that the matter was initially settled between the petitioner
and by the respondents before the Lok Adalat. Learned Sr. counsel
also referred to the earlier Writ Petition bearing W.P.(C) No. 1 of
2015 where a judgment and order was delivered on 17/03/2017 as
well as the judgment delivered on 18/04/2017 by Division Bench
of this High Court in Writ Appeal bearing W.A. No. 4 of 2017.
3. On perusal of the said judgments, it is understood and clear that
since the matter was settled before the Lok Adalat, this Court as
well as the Division Bench had taken a view that there is no prima
facie case to entertain. However, it is not necessary to discuss
those judgments in detail further as it is on record. I make it clear
that Section 21(2) of the Legal Services Authorities Act, 1987
makes it clear that “Every award made by a Lok Adalat shall be
final and binding on all the parties to the dispute, and no appeal
shall lie to any court against the award.” Similarly, in this case
also when the matter was settled in the Lok Adalat between the
parties, further interference of the Court is not tenable in law.
4. Learned State counsel for the respondents No. 1-4, Mr. H.Abraham
submits that he has no dispute or any grievance or objection nor
denies that the matter was settled before the Lok Adalat. The only
question is that the petitioner while constructing the boundary wall
encroached some part of Government land. If it is so, Government
should have approached an appropriate forum.
5. Learned Sr. counsel on behalf of the petitioner, Mr. S.C
Chakrawarty also pointed to Annexure -7 (page-29) as well as
Annexure-9 (page-31). From the said Annexures, it appears that
the petitioner had informed the Deputy Commissioner that she had
constructed the boundary wall and also expressed her gratitude to
the Deputy Commissioner for providing security to construct the
wall.
6. It is also noticed from the Annexure-9 dated 14th August, 2017 that
the
Executive
Engineer,
P.W.D.(Roads),
Shillong
Central
Division, Shillong had written a letter to the petitioner that she has
encroached the P.W.D land approximately 12.15 square meter and
directed her to dismantle the compound wall from the said P.W.D.
road.
7. Learned counsel for respondent No. 5, Mr K. Paul submits that he
is not disputing the settlement of the matter before the Lok Adalat.
However, respondent No. 5 is suffering due to the boundary wall
and her entry is partially blocked.
8. After hearing the submissions advanced by the learned counsels
for the parties, I am of the view that once the matter is settled in
the Lok Adalat, it is a bar under Section 21(2) to reopen it which is
also agreed by all the learned counsels for the parties present
before the Court. However, the question remains about the
encroachment; if at all any encroachment is done, a specific law is
available on what action to be taken. But it appears that in one way
the Government is giving security to construct the boundary wall
and the other way notice is being issued to dismantle the wall. I
cannot understand the position of the Government, why they are
taking diverse views and stand.
9. If at all there is any encroachment by the petitioner they should
approach the appropriate forum and the appropriate forum will do
what is necessary after hearing and giving opportunities to the
parties in accordance with law.
10. Therefore, I find that the Annexure-9 i.e., the letter address to the
petitioner dated 14th August, 2017 has no stand in the eye of law.
Accordingly, I set aside the said order.
11. With this observation and direction, the petition is allowed and
stands disposed of. Misc. case also stands disposed of.
(S.R.Sen)
JUDGE
Meghalaya
19.02.2019
“S.Rynjah PS”
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review