2026:JHHC:32758
IN THE HIGH COURT OF JHARKHAND AT RANCHI
Cr. Revision No. 357 of 2022
--------Ajit Kumar Choudhary, aged about 55 years, son of Late Tej Narayan
Choudhary, Resident of Quarter No. M.B. 6C Near Shiv Mandir, B Type,
Adityapur, P.O. and P.S.-Adityapur, Dist. Seraikella-Kharsawan, Jharkhand
……Petitioner
Versus
1. The State of Jharkhand
2. Prabhat Kumar Bardiyar, S/o-Late Sukhdeo Ram Bardiyar (B.D.O.,
Kharsawan), Village-Jojohatu, P.O. & P.S. and District-Khunti
…. Opp. Parties
---------For the Petitioner
: Mr. Naveen Kumar Jiaswal, Advocate
For the State
: Mrs. Priya Shrestha, Spl.P.P.
--------PRESENT
CORAM: HON’BLE MR. JUSTICE PRADEEP KUMAR SRIVASTAVA
ORDERS
----------CAV on 07.09.2026
Pronounced on 06/11/2026
1. I have heard Mr. Naveen Kumar Jaiswal, learned counsel for the
petitioner and Mrs. Priya Shrestha, learned Spl.P.P. for the State.
2. Instant criminal revision is directed against the order dated 28.02.2022
whereby and whereunder an application under section 239 of Cr.P.C for
discharge of the petitioner has been rejected by learned Additional Chief
Judicial Magistrate, Seraikella in connection with G.R. Case No.727 of
2013 corresponding to Kharsawan P.S. Case No.42 of 2013 for the
offence under sections 406 and 409 of IPC.
Factual Matrix:3. Factual Matrix giving rise to this revision as per FIR lodged by Block
Development Officer, Seraikella, Kharsawan is that the construction
Cr. Revision No.357 of 2022
2026:JHHC:32758
work of Panchyat Bhawan, Telaiyadih under the scheme No.30/2011-12
estimated cost of Rs.21,15,900/- got administrative approval on
05.05.2010. Initially the departmental contractor Sri Bam Prasad, Junior
Engineer was advanced Rs.6 lakhs to initiate the above construction
work to which he declined and returned the money. Thereafter, the
above scheme work was allotted to Junior Engineer, Ajit Kumar
Choudhary (present petitioner). It is alleged that total Rs.12 lakhs was
advanced to the said Ajit Kumar Choudhary and till the date of lodging
the FIR, physical structure of the building was (i) casting of roof of
ground floor roof was completed (ii) Erection of wall of first floor was
completed and casing of roof remain pending (iii) Up-to-date
measurement of Rs.12,83,609/-, (iv) royalty and sales tax of Rs.13,698/and (v) dues-83,609/-.
The measurement book was also certified by Assistant
Engineer and Executive Engineer. The bills raised as per measurement
book by the departmental agent (petitioner), the amount of royalty and
sales tax of Rs.13,698/- was provided through cheque dated 24.12.2010
and dues of Rs.83,609/- was also paid through cheque No.016704 by the
Executive Engineer. It is further alleged that for completion of
remaining work, petitioner demanded advance of Rs.2 lakhs for casting
of roof of first floor and the same amount was paid by BDO, Kharsawan
and labour charges Rs.7,200./- was sent to Post Master, Chaibasa. The
petitioner produced measurement book on 20.02.2012 for the amount
Cr. Revision No.357 of 2022
2026:JHHC:32758
Rs.2,51,336/- and the same was certified by Assistant Engineer and
Executive Engineer. It is further alleged that for installing doors and
windows and plaster work, advance of Rs.3 lakhs were demanded by
the petitioner but in spite of paying advance as per Measurement Book
Rs.50,000/- was paid through Cheque No.295791 dated 12.03.2012. It is
further alleged that the present petitioner by his application dated
24.04.2012 informed that Blocks MNREGA and others works are going
on and due to posting of only two junior engineers, it is very difficult to
complete the work of Telaidyah Panchyat Bhawan and also prayed to
get the work completed by Panchyat Secretary/Mukhiya, Telaiyadih and
he may be exonerated. It is further alleged that the petitioner also
deposited all bills, master rolls and receipts of his work and requested to
complete the work through Panchyat Sevak but Panchayat Sevak from
entering into the agreement due to meager amount of the scheme. In the
aforesaid situation, the construction work remained pending for two
months without any progress, then show-cause notice was issued vide
Letter No.597 dated 19.05.2012 against the departmental agent, Ajit
Kumar Choudhary (present petitioner) and also directed to deposit
royalty and sales tax deductions but he did not reply. Thereafter, the
work measurement through physical inspection was conducted and
several irregularities and discrepancies was found and it was also found
that the work is not in accordance with his measurement mentioned in
the scheme. Therefore, Ajit Kumar Choudhary (petitioner) has
Cr. Revision No.357 of 2022
2026:JHHC:32758
withdrawn the Government money by placing false measurement of
work done by him against the specification of the scheme and also not
paid the royalty and sales tax and misappropriated the government
money.
On the basis of above written report (computerized typing),
FIR was registered as Seraikella P.S. Case No.42 of 2013 dated
25.07.2013 for the offence under sections 406 and 409 of IPC. After
completion of investigation, charge-sheet was submitted against the
petitioner. He filed an application for discharge the petition under
section 239 of Cr.P.C, which has been rejected and assailed in this
revision against which this petition is filed.
Submission on behalf of petitioner:4. Learned counsel for the petitioner has submitted that after institution of
FIR, the petitioner was requested to complete the remaining work of
Panchyat Bhawan (Anxxure-8) and re-inquiry was also conducted for
verifying the measurement of the work completed as per terms and
specification of the project under the scheme. District Panchyat Raj
Officer vide letter No.2012 dated 07.03.2017 directed the B.D.O.,
Kharsawan to allow the present petitioner to complete the Panchyat
Bhawan. Accordingly, B.D.O., Kharsawan wrote Letter No.299
(Annexure-7) dated 08.03.2017 to APP civil court, Seraikella to obtain
the permission of the court concern for the completion of the work by
the petitioner. Learned Additional Public Prosecutor filed an application
Cr. Revision No.357 of 2022
2026:JHHC:32758
before the concerned court, ACJM, Kharsawan seeking permission to
complete the work under the scheme by the petitioner vide order dated
19.04.2017. The said application was allowed with observation that
“The court has no objection if the concerned authorities have decided to
complete the pending work from the accused since this case has been
filed by the state.” Thereafter, Block Development Officer, Kharsawan
vide Memo No.844 dated 10.06.2017 addressed to Mukhiya/Panchyat
Secretary (Annexure-9), Gram Panchyat, Telaiya including the entire
documents regarding the construction of the said Panchyat Building to
start remaining the construction work through the present petitioner.
Accordingly, Village Pradhan Secretary/Mukhiya directed the present
petitioner to start the remaining work of building in question vide his
Letter No.27 dated 11.06.2017 (Annexure-10). The petitioner completed
the entire building work of the Panchyat Bhawan and after satisfying the
work, a Work Completion Certificate dated 18.10.2017 (Annexure-11)
was jointly issued by the Assistant Engineer, Junior Engineer, Panchyat
Secretary/Mukhiya of Telaiyadih Panchayat. After finding the
construction work satisfactory and as per scheme, the newly constructed
Panchyat Bhawan of Telaiyadih along with original measurement books
of the said building was handed over by the petitioner to Receiving
Officer on 18.10.2017 and in this regard, the certificate was also issued
under signature of Receiving Officer, Panchyat Sevak (Annexure Nos.
12 and 13). It is further submitted that after handing over the said
Cr. Revision No.357 of 2022
2026:JHHC:32758
building vide Letter dated 25.04.2018 addressed to BDO, Kharsawan,
the petitioner informed that he has received the entire amount and there
is no dues relating to the construction of the above building
(Annexure-14). It is further submitted that the petitioner has never
defalcated any government money in connection with the aforesaid
scheme rather due to meager amount of estimated cost and its delayed
payment of installment, the construction work was delayed. Even, after
institution of the FIR, the petitioner was extended the period for
completion of the construction work and ultimately satisfying from all
corners, the building was handed over and Panchyat Bhawan is
functional. Not a single penny has been defalcated by the petitioner. In
spite of the above information given to the Investigating Officer,
charge-sheet was submitted against the petitioner for the aforesaid
offence and cognizance has been taken. It is further submitted that the
entire factual scenario as depicted above do not constitute any offence
under sections 406 and 409 of IPC against the petitioner. Learned trial
court without discussing the above materials, which were also pointed
out during argument has relied upon the earlier report submitted by the
Department. Although, the re-inquiry report submitted to the
Investigating Officer and part of the record has also not considered at all
and the further development, which took place in this case with
permission of the court has been ignored. Learned trial court has not
recorded any sound reasoning as to how the offence under sections 406
Cr. Revision No.357 of 2022
2026:JHHC:32758
and 409 of IPC is constituted in the present facts and circumstances
against the petitioner. Therefore, passed an absolutely illegal and
erroneous order, which is liable to be set aside allowing this revision.
Submission on behalf of State:5. On the other hand, learned Spl.P.P controverting the aforesaid points of
argument has submitted that all the points taken by the petitioner are
concerned with the probable defence, which has to be proved during
trial and not warranted to be decided at the very initial stage of the
proceeding. It is further submitted that during enquiry several
discrepancies in the actual construction work and measurement book
were found, which is indicative of defalcation of money provided under
the scheme for construction work. At this stage of proceeding, there is
no valid reason for interfering with the impugned order. Therefore, this
revision has no merits and fit to be dismissed.
Analysis, Reasons and Decision:6. I have gone through the record of the case along with impugned order in
the light of contentions raised on behalf of both side.
7. It appears that the main dispute arose in this case for delayed
construction work of the Panchyat Bhawan by the petitioner. The
constraints and compelling circumstances like meager amount of
estimated cost and others were pointed out by the petitioner before the
Authorities and alternative request was also suggested to get completion
of remaining work through Panchyat Secretary/Mukhiya appointing him
Cr. Revision No.357 of 2022
2026:JHHC:32758
as an agent. In spite of that the petitioner was prosecuted issuing a show
cause notice to him. It further transpires that after institution of FIR and
realizing the consequences, the petitioner requested the authority to
extend the time for completion of the remaining work and also
requested for re-inquiry regarding discrepancies as pointed out in the
earlier inquiry and to permit him to complete work in accordance with
terms and conditions of the scheme. Thereafter, the completion work of
the building was expedited and the same was completed and verified by
the Competent Authority. Being satisfied with specification of work
completed and detailed project of the scheme, a certificate was issued
by the Competent Authority and finally the building was handed over
and receipt of the same has also been issued from the Office of Deputy
Commissioner, Kharsawan. These developments and correspondence
were held under official norms and cannot be categorized as probable
defence of the petitioner. It further transpires that there is no whisper in
the entire FIR and materials collected during investigation as to how
much money was defalcated under the scheme by the petitioner rather
the entire allegations are centered around against the delay of
construction work. Therefore, it appears that learned trial court has not
taken into consideration the entire factual aspects of the case and further
developments in this case after institution of FIR under the permissive
umbrella of the court and the officials involved in the completion of
scheme work and passed the impugned order without recording any
Cr. Revision No.357 of 2022
2026:JHHC:32758
valid reasons as to what are the materials constituting the offence under
sections 406 and 409 of IPC against the petitioner.
8. In view of the above discussion and reasons, I find substance in this
revision. Therefore, the impugned order dated 28.02.2022 passed by
learned Additional Chief Judicial Magistrage, Seraikella is hereby set
aside and this criminal revision is allowed.
9. The matter is remitted back to the learned trial court for hearing the
parties afresh and pass a fresh reasoned order in the light of aforesaid
observation without being prejudiced by its previous rejection order.
10.Pending I.A(s), if any, is also disposed of accordingly.
11.Let a copy of this order be sent back to the concerned court for
information and needful.
(Pradeep Kumar Srivastava, J.)
High Court of Jharkhand, Ranchi
Date:-06/11 /2026
Pappu/-N.A.F.R.
Uploaded on 06/11 /2026
Cr. Revision No.357 of 2022
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review