The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
03. 03.2016, we have expressed serious reservations in the approach on the part of the Airports Authority of India, who has, with impunity attempted to suggest about 2½ years time hence for completion of the project, squarely contrary to what was noticed, observed and directed by this Court in the order dated 15.12.2015. We have expressed reservations on the very suggestion on the part of the Airports Authority of India that they would purportedly take up the work of expansion of runway etc. only after the completion of construction of boundary wall and then, we have also found it quite unacceptable that this is suggested as if the State Public Works Department would need time upto January, 2017 to complete the boundary wall. A look at the suggestion made in the application leave nothing to doubt of the Airports Authority has taken the order passed by this Court for granted and has no intention to comply with the directions of the Court with reasonable expedition. Going by the suggestions made in this application, it would appear as if the authorities of the Government of Meghalaya are also not keenly pursuing the project and are taking up the execution of the work at their own leisure. The scenario emanating of the contents of this miscellaneous application being entirely unacceptable and being directly at conflict with the letter and spirit with the order passed by this Court. We…
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
BEFORE
HON’BLE THE CHIEF JUSTICE
HON’BLE SHRI JUSTICE S.R. SEN
MC [WP(C)] No.67 of 2016
20.04.2016
By way of this application [M.C.WP(C)] No.67 of 2016],
the applicant-Airports Authority of India, through its Airport Director,
Shillong (Umroi) Airport, has sought extension of time until
30.09.2018, for compliance of the order dated 15.12.2015 passed by
this Court in WP(C) No.164 of 2015.
The said writ petition [WP(C) No.164 of 2015] was
registered as Public Interest Litigation on the basis of the report
placed
before
the
Court
pointing
out
undue
hardship
and
inconvenience to the local populace of the State of Meghalaya, who
stood deprived of the services of regular aircrafts for want of proper
functional airport.
Without going into several orders passed in the said writ
petition from time to time by the Court, suffice it would be to take note
of the fact that after the submissions of various propositions and
clearing of various hindrances and obstacles, a Full Bench of this
Court ultimately concluded the matter in the said writ petition by the
order dated 15.12.2015, while granting time to the authorities to
complete the project expeditiously, after taking note of the fact that
there was no hindrance in completing the work of expansion and
upgradation of Umroi Airport. For the purpose of monitoring of the
project, a Committee to be chaired by the Secretary of Defence or his
representatives in the Ministry of Defence was also constituted. It was
also indicated that if there be any hindrance in the progress of the
project by any individual or authority, the Committee shall inform the
Registry of this Court for appropriate proceedings. The concluding
passages in the order dated 15.12.2015 could be taken note of as
under:-
“17. ....As there is no hindrance in completing the expansion
and upgradation of the Umroi Airport for aircraft operation from
Umroi Airport during bad weather and low visibility conditions
by turbo-jet AB-321 aircrafts like Boeing, Airbus etc, the
concerned authorities (Respondents) should complete the
project as expeditiously as possible not later than 4(four)
months from the date of passing this order. The progress of
the project i.e. expansion of the Umroi Airport should be
monitored by a Committee consisting of :1) Secretary of Defence/ His representative,
Defence Ministry, Government of India.
- Chairman
2) The Chief of Army Staff of the Indian
Army/His representative, Government
of India.
- Member
3) Chief Secretary/ His representative,
Government of Meghalaya.
- Member
4) Secretary Revenue, Department of Revenue,
Government of Meghalaya.
- Convenor
5) Deputy Commissioner, Ri-Bhoi District,
Nongpoh, Government of Meghalaya
- Member
6) Airport Director (Shillong)
Airport Authority of India.
- Member
18. Further, it is made clear that if there be any hindrance in
the progress of the project by any individual or authority, the
Committee shall inform the Registry of this High Court so that
the High Court may take appropriate proceedings by invoking
writ jurisdiction or contempt proceedings against those who
cause hindrance in the expansion work of Umroi Airport.
19. With the above directions, writ petition is disposed of with
liberty to the Registry to bring to the notice of this court if there
be any report of hindrance so submitted by the Committee
aforesaid.”
Shocking and surprising it had been that on the date of
completion of the aforesaid period of four months, the Director,
Shillong Airport, working under the instructions of the Airports
Authority of India, has chosen to file this application seeking extension
of time for completion of the project by 30.09.2018. While stating that
some works have been carried out and some have not been
executed, the Director has suggested in this application the work of
construction of boundary wall will be completed by the month
of January, 2017 by the Public Works Department of the State and
that twenty months further time would be needed for the work of
expansion and construction of runway/extension of apron for parking
of aircrafts etc. after completion of the construction of the boundary
wall. It is also submitted that the Monitoring Committee met on
03.03.2016 and minutes have been placed on record as Annexure-A2.
Having gone through the contents of the application and
the minutes of the meeting of the Monitoring Committee dated
03.03.2016, we have expressed serious reservations in the approach
on the part of the Airports Authority of India, who has, with impunity
attempted to suggest about 2½ years time hence for completion of the
project, squarely contrary to what was noticed, observed and directed
by this Court in the order dated 15.12.2015.
We have expressed reservations on the very suggestion
on the part of the Airports Authority of India that they would
purportedly take up the work of expansion of runway etc. only after the
completion of construction of boundary wall and then, we have also
found it quite unacceptable that this is suggested as if the State Public
Works Department would need time upto January, 2017 to complete
the boundary wall.
A look at the suggestion made in the application leave
nothing to doubt of the Airports Authority has taken the order passed
by this Court for granted and has no intention to comply with the
directions of the Court with reasonable expedition. Going by the
suggestions made in this application, it would appear as if the
authorities of the Government of Meghalaya are also not keenly
pursuing the project and are taking up the execution of the work at
their own leisure.
The
scenario
emanating
of
the
contents
of
this
miscellaneous application being entirely unacceptable and being
directly at conflict with the letter and spirit with the order passed by
this Court. We have indicated to the learned counsel for the parties
that such intents to avoid compliance of the order of this Court and
thereby delay the public utility work is bound to be seen seriously and
requisite order shall have to be passed.
Upon our expressing thus, learned counsel for the parties
prayed for some time to complete their instructions from their
respective clients. This matter was passed over so as to enable the
learned counsel to complete all their instructions.
In the second round of call, learned counsel Mr. N Mozika
appearing for the applicant Airports Authority of India with Shri.Sanjay
Tyagi, Airport Director, Shillong (Umroi) Airport, has submitted that he
has the instructions to make a prayer for permission to withdraw this
application. It is submitted that the authorities of the Airports Authority
of India shall make a request for convening the meeting of the
Monitoring Committee and make the submissions before the
Monitoring Committee for its consideration.
Learned counsel Mr. K Paul appearing for the Chief of
Army Staff has also submitted that so far defence establishment is
concerned, from their side, whatever had been the doubt or dispute,
that stands resolved on their part and there is no interference or
hindrance in expeditious execution of the project. Mr. K Paul further
submitted that reservations expressed by this Court on this application
have been convened to the learned Defence Secretary who has
directed to convene an emergent meeting of the Monitoring
Committee.
Learned Sr.GA Mr. ND Chullai submits that as per his
instructions, the construction work undertaken by the Public Works
Department is going on and that the State authorities shall work in
tandem with the other concerned authorities so as to ensure
expeditious execution of the work.
After taking note of the submissions so made by the
respective counsel, we are inclined to grant the prayer made on behalf
of the applicant-Airports Authority of India to withdraw from this
application but then, looking to the nature of the project which requires
serious attention by all concerned and then, looking to the fact that the
application has been moved in this Court in an entirely irresponsible
manner asking for time until 30.09.2018 with impunity and with no
respect to the order of this Court, we are clearly of the view that such
permission for withdrawal ought to be granted only after saddling the
applicant with costs, to be personally recovered from the person who
has moved this application. We would have considered saddling the
applicant with substantial amount of costs, but on the submissions as
made by Mr. N Mozika for leniency and that the application was
moved by the Director of Airports Authority of India not precisely on
his own but on the instructions of the higher authorities, we would
prefer saddling the applicant with a token of costs only.
Therefore, the applicant is permitted to withdraw this
application and this application stands dismissed as withdrawn with
costs quantified at Rs.5000/- which shall be deposited by the applicant
of this application in the account of the Meghalaya State Legal
Services Authority within a week’s time from today.
However, dismissal of this application [M.C. No.67 of
2016] is not the end of the matter because as per the order dated
15.12.2015, the project was to be completed within four months and
that period has already expired. Obviously, all the officers/authorities
concerned with the project have failed to carry out compliance of the
order passed by this Court. However, before any other steps in the
matter, it appears appropriate to give a chance to the Monitoring
Committee to take stock of the situation and make a specific and
comprehensive report to this Court as required by the order dated
15.12.2015.
It has been indicated on behalf of the applicant-Airports Authority
that they would be requesting for convening of emergent meeting of
the Monitoring Committee and it has also been indicated that the
Defense Secretary had already issued instructions for convening of
emergent meeting. It is considered appropriate and hence directed
that such meeting shall be held at the earliest and in any case, not
beyond 30.4.2016 and the minutes of the meeting of the Monitoring
Committee shall be forwarded to the Registry of this Court without
delay.
A separate misc. application in WP(C) No.164 of 2015
shall now be registered on this order and such misc. case shall be
placed for orders before the Court on 12.5.2016 alongwith the record
of WP(C) No.164 of 2015.
JUDGE
Lam
Item No.1
CHIEF JUSTICE
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review