Assistant Engineer (D1), Ajmer Vidyut Vitran Nigam Limited & Anr. vs Rahamatullah Khan alias Rahamjulla
SC · 18 February 2020
[2020] 2 S.C.R. 929 : 2020 INSC 205
Electricity Act, 2003: s. 56(2) – Disconnection of supply in default of payment – Term ‘first due’ in s.56(2) – Meaning of – Commencement limitation period of two years, when – Held: Electricity charges would become “fir…
Hindustan Zinc Limited (H.Z.L.) vs Ajmer Vidyut Vitran Nigam Limited
SC · 4 December 2019
[2019] 15 S.C.R. 113 : 2019 INSC 1319
Electricity Act, 2003 – ss.86(1)(f) and ss.37, 42, 158 – Appellant has four high tension electricity connections for its units at Chanderiya, Debari, Aghucha and Dariba, for which four contracts with the respondent were…
M/s Adani Power (Mundra) Ltd. vs Gujarat Electricity Regulatory Commission and Ors.
SC · 2 July 2019
[2019] 8 S.C.R. 1017 : 2019 INSC 711
Electricity Act, 2003 – ss. 86 (1) (F), 95 – Respondent No. 2-Procurer initiated the process of bidding for supply of power on long term basis, by issuing Request for Qualification – Three separate bids were invited – Ap…
Maharashtra State Electricity Distribution Co. Ltd. vs The Appellate Authority & Anr.
SC · 15 February 2018
[2018] 2 S.C.R. 537 : 2018 INSC 144
Electricity Act, 2003 – ss. 126, 127 – Respondent No.2 are consumers of electricity, which is supplied to them by the State Electricity Board – The sleuths of the Board visited the respondent no.2’s factory and replaced…