Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013: s.24(2) – Land Acquisition – Possession taken on 16.03.2004 – High Court declared that the land acquisition with respect to the land in question is deemed to have lapsed on the ground that the amount of compensation was not paid to the land owners – Held: The view taken by the High Court is not sustainable in view of the Constitutional Bench decision of Supreme Court in Indore Development Authority v. Manoharlal and Ors. wherein it was held that in case possession was taken but compensation not paid then there is no lapse – High Court order set aside.
Indore Development Authority v. Manoharlal and Ors. (2020) 8 SCC 129 : [2020] 3 SCR 1 – followed. Pune Municipal Corporation and Anr. v. Harakchand Misirimal Solanki and Ors. (2014) 3 SCC 183 : [2014]
1 SCR 783 – referred to.
As published in the Supreme Court Reports, Supreme Court of India. Text from the Indian Supreme Court Judgments open data set (Dattam Labs), CC BY 4.0.
This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.