LegalFirms.in
LegalFirms.in Judgments · legalfirms.in/judgments/delhi-development-authority-vs-nem-chand-sharma-and-ors-20230120/ · Printed 07 Nov 2026
Civil · Reportable judgment

Delhi Development Authority vs Nem Chand Sharma and Ors.

Court
Supreme Court of India
Date
20 January 2023
Case No.
Civil Appeal No. 395 of 2023
Result
Allowed
Bench
M.R. Shah, C.T. Ravikumar
Citation
[2023] 1 S.C.R. 725 : 2023 INSC 73
Supreme Court Reports [2023] 1 S.C.R. 725 : 2023 INSC 73
Headnote

Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013: s. 24(2) – Lapse of Acquisition proceedings – Writ petition by the respondentoriginal writ petitioners seeking declaration that acquisition proceedings pertaining to subject land is deemed to have lapsed in view of s.24(2) – High Court allowed the petition solely on the ground that it is not clear as to what compensation was paid and if so, who raised the dispute – On appeal, held: For attracting the provisions of s. 24(2), twin conditions of not taking over of possession and not tendering/paying the compensation are to be satisfied and if one of the conditions is not satisfied, there shall not be any deemed lapse of acquisition – On facts, the possession of the land was taken andhanded over to the beneficiary department initially in 1990 and thereafter, remaining 1 bigha was taken and handed over to the beneficiary department in the year 2007 – Thus, the order passed by the High Court is not sustainable and is quashed and set aside – Land Acquisition Act, 1894.

Pune Municipal Corporation & Anr. Vs Harakchand Misrimal Solanki & Ors. (2014) 3 SCC 183 : [2014] 1 SCR 783 – referred to.

Indore Development Authority vs Manoharlal & Ors. (2020) 8 SCC 129 : [2020] 3 SCR 1 – followed.

As published in the Supreme Court Reports, Supreme Court of India. Text from the Indian Supreme Court Judgments open data set (Dattam Labs), CC BY 4.0.

Full Judgment Text

The Judgment of the Court was delivered by M. R. SHAH, J. 1. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the High Court of Delhi at New Delhi in Writ Petition (C) No. 3446 of 2015 by which the High Court has allowed the said writ petition preferred by the original writ petitioners – respondents herein and has declared that the acquisition proceedings initiated under the Land Acquisition Act, 1894 (hereinafter referred to as “Act, 1894”) with regard to the land in question is deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and T
Full text available to subscribers
Subscribe to access complete judgment text, daily digests, and AI-powered legal research tools. For informational and research purposes only.
View Subscription Plans →
Annual plans from ₹1,599 + GST.

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

All SC judgments →